PROYECTO: ADECUACION AL PROYECTO EJECUTIVO DEL DISTRIBUIDOR VIAL EN EL ENTRONQUE CON LA AUTOPISTA

GUANAJUATO - SAN MIGUEL DE ALLENDE Y LA CARRETERA FEDERAL 45


MUNICIPIO: GUANAJUATO TRAMO: KM 100+430.87 SUBTRAMO:
KM: 11+260 A 11+460 ORIGEN: GUANAJUATO
CALCULO DE VOLUMENES
AREAS
ESTACION
A.CARP.A. A.B.A. A.B.H. A.S.R.S. A.S.Y.S. A.CORTE A.TERR. A.COMP A.DESP. A.D.CARP.

11+260.00 0.429 0.880 2.138 3.257 6.033 0.000 25.031 5.051 3.367 0.000
11+280.00 0.429 0.880 2.138 3.258 6.036 0.000 25.394 5.071 3.380 0.000
11+300.00 0.429 0.880 2.138 3.258 6.036 0.000 24.295 5.036 3.358 0.000
11+308.97 0.429 0.880 2.138 3.258 6.036 0.000 25.990 5.112 3.409 0.000
11+320.00 0.429 0.880 2.138 3.256 6.037 0.000 26.739 5.170 3.448 0.000
11+340.00 0.429 0.881 2.142 3.258 6.042 0.000 27.931 5.215 3.477 0.000
11+360.00 0.429 0.881 2.142 3.258 6.042 0.000 28.285 5.242 3.496 0.000
11+380.00 0.429 0.881 2.142 3.258 6.042 0.000 32.242 5.467 3.646 0.000
11+400.00 0.429 0.881 2.142 3.258 6.042 0.000 60.206 6.601 4.401 0.000
11+420.00 0.429 0.881 2.142 3.258 6.042 0.000 40.528 5.785 3.857 0.000
11+440.00 0.429 0.881 2.142 3.258 6.042 0.000 44.190 5.936 3.957 0.000
11+460.00 0.429 0.881 2.142 3.258 6.042 0.000 46.242 6.000 4.000 0.000
NOTA. LA VOLUMETRIA DE LOS CADENAMIENTOS 11+000 AL 11+260 SE CUANTIFICAN CON EL EJE 100
A1+A2 D/2
ESTACION
A.CARP.A. A.B.A. A.B.H. A.S.R.S. A.S.Y.S. A.CORTE A.TERR. A.COMP A.DESP. A.D.CARP.

11+260.00 0.429 0.880 2.138 3.257 6.033 0.000 25.031 5.051 3.367 0.000 10.000
11+280.00 0.858 1.760 4.276 6.515 12.069 0.000 50.425 10.122 6.747 0.000 10.000
11+300.00 0.858 1.760 4.276 6.516 12.072 0.000 49.689 10.107 6.738 0.000 10.000
11+308.97 0.858 1.760 4.276 6.516 12.072 0.000 50.285 10.148 6.767 0.000 4.485
11+320.00 0.858 1.760 4.276 6.514 12.073 0.000 52.729 10.282 6.857 0.000 5.515
11+340.00 0.858 1.761 4.280 6.514 12.079 0.000 54.670 10.385 6.925 0.000 10.000
11+360.00 0.858 1.762 4.284 6.516 12.084 0.000 56.216 10.457 6.973 0.000 10.000
11+380.00 0.858 1.762 4.284 6.516 12.084 0.000 60.527 10.709 7.142 0.000 10.000
11+400.00 0.858 1.762 4.284 6.516 12.084 0.000 92.448 12.068 8.047 0.000 10.000
11+420.00 0.858 1.762 4.284 6.516 12.084 0.000 100.734 12.386 8.258 0.000 10.000
11+440.00 0.858 1.762 4.284 6.516 12.084 0.000 84.718 11.721 7.814 0.000 10.000
11+460.00 0.858 1.762 4.284 6.516 12.084 0.000 78.484 11.467 7.646 0.000 10.000
NOTA. LA VOLUMETRIA DE LOS CADENAMIENTOS 11+000 AL 11+260 SE CUANTIFICAN CON EL EJE 100
PROYECTO: ADECUACION AL PROYECTO EJECUTIVO DEL DISTRIBUIDOR VIAL EN EL ENTRONQUE CON LA AUTOPISTA
GUANAJUATO - SAN MIGUEL DE ALLENDE Y LA CARRETERA FEDERAL 45
MUNICIPIO: GUANAJUATO TRAMO: KM 100+430.87 SUBTRAMO:
KM: 11+260 A 11+460 ORIGEN: GUANAJUATO
CALCULO DE VOLUMENES
VOLUMENES
ESTACION
V.CARP.A. V.B.A. V.B.H. V.S.R.S. V.S.Y.S. V.CORTE V.TERR. V.COMP V.DESP. V.D.CARP.

