MAYORES Y MENORES METRADOS 01

DESCRIPCION PRESUPUESTO CONTRATADO


COSTO DIRECTO (CD) 2,267,147.39
GASTOS GENERALES (12%) 272,057.69
UTILIDAD (10%) 226,714.74
SUB TOTAL 2,765,919.82
IGV. (18%) 497,865.57
COSTO DE EJECUCION DE OBRA 3,263,785.39
EXPEDIENTE 35,000.00
SUPERVISION (5%) 113,357.37
LIQUIDACION (1%) 22,671.47
PRESUPUESTO TOTAL DE EJECUCION DE OBRA 3,434,814.23
PRESUPUESTO NUEVO MAYORES METRADOS ADICIONAL 01
2,450,794.85 287,056.12
272,057.69
245,079.49 28,705.61
2,967,932.03 315,761.73
534,227.76 56,837.11
3,502,159.79 372,598.84
35,000.00
122,539.74 14,352.81
22,671.47
3,682,371.01 386,951.65

1898 26000

589.2406
1898 138.554
MENORES METRADOS ADICIONAL 01 TOTAL ADICIONAL POR MAYORES METRADOS
-103,408.66 183,647.46

-10,340.87 18,364.75
-113,749.53 202,012.21
-20,474.91 36,362.20
-134,224.44 238,374.40

-5,170.43 9,182.37

-139,394.87 247,556.78
CUADRO RESUMEN MAYORES Y MENORES METRADOS 02

PRESUPUESTO PRESUPUESTO MAYORES PRESUPUESTO


DESCRIPCION CONTRATADO METRADOS 02 DEDUCTIVOS 01
COSTO DIRECTO 2,267,147.39 51,380.67 0.00
GASTOS GENERALES 12% 272,057.69
UTILIDAD 10% 226,714.74 5,138.07 0.00

SUBTOTAL 2,765,919.82 56,518.74 0.00


IGV 18% 497,865.57 10,173.37 0.00

COSTO DE EJECUCION DE OBRA 3,263,785.38 66,692.11 0.00


% DE INCIDENCIA

MONTO CONTRATO INCIDENCIA


SUPERVISOR DE OBRA 26,000.00 2.04340%
TOTAL ADICIONAL

51,380.67

5,138.07

56,518.74
10,173.37

S/ 66,692.11
2.04340%

MONTO ADICIONAL
S/ 531.28