Documentos de Académico
Documentos de Profesional
Documentos de Cultura
UNIVERSIDAD DE CANTABRIA
2
Cuaderno 3. PLANOS -110-
3
ESCUELA TÉCNICA SUPERIOR DE NÁUTICA
UNIVERSIDAD DE CANTABRIA
Cuaderno 1
MEMORIA
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
1.1.TÍTULO
Cálculo y diseño del circuito de refrigeración centralizada de los MMPP del
buque Tenerife Car
1.2.DESTINATARIO
5
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
1.4.INTRODUCCIÓN
6
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
1.5.NORMATIVA
El buque “Tenerife Car” pertenece a las series de “Short Sea Shipping Ro-
Ro / Car Carriers” de la Flota Suardiaz que, opera en líneas regulares
propias y está especializada en el tráfico ro-ro (carga rodada).
7
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
El Tenerife Car dispone de seis cubiertas fijas y dos cubiertas móviles. Tiene
una altura entre ellas de 1,80 m en el caso de los turismos, 2,70 m en el
caso de las furgonetas, car-deck extendido, y 4,55 m en el caso de los
trailers, car-deck recogido.
− Puntal: 15’40 m
8
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
El equipo propulsor del buque está compuesto por dos motores Wartsila
9L38B.
9
ESCUELA TÉCNICA SUPERIOR DE NÁUTICA
UNIVERSIDAD DE CANTABRIA
Cuaderno 2
CÁLCULOS
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
11
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Para poder calcular un enfriador debemos saber los siguientes datos para
las condiciones de diseño:
− Calor a disipar
12
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
En este caso sabemos que los fluidos que van a circular por los enfriadores
serán agua dulce, agua de mar y aceite de lubricación con las siguientes
densidades y calores específicos:
Para conocerlo debemos basarnos en los datos que nos facilita el fabricante
del motor, en el Project Guide de Wartsila ya que éste tiene los calores que
deben disiparse en los enfriadores de cada uno de los servicios, en función
del régimen del motor incluyendo en sus cálculos un coeficiente de
sobredimensionamiento o margen de seguridad del enfriador y por tanto,
también de caudal de las bombas necesario y que pasarán por el interior de
los enfriadores.
Estos son los datos que nos da el Project Guide de Wartsila, a falta del calor
a disipar por los enfriadores centrales, el cual tendremos que calcular
basándonos en estos datos, añadiéndole un 18% de margen de seguridad.
Por tanto:
13
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
14
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
AGUA DE MAR 32
AGUA B.T. 38 44
AGUA A.T. 75
ACEITE 45
LUBRICACIÓN
Siendo:
15
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Q=Sv
Siendo:
16
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Q: caudal (m3/s)
π D2/4 = Q/v
D2 = (4Q)/(π 3600 v)
17
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Dint = DN – 2e
Siendo:
PÉRDIDAS DE CARGA
1. Pérdidas primarias
La pérdida de energía por fricción es la energía que se utiliza para vencer los
esfuerzos de corte existentes en el sistema.
18
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
- Nº de Reynolds
Re = (v D) / µ
Siendo:
- Factor de fricción
∆PPR = (f L v2) / 2D
19
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Re = (v D)/ µ
f=
Procedimiento de cálculo:
Las pérdidas de carga se deben calcular para todo tramo de tubería donde
se encuentre una variación en la sección.
2. Pérdidas Secundarias
Siendo:
k: coeficiente de pérdida
20
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
- Entradas y salidas
- Aumentos y contracciones
- Codos de tuberías
- Válvulas y conectores
Procedimiento de cálculo.
∆Psec = (k v2) / 2g
Por tanto las pérdidas de carga totales serán la suma de las primarias y
secundarias:
CÁLCULO DE LA BOMBA
21
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Siendo:
Q: caudal (m3/s)
22
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Pe = Pb/µe
Más de 45 0’92
Entre 25 y 45 0’91
Entre 15 y 25 0’9
Entre 7 y 15 0’88
Entre 5 y 7 0’86
Ahora bien, para tomar un factor de seguridad que tenga en cuenta las
vibraciones, variaciones de caudal, sobrecargas, sobrecalentamientos,
tomaremos un motor con una potencia nominal igual a la potencia eléctrica
multiplicada por un factor K:
23
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Menor de 3 1’25
Pn = P e * K
- Caudal que tiene que suministrar para satisfacer las necesidades del
servicio al que se va a diseñar.
- Presión o altura de la columna de líquido que debe enviar el fluido
venciendo los cambios de altura (dif. entre aspiración y descarga),
cambios en el área (debido a reducciones, que provocan una
variación de la velocidad) y la fricción ocasionado por la rugosidad de
los materiales de las conducciones o por los accesorios (válvulas,
codos, …).
- Fluido a bombear ya que dependerá de que tipo de bomba
utilizaremos y su principio de funcionamiento. En nuestro caso será
agua.
24
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
25
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
TOMAS DE MAR
26
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
En el colector que une las dos tomas de mar se sitúan las aspiraciones de
todas las bombas. El colector deberá suministrar el suficiente caudal en las
peores condiciones de demanda y su dimensionamiento igual a 2.5 veces la
sección de todas las aspiraciones de cada una de las bombas. Como norma,
las aspiraciones deberán situarse de menor a mayor, es decir las tomas de
bombas pequeñas y con poca capacidad de aspiración deberán situarse
próximas a las cajas de mar y las mayores próximas al centro del colector.
ASPIRACIONES
BOMBAS
Tipo
27
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Características
ELEMENTO MATERIAL
CUERPO BRONCE RG – 5
TAPA BRONCE RG – 5
28
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
IMPULSOR GSnBz 10
Pruebas y Certificados
o Materiales:
o Producto:
Ph = 1,5 P cuando P = 4
Siendo:
Mantenimiento
29
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
INTERCAMBIADORES DE CALOR
Tipo
Tanto el BV como Wartsila no especifican cuál de los 2 tipos hay que utilizar,
luego podremos escoger libremente.
Nosotros nos decantamos por el tipo de Placas ya que representa una serie
de ventajas que lo hacen el idóneo para la instalación:
30
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Frente a estas numerosas ventajas, el único “pero” que puede haber es:
31
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Pruebas y Certificados
Mantenimiento
32
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
DESCARGA AL MAR
VÁLVULAS
Válvulas de Mariposa
Las válvulas de mariposa permiten una regulación del flujo por medio de un
disco circular; es de ¼ de vuelta y controla la circulación con el eje de su
orificio en ángulos rectos con el sentido de la circulación.
33
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
34
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
o Tipo
Utilizaremos válvulas tipo Lug, ya que según fabricante son las ideales para
incomunicación de circuitos.
o Ejecución
o Pruebas y Certificados
Todas las válvulas serán de PN 10 ya que las del costado del buque y/o las
que estén por debajo de la Línea de Flotación o que sean válvulas de
incomunicación deberán ser realizadas una prueba de Presión Hidrostática
soportando 1.5 veces la presión nominal de trabajo no siendo inferior a 6 bar
de presión sin signos aparentes de fugas, antes del montaje en presencia
35
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Válvulas intermedias
o Tipo
Serán válvulas de mariposa tipo Wafer, que son ideales para posiciones
intermedias, además de ser más baratas y más sencillo su montaje.
o Ejecución
o Pruebas y Certificados
Todas las válvulas serán de PN 10, ya que deben soportar como mínimo un
1.5 veces la presión máxima de descarga de las bombas, esto es 1,5*3 bar =
4,5 bar, no siendo menor a 4 bar según BV en Sección 2, Apartado 4.4 sobre
pruebas hidrostáticas.
Utilizaremos esta presión que es bastante superior debido a que no hay otra
ejecución disponible en el mercado.
36
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
- Poder aislar las bombas del circuito sin tener que interrumpir el
servicio, según BV en Sección 10, Apartado 2.7 sobre válvulas y
accesorios.
- Evitar que en la parada de la bomba, la columna de líquido retroceda
provocando importantes averías en las bombas, girando a
contrasentido la bomba en Standby, pudiendo provocar una parada
del motor por sobre intensidad.
- Permite tener el circuito presurizado.
o Tipo
o Ejecución
o Pruebas y Certificados
TUBERÍA
37
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Condiciones de diseño
Clasificación
Conduciremos agua de mar, por ello, según tabla 3, página 139 de BV, se
establece que la tubería que utilizaremos para conducir fluidos como agua
de mar será de clase II ya que trabajará a una presión menor de 4 bar y una
temperatura menor de 200ºC.
