VALORIZACIONES CONTRACTUALES CONTRACTUAL

VALORIZACION N°01 - OCTUBRE 2022 S/ 487,400.71


VALORIZACION N°02 - NOVIEMBRE 2022 S/ 4,324,006.77
VALORIZACION N°03 - DICIEMBRE 2022 S/ 1,729,392.96
VALORIZACION N°04 - ENERO 2023 S/ 4,899,276.36
VALORIZACION N°05 - FEBRERO 2023 S/ 6,539,471.21
VALORIZACION N°06 - MARZO 2023 S/ 4,816,773.04 ADICIONAL N°01 ADI. VINC. N°01 MM N°01 MM N°02 ADICIONAL N°03 ADICIONAL N°05 TOTAL DE MES
VALORIZACION N°07 - ABRIL 2023 S/ 4,917,436.38 Apr-23 S/ 183,208.99 S/ 5,100,645.37
VALORIZACION N°08 - MAYO 2023 S/ 5,413,006.40 May-23 S/ 676.27 S/ 55,077.67 S/ 5,468,760.34
VALORIZACION N°09 - JUNIO 2023 S/ 9,709,281.11 Jun-23 S/ 2,256.37 S/ 189,831.30 S/ 150,941.09 S/ 10,052,309.87
VALORIZACION N°10 - JULIO 2023 S/ 10,285,963.06 Jul-23 S/ 155,997.18 S/ 29,873.35 S/ 510,167.99 S/ 584,407.17 S/ 11,566,408.75
TOTAL S/ 42,836,044.94 TOTAL S/ 186,141.63 S/ 345,828.48 S/ 55,077.67 S/ 180,814.44 S/ 510,167.99 S/ 584,407.17

VALOR CONTRACTUAL S/ 73,843,631.22 Inc/IGV


RETENCION POR CARTA FIANZA S/ 7,384,363.12 Inc/IGV

DESCRIPCION MONTO (INC/IGV) % INC.


VALOR CONTRACTUAL S/ 73,843,631.22 100.00%
MONTO DEL ADICIONAL DE OBRA N°01 - HDPE S/ 186,141.63 0.25%
MONTO DEL ADICIONAL DE OBRA N°02 - ENCAUSAMIENTO - 0.00%
MONTO DEL ADICIONAL DE OBRA N°03 - REPOSICION S/ 2,017,440.28 2.73%
MONTO DEL ADICIONAL DE OBRA N°04 - GAVIONES - -
MONTO DEL ADICIONAL DE OBRA N°05 - BADENES Y ALC. S/ 1,459,494.12 1.98%
MONTO DEL ADICIONAL VINCULANTE DE OBRA N°01 S/ 345,828.48 0.47%
MONTO DEL DEDUCTIVO VINCUALNTE DE OBRA N°01 -S/ 642,297.51 -0.87%
REDUCCION DE METAS N°01 (ALCANTARILLAS Y CUNETAS) -S/ 4,120,169.04 -5.58%
REDUCCION DE METAS N°02 (PAVIMENTO) -S/ 245,137.37 -0.33%
TOTAL S/ 72,844,931.81 98.65%
SALDO A FAVOR DE LA ENTIDAD S/ 998,699.41 1.35%

MAYOR METRADO N°01 - PERFILADO S/ 55,077.67 0.07%


MAYOR METRADO N°02 - OBRAS DE ARTE S/ 180,814.44 0.24%
TOTAL S/ 235,892.11 0.32%

TOTAL S/ 73,080,823.92 98.97%


SALDO A FAVOR DE LA ENTIDAD S/ 762,807.30 1.03%

PLAZO DE EJECUCION 365 DIAS CALENDARIOS


AMPLIACION DE PLAZO N°01 9 APROBADO
REDUCCION DE METAS N°01 0 APROBADO
REDUCCION DE METAS N°02 -1 APROBADO 8/7/2023
ADICIONAL DE OBRA N°05 44.00 DIAS CALENDARIOS 44.00 9/20/2023
TOTAL DE PLAZO DE EJECUCION 417 DIAS CALENDARIOS 7/25/2023
13.00 8/7/2023

