GEOVOLADURAS S.A. DE C.V.

Cliente: WEG
Obra: ESTABILIZACION DE TALUD WEG
Lugar: PARQUE QUMA ATOTONILCO DE HIDALGO HIDALGO

ANALISIS DE BASICOS
Código Concepto Unidad Costo Cantidad Importe %
Partida: A Análisis No.: 1
Análisis: BANQUETA ML
BANQUETA DE CONCRETO HECHO EN OBRA DE F´C:150KG/CM2 REFORZADO CON MALLA ELECTROSOLDADA 6-6/6-6. INCLUYE:
MATERIAL, MANO DE OBRA, HERRAMIENTA Y TODO LO NECESARIO PARA SU CORRECTA EJECUCION.TOPOGRAFO, SANITARIOS,
LABORATORIO Y SEGURISTA SERA PROPORCIONADO POR WEG.P.U.O.T.
MATERIALES
CONCR150 CONCRETO F´C:150KG/CM2 M3 $1,300.00 0.200000 $260.00 58.38%
SUBTOTAL: MATERIALES $260.00 58.38%
MANO DE OBRA
MO SOBRE SOBRESTANTE JOR $857.15 / 25.000000 $34.29 7.70%
MO CUAD 2 2 OF + 2 AYTES JOR $2,930.24 / 25.000000 $117.21 26.32%
SUBTOTAL: MANO DE OBRA $151.50 34.02%
EQUIPO Y HERRAMIENTA
%MO HERRAMIENTA MENOR 3% %MO $151.50 0.030000 $4.55 1.02%
VIBRADOR CON VIBRADOR DE CONCRETO HRA $50.00 / 5.000000 $10.00 2.25%
BAILARINA BAILARINA COMPACTADORA HRA $55.00 / 21.000000 $2.62 0.59%
MAQ CORTADORA CONCRETO HRA $250.00 / 15.000000 $16.67 3.74%
CORTADORA
SUBTOTAL: EQUIPO Y HERRAMIENTA $33.84 7.60%
Costo Directo: $445.34
INDIRECTOS 12% 53.44
SUBTOTAL 498.78
FINANCIAMIENTO
SUBTOTAL 498.78
UTILIDAD 10% 49.88
PRECIO UNITARIO 548.66
(* QUINIENTOS CUARENTA Y OCHO PESOS 66/100 M.N. *)

DIRECTOR GENERAL ING. GONZALO ORTIZ ARELLANO


GEOVOLADURAS S.A. DE C.V.
Cliente: WEG
Obra: ESTABILIZACION DE TALUD WEG
Lugar: PARQUE QUMA ATOTONILCO DE HIDALGO HIDALGO

ANALISIS DE BASICOS
Código Concepto Unidad Costo Cantidad Importe %
Partida: A Análisis No.: 2
Análisis: TRINCHERA ML
CONFORMACION DE TRINCHERA
MATERIALES
ANG 2"X1/4 ANGULO 2" X1/4" ML $141.66 2.100000 $297.49 27.69%
VAR 3/8 VARILLA 3/8 KG $19.00 2.684000 $51.00 4.75%
ALAMBRE REC ALAMBRE RECOCIDO KG $25.00 0.100000 $2.50 0.23%
REDONDO 3/8 REDONDO 3/8 KG $19.00 0.195700 $3.72 0.35%
MALLA1010 MALLA ELECTROSOLDADA 1010 M2 $22.28 1.900000 $42.33 3.94%
RETIRO EXC RETIRO EXCAVA M3 $130.00 0.564000 $73.32 6.82%
POLIN POLIN 4X4 3ER PZA $60.00 / 0.800000 $75.00 6.98%
TRIPLAY 3/4 TRIPLAY 3/4 M2 $233.33 / 4.000000 $58.33 5.43%
CLAVO CLAVO KG $40.00 0.100000 $4.00 0.37%
CONCR150 CONCRETO F´C:150KG/CM2 M3 $1,300.00 0.222000 $288.60 26.86%
SUBTOTAL: MATERIALES $896.29 83.42%
MANO DE OBRA
MO EXCAVA MO EXCAVACION 1 OF + 2 AYTE JOR $1,020.00 / 15.000000 $68.00 6.33%
MO SOBRE E MO SOBREESTANTE EXCAVA JOR $525.00 / 20.000000 $26.25 2.44%
MO SOLDADOR MO SOLDADOR JOR $375.00 / 40.000000 $9.38 0.87%
MO COLADO 1 OF + 2 AYTE JOR $1,020.00 / 35.000000 $29.14 2.71%
MO COL SOBRE SOBRESTANTE COLADO JOR $525.00 / 35.000000 $15.00 1.40%
SUBTOTAL: MANO DE OBRA $147.77 13.75%
EQUIPO Y HERRAMIENTA
PLANTA SOLDAR PLANTA SOLDAR HRA $200.00 / 10.000000 $20.00 1.86%
GEN GENERADOR GASOLINA HRA $126.56 / 30.000000 $4.22 0.39%
VIBRADOR CON VIBRADOR DE CONCRETO HRA $50.00 / 30.000000 $1.67 0.16%
%MO HERRAMIENTA MENOR 3% %MO $147.77 0.030000 $4.43 0.41%
SUBTOTAL: EQUIPO Y HERRAMIENTA $30.32 2.82%
Costo Directo: $1,074.38
INDIRECTOS 12% 128.93
SUBTOTAL 1203.31
FINANCIAMIENTO
SUBTOTAL 1203.31
UTILIDAD 10% 120.33
PRECIO UNITARIO 1323.64
(* UN MIL TRESCIENTOS VEINTITRES PESOS 64/100 M.N. *)