PRESUPUESTO DE OBRA
COSTO GASTO DE SALDO
COSTO PARCIAL AVANCE % Materiales
EJECTUTADO OBRA PARCIAL
ITEM DESCRIPCION METRADO SUB-TOTAL (S/) Mano de obra
GASTO DE O/C
UND UNITARIO (S/) (S/) OBRA
MEJORAMIENTO DE VIA EXTERNA 4KM
1.00 OBRAS PRELIMINARES 6,000.00
1.01 Movilizacion y desmovilizacion de maquinarias glb 1.00 4,000.00 4,000.00 100% S/ 4,000.00 S/ 2,360.00 S/ 1,640.00 S/ 2,360.00
1.02 Control topografico glb 1.00 2,000.00 2,000.00 100% S/ 2,000.00 S/ - S/ 2,000.00
2.00 MOVIMIENTO DE TIERRAS 182,000.00
2.01 Relleno con afirmado m3 2,600.00 70.00 182,000.00 100% S/ 182,000.00 S/ 55,620.66 S/ 126,379.34 S/ 55,620.66
3.00 COMPACTACION 40,000.00
3.01 Motoniveladora y rodillo glb 1.00 30,000.00 30,000.00 100% S/ 30,000.00 S/ 19,632.30 S/ 10,367.70
S/ 1,070.00 S/ 18,562.30
3.02 Agua glb 1.00 10,000.00 10,000.00 100% S/ 10,000.00 S/ 4,602.00 S/ 5,398.00 S/ 4,602.00
TOTAL EN SOLES 228,000.00 S/ 228,000.00 S/ 79,854.96 S/ 145,785.04 S/ 1,070.00 S/ 81,144.96
S/ 82,214.96