SON: UN MILLON SEISCIENTOS SETENTA Y CINCO MIL QUINIENTOS VEINTINUEVE 38/100 BOLIVIANOS
PRESUPUESTO GENERAL
Proyecto : Construcción Sistema Microriego en Mekaraya D-6
Ubicación : Comunidad Mekaraya - Municipio Independencia Tipo de cambio :
PRECIO TOTAL APORTE E.F.
ÍTEM DESCRIPCION DEL ITEM UNID. CANTIDAD
UNIT. Bs. Bs. UNIT. Bs.
SON: DOSCIENTOS CUARENTA MIL SETECIENTOS TREINTA Y SEIS 98/100 DOLARES AMERICANOS
Fecha : Enero 2,019
Tipo de cambio : 6.96
TOTAL AP. COMUNIDAD TOTAL
Bs. UNIT. Bs. (Bs.)
24,189.19
10,074.98
11,254.96
2,859.25
33,709.37
296.63
7,680.74
401.92
17,196.67
3,707.70
659.61
1,210.84
422.36
2,132.89
24,037.98
257.08
7,680.74
1,505.03
14,595.13
13,569.14
269.74
672.19
175.42
4,809.99
2,132.84
970.11
1,225.68
343.75
2,969.41
84,721.83
4,150.24
16,662.67
45,143.42
3,229.09
Fecha : Enero 2,019
Tipo de cambio : 6.96
TOTAL AP. COMUNIDAD TOTAL
Bs. UNIT. Bs. (Bs.)
5,306.59
7,898.63
2,331.19
330,822.93
13,874.30
49,621.57
210,054.96
9,785.60
15,751.81
23,941.47
7,793.21
101,097.31
819.64
336.81
24,190.27
4,527.19
919.54
3,634.74
4,399.54
8,816.59
8,601.71
8,119.86
10,496.56
8,425.90
8,705.89
9,103.09
659,428.63
14,282.37
3,734.30
141,233.48
22,697.06
19,788.03
180,305.61
36,262.64
Fecha : Enero 2,019
Tipo de cambio : 6.96
TOTAL AP. COMUNIDAD TOTAL
Bs. UNIT. Bs. (Bs.)
59,197.86
42,177.88
23,288.08
29,964.37
31,269.38
21,249.54
33,978.04
12,578.58
411.99
77.52
3,888.08
259.99
1,417.03
2,784.95
3,739.02
9,100.87
151.24
39.76
1,112.31
434.42
1,432.07
5,931.07
21,222.92
352.90
92.56
2,585.37
1,013.64
3,339.30
13,839.15
27,857.57
62.34
901.87
620.60
1,484.87
Fecha : Enero 2,019
Tipo de cambio : 6.96
TOTAL AP. COMUNIDAD TOTAL
Bs. UNIT. Bs. (Bs.)
18,148.54
6,639.36
254,520.98
5,176.20
36,298.70
4,894.62
159,561.36
1,783.71
17,068.36
6,102.13
3,590.08
13,899.78
2,636.35
2,970.09
539.62
58,790.30
974.67
8,938.57
47,506.30
1,370.75
4,260.92
292.73
715.67
3,252.52
15,620.87
5,011.65
1,932.11
732.92
7,944.19
1,675,529.38
240,736.98
LIVIANOS 1,806,387.69
Fecha : Enero 2,019
Tipo de cambio : 6.96
TOTAL AP. COMUNIDAD TOTAL
Bs. UNIT. Bs. (Bs.)