FECHA DE INICIO 10/26/2022


SUSPENSION N°01 3.00
INICIO DE SUSPENSION N°01 12/13/2022
TERMINO DE SUSPENSION N°01 12/15/2022
SUSPENSION N°02 7.00
INICIO DE SUSPENSION N°02 1/18/2023
TERMINO DE SUSPENSION N°02 1/24/2023
SUSPENSION N°03 5.00
INICIO DE SUSPENSION N°03 3/15/2023
TERMINO DE SUSPENSION N°03 3/19/2023

NUEVA FECHA DE TERMINO 10/28/2023 CON SUS N°01


NUEVA FECHA DE TERMINO 11/4/2023 CON SUS N°02
NUEVA FECHA DE TERMINO 11/9/2023 CON SUS N°03
NUEVA FECHA DE TERMINO 11/18/2023 CON AMPLIACION N°01
NUEVA FECHA DE TERMINO 11/17/2023 CON REDUCCION DE METAS N°02
NUEVA FECHA DE TERMINO 12/31/2023 CON ADICIONAL N°05 Y N°03

COMPROBACION 12/31/2023 FECHA DE TERMINO


TOTAL DE PLAZO DE EJECUCION 417.00 DIAS CALENDARIOS
TOTAL DE TIEMPO 432.00 DIAS CALENDARIOS
1362385.93

ADICIONALES, DEDUCTIVO, REDUCCIONES Y MAYORES METRADOS


DESCRIPCION TRAMITADO A EJECUTAR DEDUCIR OBSERVACION
MONTO DEL ADICIONAL DE OBRA N°01 - HDPE S/ 186,141.63 S/ 186,141.63 RESOLUCION GERENCIAL N°028-2023-GIDUR-JCBP-MDCH/AD
MONTO DEL ADICIONAL DE OBRA N°02 - ENCAUSAMIENTO DENEGADO DENEGADO ENCAUSAMIENTO
MONTO DEL ADICIONAL DE OBRA N°03 - REPOSICION S/ 2,017,440.28 S/ 2,017,440.28 REPOSICION DE CARPETA
MONTO DEL ADICIONAL DE OBRA N°04 - GAVIONES S/ 2,053,975.15 S/ 1,362,385.93 S/ 691,589.22 DEDUCIRA 4 BADENES Y 4 ALCANTARILAS QUE NO SE EJECUTARAN
MONTO DEL ADICIONAL VINCULANTE DE OBRA N°01 S/ 345,828.48 S/ 345,828.48 ALCANTARILLAS
MONTO DEL DEDUCTIVO VINCUALNTE DE OBRA N°01 -S/ 642,297.51 -S/ 642,297.51 BADENES
MONTO DEL ADICIONAL DE OBRA N°05 - (ALC. Y BAD) S/ 1,539,490.88 S/ 1,539,490.88 CONTRAPENDIENTES
REDUCCION DE METAS -S/ 4,120,169.04 -S/ 4,120,169.04 OBRAS DE ARTE
MAYORES METRADOS (PERFILADO) S/ 55,077.67 S/ 55,077.67 SE PRESENTO LA VALORIZACION - MAYO 2023
MAYOR METRADO (EJE KM 42+000) S/ 1,285,144.57 S/ 1,285,144.57 RIO SOCAVADO
MAYOR METRADO DEL KM 37+ S/ 300,000.00 S/ 300,000.00 tramo socavado
REDUCCION DE CARPETA ASFALTICA -S/ 245,137.38 -S/ 245,137.38 19+360 - 19+650, EXISTENTE
MAYOR METRADO DE CARPETA POR (50M MOD EJE) S/ 40,000.00 S/ 40,000.00 MODIFICACION DE EJE