Material
Los codos serán de radio largo y las reducciones serán de acero negro
acorde a la norma DIN.
Forma de unión
38
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Según BV únicamente podremos utilizar bridas del tipo A1, A2, B1, B2, B3
para el agua de mar.
Soldadura
Tratamiento
Pruebas e Inspecciones
o Materiales
39
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Tests for the materials Inspections and tests for the product (1)
(1)
Equipo y DN del Servicio
correspondiente Tests Type of During After Type of
required material manufacturing completion product
(8) certificate (NDT) certificate
(2) (2)
40
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Forced NR 216 C
circulation Materials
pumps for
main
boiler:
casing and
bolts
(3) or alternative type of certificate, depending on the Survey Scheme. See Part A
(8) The material generally shall comply with [2.1.2] and Tab 5. Detail requirements are specified within
NR216 Materials, Ch 2.
(9) Attention is to be drawn to Tab 3 (valves and fittings fitted to the ship side are considered class II,
as well as valves on the collision bulkheads, on fuel oil tanks or on lubricating oil tanks under static
pressure)
41
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
2.3.2. CÁLCULOS
INTERCAMBIADORES DE CALOR
CENTRALES
o Datos
DATOS VALOR
Q (m3/h) 572
Tin (ºC) 32
o Cálculos:
Temperaturas
∆t = Qdisipar / φ ρ Ce
∆t = 8600*3600 / 572*1’025*3950= 13
Tout = 45ºC
De esta manera, con los datos obtenidos, el fabricante, Alfa Laval, nos da los
siguientes valores:
Sefectiva = 630 m2
42
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
TUBERÍA
DIÁMETROS DE TUBO
Consideraciones:
Datos:
DATOS Valor
v (m/s) 1.5
Q (m3/h) 572
Cálculos
D2 = (4 Q) / (π 3600 v)
43
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Dint = DN – 2 e
v’ = 4 Q / π Dint2 (m/s)
o Aspiración de bombas:
Datos:
DATOS Valor
v (m/s) 1.5
Q (m3/h) 215
Cálculos:
D2 = (4Q) / (π 3600 v)
Dint = DN – 2 e
v’ = 4 Q / π Dint2 (m/s)
44
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
• Descarga de bombas:
Datos:
DATOS Valor
v (m/s) 2.5
Q (m3/h) 215
Cálculos:
D2 = (4Q) / (π 3600 v)
Dint = DN – 2 e
v’ = 4 Q / π Dint2 (m/s)
Se unen los 2 ramales de las bombas sumando los caudales de cada una,
luego habrá una variación de diámetros.
Datos:
DATOS Valor
v (m/s) 2.5
Q (m3/s) 430
45
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Cálculos:
D2 = (4Q) / (π 3600 v)
Dint = DN – 2 e
v’ = 4 Q / π Dint2 (m/s)
Consideraciones:
Datos:
DATOS Valor
v (m/s) 1’34
Q (m3/h) 430
Cálculos:
D2 = (4Q) / (π 3600 v)
46
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Dint = DN – 2 e
v’ = 4 Q / π Dint2 (m/s)
Datos:
DATOS Valor
Cálculos:
Con los datos aportados, aproximadamente las medidas de los tubos para
nuestros cálculos de pérdidas de carga serán:
47
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
ASPIRACIÓN
DE BOMBAS
450 5100 5 - -
DEL
COLECTOR
ASPIRACIÓN
250 - - - -
DE BOMBAS
DESCARGA
250 4100 7 - 2
DE BOMBAS
DESCARGA
BOMBAS A
350 10200 4 - -
DESCARGA
MAR
Pérdidas de carga
Consideraciones de diseño:
Para realizar los cálculos, utilizaremos las mismas divisiones del circuito.
Datos
48
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
DATOS Valor
v (m/s) 1‘09
Cálculos
- Número Reynolds:
Re = (v D)/µ
- Rugosidad Relativa:
- Factor de Fricción:
f = 0’017
∆PPR = (f L v2)/2 D
49
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Datos
SALIDA DE
DEPOSITO
1 0’8 0’8
PENETRANDO
ASP.
VÁLVULAS DE
5 0’003 0’015
MARIPOSA
VALVULAS DE
2 2’5 5
CLAPETA
TOTAL 6’015
Cálculos
∆PSEC = k v2/2 g
2) Aspiración de Bombas
Datos
DATOS Valor
50
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
v (m/s) 1’17
Cálculos
- Número Reynolds:
Re = (v D)/µ
- Rugosidad Relativa:
- Factor de fricción:
f = 0’021
∆PPR = (f L v2)/2 D
Datos
51
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
MARIPOSA
TOTAL 0’009
Cálculos
∆PSEC = k v2/2 g
3) Descargas bombas:
Datos
DATOS Valor
v (m/s) 1’17
Cálculos
- Número Reynolds:
52
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Re = (v D)/µ
- Rugosidad Relativa:
- Factor de fricción:
f = 0’022
∆PPR = (f L v2)/2 D
Datos
VÁLVULAS DE
2 0’003 0’006
MARIPOSA
VÁLVULAS DE
3 5 15
ÁNGULO
TOTAL 16’166
Cálculos
∆PSEC = k v2 / 2g
53
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Datos
DATOS Valor
v (m/s) 1’34
Cálculos
- Número Reynolds:
Re = (v D)/µ
- Rugosidad Relativa:
- Factor de fricción:
f = 0’017
54
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
∆PPR = (f L v2)/2 D
Datos
VÁLVULAS
3 0’003 0’009
MARIPOSA
VÁLVULA DE
1 2’5 2’5
CLAPETA
TOTAL 3’069
Cálculos
∆PSEC = k v2 / 2g
55
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
CENTRAL 10’01
TOTAL 10’01
Ésta será la altura que tendrá que elevar la bomba para poder vencer las
pérdidas de carga del circuito. Debemos tener en cuenta que las pérdidas de
carga se han calculado partiendo de unas condiciones de diseño y que
además las dimensiones de la tubería son aproximadas.
Potencias
• Cálculo de la potencia al eje de la bomba
Datos
Para el cálculo del rendimiento, lo fijamos de la tabla que en función del tipo
y caudal nos establece un rendimiento:
DATOS Valor
Rendimiento η 0’71
56
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Peje = Q ρ ∆ P / 75 η (CV)
1 CV = 0’735 kW
34’6 CV – 25’5 kW
Datos
DATOS Valor
Pe = P b / µ
Pe = 25’5/0’91 = 28’02 kW
Pn = P e K
Selección de la bomba
57
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
BOMBA IL 125/315
58
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
59
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
BOMBAS
Tipo
Las bombas serán iguales a las utilizadas en el Circuito de Agua salada, tal y
como nos indica el Project Guide de Wartsila, es decir, centrífugas y no
autoaspirantes con la disposición del grupo electrobomba en vertical.
Características
Ejecución
60
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
ELEMENTO MATERIAL
IMPULSOR GSnBz 10
Pruebas y Certificados
Materiales
Producto
Ph = 1,5 P cuando P = 4
Siendo:
En nuestro caso, la presión que deberá soportar será 4 bar, no ser nunca
menor de ésta:
61
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Mantenimiento
INTERCAMBIADORES DE CALOR
Características
62
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
MM.PP.
Pruebas y Certificados
El fabricante establece las siguientes presiones para cada uno de los fluidos:
Mantenimiento
AGUA A.T.
ENFRIADOR DE AIRE
63
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
• Características
• Pruebas y Certificados
• Mantenimiento
TANQUE DE COMPENSACIÓN
• Normativa
64
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
- Una desaireación
- Indicador de nivel
- Una línea de alimentación
- Un drenaje
• Características
VÁLVULA TERMOSTÁTICA
Es una válvula que permitirá regular el flujo, recirculando todo o parte, como
válvula de mezcla, en función de la temperatura prefijada de salida del agua
de B.T. de los enfriadores. El sensor estará colocado a la descarga de las
bombas y después de la salida del agua de los Enfriadores Centrales.
Tipo
El sector, por acción del actuador se posiciona entre las bocas de la válvula
que le corresponda. Como se montará como válvula mezcladora, permitirá
65
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Será de 3 vías con actuador eléctrico regulado por un termostato, con tapa y
cuerpo de hierro fundido, GG 20, eje de A/inox, AISI 316 y sector de bronce.
Rg 5, cumpliendo las mismas condiciones de compatibilidad que las demás
válvulas.
