Documentos de Académico
Documentos de Profesional
Documentos de Cultura
"CONSTRUCCION DE PISTAS Y MEJORAMIENTO DE VEREDAS EN EL A.H. SAN FRANCISCO DE ASIS, PROVINCIA DE SANTA - ANCASH"
"CONSTRUCCION DE PISTAS Y MEJORAMIENTO DE VEREDAS EN EL A.H. SAN FRANCISCO DE ASIS, PROVINCIA DE SANTA - ANCASH"
ME 1 ME 2 ME 3 ME 4 ME 5 ME 6
ITEM DESCRIPCION UNID. PARCIAL (S/.)
0-15 16-30 0-15 16-30 0-15 16-30 0-15 16-30 0-15 16-30 0-15 16-30
01 OBRAS PROVISIONALES 22,519.20 22,519.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
01.01 CARTEL DE OBRA DE 3.60x4.80m CON GIGANTOGRAFIA und 2,519.20 2,519.20
01.02 OFICINA, ALMACEN Y CASETA DE GUARDIANIA GLB 10,000.00 10,000.00
01.03 MOVILIZACION Y DESMOVILIZACION DE EQUIPO Y MAQUINARIA GLB 10,000.00 10,000.00
02 TRABAJOS PRELIMINARES 93,520.86 56,533.63 3,362.48 3,362.48 3,362.48 3,362.48 3,362.48 3,362.48 3,362.48 3,362.48 3,362.48 3,362.48 3,362.48
02.01 TRAZO, NIVELACION Y REPLANTEO INICIAL m2 48,035.37 48,035.37
02.02 TRAZO, NIVELACION PERMANENTE EN OBRA m2 40,349.71 3,362.48 3,362.48 3,362.48 3,362.48 3,362.48 3,362.48 3,362.48 3,362.48 3,362.48 3,362.48 3,362.48 3,362.48
02.03 MANTENIMIENTO DE TRANSITO Y SEGURIDAD VIAL und 5,135.78 5,135.78
03 MOVIMIENTO DE TIERRAS 1,102,362.14 132,406.40 185,093.52 175,599.54 52,687.12 154,933.83 401,641.73 0.00 0.00 0.00 0.00 0.00 0.00
03.01 DEMOLICION DE PAVIMENTO ASFALTICO DE 2" m2 18,987.95 9,493.98 9,493.98
03.02 CORTE DE MATERIAL SUELTO A NIVEL DE SUB RASANTE m3 218,899.98 72,966.66 72,966.66 72,966.66
03.03 ACARREO DE MATERIAL EXCEDENTE m3 149,837.28 49,945.76 49,945.76 49,945.76
03.04 MEJORAMIENTO Y ESTABILIZACION DEL SUELO A NIVEL DE SUBRASANTE CON GRAVA DE DEm3 2 263,435.62 52,687.12 52,687.12 52,687.12 52,687.12 52,687.12
03.05 CONFORMACION DE SUB RASANTE PARA PAVIMENTO m2 204,493.41 102,246.71 102,246.71
03.06 ELIMINACION DE MATERIAL EXCEDENTE m3 246,707.90 246,707.90
04 PAVIMENTACION 2,020,230.21 0.00 0.00 0.00 0.00 208,199.00 430,314.52 845,642.02 536,074.68 0.00 0.00 0.00 0.00
04.01 BASE DE AFIRMADO E= 0.15 M. m2 347,227.07 173,613.54 173,613.54
04.02 SUB - BASE DE MATERIAL GRANULAR E= 0.20m, IP=0 m2 416,397.99 208,199.00 208,199.00
04.03 IMPRIMACION ASFALTICA RC-250 m2 161,673.31 48,501.99 113,171.32
04.04 BARRIDO Y LIMPIEZA A NIVEL DE IMPRIMADO m2 22,782.49 22,782.49
04.05 CARPETA ASFALTICA EN CALIENTE e=2" m2 1,072,149.35 536,074.68 536,074.68
05 SEÑALIZACION 90,766.17 0.00 0.00 0.00 0.00 0.00 0.00 0.00 8,084.81 82,681.36 0.00 0.00 0.00
05.01 PINTADO DE PAVIMENTOS (SIMBOLOS - Y LETRAS) m2 40,424.04 8,084.81 32,339.23
05.02 PINTADO DE PAVIMENTOS ( LINEA DISCONTINUA) m 16,780.73 16,780.73
05.03 PINTADO DE PAVIMENTOS ( LINEA CONTINUA) m 33,561.40 33,561.40
06 VARIOS 87,993.33 377.00 377.00 377.00 377.00 81,346.28 377.00 377.00 377.00 377.00 377.00 1,627.00 1,627.00
06.01 ENCIMADO DE BUZONES DE CONCRETO EXIST. H PROM. =0.50M. INCL. TAPA NUEVA und 80,969.28 80,969.28