SALDO A FAVOR DEL CONTRATISTA S/ 2,815,494.73 S/ 2,123,905.51


S/ 1,466,206.06 SIN ENCAUSAMIENTO
S/ 761,439.66 SIN GAVIONES
CONTROL DE ALCANTARILLAS
CANT. ALCANTARILLA REPLANTEO REPLANTEO ENTERRADO ENCOFRADO VACIADO EMBOQUILLADO DIFERENCIA
1 01 OJO TMC 1.50 m 3+880.00 9.72 VAL N°06 VAL N°06 VAL N°06 VAL N°08 - 2.43
2 01 OJO TMC 1.50 m 4+610.00 17.01 VAL N°04 VAL N°06 VAL N°06 VAL N°08 5.67
3 01 OJO TMC 0.90 m 5+135.00 10.53 VAL N°04 VAL N°05 VAL N°05 VAL N°08 - 0.81
4 01 OJO TMC 0.90 m 26+030.00 7.95 NO SE REQUIERE DE SU EJECUCION - 3.39
5 01 OJO TMC 1.20 m 5+830.00 15.01 VAL N°04 VAL N°05 VAL N°05 VAL N°08 2.86
6 01 OJO TMC 1.20 m 6+420.00 9.72 VAL N°05 VAL N°05 VAL N°05 VAL N°08 -
7 01 OJO TMC 1.20 m 6+800.00 13.25 VAL N°05 VAL N°05 VAL N°05 VAL N°08 - 2.14
8 01 OJO TMC 1.20 m 10+800.00 10.60 VAL N°05 VAL N°06 VAL N°06 VAL N°08 - 0.74
9 01 OJO TMC 1.20 m 35+880.00 8.83 NO SE REQUIERE DE SU EJECUCION DEDUCTIVO - 0.89
10 01 OJO TMC 1.20 m 17+980.00 7.95 VAL N°05 VAL N°06 VAL N°06 VAL N°08 GAVIONES - 0.96
11 01 OJO TMC 1.20 m 18+040.00 8.83 VAL N°05 VAL N°06 VAL N°06 VAL N°08 CANAL - 0.08
12 01 OJO TMC 1.20 m 37+150.00 8.83 NO SE REQUIERE DE SU EJECUCION OPONE LA POBLACION - 11.26
13 01 OJO TMC 1.20 m 18+360.00 8.83 VAL N°05 VAL N°06 VAL N°06 VAL N°08 - 0.08
14 01 OJO TMC 1.20 m 18+533.00 15.89 VAL N°06 VAL N°06 VAL N°06 2.93
15 01 OJO TMC 1.20 m 18+760.00 14.13 VAL N°06 VAL N°07 VAL N°07 5.22
16 01 OJO TMC 1.20 m 18+840.00 12.36 VAL N°06 VAL N°07 VAL N°07 3.45
17 01 OJO TMC 1.20 m 19+879.78 8.83 NO INTERVENIR POR EXISTENCIA DE CANAL - 0.08
18 01 OJO TMC 1.20 m 20+058.16 8.83 FIRMARON ACTA DE ACUERDOS - NO EJECUTAR - 0.08
19 01 OJO TMC 1.20 m 20+412.22 16.77 VAL N°08 VAL N°09 VAL N°09 6.24
20 01 OJO TMC 1.20 m 20+448.20 8.83 - 1.70
OPOSICION DE LA POBLACION
21 01 OJO TMC 1.20 m 20+596.00 7.95 - 0.96
22 01 OJO TMC 0.90 m 22+147.22 7.95 NO INTERVENIR POR EXISTENCIA DE CANAL - 0.15
23 01 OJO TMC 0.90 m 22+194.64 7.95 NO INTERVENIR POR EXISTENCIA DE CANAL - 0.96
24 01 OJO TMC 0.90 m 22+307.35 7.95 VAL N°08 VAL N°09 VAL N°09 - 0.94
25 01 OJO TMC 0.90 m 22+370.42 7.95 - 0.96
26 01 OJO TMC 1.20 m 22+617.26 8.83 - 0.89
27 01 OJO TMC 0.90 m 22+712.00 8.83 NO INTERVENIR POR EXISTENCIA DE CANAL - 0.08
28 01 OJO TMC 0.90 m 22+795.10 7.95 - 0.96
29 01 OJO TMC 0.90 m 22+965.00 8.83 - 0.08
30 01 OJO TMC 0.90 m 33+435.00 7.95 NO SE REQUIERE DE SU EJECUCION - 0.96
31 01 OJO TMC 0.90 m 23+166.95 7.95 NO INTERVENIR POR EXISTENCIA DE CANAL - 0.15
32 01 OJO TMC 0.90 m 23+299.50 8.83 VAL N°08 VAL N°09 VAL N°09 - 0.08
33 01 OJO TMC 1.20 m 23+425.63 8.83 VAL N°08 VAL N°08 VAL N°09 - 0.89
34 01 OJO TMC 0.90 m 36+630.00 9.72 NO SE REQUIERE DE SU EJECUCION 0.81
35 01 OJO TMC 0.90 m 23+573.28 7.95 VAL N°08 VAL N°09 VAL N°09 - 1.77
36 01 OJO TMC 0.90 m 23+723.98 7.95 VAL N°08 VAL N°08 VAL N°09 - 4.20
37 01 OJO TMC 0.90 m 23+788.34 8.83 VAL N°08 VAL N°08 VAL N°08 - 1.70