Pruebas y certificados
VÁLVULAS
Tipo
Serán válvulas de mariposa tipo Wafer, que son ideales para posiciones
intermedias, además der ser más baratas y más sencillo su montaje.
Ejecución
Serán válvulas con el cuerpo de fundición nodular, GGG 40, accesorios, eje
y mariposa, de A/inox, AISI 316 y elastómero de E.P.D.M.
Pruebas y Certificados
66
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Ejecución
Será de las mismas características de los materiales que las válvulas del
circuito de agua de mar.
Pruebas y Certificados
TUBERIA
Condiciones de diseño
Tª de diseño: 44 ºC
Tratamiento
Pruebas e inspecciones
- Materiales
Se realizará las mismas pruebas que para las de agua de mar al tratarse del
mismo tipo de material.
- Producto
Se deberán realizar pruebas hidráulicas de todos los sistemas de tuberías,
de acuerdo a lo expuesto en el Circuito de Agua salada.
2.4.2 Cálculos
INTERCAMBIADORES DE CALOR
Centrales
- Datos
Los datos que tenemos son los siguientes para calcular las temperaturas en
el lado caliente:
67
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
DATOS Valor
Q (m3/h) 572
Tin (ºC) 45
- Cálculos
• Temperaturas:
∆t = Qdisipar/ Φ ρ Ce
Tout = 32 ºC
De esta manera, con los datos obtenidos, el fabricante, Alfa Laval, nos da los
siguientes valores:
Sefectiva = 630 m2
Datos
Los datos que tenemos son los siguientes para calcular las temperaturas:
DATOS Valor
Q (m3/h) 126
68
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Tin (ºC) 38
Cálculos
• Temperaturas
∆t = Qdisipar/Φ ρ Ce
∆t = 577*3600*1000/126*1000*4180 = 4ºC
Tout = 42ºC
Datos:
DATOS Valor
Q (m3/h) 142
Tin (ºC) 63
Cálculos:
• Temperaturas
69
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
∆t = Qdisipar/Φ ρ Ce
Tout = 74 ºC
Sefectiva= 90 m2
TUBERIA
Diámetros de tubo
• Descarga de bomba B.T. y Bypass hasta desvío enfriadores:
Consideraciones
Datos
DATOS Valor
v (m/s) 2’5
Q (m3/h) 126
70
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Cálculos
Din=DN – 2e
v’ = 1’09 m/s
Datos
DATOS Valor
v (m/s) 2’5
Q (m3/h) 142
Cálculos
Din=DN – 2e
71
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
v’ = 2’12 m/s
• Aspiración bombas
- Se unen los 2 ramales con el caudal inicial, luego:
Datos
DATOS Valor
v (m/s) 2’5
Q (m3/h) 126
Cálculos
Din=DN – 2e
v’ = 1’09 m/s
72
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
encuentran situados los equipos nos permiten saber las dimensiones del
buque. Por tanto, las dimensiones con las que aproximadamente
podremos estimar las longitudes de tubería son:
DATOS Valor
Cálculos
DESCARGA
BOMBAS A
200 6200 6 - -
SALIDA
TERMOSTÁT.
ENFRIADORES
EN SERIE
150 6500 6 2 2
ASPIRACIÓN
BOMBA
200 900 - 1 -
Pérdidas de Carga
Consideraciones de diseño:
Para realizar los cálculos, utilizaremos las mismas divisiones del circuito.
73
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Datos
DATOS Valor
v (m/s) 1’09
Cálculos
- Número de Reynolds:
Re = (v D)/µ
Re = 1’09 * 0’202/1’3 10-6= 1’7 105
- Rugosidad Relativa:
Rugosidad relativa = e/D
Rugosidad relativa = 0’15/202’7 = 0’0007
- Factor de Fricción:
f = 0’019
∆PPR = (f L v2)/2D
74
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
V. ÁNGULO 2 5 10
TOTAL 10’967
Cálculos
∆PSEC = k v2/2g
Datos
DATOS Valor
v (m/s) 2’12
Cálculos
- Número de Reynolds:
Re = (v D)/µ
Re = 2’12 * 0’154/1’3 10-6= 2’5 105
- Rugosidad Relativa:
Rugosidad relativa = e/D
75
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
f = 0’021
∆PPR = (f L v2)/2D
Datos
V. ÁNGULO 4 5 20
TOTAL 21’548
Cálculos
∆PPR = (f L v2)/2D
3) Aspiración Bombas
76
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Datos
DATOS Valor
v (m/s) 1’09
Cálculos
- Número de Reynolds:
Re = (v D)/µ
Re = 1’09 * 0’202/1’3 10-6= 1’69 105
- Rugosidad Relativa:
Rugosidad relativa = e/D
Rugosidad relativa = 0’15/202’7 = 0’0007
- Factor de Fricción:
f = 0’019
∆PPR = (f L v2)/2D
Datos
77
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
TOTAL 0’068
Cálculos
∆PSEC = (K v2)/2g
CENTRAL 10’01
TOTAL 22’67
Esta será la altura que tendrá que elevar la bomba para poder vencer las
pérdidas de carga del circuito. Debemos tener en cuenta que las pérdidas de
carga se han calculado partiendo de unas condiciones de diseño, por lo que
la presión será en condiciones normales de funcionamiento algo menor,
además que las dimensiones de la tubería son aproximadas.
78
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Potencias
• Cálculo de la potencia al eje de la bomba
Datos
Para el cálculo del rendimiento, lo fijamos de la tabla que en función del tipo
y caudal nos establece un rendimiento.
DATOS Valor
Rendimiento η 0’71
1 CV = 735 kW
Datos
DATOS Valor
Potencia bomba Pb 15
79
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Pe = Pb/µ
Pe = 15/0’88 = 17’04 kW
Pn = P e K
Pn = 17’04*1’16 = 19’76 kW
Selección de la bomba
80
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
BOMBA IL 100/315
BOMBAS
Tipo
81
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Las bombas serán iguales a las utilizadas en el Circuito de B.T., tal y como
nos indica el Project Guide Wartsila, es decir, centrífugas y no
autoaspirantes con la disposición del grupo electrobomba en vertical.
Características
Ejecución
En nuestro caso, el fluido será agua dulce tratada, los materiales a emplear
serán igual a los empleados en el Circuito de Agua De mar y, según el
catálogo de Bombas Itur serán:
ELEMENTO MATERIAL
EJE AISI-316L
IMPULSOR GSnBz 10
82
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Pruebas y certificados
- Materiales:
- Producto:
Siendo:
- Mantenimiento:
ENFRIADORES
AGUA A.T.
- Características
83
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
- Pruebas y Certificados
- Mantenimiento
TANQUE DE COMPENSACIÓN
DESAIREADOR
84
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
- Características
Según Project Guide Wartsila, el volumen será mínimo el 10% del volumen
total del sistema y las dimensiones serán:
- Principio de funcionamiento
- Condiciones de diseño
85
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
En función del régimen del motor producirá mayor o menor cantidad de agua
al variarse la cantidad de agua que se desvíe del circuito de A.T. ya que la
temperatura que el circuito debe mantenerse en todo momento es de 80 ºC,
mediante el uso de una válvula termostática situada a la entrada del agua de
A.T., debiendo funcionar únicamente para un régimen de carga del MM.PP.
por encima del 50% según condiciones recomendadas por Wartsila.
- Cálculos
Siendo:
Por tanto:
- Características
86
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
87
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
- Condiciones de diseño
- Características
88
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Design data:
where:
89
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
- Temperaturas:
CARACTERÍSTICAS TÉCNICAS
Tª ENTRADA 170 ºC 15 ºC
Tª SALIDA 165 ºC 24 ºC
CONDICIONES DE DISEÑO
Tª diseño 200 ºC 80 ºC
VÁLVULAS
Tipo
90
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Ejecución
Serán válvulas con el cuerpo de fundición nodular, GGG 40, accesorios, eje
y mariposa, de acero inoxidable, AISI 316 y elastómero de E.P.D.M.
Pruebas y Certificados
Tipo
Ejecución
Pruebas y Certificados
Todas las válvulas serán de PN 10 y cumplirán con los requisitos para las
válvulas intermedias en el circuito de agua de mar.
VÁLVULAS TERMOSTÁTICAS
Características
- Bypass Enfriadores:
91
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Ejecución
Pruebas y Certificados
TUBERIA
Condiciones de Diseño
Tratamiento
Pruebas e Inspecciones
- Materiales
Se realizará las mismas pruebas que para las de agua de mar al tratarse del
mismo tipo de material.