CANOS 259,538.46
DESGLOSE EVALUACIÓN ECONÓMICA FINANCIER
Proyecto : Construcción Sistema Microriego en Mekaraya D-6
Ubicación : Comunidad Mekaraya - Municipio Independencia
PRECIO UNITARIO ($
ÍTEM DESCRIPCIÓN UNIDAD CANTIDAD BIENES MATERIAL
TRANSABLES LOCAL
1.0 TRABAJOS PRELIMINARES
1.1 INSTALACION DE FAENAS GLOBAL 1.00 1,351.00 0.00
1.2 MOVILIZACIÓN Y DESMOVILIZACIÓN GLOBAL 1.00 1,536.63 0.00
1.3 LETRERO DE OBRAS PIEZA 1.00 375.25 1.65
SUB TOTAL 3,262.89 1.65
2.0 OBRA DE TOMA - DREN FRANCES
2.1 REPLANTEO Y CONTROL TOPOGRÁFICO OBRA DE TOMA M2 15.00 36.56 0.00
2.2 DESVIO Y CONTROL DE AGUAS PARA OBRA DE TOMA GLOBAL 1.00 767.35 0.00
2.3 EXCAVACIÓN DE MATERIAL NO CLASIFICADO M3 6.93 31.83 0.00
2.4 HORMIGÓN ARMADO TIPO "A" H-21 M3 4.63 1,772.30 199.57
2.5 HORMIGÓN CICLÓPEO TIPO "C" H-17,5 (50% P.D.) M3 3.70 336.55 108.98
2.6 PROVISIÓN Y TENDIDO DE TUBERÍA PVC SDR26 D=4" M 12.50 90.96 0.00
2.7 MATERIAL GRADUADO DE SUB DREN 3" - 1/4" M3 3.64 35.05 130.75
2.8 PROVISIÓN Y COLOCADO TAPA METÁLICA M2 0.64 51.14 0.00
2.9 PROVISIÓN; INSTALACIÓN ACCESORIOS CÁMARA DE LIMPIEZA PIEZA 1.00 292.98 0.00
SUB TOTAL 3,414.72 439.30
3.0 OBRAS DE PROTECCIÓN
3.1 REPLANTEO Y CONTROL TOPOGRÁFICO OBRAS DE PROTECCIÓN M2 13.00 31.68 0.00
3.2 DESVIO Y CONTROL DE AGUAS PARA OBRA DE PROTECCIÓN GLOBAL 1.00 767.35 0.00
3.3 EXCAVACIÓN DE MATERIAL NO CLASIFICADO M3 25.95 119.21 0.00
3.4 PROVISIÓN Y COLOCADO DE GAVIONES M3 30.00 1,415.43 452.59
SUB TOTAL 2,333.67 452.59
4.0 DESARENADOR
4.1 REPLANTEO Y CONTROL TOPOGRAFICO ESTRUCTURA M2 13.64 33.24 0.00
4.2 EXCAVACIÓN COMÚN MANUAL TERRENO DURO H<1,5 M M3 12.40 53.24 0.00
4.3 RELLENO Y COMPACTADO C/TIERRA COMÚN M3 5.25 19.94 0.00
4.4 HORMIGÓN CICLÓPEO TIPO "C" H-17,5 (50% P.D.) PISO, PAREDES M3 4.80 436.61 141.38
4.5 REVOQUE INTERIOR CON IMPERMEABILIZANTE M2 22.79 170.19 83.04
4.6 PROVISIÓN Y COLOCADO TAPA METÁLICA M2 1.47 117.47 0.00
4.7 LOSA TAPA Hº Aº PREFABRICADO TIPO "A" H-21 M3 0.33 126.32 14.22
4.8 PROVISIÓN Y TENDIDO DE TUBERÍA PVC SDR26 D=3" M 10.00 46.34 0.00
4.9 PROVISIÓN; INSTALACIÓN ACCESORIOS CÁMARAS PIEZA 3.00 386.23 0.00
SUB TOTAL 1,389.59 238.64
5.0 SISTEMA DE ADUCCIÓN PROG. 0+000 - 1+340,00
5.1 REPLANTEO Y CONTROL TOPOGRAFICO M 1,340.00 500.03 0.00
DESGLOSE EVALUACIÓN ECONÓMICA FINANCIER
Proyecto : Construcción Sistema Microriego en Mekaraya D-6
Ubicación : Comunidad Mekaraya - Municipio Independencia
PRECIO UNITARIO ($
ÍTEM DESCRIPCIÓN UNIDAD CANTIDAD BIENES MATERIAL
TRANSABLES LOCAL
5.2 EXCAVACIÓN COMÚN TERRENO DURO H<1,5 M M3 307.38 1,319.78 0.00
5.3 PROVISIÓN Y TENDIDO TUBERÍA PVC SDR26 D=3" M 1,313.25 6,085.17 0.00
5.4 CAMA DE ARENA (MATERIAL SELECCIONADO) M3 26.27 80.09 377.44