38 01 OJO TMC 0.90 m 23+877.82 7.95 VAL N°09 VAL N°09 VAL N°09 - 2.58
39 01 OJO TMC 0.90 m 23+931.64 7.95 VAL N°09 VAL N°09 VAL N°09 - 2.58
40 01 OJO TMC 0.90 m 24+360.00 7.95 VAL N°08 VAL N°08 VAL N°08 - 2.58
41 01 OJO TMC 0.90 m 24+490.00 7.95 VAL N°09 VAL N°09 VAL N°09 - 0.96
42 01 OJO TMC 0.90 m 24+737.29 7.95 VAL N°09 VAL N°09 VAL N°09 - 1.77
43 01 OJO TMC 1.20 m 25+105.00 8.83 VAL N°08 VAL N°08 VAL N°08 - 0.89
44 01 OJO TMC 0.90 m 25+245.83 7.95 VAL N°08 VAL N°08 VAL N°08 - 1.77
45 01 OJO TMC 0.90 m 25+309.00 7.95 VAL N°08 VAL N°08 VAL N°08 - 1.68
46 01 OJO TMC 0.90 m 25+449.22 11.48 VAL N°08 VAL N°08 VAL N°08 1.76
47 01 OJO TMC 0.90 m 25+614.57 7.95 VAL N°08 VAL N°08 VAL N°08 - 0.96
48 01 OJO TMC 1.20 m 25+840.00 7.95 VAL N°08 VAL N°08 VAL N°08 - 2.58
49 01 OJO TMC 0.90 m 26+100.00 7.95 VAL N°08 VAL N°08 VAL N°08 - 3.39
50 01 OJO TMC 0.90 m 26+181.13 7.95 VAL N°08 VAL N°08 VAL N°08 - 0.15
51 01 OJO TMC 1.20 m 26+267.29 8.83 VAL N°08 VAL N°08 VAL N°08 - 1.95
52 01 OJO TMC 0.90 m 26+387.82 7.95 VAL N°08 VAL N°08 VAL N°08 - 2.58
53 01 OJO TMC 0.90 m 26+468.80 7.95 VAL N°08 VAL N°08 VAL N°08 - 0.15
54 01 OJO TMC 0.90 m 26+547.10 9.72 VAL N°08 VAL N°08 VAL N°08 -
55 04 OJO TMC 1.80 m 26+954.30 70.64 VAL N°07 VAL N°08 VAL N°08 - 21.36
56 01 OJO TMC 0.90 m 28+240.00 7.95 VAL N°07 VAL N°08 VAL N°08 - 1.77
57 01 OJO TMC 0.90 m 28+335.40 7.95 OPOSICION DE LA POBLACION - 0.96
58 01 OJO TMC 1.20 m 28+465.00 7.95 VAL N°07 VAL N°08 VAL N°08 - 2.58
59 01 OJO TMC 1.20 m 28+704.30 7.95 OPOSICION DE LA POBLACION - 5.01
60 01 OJO TMC 0.90 m 28+910.10 10.60 VAL N°07 VAL N°08 VAL N°08 0.88
61 01 OJO TMC 1.50 m 29+090.00 8.83 VAL N°07 VAL N°08 VAL N°08 - 1.70
62 01 OJO TMC 1.50 m 29+698.30 8.83 VAL N°07 VAL N°08 VAL N°08 - 1.70
63 01 OJO TMC 1.20 m 32+242.00 8.83 - 0.89
DEDUCIDO POR QUE EXISTE
64 03 OJO TMC 1.80 m 8+926.00 34.44 5.28
65 01 OJO TMC 1.50 m 31+444.90 9.72 VAL N°07 VAL N°08 VAL N°08 -
66 01 OJO TMC 1.20 m 31+600.00 8.83 VAL N°07 VAL N°07 VAL N°07 - 0.89
67 04 OJO TMC 1.50 m 32+727.30 42.40 VAL N°08 VAL N°09 VAL N°09 0.28
68 01 OJO TMC 1.80 m 33+225.70 9.72 VAL N°11 VAL N°11 VAL N°11 -
69 01 OJO TMC 1.50 m 46+938.00 7.95 DEDUCIDO POR QUE EXISTE - 1.77
70 01 OJO TMC 1.50 m 33+835.00 10.60 VAL N°11 VAL N°11 VAL N°11 - 1.04
71 01 OJO TMC 1.20 m 38+237.00 13.25 VAL N°10 VAL N°11 VAL N°11 1.91
72 02 OJO TMC 1.50 m 38+524.00 28.26 VAL N°10 VAL N°11 VAL N°11 5.58
73 01 OJO TMC 1.20 m 38+839.00 15.01 VAL N°10 VAL N°11 VAL N°11 2.86
74 01 OJO TMC 1.50 m 39+040.00 8.83 FIRMARON ACTA DE ACUERDOS - NO EJECUTAR - 2.21
75 01 OJO TMC 1.80 m 40+382.30 10.60 VAL N°09 VAL N°10 VAL N°10 - 3.17
76 03 OJO TMC 1.80 m 36+961.50 26.49 - 5.10
DEDUCIDO POR QUE EXISTE
77 01 OJO TMC 1.50 m 34+362.02 11.48 1.76
78 01 OJO TMC 1.50 m 41+370.00 7.95 VAL N°09 VAL N°09 VAL N°09 - 3.39
79 02 OJO TMC 1.50 m 41+766.00 17.66 VAL N°09 VAL N°09 VAL N°09 - 0.16
80 01 OJO TMC 1.50 m 46+370.00 9.72 VAL N°09 VAL N°10 VAL N°10 - 0.81