06.02 SEÑALIZACION Y SEGURIDAD DE OBRA GLB 4,524.05 377.00 377.00 377.00 377.00 377.00 377.00 377.00 377.00 377.00 377.00 377.00 377.00
06.03 LIMPIEZA FINAL DE OBRA - PAVIMENTO GLB 2,500.00 1,250.00 1,250.00
01 VEREDAS 1,221,229.31 0.00 0.00 33,901.55 85,978.94 34,596.44 422,043.89 555,332.65 68,768.10 11,594.48 6,337.76 1,337.76 1,337.76
01.01 TRABAJOS PRELIMINARES 141,599.15 0.00 0.00 33,901.55 85,978.94 12,354.36 1,337.76 1,337.76 1,337.76 1,337.76 1,337.76 1,337.76 1,337.76
01.01.01 TRAZO, NIVELACION Y REPLANTEO-VEREDAS m2 14,378.62 14,378.62
01.01.02 TRAZO, NIVELACION PERMANENTE EN OBRA m2 13,377.57 1,337.76 1,337.76 1,337.76 1,337.76 1,337.76 1,337.76 1,337.76 1,337.76 1,337.76 1,337.76
01.01.03 DEMOLICION DE VEREDAS EXISTENTES CON EQUIPO m2 90,925.87 18,185.17 72,740.70
01.01.04 ACARREO DE MATERIAL DE DEMOLICION m3 7,179.08 7,179.08
01.01.05 ELIMINACION DE MATERIAL EXCEDENTE C/VOLQUETE 15 m3. d=15km m3 15,738.01 4,721.40 11,016.61
01.02 MOVIMIENTO DE TIERRAS 252,109.94 0.00 0.00 0.00 0.00 22,242.07 126,525.68 103,342.19 0.00 0.00 0.00 0.00 0.00
01.02.01 CORTE SUPERFICIAL MANUAL HASTA 0.20 M m2 19,838.85 9,919.43 9,919.43
01.02.02 ACARREO DE MATERIAL EXCEDENTE m3 17,603.78 12,322.65 5,281.13
01.02.03 PREPARACION DE SUB-RASANTE PARA VEREDAS m2 41,770.79 41,770.79
01.02.04 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 41,570.63 41,570.63
01.02.05 AFIRMADO DE 4" PARA VEREDAS m2 93,279.00 27,983.70 65,295.30
01.02.06 ELIMINACION DE MATERIAL EXCEDENTE m3 38,046.89 38,046.89
01.03 OBRAS DE CONCRETO SIMPLE 650,390.67 0.00 0.00 0.00 0.00 0.00 256,563.00 393,827.67 0.00 0.00 0.00 0.00 0.00
01.03.01 CONCRETO P/VEREDA F´C=175Kg/cm2, E=4", ACABADO 1:2, Inc. Encofrado m2 526,912.58 210,765.03 316,147.55
01.03.02 SARDINEL SUMERGIDO CONCRETO F'C=175KG/CM2(0.15X0.20) PARA VEREDAS m 114,494.91 45,797.96 68,696.95
01.03.03 RAMPA DE ACCESO F´C=175Kg/cm2, FROTACHADO Y BRUÑADO m2 8,983.18 8,983.18
01.04 JUNTAS 6,430.62 0.00 0.00 0.00 0.00 0.00 0.00 6,430.62 0.00 0.00 0.00 0.00 0.00
01.04.01 JUNTAS DE DILATACION ASFALTICA e=1", @ 4m m 6,430.62 6,430.62
01.05 PINTURA 10,256.72 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 10,256.72 0.00 0.00 0.00
01.05.01 PINTADO DE BORDE VEREDAS P=0.30m m 10,256.72 10,256.72
01.06 SUMINISTRO Y REPOSISCION DE CAJAS DOMICILIARIAS 112,852.38 0.00 0.00 0.00 0.00 0.00 37,617.46 37,617.46 37,617.46 0.00 0.00 0.00 0.00
01.06.01 SUM. NIVELACION Y COLOCACION DE CAJAS AGUA und 44,618.16 14,872.72 14,872.72 14,872.72
01.06.02 SUM. NIVELACION Y COLOCACION DE CAJAS DESAGUE und 68,234.22 22,744.74 22,744.74 22,744.74
01.07 VARIOS 47,589.83 0.00 0.00 0.00 0.00 0.00 0.00 12,776.95 29,812.88 0.00 5,000.00 0.00 0.00
01.07.01 CURADO DE VEREDAS m2 42,589.83 12,776.95 29,812.88
01.07.02 LIMPIEZA FINAL DE OBRA GLB 5,000.00 5,000.00
02 AREAS VERDES 250,764.61 0.00 0.00 0.00 0.00 131,311.75 61,531.50 17,017.47 30,903.89 2,500.00 2,500.00 2,500.00 2,500.00