5.5 RELLENO Y COMPACTADO c/TIERRA CERNIDA M3 120.69 582.53 0.00
5.6 RELLENO Y COMPACTADO C/TIERRA COMÚN M3 236.39 897.96 0.00
5.7 PRUEBA HIDRÁULICA M 1,340.00 233.86 4.81
SUB TOTAL 9,699.43 382.26
6.0 SISTEMA DE DISTRIBUCIÓN PROG. 1+340,00 - 5+519,64
6.1 REPLANTEO Y CONTROL TOPOGRAFICO M 4,479.64 1,671.62 0.00
6.2 EXCAVACIÓN COMÚN TERRENO DURO H<1,5 M M3 915.38 3,930.31 0.00
6.3 PROVISIÓN Y TENDIDO TUBERÍA PVC SDR26 D=4" M 3,980.64 28,964.96 0.00
6.4 CAMA DE ARENA (MATERIAL SELECCIONADO) M3 79.61 242.71 1,143.82
6.5 RELLENO Y COMPACTADO C/TIERRA CERNIDA M3 358.25 1,729.16 0.00
6.6 RELLENO Y COMPACTADO C/TIERRA COMÚN M3 716.52 2,721.80 0.00
6.7 PRUEBA HIDRÁULICA M 4,479.64 781.81 16.09
SUB TOTAL 40,042.37 1,159.91
7.0 PASO DE QUEBRADA
7.1 EXCAVACIÓN COMÚN MANUAL TERRENO DURO H<1,5 M M3 15.12 64.92 0.00
7.2 RELLENO Y COMPACTADO C/TIERRA COMÚN M3 10.08 38.29 0.00
7.3 HORMIGÓN CICLÓPEO H-17,5 (50% P.D.) M3 24.14 2,195.78 711.02
7.4 PROVISIÓN Y COLOCADO TAPA METÁLICA M2 6.86 548.20 0.00
7.5 PROVISIÓN Y TENDIDO DE TUBERÍA PVC SDR26 D= 3" M 26.75 123.95 0.00
7.6 PROVISIÓN Y TENDIDO DE TUBERÍA PVC SDR26 D= 4" M 68.88 501.20 0.00
7.7 PROTECCIÓN TUBERÍA CON LÁMINA ASFÁLTICA M 95.63 587.55 0.00
7.8 MÓDULO METÁLICO M 95.63 7,792.62 0.00
SUB TOTAL 11,852.51 711.02
DESGLOSE EVALUACIÓN ECONÓMICA FINANCIER
Proyecto : Construcción Sistema Microriego en Mekaraya D-6
Ubicación : Comunidad Mekaraya - Municipio Independencia
PRECIO UNITARIO ($
ÍTEM DESCRIPCIÓN UNIDAD CANTIDAD BIENES MATERIAL
TRANSABLES LOCAL
8.0 PASO DE QUEBRADA
8.1 EXCAVACIÓN COMÚN MANUAL TERRENO DURO H<1,5 M M3 263.47 1,131.24 0.00
8.2 RELLENO Y COMPACTADO C/TIERRA COMÚN M3 111.76 424.54 0.00
8.3 HORMIGÓN CICLÓPEO H-17,5 (50% P.D.) M3 140.94 12,819.92 4,151.25
8.4 PROVISIÓN Y TENDIDO DE TUBERÍA PVC SDR26 D= 4" M 430.12 3,129.75 0.00
8.5 PROTECCIÓN TUBERÍA CON LÁMINA ASFÁLTICA M 430.12 2,642.65 0.00
8.6 PASO DE QUEBRADA L=150m (D=4") (PROG. 2+030,00 - 2+180,00) M 150.00 21,477.10 0.00
8.7 PASO DE QUEBRADA L=36.50m (D=4") (PROG. 2+220,00 - 2+256,50) M 36.50 4,132.46 0.00
8.8 PASO DE QUEBRADA L=57,22m (D=4") (PROG. 2+689,53 - 2+746,75) M 57.22 6,815.97 0.00
8.9 PASO DE QUEBRADA L=42,22m (D=4") (PROG. 2+950,98 - 2+993,20) M 42.22 4,813.46 0.00
8.10 PASO DE QUEBRADA L=24,39m (D=4") (PROG. 3+580,00 - 3+604,39) M 24.39 2,625.85 0.00
8.11 PASO DE QUEBRADA L=30,98m (D=4") (PROG. 3+740,00 - 3+770,98) M 30.98 3,390.51 0.00
8.12 PASO DE QUEBRADA L=32,23m (D=4") (PROG. 4+000,00 - 4+032,23) M 32.23 3,541.11 0.00
8.13 PASO DE QUEBRADA L=22,26m (D=4") (PROG. 4+182,37 - 4+204,63) M 22.26 2,395.85 0.00
8.14 PASO DE QUEBRADA L=34,32m (D=4") (PROG. 5+363,92 - 5+398,24) M 34.32 3,868.57 0.00
