FORMATO CALCULO TIEMPOS

Consu
mo Consu HH - ayud o N° No. duracion dias
Unidad N° Duracion Duracio cantidad/di
ID Actividad mano mo ayud HM Maqui Cuadrill factor dias ajustada H operador
medida Cantidad Hombres horas n dias a
obra HM/Um Maquina nas as factor s
HH/Um

1 PRELIMINARES
2 Localización m2 600 0.09 53.33 0.00 2.00 1.00 26.67 3.33 1.00 3.33 180.00 4.00 0.00
3 Cerramiento ml 170 0.50 85.00 0.00 2.00 1.00 42.50 5.31 1.00 5.31 32.00 6.00 - HH [ 85.00 ] HH[85]
4 Instalaciones provisionales m2 80 3.00 240.00 0.00 2.00 2.00 60.00 7.50 1.00 7.50 10.67 8.00 - HH [ 240.00 ] HH[240]
5 EXCAVACIÓN -
6 Descapote m2 1,800 0.02 - 36.00 1.00 1.00 36.00 4.50 1.00 4.50 400.00 5.00 36.00 HH [ - ] HH[0]
7 Excavación a máquina m3 2,100 0.01 - ### 1.00 1.00 26.25 3.28 ### 3.28 640.00 4.00 HH [ - ] HH[0]
8 Replanteo m2 600 0.09 53.33 0.00 2.00 1.00 26.67 3.33 1.00 3.33 180.00 4.00 - HH [ 53.33 ] HH[53.3333333333333]
9 Exc Pilas m3 407 10.00 4,071.51 0.00 2.00 6.00 339.29 42.41 1.00 42.41 9.60 43.00 - HH [ 4,071.51 ] HH[4071.5136]
10 Exc V Amarre m3 38 2.00 76.00 0.00 2.00 1.00 38.00 4.75 1.00 4.75 8.00 5.00 - HH [ 76.00 ] HH[76]
11 CIMENTACIONES -
12 Acero Pilas kg 14,137 0.03 466.53 0.00 4.00 1.00 116.63 14.58 1.00 14.58 969.70 15.00 - HH [ 466.53 ] HH[466.5276]
13 Vaciado Pilas m3 283 2.50 706.86 0.00 4.00 1.00 ### 22.09 ### 22.09 12.80 23.00 - HH [ 706.86 ] HH[706.86]
14 Acero Vigas de Amarre kg 2,660 0.03 87.78 0.00 2.00 1.00 43.89 5.49 1.00 5.49 484.85 6.00 - HH [ 87.78 ] HH[87.78]
15 Vaciado Vigas de Amarre m3 38 6.00 228.00 0.00 2.00 2.00 57.00 7.13 1.00 7.13 5.33 8.00 - HH [ 228.00 ] HH[228]
16 Acero Cabezotes kg 2,827 0.06 155.51 0.00 2.00 1.00 77.75 9.72 1.00 9.72 290.91 10.00 - HH [ 155.51 ] HH[155.5092]
17 Vaciado Cabezotes m3 24 14.00 329.87 0.00 2.00 2.00 82.47 10.31 1.00 10.31 2.29 11.00 - HH [ 329.87 ] HH[329.868]
18 ESTRUCTURA -
19 Acero Columnas Sótano kg 1,843 0.03 60.83 0.00 2.00 2.00 15.21 1.90 1.00 1.90 969.70 2.00 - HH [ 60.83 ] HH[60.8256]
20 Vaciado Columnas Sótano m3 23 19.00 437.76 0.00 2.00 6.00 36.48 4.56 1.00 4.56 5.05 5.00 - HH [ 437.76 ] HH[437.76]
21 Armado losa 1er piso m2 600 2.00 1,200.00 0.00 4.00 6.00 50.00 6.25 1.00 6.25 96.00 7.00 - HH [ 1,200.00 ] HH[1200]
22 Acero losa 1er piso kg 10,800 0.03 356.40 0.00 3.00 3.00 39.60 4.95 1.00 4.95 2,181.82 5.00 - HH [ 356.40 ] HH[356.4]
23 Vac losa 1er piso m3 108 0.45 48.60 0.00 4.00 6.00 2.03 0.25 ### 0.25 426.67 1.00 - HH [ 48.60 ] HH[48.6]
24 Acero Columnas 1er piso kg 1,843 0.03 60.83 0.00 2.00 2.00 15.21 1.90 1.00 1.90 969.70 2.00 - HH [ 60.83 ] HH[60.8256]
25 Vaciado Columnas 1er piso m3 23 19.00 437.76 0.00 2.00 6.00 36.48 4.56 1.00 4.56 5.05 5.00 - HH [ 437.76 ] HH[437.76]
26 Armado losa 2do piso m2 600 2.00 1,200.00 0.00 4.00 6.00 50.00 6.25 1.00 6.25 96.00 7.00 - HH [ 1,200.00 ] HH[1200]
27 Acero losa 2do piso kg 10,800 0.03 356.40 0.00 3.00 3.00 39.60 4.95 ### 4.95 ### 5.00 HH [ 356.40 ] HH[356.4]
28 Vac losa 2do piso m3 108 0.45 48.60 0.00 4.00 6.00 2.03 0.25 1.00 0.25 426.67 1.00 - HH [ 48.60 ] HH[48.6]
29 Acero Columnas 2do piso kg 1,843 0.03 60.83 0.00 2.00 2.00 15.21 1.90 1.00 1.90 969.70 2.00 - HH [ 60.83 ] HH[60.8256]