LONGITUD SALDOS POR DEDUCTIVO


DIAMETRO DE TUBERIA
REPLANTEO DED. REP REPLANTEO EXP. TEC
TMC 0.90 M 278.17 90.98 187.19 216.97 224.81
TMC 1.20 M 290.53 68.88 221.65 210.04 231.72
TMC 1.50 M 198.96 19.43 179.53 170.4 181.45
TMC 1.80 M 151.89 60.93 90.96 115.49 115.31
TOTAL 919.55 240.22 679.33 712.9

PTO. FINAL SALDO


DIFERENCIA EXP - REP. TMC 0.90 M 221.27 34.08
REPLANTEO - DEDUC TMC 1.20 M 229.86 8.21
TMC 1.50 M 181.44 1.91
TMC 1.80 M 115.49 24.53
CONTROL DE BADENES BADEN
CANT. LONGITUD PROYECTO REPLANTEO EXCAVACION AFIRMADO
1 60 7+753.00 DEDUCIDO
2 60 8+137.00 8+137.00 VAL N°05 VAL N°05
3 50 8+770.00 8+811.00 VAL N°05 VAL N°05
4 50 8+926.00 DEDICTIVO VINCULANTE N°01
5 60 9+326.00 9+326.00 VAL N°05 VAL N°05
6 35 34+895.00 34+900.00 VAL N°09 VAL N°09
7 35 36+955.00 DEDUCTIVO VINCULANTE N°01
8 30 39+462.00 39+520.50 VAL N°07 VAL N°07
9 90 42+005.00 42+034.14 VAL N°09 VAL N°09
10 70 46+845.00 DEDUCIDO
11 80 47+440.00 47+446.04 VAL N°07 VAL N°07
BADEN
ENCOFRADO ACERO VACIADO
DEDUCIDO
VAL N°05 VAL N°05 VAL N°06
VAL N°06 VAL N°06 VAL N°06
DEDICTIVO VINCULANTE N°01
VAL N°07 VAL N°07 VAL N°07
VAL N°09 VAL N°09 VAL N°09
DEDUCTIVO VINCULANTE N°01
VAL N°08 VAL N°08 VAL N°08
VAL N°10 VAL N°10 VAL N°10
DEDUCIDO
VAL N°07 VAL N°07 VAL N°07
BADENES ADICIONALES VALORIZADO - ADICIONAL
CANT. O. ARTE PROYECTO LONGITUD (m) OBSERVACIÓN EXCAVACION