SUB TOTAL 73,208.97 4,151.25
9.0 CÁMARA ROMPEPRESIÓN
9.1 EXCAVACIÓN COMÚN TERRENO DURO H<1,5 M M3 7.60 32.63 0.00
9.2 RELLENO Y COMPACTADO C/TIERRA COMÚN M3 2.32 8.81 0.00
9.3 HORMIGÓN CICLÓPEO H-17,5 (50% P.D.) M3 3.88 352.93 114.28
9.4 HORMIGÓN ARMADO TIPO "A" H-21 - PANTALLA M3 0.07 26.79 3.02
9.5 REVOQUE INTERIOR C/CEMENTO M2 16.44 113.54 59.05
9.6 PROVISIÓN Y COLOCADO TAPA METÁLICA M2 4.22 337.23 0.00
9.7 PROVISIÓN; INSTALACIÓN HIDRÁULICA C/ACCESORIOS PIEZA 2.00 489.08 0.00
SUB TOTAL 1,361.02 176.35
10.0 CÁMARAS DE CONTROL
10.1 EXCAVACIÓN COMÚN TERRENO DURO H<1,5 M M3 2.79 11.98 0.00
10.2 RELLENO Y COMPACTADO C/TIERRA COMÚN M3 1.19 4.52 0.00
10.3 HORMIGÓN CICLÓPEO H-17,5 (50% P.D.) M3 1.11 100.97 32.69
10.4 REVOQUE INTERIOR C/CEMENTO M2 5.04 34.81 18.10
10.5 PROVISIÓN Y COLOCADO TAPA METÁLICA M2 2.17 173.41 0.00
10.6 PROVISIÓN; INSTALACIÓN HIDRÁULICA C/ACCESORIOS PIEZA 3.00 0.00 40.41
SUB TOTAL 325.68 91.21
11.0 CÁMARAS DE DISTRIBUCIÓN
11.1 EXCAVACIÓN COMÚN TERRENO DURO H<1,5 M M3 6.51 27.95 0.00
DESGLOSE EVALUACIÓN ECONÓMICA FINANCIER
Proyecto : Construcción Sistema Microriego en Mekaraya D-6
Ubicación : Comunidad Mekaraya - Municipio Independencia
PRECIO UNITARIO ($
ÍTEM DESCRIPCIÓN UNIDAD CANTIDAD BIENES MATERIAL
TRANSABLES LOCAL
11.2 RELLENO Y COMPACTADO C/TIERRA COMÚN M3 2.77 10.52 0.00
11.3 HORMIGÓN CICLÓPEO H-17,5 (50% P.D.) M3 2.58 234.68 75.99
11.4 REVOQUE INTERIOR C/CEMENTO M2 11.76 81.22 42.24
11.5 PROVISIÓN Y COLOCADO TAPA METÁLICA M2 5.06 404.36 0.00
11.6 PROVISIÓN; INSTALACIÓN HIDRÁULICA C/ACCESORIOS PIEZA 7.00 1,831.24 0.00
SUB TOTAL 2,589.96 118.23
12.0 HIDRANTES
12.1 EXCAVACIÓN COMÚN TERRENO DURO H<1,5 M M3 1.15 4.94 0.00
12.2 HORMIGÓN CICLÓPEO H-17,5 (50% P.D.) M3 0.90 81.86 26.51
12.3 REVOQUE INTERIOR C/CEMENTO M2 7.20 49.73 25.86
12.4 PROVISIÓN Y COLOCADO TAPA METÁLICA M2 2.25 179.80 0.00
12.5 PROVISIÓN Y TENDIDO TUBERÍA SDR26 D=1 1/2" M 1,000.00 2,418.97 0.00
12.6 PROVISIÓN; INSTALACIÓN HIDRÁULICA C/ACCESORIOS HIDRANTE PIEZA 9.00 792.29 0.00
SUB TOTAL 3,527.60 52.37
13.0 ESTANQUE DE REGULACIÓN CAP. 25 M3
13.1 REPLANTEO Y CONTROL TOPOGRÁFICO M2 261.75 637.93 0.00
13.2 EXCAVACIÓN COMÚN TERRENO DURO H<1,5 M M3 669.61 2,875.06 0.00
13.3 SOLADURA DE PIEDRA MANZANA e=0.17m M2 115.52 538.52 0.00
13.4 HORMIGÓN ARMADO TIPO "A" H-21 M3 42.96 16,444.45 1,851.72
13.5 HORMIGÓN CICLÓPEO H-17,5 (50% P.D.) M3 1.78 161.91 52.43
DESGLOSE EVALUACIÓN ECONÓMICA FINANCIER
Proyecto : Construcción Sistema Microriego en Mekaraya D-6
Ubicación : Comunidad Mekaraya - Municipio Independencia
PRECIO UNITARIO ($
ÍTEM DESCRIPCIÓN UNIDAD CANTIDAD BIENES MATERIAL
TRANSABLES LOCAL
