0 5.83 5.

83
A
7.17 13
7.17

0 0 0 0 3.67 3.67
Inicio B
0 0 5.33 9
0 5.33

0 2 2 2
C
0 2 2
0

RUTA CRITICA C-D-E-F-H-K


TIEMPO DE TERMINACION DEL PROYECTO 36.33 DIAS
PROBABILIDAD TERMINAR EL PROYECTO EN 36.33 DIAS
PROBABILIDAD TERMINAR EL PROYECTO EN 41 DIAS
TIEMPO DE 39.28 DIAS PARA TERMIANR PROEYCTO CON PR
13 2.17 15.17
G
15.83 18
2.83

13 10 23
F
13 23
0

9 4 13
E
9 13
0

7 9
D
9
0

2 16.33 18.33
J
20 36.33
18

C-D-E-F-H-K
36.33 DIAS
N 36.33 DIAS 50% POR QUE z=0
N 41 DIAS 97.93% z= 2.04
ROEYCTO CON PROBABILIDAD DE 90%
15.17 11 26.17
I
18 29
2.83

23 6 29 29 7.33 36.33
H K
23 29 29 36.33
0 0
36.33 0 36.33
final
36.33 36.33
0
ACTIVIDAD To Tm Tp Te Varianza Des Estan proy
A 3 6 8 5.83
B 2 4 4 3.67
C 1 2 3 2.00 0.111
D 6 7 8 7.00 0.111
E 2 4 6 4.00 0.444
F 6 10 14 10.00 1.778
G 1 2 4 2.17
H 3 6 9 6.00 1.000
I 10 11 12 11.00
J 14 16 20 16.33
K 2 8 10 7.33 1.778
5.222 2.29

CALCULAMOS Z PARA UN TERMINO DE 41 DIAS DEL PROYECTO

Z= (41 -36.33)/2.29

Z= 2.044 Probabilidad 97.93%

CALCULAMOS el tiempo de termino del proeycto

z= 1.29 Probabilidad 90.00%

T= 39.28
0 5.83
A
7.17
7.17

0 0 0 0 3.67
INICIO B
0 0 5.33
0 5.33

0 2
C
0
0
13 2.17 15.17
G
15.83 18
2.83

13 10 23
F
13 23
0
5.83

13

9 4 13
E
3.67 9 13
0
9

2 2 7 9
D
2 2 9
0
15.17 11 26.17
I
18 29
2.83

23 6 29 29 7.33
H K
23 29 29
0 0

2 16.33 18.33
J
20 36.33
18
36.33

36.33

36.33 0 36.33
FINAL
36.33 36.33
0