- Producto
2.5.2. Cálculos
ENFRIADORES
92
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Los datos que tenemos son los siguientes para calcular las temperaturas en
el lado caliente son:
DATOS Valor
Q (m3/h) 99
Tin (ºC) 73
- Cálculos
• Temperaturas:
∆t = Qdisipar/Φ ρ Ce
Tout = 84 ºC
TUBERIA
Diámetros de tubos
93
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Datos
DATOS Valor
v (m/s) 2’5
Q (m3/h) 99
Cálculos
D2 = 4Q/(π 3600 v)
Dint = 118’3 mm
Dint = DN-2e
v’ = 4Q/3600ρDint2
v’ = 2’2 m/s
Datos
94
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
DATOS Valor
v (m/s) 2’5
Q (m3/h) 50
Cálculos
D2 = 4Q/(π 3600 v)
Dint = 84’1 mm
Dint = DN-2e
v’ = 4Q/π Dint2
Para nuestro diseño se considerará que todo el flujo pasa a través del
Enfriador de A.T. ya que es la zona por donde mayor pérdida de carga
tendrá.
Datos
DATOS Valor
v (m/s) 2’5
Q (m3/h) 99
95
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Cálculos
D = 4Q/(π 3600 v)
Dint = 118’3 mm
Dint = DN-2e
v’ = 4Q/ρ Dint2
v’ = 2’20 m/s
• Aspiración bombas:
Datos
DATOS Valor
v (m/s) 2’2
Q (m3/h) 99
Cálculos
96
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
D2 = 4Q/(π 3600 v)
Dint = 126’1 mm
Dint = DN-2e
v’ = 4Q/ρ Dint2
v’ = 1’47 m/s
Datos
DATOS Valor
97
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Cálculos
Con los datos aportados, aproximadamente las medidas de los tubos serán
para cada uno de los ramales:
DESCARGA
DE BOMBA
125 12400 7 - 1
A.T. HASTA
ENTRADA A
TERMOSTÁTI
CA
GENERADOR
DE AGUA
DULCE
80 11200 2 - -
SALIDA DE
TERMOSTÁTI
CA A
125 19200 3 1 -
ASPIRACIÓN
BOMBAS
Pérdidas de Carga
Consideraciones de Diseño
Para realizar los cálculos, utilizaremos las mismas divisiones del circuito.
98
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Datos
DATOS Valor
v (m/s) 2’2
Cálculos
- Número de Reynolds:
Re = (v D)/µ
- Rugosidad Relativa:
- Factor de Fricción:
f = 0’023
∆PPR = (f L v2)/2D
Datos
99
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
VÁLVULAS 4 5 20
ÁNGULO
TOTAL 22’12
Cálculos
∆PSEC = Kv2/2g
Datos
DATOS Valor
v (m/s) 2’98
100
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Cálculos
- Número de Reynolds:
Re = (v D)/µ
- Rugosidad Relativa:
- Factor de Fricción:
f = 0’025
∆PPR = (f L v2)/2D
Datos
TOTAL 0’68
Cálculos
101
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
∆PSEC = Kv2/2g
Datos
DATOS Valor
v (m/s) 2’2
Cálculos
- Número de Reynolds:
Re = (v D)/µ
- Rugosidad Relativa:
- Factor de Fricción:
f = 0’023
102
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
∆PPR = (f L v2)/2D
Datos
TOTAL 1’708
Cálculos
∆PSEC = Kv2/2g
GENERADOR A.D. 6
TOTAL 11’394
103
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Consideraciones
Ésta será la altura que tendrá que elevar la bomba para poder vencer las
pérdidas de carga del circuito. Debemos tener en cuenta que:
Potencias
• Cálculo de la potencia al eje de la bomba
Datos
Para el cálculo del rendimiento, lo fijamos de la tabla que en función del tipo
y caudal nos establece un rendimiento.
DATOS Valor
Q caudal (m3/h) 99
104
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
η rendimiento 0’71
Peje = Q ρ ∆ P/75η
1 CV = 735 W
18’07 CV = 13’3 kW
Datos
DATOS Valor
Pe = Pb/µ
Pe = 13’3/0’88 = 15’11 kW
Pn = P e * K
Pn = 15’11*1’16 = 17’5 kW
Selección de la bomba
105
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
BOMBA IL 80/315
106
ESCUELA TÉCNICA SUPERIOR DE NÁUTICA
UNIVERSIDAD DE CANTABRIA
Cuaderno 3
PLANOS
ESCUELA TÉCNICA SUPERIOR DE NÁUTICA
UNIVERSIDAD DE CANTABRIA
Cuaderno 4
PLIEGO DE CONDICIONES
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
109
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
110
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
111
ESCUELA TÉCNICA SUPERIOR DE NÁUTICA
UNIVERSIDAD DE CANTABRIA
Cuaderno 5
PRESUPUESTO
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
1. OFICINA TÉCNICA
CÁLCULOS
80 h * 50 €/h = 4.000 €
2. ELECTROBOMBAS
Cantidad: 3 bombas
Modelo: IL-125/315
113
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Cantidad: 2 bombas
Modelo: IL-100/315
Cantidad: 2 bombas
Modelo: IL-80/315
OPERARIOS
- Conexión eléctrica: 1 h.
ENCARGADO DE OPERARIOS
114
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
CÁLCULOS
OPERARIOS:
3*7’5 h = 22’5 h
ENCARGADO DE OPERARIOS:
1*7’5 h = 7’5 h
3. INTERCAMBIADORES
Cantidad: 2
Modelo: T20-FG
Cantidad: 1
Cantidad: 1
Modelo: 30 kW
115
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
OPERARIOS:
ENCARGADO DE OPERARIOS:
CÁLCULOS
OPERARIOS:
2*19’5 h = 39 h
39 h * 30 €/h = 1170 €
ENCARGADO DE OPERARIOS:
1*19’5 h = 19’5 h
116
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Cantidad: 1
OPERARIOS:
ENCARGADO DE OPERARIOS
- Supervisión de trabajos: 8h
CÁLCULOS
OPERARIOS:
2*8 h = 16 h
16 h * 30 €/h = 480 €
ENCARGADO DE OPERARIOS:
1*8 h = 8 h
8 h * 40 €/h = 320 €
5. VÁLVULAS TERMOSTÁTICAS
Válvulas termostáticas
Cantidad: 2
Modelo: MV5321-150
117
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
OPERARIO:
ENCARGADO DE OPERARIO
CÁLCULOS
OPERARIO:
1’5 h * 30 €/h = 45 €
ENCARGADO DE OPERARIO:
1’5 h * 40 €/h = 60 €
6. VÁLVULAS
VÁLVULAS DE MARIPOSA
• DN 450
Tipo: WAFER
Cantidad: 5
118
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
• DN 350
Tipo: WAFER
Cantidad: 5
• DN 250
Tipo: WAFER
Cantidad: 3
• DN 200
Tipo: WAFER
Cantidad: 1
• DN 150
Tipo: WAFER
Cantidad: 5
• DN 125
Tipo: WAFER
Cantidad: 8
119
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
• DN 80
Tipo: WAFER
Cantidad: 2
VÁLVULAS DE ÁNGULO
• DN 250
Cantidad: 3
• DN 200
Cantidad: 2
• DN 150
Cantidad: 4
• DN 125
Cantidad: 4
• DN 450
Cantidad: 2
120
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
• DN 350
Cantidad: 1
OPERARIOS:
ENCARGADO DE OPERARIOS
CÁLCULOS
OPERARIOS:
15 h * 30 €/h = 450 €
ENCARGADO DE OPERARIOS:
15 h * 40 €/h = 600 €
7. TUBERÍA
121
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
incremento ya que los tubos se tienen que cortar varias veces y habrá
sobrantes que no se puedan utilizar.
- Las bridas serán planas para soldar y aptas para PN10, según norma
DIN 2576.
