CRONOGRAMA DE DESEMBOLSOS

Presupuesto: "INSTALACION DE UN POLIDEPORTIVO EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS - HUARI - ANCASH "

Lugar: C.P. SANTA CRUZ DE MOSNA, SAN MARCOS - HUARI - ANCASH


Costo al: 5/31/2012

DESEMBOLSOS DE EJECUCION DE OBRAS MONTO EN NUEVOS SOLES

ADELANTOS Y AMORTIZACIONES VALORIZACION DESEMBOLSOS PARA OBRAS


PARCIALES DE
CALENDARIO EFECTIVO MATERIALES TOTAL LA OBRA PRESUPUESTO IGV. (18%) PRESUPUESTO
(1) (2) (1 + 2) (3) PARCIAL 3-(1+2) (INCL IGV)

0 1,061,256.80 2,122,513.60 3,183,770.40 3,183,770.40 573,078.67 3,756,849.07

30 120,390.66 240,781.32 361,171.99 601,953.31 240,781.32 43,340.64 284,121.96

60 304,277.07 608,554.14 912,831.20 1,521,385.34 608,554.14 109,539.74 718,093.88

90 325,850.01 651,700.02 977,550.03 1,629,250.05 651,700.02 117,306.00 769,006.02

120 147,864.15 295,728.30 443,592.44 739,320.74 295,728.30 53,231.09 348,959.39

150 90,218.73 180,437.45 270,656.18 451,093.63 180,437.45 32,478.74 212,916.19

180 10,119.22 20,238.44 30,357.67 50,596.11 20,238.44 3,642.92 23,881.36

210 62,536.96 125,073.93 187,610.89 312,684.82 125,073.93 22,513.32 147,587.25

PARCIAL 0.00 0.00 0.00 5,306,284.00 5,306,284.00 955,131.12 6,261,415.12

MONTO TOTAL DEL PRESUPUESTO Incl. IGV 6,261,415.12

Costos no incluyen IGV


Ejecucion de Obras = ###
Adelanto en efectivo 20% de Obras = ###
Adelanto para materiales 40% de Obras = ###