30 Vaciado Columnas 2do piso m3 23 19.00 437.76 0.00 2.00 6.00 36.48 4.56 1.00 4.56 5.05 5.00 - HH [ 437.76 ] HH[437.76]
31 Armado losa 3er piso m2 600 2.00 1,200.00 0.00 4.00 6.00 50.00 6.25 1.00 6.25 96.00 7.00 - HH [ 1,200.00 ] HH[1200]
32 Acero losa 3er piso kg 10,800 0.03 356.40 0.00 3.00 3.00 39.60 4.95 ### 4.95 ### 5.00 HH [ 356.40 ] HH[356.4]
33 Vac losa 3er piso m3 108 0.45 48.60 0.00 4.00 6.00 2.03 0.25 1.00 0.25 426.67 1.00 - HH [ 48.60 ] HH[48.6]
34 Acero Columnas 3er piso kg 1,843 0.03 60.83 0.00 2.00 2.00 15.21 1.90 1.00 1.90 969.70 2.00 - HH [ 60.83 ] HH[60.8256]
35 Vaciado Columnas 3er piso m3 23 19.00 437.76 0.00 2.00 6.00 36.48 4.56 1.00 4.56 5.05 5.00 - HH [ 437.76 ] HH[437.76]
36 Armado losa 4to piso m2 600 2.00 1,200.00 0.00 4.00 6.00 50.00 6.25 1.00 6.25 96.00 7.00 - HH [ 1,200.00 ] HH[1200]
37 Acero losa 4to piso kg 10,800 0.03 356.40 0.00 3.00 3.00 39.60 4.95 1.00 4.95 2,181.82 5.00 - HH [ 356.40 ] HH[356.4]
38 Vac losa 4to piso m3 108 0.45 48.60 0.00 4.00 6.00 2.03 0.25 1.00 0.25 426.67 1.00 - HH [ 48.60 ] HH[48.6]
39 Acero Columnas 4to piso kg 1,843 0.03 60.83 0.00 2.00 2.00 15.21 1.90 1.00 1.90 969.70 2.00 - HH [ 60.83 ] HH[60.8256]
40 Vaciado Columnas 4to piso m3 23 19.00 437.76 0.00 2.00 6.00 36.48 4.56 1.00 4.56 5.05 5.00 - HH [ 437.76 ] HH[437.76]
41 Arm Vigas de Cub m3 14 12.00 172.80 0.00 2.00 2.00 43.20 5.40 ### 5.40 2.67 6.00 HH [ 172.80 ] HH[172.8]
42 Acero Vigas de Cub kg 720 0.03 23.76 0.00 2.00 1.00 11.88 1.49 1.00 1.49 484.85 2.00 - HH [ 23.76 ] HH[23.76]
43 Vac Vigas de Cub m3 14 2.50 36.00 0.00 2.00 2.00 9.00 1.13 1.00 1.13 12.80 2.00 - HH [ 36.00 ] HH[36]
44 MAMPOSTERÍA -
45 Mam. Sucio 10-20-40 Sótano m2 456 1.20 547.20 0.00 2.00 5.00 54.72 6.84 1.00 6.84 66.67 7.00 - HH [ 547.20 ] HH[547.2]
46 Mam. Sucio 10-20-40 1er piso m2 456 1.20 547.20 0.00 2.00 5.00 54.72 6.84 1.00 6.84 66.67 7.00 - HH [ 547.20 ] HH[547.2]
47 Mam. Sucio 10-20-40 2do piso m2 456 1.20 547.20 0.00 2.00 5.00 54.72 6.84 1.00 6.84 66.67 7.00 - HH [ 547.20 ] HH[547.2]
48 Mam. Sucio 10-20-40 3er piso m2 456 1.20 547.20 0.00 2.00 5.00 54.72 6.84 1.00 6.84 66.67 7.00 -
49 Mam. Sucio 10-20-40 4to piso m2 456 1.20 547.20 0.00 2.00 5.00 54.72 6.84 1.00 6.84 66.67 7.00 -
50 REDES 0
51 Redes sótano Sal 575 0.80 460.00 0.00 2.00 4.00 57.50 7.19 1.00 7.19 80.00 8.00 -
52 Redes piso 1 Sal 575 0.80 460.00 0.00 2.00 4.00 57.50 7.19 1.00 7.19 80.00 8.00 -
53 Redes piso 2 Sal 575 0.80 460.00 0.00 2.00 4.00 57.50 7.19 1.00 7.19 80.00 8.00 -
54 Redes piso 3 Sal 575 0.80 460.00 0.00 2.00 4.00 57.50 7.19 1.00 7.19 80.00 8.00 -
55 Redes piso 4 Sal 575 0.80 460.00 0.00 2.00 4.00 57.50 7.19 1.00 7.19 80.00 8.00 -
56 REVOQUE 0.0
57 Revoque sótano m2 912 0.40 364.80 0.00 2.00 3.00 60.80 7.60 1.00 7.60 120.00 8.00 -
58 Revoque piso 1 m2 912 0.40 364.80 0.00 2.00 3.00 60.80 7.60 1.00 7.60 120.00 8.00 -
59 Revoque piso 2 m2 912 0.40 364.80 0.00 2.00 3.00 60.80 7.60 1.00 7.60 120.00 8.00 -
60 Revoque piso 3 m2 912 0.40 364.80 0.00 2.00 3.00 60.80 7.60 1.00 7.60 120.00 8.00 -
61 Revoque piso 4 m2 912 0.40 364.80 0.00 2.00 3.00 60.80 7.60 1.00 7.60 120.00 8.00 -