02.01 TRABAJOS PRELIMINARES 14,665.19 0.00 0.00 0.00 0.00 9,182.58 5,482.61 0.00 0.00 0.00 0.00 0.00 0.00
02.01.01 NIVELACION Y TRAZO DE TRATAMIENTO DE LOS JARDINES m2 2,100.10 2,100.10
02.01.02 CORTE SUPERFICIAL MANUAL HASTA 0.20 M m2 3,752.63 3,752.63
02.01.03 ACARREO DE MATERIAL EXCEDENTE m3 3,329.85 3,329.85
02.01.04 ELIMINACION DE MATERIAL EXCEDENTE m3 5,482.61 5,482.61
02.02 SUMINISTRO DE AREAS VERDES 96,647.04 0.00 0.00 0.00 0.00 23,926.69 21,426.69 17,017.47 24,276.20 2,500.00 2,500.00 2,500.00 2,500.00
02.02.01 TRANSPORTE DE PLANTAS A OBRA GLB 2,500.00 2,500.00
02.02.02 MEJORAMIENTO DE SUELOS CON MATERIAL ORGANICO E=0.20 M m2 37,853.37 18,926.69 18,926.69
02.02.03 SUMINISTRO Y SEMBRADO DE GRASS AMERICANO m2 23,238.77 9,295.51 13,943.26
02.02.04 SUMINISTRO DE PLANTAS ORNAMENTALES und 13,054.90 5,221.96 7,832.94
02.02.05 RIEGO PERMANENTE HASTA ENTREGA DE OBRA GLB 20,000.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00 2,500.00
02.03 SARDINEL SUMERGIDO PARA JARDINERA Y PROTECCION DE PAVIMENTO 139,452.38 0.00 0.00 0.00 0.00 98,202.48 34,622.21 0.00 6,627.69 0.00 0.00 0.00 0.00
02.03.01 EXCAVACION DE ZANJA PARA SARDINELES H=0.50M m3 4,562.48 2,281.24 2,281.24
02.03.02 ACARREO DE MATERIAL EXCEDENTE m3 1,517.02 606.81 910.21
02.03.03 RELLENO COMPACTADO CON MATERIAL DE PRESTAMO m3 4,298.94 1,719.58 2,579.36
02.03.04 ELIMINACION DE MATERIAL EXCEDENTE C/VOLQUETE 15 m3. d=15km m3 3,325.61 3,325.61
02.03.05 SARDINEL DE CONCRETO F'C=175KG/CM2 m3 29,959.07 14,979.54 14,979.54
02.03.06 ENCOFRADO Y DESENCOFRADO CARAVISTA EN SARDINELES m2 54,007.42 54,007.42
02.03.07 ACEROPARA SARDINELES FY=4200 KG/CM2 GRADO 60 kg 35,154.15 24,607.91 10,546.25
02.03.08 PINTADO DE SARDINELES m2 6,627.69 6,627.69
COSTO DIRECTO 4,889,385.83 211,836.23 188,833.00 213,240.58 142,405.54 613,749.77 1,319,271.13 1,421,731.62 647,570.95 100,515.32 12,577.24 8,827.24 8,827.24
GASTOS GENERALES (10 %) 488938.58 21183.62 18883.3 21324.06 14240.55 61374.98 131927.11 142173.16 64757.1 10051.53 1257.72 882.72 882.72
UTILIDAD (10 %) 488938.58 21183.62 18883.3 21324.06 14240.55 61374.98 131927.11 142173.16 64757.1 10051.53 1257.72 882.72 882.72
SUB TOTAL 5,867,262.99 254,203.47 226,599.60 255,888.70 170,886.64 736,499.73 1,583,125.35 1,706,077.94 777,085.15 120,618.38 15,092.68 10,592.68 10,592.68
IGV (18 %) 1056107.34 45756.62 40787.93 46059.97 30759.6 132569.95 284962.56 307094.03 139875.33 21711.31 2716.68 1906.68 1906.68
PRESUPUESTO TOTAL 6,923,370.33 299,960.09 267,387.53 301,948.67 201,646.24 869,069.68 1,868,087.91 2,013,171.97 916,960.48 142,329.69 17,809.36 12,499.36 12,499.36
PORCENTAJE DE AVANCE PROGRAMADO 4.33% 3.86% 4.36% 2.91% 12.55% 26.98% 29.08% 13.24% 2.06% 0.26% 0.18% 0.18%
PORCENTAJE DE AVANCE PROGRAMADO ACUMULADO 4.33% 8.19% 12.56% 15.47% 28.02% 55.00% 84.08% 97.33% 99.38% 99.64% 99.82% 100.00%