• TUBERÍA
DN DN DN DN DN DN DN
450 350 250 200 150 125 80
CODOS 5 4 7
BRIDAS 6 12 4
CIRCUITO
A/S JUNTAS 3 6 2
REDUCCIONES
ENSANCHAMIENTOS 2
CODOS 6 6
BRIDAS 8 7
CIRCUITO
A/D B.T. JUNTAS 4 4
REDUCCIONES 1 2
ENSANCHAMIENTOS 2
122
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
CODOS 10 2
CIRCUITO BRIDAS 32 13
REDUCCIONES 1
ENSANCHAMIENTOS
SUBTOTAL 4.099’68
• GALVANIZACIÓN
123
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
TOTAL 1.887’32
• CODOS
SUBTOTAL 1.472’12
• BRIDAS
124
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
SUBTOTAL 1.497’88
• JUNTAS
SUBTOTAL 77’03
OPERARIOS
ENCARGADO DE OPERARIOS
CÁLCULOS
125
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
• Pruebas: 375 €
CÁLCULOS
8. RESUMEN PRESUPUESTO
126
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
CONCEPTO IMPORTE €
127
ESCUELA TÉCNICA SUPERIOR DE NÁUTICA
UNIVERSIDAD DE CANTABRIA
Cuaderno 6
ANEXOS
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
129
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
130
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
131
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
DIAGRAMA DE MOODY
132
SOCIEDAD DE CLASIFICACIÓN BUREAU VERITAS
1 General
1.1 Application
1.1.1
1.2.1 Documents
Item
I/A (1) Document (2)
No
Drawing showing the arrangement of the sea chests and ship side
1 A
valves
Diagram of the bilge and ballast systems (in and outside machinery
2 A spaces), including calculation for the bilge main, bilge branch lines
and bilge pumps capacity as per Rule requirements
when provided
8 A Drawings of the fuel oil tanks not forming part of the ship’s structure
134
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
(2) Diagrams are also to include, where applicable, the (local and remote) control and
monitoring systems and automation systems.
Item
I/A (1) Document
No
1.3 Definitions
a) Piping includes pipes and their connections, flexible hoses and expansion
joints, valves and their actuating systems, other accessories (filters, level
gauges, etc.) and pump casings.
b) Piping systems include piping and all the interfacing equipment such as
tanks, pressure vessels, heat exchangers, pumps and centrifugal purifiers,
135
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Note 1: The equipment other than piping is to be designed in accordance with the relevant
Sections of Part C, Chapter 1.
136
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
b) The design pressure of a boiler feed system is not to be less than 1,25
times the design pressure of the boiler or the maximum pressure
expected in the feed piping, whichever is the greater.
Flammable oils include fuel oils, lubricating oils, thermal oils and hydraulic
oils.
137
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
1.4.1 The following symbols and related units are commoly used in this
Section. Additional symbols, related to some formulae indicated in this
Section, are listed wherever it is necessary.
T: design temperature, in ºC
• Cargo piping for oil tankers, gas tankers and chemical tankers, and
138
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Media
conveyed by
Class I Class II (1) (4) Class III (7)
the piping
system
Flammable
media:
• Heated
above
flashpoint,
Without special With special
or Not applicable
safeguards (3) safeguards (3)
• Having
flashpoint
<60ºC
Liquefied gas
139
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
(1) Valves under static pressure on oil fuel tanks or lubricating oil tanks belong to
class II.
(2) Pressure and temperature conditions other than those required for Class I and
Class III.
(3) Safeguards for reducing leakage possibility and limiting its consequences
(4) Valves and fittings fitted on the ship side and collision bulkhead belong to class II
(5) Steering gear hydraulic piping system belongs to class I irrespective of p and T.
(7) The open ended pipes, irrespecitive of T, generally belong to class III (as drains,
overflows, vents, exhaust gas lines, boiler escape pipes, etc)
(8) Design pressure for fuel oil systems is to be determined in accordance with Tab 4.
140
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
2.1 Materials
2.1.1 General
c) Materials for class III piping systems are to be manufactured and tested
in accordance with the requirements of acceptable national or
international standards or specifications.
b) Plastics intended for piping systems dealt with in this Section are to be
of a type approved by the Society.
141
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Maximu
Allowable m design
Material Particular conditions of use
classes temperat
ure (1)
Carbon and
carbon- Class I and II pipes are to be
III, II, I 400 (2)
manganese seamless drawn pipes (3)
steels
(4)
142
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
143
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
144
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
• Fire-extinguishing
systems
145
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
(1) Maximum design temperature is not to exceed that assigned to the class of piping
(2) Higher temperatures may be accepted if metallurgical behavior and time dependent
strength (ultimate tensile strength after 100 000 hours) are in accordance with national or
international standards or specifications and if such values are guaranteed by the steel
manufacturer
(3) Pipes fabricated by a welding procedure approved by the Society may also be used
(5) Use of spheroidal cast iron for class I piping systems will be given special consideration
by the Society
(6) Use of grey cast iron is not allowed when the design pressure exceeds 1,3 MPa
Minimum
Vent, Minimum
Sea water reinforced
overflow and extrareinforced
pipes, bilge wall
External Pipes in sounding wall thickness
and ballast thickness
diameter (mm) general (1) pipes for (mm) (3)
systems (mm) (2)
integral tanks
(1) (4)
(1) (5)
10,2 – 12 1,6 - - - -
20 2 - - - -
21,3 – 25 2 - 3,2 - -
146
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
(2) Reinforced wall thickness applies to pipes passing through tanks containing a fluid distinct
from that conveyed by the pipe and to pipe connections fitted to the tanks.
(3) Extra-reinforced wall thickness applies to pipes connected to the shell below the freeboard
deck.
(4) The minimum wall thickness for bilge lines and ballast lines through deep tanks is to be
subject to special consideration by the Society. The ballast lines within oil cargo tanks (where
permitted) is to be subject to special consideration by the Society (see Pt D, Ch 7, Sec 4,
[2.1.3]).
(5) For sounding pipes, except those for flammable cargoes, the minimum wall thickness is
intended to apply only to the part outside the tank.
147
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Where:
With:
• Equal to 10 for copper and copper alloy pipes, cold drawn seamless
steel pipes and steel pipes fabricated according to a welding
procedure approved by the Society,
• Equal to 12,5 for hot laminated seamless steel pipes,
• Subject to special consideration by the Society in other cases.
148
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
b) The thickness thus determined does not take into account the particular
loads to which pipes may be subjected. Attention is to be drawn in particular
to the case of high temperature and low temperature pipes.
Table 7: Minimum wall thickness for copper and copper alloy pipes
8 - 10 1 0,8
12 - 20 1,2 1
50 – 76,1 2 1,5
470 4 3,5
508 4,5 4
Note 1: a different thickness may be considered by the Society on a case by case basis,
provided that it complies with recognized standards.
10,2 to 17,2 1
60,3 to 88,9 2
149
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
219,1 2,6
273 2,9
Over 406,4 4
Table 9: Minimum wall thickness for aluminium and aluminium alloy pipes
0 - 10 1,5
12 - 38 2
43 - 57 2,5
76 - 89 3
108 - 133 4
219 - 273 5
Note 1: a different thickness may be considered by the Society on a case by case basis,
provided that it complies with recognized standards.
Note 2: for sea water pipes, the minimum thickness is not to be less than 5 mm.
150
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
b) Where, for carbon steel and alloy steel pipes, the value of the permissible
stress K is not given in Tab 10 or Tab 11, it is to be taken equal to the lowest
of the following values:
Where:
• 1,6 when Re and SR values result from tests attended by the Society
• 1,8 otherwise
c) The permissible stress values adopted for materials other than carbon
steel, alloy steel, copper and copper alloy will be specially considered by the
Society.
Table 10: Permissible stresses for carbon and carbon-manganese steel pipes
Specified
minimum Design temperature (ºC)
tensile
strength
(N/mm2) <50 100 150 200 250 300 350 400 410 420 430 440 450
151
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Specified
minimum Design temperature (ºC)
Type of
tensile
steel
strength <
100 200 300 350 400 440 450 460 470
(N/mm2) 50
1Cr1/2Mo 440 159 150 137 114 106 102 101 101 100 99
2
1/4Cr1Mo 410 76 67 57 50 47 45 44 43 43 44
annealed
2
1/4Cr1Mo
normalised
and 490 167 163 153 144 140 136 130 128 127 116
tempered
below
750ºC
2
1/4Cr1Mo
normalised
and 490 167 163 153 144 140 136 130 128 127 116
tempered
above
750ºC
1/2Cr
1/2Mo 460 166 162 147 120 115 111 106 105 103 102
1/4V
152
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
strength
480 490 500 510 520 530 540 550 560 570
(N/mm2)
1Cr1/2Mo 440 98 97 91 76 62 51 42 34 27 22
2
1/4Cr1Mo 410 42 42 41 41 41 40 40 40 37 32
annealed
2
1/4Cr1Mo
normalised
and 490 106 96 86 79 67 58 49 43 37 32
tempered
below
750ºC
2
1/4Cr1Mo
normalised
and 490 96 88 79 72 64 56 49 43 37 32
tempered
above
750ºC
1/2Cr
1/2Mo 460 101 99 97 94 82 72 62 53 45 37
1/4V
Table 12: Permissible stresses for copper and copper alloy pipes
Specified
minimum Design temperature (ºC)
Material
tensile
(annealed)
strength <
2
75 100 125 150 175 200 225 250 275 300
(N/mm ) 50
153
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
brass
Copper-
nickel 95/5 275 68 68 67 65,5 64 62 59 56 52 48 44
and 90/10
Copper-
nickel 365 81 79 77 75 73 71 69 67 65,5 64 62
70/30
Compressed air 1
Fuel oil 1
Thermal oil 1
Sea water 3
154
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Where:
D : as defined in [1.4.1]
t0 : as defined in [2.2.1]
t0/10
The values of corrosion allowance c are given for steel pipes in Tab 13 and
for non-ferrous metallic pipes in Tab 14.