1 BADEN N°01 20+832.11 30.00 VALO N°01


2 BADEN N°02 21+570.00 20.00 VALO N°01
3 BADEN N°03 22+370.00 15.00 VALO N°01
4 BADEN N°04 22+860.00 30.00 VALO N°01
5 BADEN N°05 23+166.95 20.00 VALO N°01
6 BADEN N°06 23+987.65 20.00 VALO N°01
7 BADEN N°07 23+987.65 20.00 VALO N°01

ALCANTARILLAS ADICIONALES TIPO ALIVIADEROS VALORIZADO - A


CANT. O. ARTE PROYECTO DIAMETRO LONGITUD (m) ENTERRADO
1 ALCANTARILLA 33+061.500 0.90 7.07 VALO N°02
2 ALCANTARILLA 33+435.000 0.90 7.07 VALO N°02
3 ALCANTARILLA 34+040.000 0.90 7.95 VALO N°02
4 ALCANTARILLA 34+400.000 0.90 7.07 VALO N°02
5 ALCANTARILLA 35+010.000 0.90 7.07 VALO N°02
6 ALCANTARILLA 39+853.388 0.90 8.83 VALO N°01
7 ALCANTARILLA 41+223.388 0.90 7.07 VALO N°02
8 ALCANTARILLA 42+810.000 0.90 7.07 VALO N°01
9 ALCANTARILLA 44+060.000 0.90 9.72 VALO N°01
10 ALCANTARILLA 44+490.000 0.90 8.83 VALO N°01
11 ALCANTARILLA 44+830.000 0.90 7.07 VALO N°01
12 ALCANTARILLA 45+140.000 0.90 8.83 VALO N°01

ALCANTARILLAS ADICIONALES TMC VALORIZADO - A


CANT. O. ARTE PROYECTO DIAMETRO LONGITUD (m) ENTERRADO
1 ALCANTARILLA 32+242.000 1.20 8.83 VALO N°01
2 ALCANTARILLA 35+880.000 1.20 8.83 VALO N°02
3 ALCANTARILLA 36+630.000 0.90 9.72 VALO N°02
4 ALCANTARILLA 37+135.000 0.90 7.07 VALO N°02
5 ALCANTARILLA 37+328.710 1.80 14.13 VALO N°02
6 ALCANTARILLA 38+123.388 0.90 9.72 VALO N°02
7 ALCANTARILLA 39+320.000 0.90 7.07 VALO N°01
8 ALCANTARILLA 40+033.388 1.80 7.95 VALO N°01
9 ALCANTARILLA 46+938.000 1.20 7.95 VALO N°01
VALORIZADO - ADICIONAL N°05
ENCOFRADO VACIADO

VALO N°01 VALO N°01


VALO N°01 VALO N°01
VALO N°01 VALO N°01
VALO N°01 VALO N°01
VALO N°01 VALO N°01
VALO N°01 VALO N°01
VALO N°01 VALO N°01

VALORIZADO - ADICIONAL N°05


ENCOFRADO VACIADO EMBOQUILLADO
VALO N°02 VALO N°02
VALO N°02 VALO N°02
VALO N°02 VALO N°02
VALO N°02 VALO N°02
VALO N°02 VALO N°02
VALO N°01 VALO N°01
VALO N°02 VALO N°02
VALO N°02 VALO N°02
VALO N°02 VALO N°02
VALO N°01 VALO N°01
VALO N°01 VALO N°01
VALO N°01 VALO N°01

VALORIZADO - ADICIONAL N°05


ENCOFRADO VACIADO EMBOQUILLADO
VALO N°01 VALO N°01
VALO N°02 VALO N°02
VALO N°02 VALO N°02
VALO N°02 VALO N°02

VALO N°02 VALO N°02


VALO N°01 VALO N°01
VALO N°02 VALO N°02
VALO N°01 VALO N°01