CRONOGRAMA VALORIZADO
Mes 1 Mes 2
Nombre de tarea Total
Semana 1 Semana 2 Semana 3 Semana 4 Semana 5 Semana 6 Semana 7 Semana 8
ESTRUCTURAS S/. 3,116.59 S/. 4,341.48 S/. 4,227.86 S/. 18,679.08 S/. 39,124.68 S/. 54,610.58 S/. 109,250.06 S/. 91,927.63 S/. 325,277.96
INICIO
OBRAS PRELIMINARES S/. 1,380.00 S/. 1,380.00
LIMPIEZA DEL TERRENO MANUAL S/. 1,380.00 S/. 1,380.00
MOVIMIENTO DE TIERRAS S/. 1,736.59 S/. 4,341.48 S/. 4,227.86 S/. 1,737.46 S/. 12,043.39
EXCAVACION MANUAL DE ZANJAS PARA CIMIENTOS S/. 1,736.59 S/. 4,341.48 S/. 1,302.44 S/. 7,380.51
ELIMINACION DE MATERIAL EXCEDENTE DM=1 km S/. 483.71 S/. 483.71
RELLENO COMPACTADO CON MATERIAL PROPIO S/. 2,925.42 S/. 1,253.75 S/. 4,179.17
CONCRETO S/. 16,941.62 S/. 39,124.68 S/. 54,610.58 S/. 109,250.06 S/. 91,927.64 S/. 311,854.58
CONCRETO SIMPLE S/. 5,741.94 S/. 16,509.41 S/. 4,109.96 S/. 26,361.31
CONCRETO CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA S/. 5,741.94 S/. 13,397.85 S/. 19,139.79
ENCOFRADO DE SOBRECIMIENTO h=0.30 m S/. 3,111.56 S/. 1,037.19 S/. 4,148.75
CONCRETO SOBRECIMIENTOS MEZCLA 1:8 + 25% S/. 3,072.77 S/. 3,072.77
P.M.CONCRETO ARMADO S/. 11,199.68 S/. 22,615.27 S/. 50,500.62 S/. 109,250.06 S/. 91,927.64 S/. 285,493.27
COLUMNAS S/. 11,199.68 S/. 11,684.45 S/. 38,664.39 S/. 56,599.83 S/. 118,148.35
ACERO DE REFUERZO fy=4,200 kg/cm2 S/. 8,038.87 S/. 1,148.41 S/. 9,187.28
ENCOFRADO S/. 3,160.81 S/. 10,536.04 S/. 6,321.63 S/. 20,018.48
CONCRETO COLUMNAS f'c=210 kg/cm2 S/. 32,342.76 S/. 56,599.83 S/. 88,942.59
VIGAS S/. 10,930.82 S/. 11,836.23 S/. 52,650.23 S/. 91,927.64 S/. 167,344.92
ACERO DE REFUERZO fy=4,200 kg/cm2 S/. 10,930.82 S/. 3,643.61 S/. 14,574.43
ENCOFRADO S/. 8,192.62 S/. 20,481.54 S/. 6,144.46 S/. 34,818.62
CONCRETO VIGAS f'c=210 kg/cm2 S/. 32,168.69 S/. 85,783.18 S/. 117,951.87
FIN