Copper 0,8
Brass 0,8
(1) The corrosion allowance for other materials will be specially considered by the Society.
Where their resistance to corrosion is adequately demonstrated, the corrosion allowance
may be disregarded.
(2) In cases of media with high corrosive action, a higher corrosion allowance may be
required by the Society.
155
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
2.2.5 Tees
tT = [ 1 + (D1/D)] t0
where:
D : as defined in [1.4.1]
t0 : as defined in [2.2.1]
2.3.1 General
• The components, along the three principal axes, of the forces and
moments acting on each branch of piping
• The components of the displacements and rotations causing the
above forces and moments
• All parameters necessary for the computation of forces, moments and
stresses
In way of bends, the calculations are to be carried out taking into account,
where necessary, the pipe ovalisation and its effects on flexibility and stress
increase.
156
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
σID = (σ2+4τ2)0,5
Where:
K20 : value of the permissible stress for the material employed, calculated
according to [2.2.2], for a temperature of 20ºC, in N/mm 2
The sum of longitudinal stresses σL, in N/mm2, due to pressure, piping weight
and any other external loads is to be such as to satisfy the following
equation:
σ L < KT
157
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
2.4.1 General
c) The gaskets and packings used for the joints are to suit the design
pressure, the design temperature and the nature of the fluids conveyed.
a) Welded joints are to be used in accordance with Tab 15. Welding and non
destructive testing of welds are to be carried out in accordance with [3].
The expression “special provision for a high quality of root side” means that
butt welds were accomplished as double welded or by use of a backing ring
158
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
or inert gas back-up on first pass, or other similar methods accepted by the
Society.
c) Slip-on sleeve and socket welded joints are to have sleeves, sockets and
weldments of adequate dimensions in compliance with a standard
recognized by the Society.
a) In general, the metallic flange connections used for piping systems are to
be compliance with a standard recognized by the Society.
b) The material used for flanges and gaskets is to be suitable for the nature
and temperature of the fluid, as well as pipes on which the flanges are to be
fitted.
159
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Table 15: Use of welded and threaded metallic joints in piping systems
Permitted
Joints classes of Restrictions of use
piping
Butt-welded, without
special provision for a high III, II No restrictions
quality of root side (1)
160
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
(1) For expression “special provision for a high quality of root side” see [2.4.2] b).
(2) Particular cases may be allowed by the Society for piping systems of Class I and II
having outside diameter < 88,9 mm except for piping systems conveying toxic media or
services where fatigue, severe erosion or crevice corrosion is excepted to ocurr.
(3) In particular cases, sizes in excess of those mentioned above may be accepted by the
Society if found in compliance with a recognized national and/or international standard.
(4) May be accepted for accessory lines and instrumentation lines with external diameters
up to 25 mm.
161
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Table 16: Use of metallic flange connections in piping systems (types as shown in Fig
1)
(1) When design pressure p (see [1.3.2]) exceeds 1 MPa, types A1 and A2 only.
(2) For nominal diameter ND> 150 mm, types A1 and A2 only.
(3) When design temperature T (see [1.3.3]) exceeds 400ºC, types A1 and A2 only.
(4) For cargo piping of chemical carriers, IBC Code Ch. 5,5.3 is to be applied. For cargo
piping of gas carriers, IGC Code Ch.5,5.4 is to be applied.
(5) Type E2 only, for design pressure p< 1,6 MPa and design temperature T<150ºC.
(7) Types E1 only, for water pipelines and for open ended lines (e.g. drain, overflow, air vent
piping, etc).
162
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
b) Slip-on threaded joints may be used for piping systems in accordance with
Tab 15.
163
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
k) Slip-on joints are not to be used in pipelines in cargo holds, tanks, and
other spaces which are not easily accessible, unless approved by the
Society. Application of these joints inside tanks may be permitted only for the
same media that is in the tanks. Unrestrained slip-on joints are to be used
only in cases where compensation of lateral pipe deformation is necessary.
Usage of these joints as the main means of pipe connection is not permitted.
l) Application of mechanical joints are their acceptable use for each service is
indicated in Tab 17; dependence upon the class of piping, pipe dimensions,
working pressure and temperature is indicated in Tab 18.
164
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
1) leakage test
2.5.1 General
165
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Kind of connections
Systems
Compression
Pipe unions Slip-on joints
couplings (6)
166
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Inert gas
Sea water
20 Non-essential systems + + +
Fresh water
23 Non-essential systems + + +
Sanitary/Drains/Scuppers
167
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
25 Sanitary drains + + +
Sounding/Vent
Miscellaneous
31 Brine + + +
33 Steam + + - (7)
Note 1:
+ : application is allowed
(1) : inside machinery spaces of category A – only approved fire resistant types
(5) : In pump rooms and open decks – only approved fire resistant types
(6) : If compression couplings include any components which readily deteriorate in case of
fire, they are to be of approved fire resistant type as required for Slip-on joints
(7) : Restrained slip-on joints (which are provided with stopping bolts for axially restraining
the coupling from pull-out) may be accepted in steam lines on open decks provided that the
associated pipes are suitably supported and anchored
Table 18: Application of mechanical joints depending upon the class of piping
168
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Pipe unions
Compression couplings
Swage type + + +
Press type - - +
Slip-on joints
Grip type - + +
Slip type - + +
Note 1:
+ : application is allowed
b) When provided on the pump discharge for this purpose, safety valves are
to lead back to the pump suction or to any other suitable place.
169
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
2.6.1 General
a) Definitions:
170
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
e) Flexible hose assemblies and expansion joints intended for piping systems
with a design temperature below the ambient temperature are subject to
special consideration by the Society.
f) Specific requirements for flexible hoses and expansion joints intended for
cargo pipe lines are given in:
a) Unless otherwise specified, the Society may permit the use of flexible
hoses and expansion joints, both in metallic and non-metallic materials,
provided they are approved for the intended service. They may be accepted
for use in oil fuel, lubricating, hydraulic and thermal oil systems, fresh water
and sea water cooling systems, compressed air systems, bilge and ballast
systems, Class III steam systems and exhaust gas systems where they
comply with the requirements of this sub-article.
b) For steam systems, the flexible hose assemblies and expansion joints are
to be of metallic constructions.
171
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
g) The use of expansion joints in water lines for other services, including
ballast lines in machinery spaces, in duct keels and inside double bottom
water ballast tanks, and bilge lines inside double bottom tanks and deep
tanks, is to be subject to special consideration.
c) where rubber or plastics materials are intended for use in bilge, ballast,
compressed air, oil fuel, lubricating, hydraulic and thermal oil systems, the
construction is to incorporate a single o double closely woven integral wire
braid or equivalent reinforcement acceptable to be Society.
Rubber or plastics materials hoses used in oil supply lines to burners are to
have external wire braid protection in addition to the integral reinforcement.
172
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
e) Flexible hoses and expansion joints are to be complete with approved end
fittings in accordance with manufacturer’s specification. The end connections
that do not have a flange are to comply with [2.4.5] as applicable and each
type of hose/fitting combination is to be subject to prototype testing to the
same standard as that required by the hose with particular reference to
pressure and impulse tests.
f) The hose clamps and similar types of end attachments are not acceptable
for use in piping systems for steam, flammable media, starting air systems or
for sea water systems where failure may result in flooding. In other piping
systems, the use of hose clamps may be accepted where the working
pressure is less than 0,5 MPa and provided that there are double clamps at
each end connection.
g) The expansion joints intended for use in sea water systems are to be
provided with suitable guards which effectively enclose and reduce to the
minimum practicable any flow of water into the machinery spaces in the
event of failure of the flexible elements. However, the guards are not to
interfere with the action of the expansion joint.