13.6 REVOQUE INTERIOR CON IMPERMEABILIZANTE M2 182.38 1,362.00 664.53
13.7 REVOQUE EXTERIOR C/CEMENTO M2 69.12 488.81 248.28
13.8 PROVISIÓN Y COLOCADO TAPA METÁLICA M2 5.44 434.72 0.00
13.9 PROVISIÓN; INSTALACIÓN C/ACCESORIOS - CÁMARA DE ENTRADA - BY PASS PIEZA 2.00 1,961.18 0.00
13.10 PROVISIÓN; INSTALACIÓN C/ACCESORIOS - CÁMARA DE LIMPIEZA PIEZA 2.00 351.85 0.00
13.11 PROVISIÓN; INSTALACIÓN C/ACCESORIOS - CÁMARA DE DISTRIBUCIÓN PIEZA 2.00 390.82 0.00
13.12 PROVISIÓN Y COLOCADO ESCALERA METÁLICA M 2.40 64.60 0.00
SUB TOTAL 25,711.85 2,816.96
14.0 CERCO PERIMETRAL
14.1 EXCAVACIÓN COMÚN TERRENO DURO H<1,5 M M3 17.98 77.20 0.00
14.2 HORMIGÓN CICLÓPEO H-17,5 (50% P.D.) M3 8.92 811.36 262.73
14.3 CERCO PERIMETRAL, MALLA OLÍMPICA Nº 12 c/TUBO 2"; ALAMBRE PÚA Nº 8 M2 215.99 5,545.50 0.00
14.4 PUERTA MALLA OLÍMPICA c/TUBO 2" TRINCHES DE SEGURIDAD y ACCESORIOS M2 5.66 163.40 0.00
SUB TOTAL 6,597.47 262.73
15.0 MANEJO DE LA CUENCA
15.1 EXCAVACIÓN MANUAL TERRENO DURO H<1,5 m M3 5.40 23.19 0.00
15.2 PLANTINES PLANTINES 100.00 75.89 0.00
15.3 ZANJAS DE CORONAMIENTO M3 60.00 257.62 0.00
SUB TOTAL 356.69 0.00
16.0 MITIGACIÓN AMBIENTAL
16.1 LETRINAS GLOBAL 1.00 549.00 43.10
16.2 SEÑALIZACIÓN VERTICAL PIEZA 5.00 235.22 0.00
16.3 PROVISIÓN DE BASUREROS PIEZA 3.00 97.22 0.00
16.4 LIMPIEZA GENERAL GLOBAL 1.00 1,028.62 0.00
SUB TOTAL 1,910.06 43.10
TOTAL 187,584.47 11,097.57
ÓMICA FINANCIERA
Fecha : Febrero 2,019
Tipo de cambio : 6.96
PRECIO UNITARIO ($us)
TOTAL
MANO DE OBRA MANO DE OBRA NO CALIFICADA
CALIFICADA SEMICALIFICADA URBANA RURAL $us.
(*) Cubre costos de ingreso y salida (2/mes) oficina - zona de trabajo y movilización en la zona de riego.
SUPERVISIÓN
Proyecto : Construcción Sistema Microriego en Mekaraya D-6
PRESUPUESTO GENERAL SUPERVISIÓN DEL PROYECTO
TIEMPO DE EJECUCIÓN: 6 MESES
PRECIO UNIT.
ITEM DESCRIPCIÓN UNIDAD CANTIDAD
[$us]
1.0 PERSONAL
1.1 Ingeniero Civil Mes 6.00 900.00
1.2 Ingeniero Civil Junior Mes 4.00 500.00
2.0 EQUIPOS Y MATERIALES
2.1 Papel e informes Global 1.00 300.00
2.2 Material de escritorio Global 1.00 300.00
2.3 Computadora Mes 6.00 50.00
2.4 Impresora Mes 6.00 40.00
2.5 Fotografía Global 1.00 100.00
3.0 LOGÍSTICA Y SERVICIOS
3.1 Transporte Técnico Mes 5.00 80.00
3.2 Alojamiento Mes 5.00 70.00
3.3 Alimentación Mes 5.00 80.00
3.4 Teléfono y correo Mes 5.00 50.00
3.5 Seguros Global 1.00 400.00
TOTAL $us.
TOTAL Bs.
COSTO TOTAL
[$us]
7,400.00
5,400.00
2,000.00
1,240.00
300.00
300.00
300.00
240.00
100.00
1,800.00
400.00
350.00
400.00
250.00
400.00
10,440.00
72,662.40
Meses
Meses
$us.
%
MATERIALES E INSUMOS
Proyecto : Construcción Sistema Microriego en Mekaraya D-6
Ubicación : Comunidad Mekaraya - Municipio Independencia