MATERIAL> MADERA PARA ENCOFRADO

PARTIDA METRADO APORTE P.U CANT. MATERIAL


M2 P2 P2
04.04 CIMIENTOS CORRIDOS 98.23 5.17 507.85
04.06 SOBRECIMIENTO 33.57 4.63 155.43
05.02 ZAPATAS 242 5.74 1389.08
05.06 VIGAS DE CIMENTACIÓN 229 5.47 1252.63
05.09 SOBRECIMIENTO ARMADO
05.12 PLACAS

ESTRUCTURAS S/. 445,637.34


ARQUITECTURA S/. 68,375.14
INS. SANITARIAS S/. 7,511.89
INS. ELÉCTRICAS S/. 5,815.06
S/. 527,339.43
REAJUSTES S/. 25,897.42
DEDUCCIÓN DE REAJUSTE
--- POR ADELANTO DIRECTO S/. 2,586.00
--- POR ADELANTO DE MATERIALES S/. 1,425.63

VAL. BRUTA: VB = VM + R -D S/. 549,225.22


AMORTIZACIÓN DE ADELANTOS
--- AD. DIRECTO S/. 42,187.15
--- AD. MATERIALES S/. 15,108.27

VAL. NETA: VN = VB - A S/. 491,929.80


IGV (18%) 88547.36
TOTAL S/. 580,477.16
5 decimales
P. UNIT. MAT FR Ima Imo AMORTIZ.
S/. I.U:43 (Set-2015) I.U: 43 (Mar-2015) S/.
5 0.9 688.08 677.34 S/. 2,321.56
5 0.9 688.08 677.34 S/. 710.53
5 0.9 688.08 677.34 S/. 6,349.97
5 0.9 688.08 677.34 S/. 5,726.21
0.9 688.08 677.34 S/. 0.00
S/. 15,108.27

A. DIRECTO 406264.76
MONTO CONTRATO 5078309.44
% A. DIRECTO 8.00%

MONTO POR AMORTIZAR S/. 42,187.15


26.35
47.14