2.6.4 Testing
173
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
c) For a particular flexible hose or an expansion joint type complete with end
fittings, the tests 8see Note 1, as applicable, are to be carried out on different
nominal diameters for pressure, burst, impulse resistance and fire resistence
in accordance with the requirements of the relevant standard recognized by
the Society.
• ISO 6802 – Rubber and plastics hoses and hose assemblies with wire
reinforcements – Hydraulic pressure impulse test with flexing
• ISO 6803 – Rubber and plastics hoses and hose assemblies with wire
reinforcements – Hydraulic pressure impulse test without flexing
• ISO 15540 – Ships and marine technology – Fire resistance of hose
assemblies – Test methods
• ISO 15541 – Ships and marine technology – Fire resistance of hose
assemblies – Requirements for test bench
• ISO 10380 – Pipework – Corrugated metal hoses and hose
assemblies
Note 2: The international standards, e.g. EN or SAE for burst testing of non-metallic hoses,
require the pressure to be increased until burst without any holding period at 4 MWP.
2.6.5 Marking
174
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
• Pressure rating
• Temperature rating
2.7.1 General
Valves and fittings in piping system are to be compatible with the pipes to
which they are attached in respect of their strength (see [1.3.2] for design
pressure) and are to be suitable for effective operation at the maximum
working pressure they will experience in service.
a) Materials of valve and accessory bodies are to comply with the provisions
of [2.1].
175
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
b) Connections of valves and accessories with pipes are to comply with the
provisions of [2.4].
e) Valves are to be provided with local indicators showing whether they are
open or shut, unless this is readily apparent.
a) All valves which are provided with remote control are also to be designed
for local manual operation.
2.8.1 General
a) Except where expressly stated in Article [8], the requirements of this sub-
article do not apply to scuppers and sanitary discharges.
c) The sea inlets are to comply also with the requirements specified for
particular service notations or additional class notations, such as:
176
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
a) All inlets and discharges in the shell planting are to be fitted with efficient
and accessible arrangements for preventing the accidental admission of
water into the ship.
b) Sea inlets and overboard discharges are to be fitted with valves complying
with [2.7] and [2.8.3].
h) Sea water suction lines are to be fitted with strainers having a free
passage area of at least twice that of the sea suction valve.
2.8.3 Valves
177
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
b) The bodies of the valves and distance pieces are to have a spigot passing
through the planting without projecting beyond the external surface of such
planting or of the doubling plates and stiffening rings, if any.
e) The materials of the valve bodies and connecting pieces are to comply
with Tab 5.
f) Ship side valves serving piping systems made of plastics are to comply
with Ch 1, App 3, [3.7.1].
2.8.4 Gratings
a) Gratings are to have a free flow area not less than twice the total section
of the pipes connected to the inlet.
c) Screws used for fixing gratings are not to be located in the corners of
openings in the hull or of doubling plates.
d) In the case of large sea inlets, the screws used for fixed the gratings are to
be locked and protected from corrosion.
178
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
2.9.1 General
• In passenger ships, they are not to require penetration below the top
of the tank and their failure or overfilling of the tanks is not to permit
release of fuel
179
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Note 1: On cargo ships of less than 500 tons gross tonnage and non-propeller ships:
• Cylindrical gauges may be used provided they are fitted with self-closing valves at
their lower end as well as at their upper end if the latter is below the maximum liquid
level
• In the case of tanks not subject to filling by power pumps, with the exception of fuel
oil service tanks, the valves need not be of the self-closing type. Such valves are,
however, to be readily accessible and instruction plates are to be fitted adjacement
to them specifying that they are to be kept closed.
3.1 Application
3.1.1
They may also be applied to Class III piping systems, at the discretion of the
Society.
b) This article does not apply to refrigerated cargo installation piping systems
operating at temperatures, lower than minus 40ºC.
3.2 General
180
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
b) When the design pressure exceeds 0,7 MPa, oxyacetylene welding is not
permitted for pipes with an external diameter greater than 100 mm or a
thickness exceeding 6 mm.
a) Except for the fixing of flanges on pipes in the cases mentioned in Fig 1
and for the fixing of branch pipes, joints between pipes and between pipes
and fittings are to be of the butt-welded type. However, for Class I pipes with
an internal diameter not exceeding 50 mm and for Class II pipes, socket
welded connections of approved types may be used.
3.3.3 Accessories
181
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
3.4.1 General
182
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
t (mm)
d<150 1 1 1
300<d 1 1,5 2
a) Pressure pipes are to be welded, both on board and in the shop, away
from draughts and sudden temperature variations.
3.4.5 Preheating
b) The temperatures given in Tab 20 are based on the use of low hydrogen
processes. Where low hydrogen processes are not used, the Society
reserves the right to require higher preheating temperatures.
3.5.1 General
183
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
t<13 100
1 Cr 0,5 Mo
t>13 150
t<13 150
2,25 Cr 1 Mo (1)
t>13 200
t<13 150
0,5 Cr 0,5 Mo V (1)
t>13 200
(1) For 2,25 Cr 1 Mo and 0,5 Cr 0,5 Mo V grades with thickness up to 6 mm, preheating
may be omitted if the results of hardness tests carried out on welding procedure
qualification are considered acceptable by the Society.
(2) For welding in ambient temperature below 0ºC, the minimum preheating temperature is
required independent of the thickness unless specially approved by the Society.
184
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
2,25 Cr 1 Mo
Any (2) 650 to 720
0,5 Cr 0,5 Mo V
(1) Where steels with specified Charpy V notch impact properties at low temperature are
used, the thickness above which post-weld heat treatment is to be applied may be
increased, subject to the special agreement of the Society.
(2) For 2,25 Cr 1 Mo and 0,5 Cr 0,5 Mo V grade steels, heat treatment may be omitted for
pipes having thickness lower than 8 mm, diameter not exceeding 100 mm and service
temperature not exceeding 450ºC.
(3) For C and C-Mn steels, stress relieving heat treatment may be omitted up to 30 mm
thickness, subject to the special agreement of the Society.
185
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
3.6.1 General
186
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Every weld for D>75 Every weld for D>75 Every weld for D>75
mm. Minimum 10% mm. Minimum 10% mm. Minimum 10%
of welds selected in of welds selected in of welds selected in
Frequency of testing
agreement with the agreement with the agreement with the
Surveyor for Surveyor for Surveyor for
D<75mm D<75mm D<75mm
Radiographic or
Magnetic particle or Magnetic particle or
Type of testing equivalent accepted
liquid penetrant liquid penetrant
by the Society
Radiographic or
Magnetic particle or Magnetic particle or
Type of testing equivalent accepted
liquid penetrant liquid penetrant
by the Society
187
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
5.1 General
188
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
• Bilge pipes
• Ballast pipes
• Scuppers and sanitary discharges
• Air, sounding and overflow pipes
• Fuel oil pipes
As far as possible, pipes are not to pass near switchboards or other electrical
apparatus. If this requirement is impossible to satisfy, gutterways or masks
are to be provided wherever deemed necessary to prevent projections of
liquid or steam of live parts.
5.3.1 General
For ships other than cargo ships, see also the additional requirements for the
relevant service notations.
189
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
b) Lead or other heat sensitive materials are not to be used in piping systems
which penetrate watertight subdivision bulkhead or decks.
• Bilge system
• Ballast system
• Scuppers and sanitary discharge systems
a) in ships other than passenger ships, pipes piercing the collision bulkhead
below the freeboard deck are to be fitted with suitable valves and the valve
chest is to be secured to the bulkhead inside the fore peak.
Such valves may be fitted on the after side of the collision bulkhead provided
that they are readily accessible under all service conditions and the space in
which they are located is not a cargo space. In all cases the valves are to be
operable from above the freeboard deck.
190
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
5.4.1 As a general rule, bilge and ballast lines are to be entirely independent
and distinct from lines conveying liquid cargo, lubricating oil and fuel oil, with
the exception of:
5.5.1 Principle
191
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
a) The assumed transverse extent of damage is not to contain any pipe with
an open end in an compartment located outside this extent, except where the
section of such pipe does not exceed 50 cm2.
Note 1: Where several pipes are considered, the limit of 50 cm 2 applies to their total section.
Where the valve is remote controlled by other than mechanical means, and
where the remote control system is located, even partly, within the assumed
extent of damage penetration, this system is to be such that the valve is
automatically closed by loss of power.
192
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
5.6.1 General
All pipes subject of thermal expansion and those which, due to their length,
may be affected by deformation of the hull, are to be fitted with expansion
pieces or loops.
5.7.1 General
Unless otherwise specified, the fluid lines referred to in this Section are to
consist of pipes connected to the ship’s structure by means of collars or
similar devices.
193
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
c) If galvanized steel pipes are used for sea water systems, the water velocity
is not to exceed 3 m/s.
d) If copper pipes are used for sea water systems, the water velocity is not to
exceed 2 m/s.
f) If aluminium bras pipes are used for sea water systems, the water velocity
is not to exceed 3 m/s.
g) If 90/10 copper-nickel-iron pipes are used for sea water systems, the water
velocity is not to exceed 3,5 m/s.
h) If 70/30 copper-nickel pipes are used for sea water systems, the water
velocity is not to exceed 5 m/s.
i) If GRP pipes are used for sea water systems, the water velocity is not to
exceed 5 m/s.
194
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
a) All pipes and other components where the temperature may exceed 220ºC
are to be efficiently insulated. Where necessary, precautions are to be taken
to protect the insulation from being impregnated with flammable oils.
5.9.1 General
a) In machinery spaces and tunnels, the cocks, valves and other accessories
of the fluid lines referred to in this Section are to be placed:
b) Control-wheels of low inlet valves are to rise at least 0,45 m above the
lowest floor.
195
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
• Orientation
• End connection support (where necessary)
• Avoidance of hose contact that could cause rubbing and abrasion
• Minimum bend radii
j) Where they are likely to suffer external damage, flexible hoses and
expansion joints of the bellows type are to be provided with adequate
protection.
5.9.4 Thermometers
196
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
5.9.6 Nameplates
a) Accessories such us cocks and valves on the fluid lines referred to in this
Section are to be provided with nameplates indicating the apparatus and
lines they serve except where, due to their location on board, there is no
doubt as to their purpose.
b) Nameplates are to be fitted at the upper part of air and sounding pipes.
5.10.1 General
All necessary precautions are to be taken to reduce fire risks from flammable
liquids, such us:
• Drips
• Leaks under pressure
• Overflow
• Hydrocarbon accumulation in particular under lower floors
• Discharges of oil vapours during heating
• Soot or unburnt residue in smoke stacks or exhaust pipes
197
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
In cargo ships of more than 400 tons gross tonnage and in passenger ships,
fuel oil, lubricating oil and other flammable oils are not to be carried in
forepeak tanks or tanks forward of the collision bulkhead.
c) Parts of flammable oil systems under pressure exceeding 0,18 MPa such
as pumps, filters and heaters are to comply with the provisions of b) above.
d) Pipe connections, expansion joints and flexible parts of flammable oil lines
are to be screened or otherwise suitably protected to avoid as far as
198
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
practicable oil spray or oil leakages onto hot surfaces, into machinery air
intakes, or on other sources of ignition.
e) Any relief valve or air vent cock fitted within the flammable liquid systems
is to discharge to a safe position, such as an appropriate tank.
a) Tanks used for the storage of flammable oils together with their fittings are
to be so arranged as to prevent spillages due to leakage or overfilling.
c) The coaming height of drip trays is to be appropriate for the service and
not less than 75 mm. In case of additional class notation AUT-IMS, see also
Pt E, Ch 3, Sec 4, [3.1.1].
e) Where drain pipes are provided for collecting leakages, they are to be led
to an appropriate drain tank.
199
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
f) The draining system of the room where thermal fluid heaters are fitted, as
well as the save all of the latter, are not to allow any fire extension outside
this room. See also [13.3.2].
a) The drain tank is not to form part of an overflow system and is to be fitted
with an overflow alarm device.
5.10.6 Valves
All valves and cocks forming part of flammable oil systems are to be capable
of being operated from readily accessible positions and, in machinery
spaces, from above the working platform.
10 Cooling systems
10.1 Application
10.1.1 This article applies to all cooling systems using the following cooling
media:
• Sea water
• Fresh water
• Lubricating oil
10.2 Principle
10.2.1 General
200
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
10.3.1 General
a) Sea water cooling of the propulsion engines, auxiliary engines and other
essential equipment is to be capable of being supplied by two different
means.
b) Where required, standby pumps are not to be connected to the sea inlet
serving the order sea water pumps, unless permitted under [10.7.1], item b).
• One main cooling water pump, which may be driven by the engines, of
a capacity sufficient to provide cooling water to all the equipment
served
• One independently driven standby pump of at least the same capacity
• Two heat exchangers, each having at least 50% of the total capacity
necessary to provide cooling water to all equipment served.
201
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
d) In Ships having one or more propulsion engines, each with an output not
exceeding 375 Kw, the independent standby pump may be replaced by a
complete spare pump of appropriate capacity ready to be connected to the
cooling circuit.
• One main cooling water pump, which can be driven by the engine
• One independently driven standby pump
• Two heat exchangers having an aggregate capacity of at least 100%
of that required by the engine.
Where the output of the engine does not exceed 375 kw, the following
arrangements may be accepted:
• One main cooling water pump, which can be driven by the engine
• One spare pump of appropriate capacity ready to be connected to the
cooling circuit
• One heat exchanger of appropriate capacity
b) Where, in ships having more than one engine per propeller or having
several propellers, each engine is served by its own cooling circuit, the
second means requested in [10.3.1] is to be provided, consisting of:
202
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
This second means may be omitted, however, when safety justifications are
provided as regards the propulsion and manoeuvring capabilities of the ship
with one cooling circuit disabled.
Where each auxiliary engine is served by its own cooling circuit, no second
means of cooling is required.
b) Where the installation includes more than one propulsive unit, the standby
pump is not required, provided a branch pipe fitted between the discharges of
the circulating pumps of each unit.
c) In lieu of the main circulating pump, a sea inlet scoop system may be
accepted, provided that and additional means is fitted to ensure the
circulation of sea water to the condenser when the ship is manoeuvring.
Such means may be:
203
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
10.4.1 General
• One main cooling water pump, which can be driven by the equipment
• One independently driven standby pump.
c) The standby pump may also be omitted in the case of redundancy of the
cooled equipment.
• A de-aerating device
• A water level indicator
• A filling connection
• A drain
204
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
If cooling water is used for heating of oil, the heating coils are to be located
on the pressure side of the cooling pumps and connected by welding, with no
detachable connections where mixing of oil and water may occur.
Alternatively a primary and secondary system arrangement may be used.
10.5.1 General
a) At least two sea inlets complying with [2.8] are to be provided for the
cooling system, one for each means of cooling required in [10.3.1].
b) The two sea inlets may be connected by a cross-over supplying both main
cooling pump and standby cooling pump.
c) When the second means of cooling is a spare pump, the two sea inlets are
to be provided in any event, both serving the main cooling pump.
205
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
e) One of the sea inlets may be that of the ballast pump or of the general
service pump.
H = high, HH = high
high
I = individual alarm
R = remote
Stand
Identification of system Slow- Shut-
Alarm Indication Control by Stop
parameter down down
Start
10.7.2 Coolers
a) Coolers are to be fitted with isolating valves at the inlets and outlets.
b) coolers external to the hull (chest coolers and keel coolers) are to be fitted
with isolating valves at the shell.
10.7.3 Filters
206
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
a) Where propulsion engines and auxiliary engines for essential services are
directly cooled by sea water, both in normal service and in emergency
operating conditions, filters are to be fitted on the suction of cooling pumps.
10.7.4 Pumps
a) Cooling pumps for which the discharge pressure may exceed the design
pressure of the piping system are to be fitted with relief valves in accordance
with [2.5].
Cocks are to be installed at the highest points of the pipes conveying cooling
water to the water jackets for venting air or gases likely to accumulate
therein. In the case of closed fresh water cooling systems, the cock is to be
connected to the expansion tank
207
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Cuaderno 7
REFERENCIAS BIBLIOGRÁFICAS
208
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
Páginas de Internet:
− Wartsila. http://www.wartsila.com/en/Home.
− Bombas hidráulicas.
o http://www.hidrotecar.es
o http://www.itur.es
− Intercambiadores de calor.
o http://www.termojet.es
o http://www.alfalaval.com
− Válvulas.
http://www.ttv.es
http://www.asturfluid.com
− Evaporadores. http://www.gefico.com
− Tuberías. http://www.quiminet.com/sh2/sh_aasdvcdaasdarm.htm
Libros:
209
PROYECTO FIN DE CARRERA ITN DIEGO SAIZ PINTO
210