11+260.00 4.290 8.800 21.380 32.570 60.330 0.000 250.310 50.510 33.670 0.000
11+280.00 8.580 17.600 42.760 65.150 120.690 0.000 504.250 101.220 67.470 0.000
11+300.00 8.580 17.600 42.760 65.160 120.720 0.000 496.890 101.070 67.380 0.000
11+308.97 3.850 7.890 19.180 29.220 54.140 0.000 225.530 45.510 30.350 0.000
11+320.00 4.730 9.710 23.580 35.920 66.580 0.000 290.800 56.710 37.820 0.000
11+340.00 8.580 17.610 42.800 65.140 120.790 0.000 546.700 103.850 69.250 0.000
11+360.00 8.580 17.620 42.840 65.160 120.840 0.000 562.160 104.570 69.730 0.000
11+380.00 8.580 17.620 42.840 65.160 120.840 0.000 605.270 107.090 71.420 0.000
11+400.00 8.580 17.620 42.840 65.160 120.840 0.000 924.480 120.680 80.470 0.000
11+420.00 8.580 17.620 42.840 65.160 120.840 0.000 1007.340 123.860 82.580 0.000
11+440.00 8.580 17.620 42.840 65.160 120.840 0.000 847.180 117.210 78.140 0.000 NOTA. LA VOLUMETRIA DE LOS
11+460.00 8.580 17.620 42.840 65.160 120.840 0.000 784.840 114.670 76.460 0.000 CADENAMIENTOS 11+000 AL 11+260 SE
TOTAL 90.090 184.930 449.500 684.120 1 268.290 0.000 7 045.750 1 146.950 764.740 0.000 CUANTIFICAN CON EL EJE 100
SIMBOLOGIA
A.CARP.A. ÁREA DE CARPETA ASFÁLTICA.
A.B.A AREA DE BASE ASFALTCA
A.B.H. AREA DE BASE HIDRAULICA
A.S.R.S. AREA DE SUBRASANTE
A.S.Y.S. AREA DE SUBYACENTE
A.CORTE. AREA DE CORTE
A.TERR. AREA DE TERRAPLEN
A.COMPACT. AREA DE COMPACTACION
A.DESP. AREA DE DESPALME
A.ESC.L. AREA DE ESCALON DE LIGA
A.D.CARP. AREA DE DEMOLICION DE CARPETA
EMULSION PARA RIEGO DE IMPREGNACIÓN = 2702.700 LT
BARRIDO DE LA SUPERFICIE A TRATAR = 0.180 HA
ARENA PARA CUBRIR LA BASE IMPREGNADA = 14.414 M3

VOLUMEN DE CARPETA ASFÁLTICA. V.CARP.A.= 90.090 m³


VOLUMEN DE BASE ASFALTCA V.B.A= 184.930 m³
VOLUMEN DE BASE HIDRAULICA V.B.H.= 449.500 m³
VOLUMEN DE SUBRASANTE V.S.R.S.= 684.120 m³
VOLUMEN DE SUBYACENTE V.S.Y.S.= 1268.290 m³
VOLUMEN DE CORTE V.CORTE.= 0.000 m³
VOLUMEN DE TERRAPLEN V.TERR.= 7045.750 m³
VOLUMEN DE COMPACTACION V.COMPACT.= 1146.950 m³
VOLUMEN DE DESPALME V.DESP. = 764.740 m³
VOLUMEN DE ESCALON DE LIGA V.ESC.L.= 0.000 m³
VOLUMEN DE DEMOLICION DE CARPETA V.D.CARP.= 0.000 m³
PROYECTO: ADECUACION AL PROYECTO EJECUTIVO DEL DISTRIBUIDOR VIAL EN EL ENTRONQUE CON LA AUTOPISTA
GUANAJUATO - SAN MIGUEL DE ALLENDE Y LA CARRETERA FEDERAL 45
MUNICIPIO: GUANAJUATO TRAMO: KM 100+430.87 SUBTRAMO:
KM: 11+480 A 11+700 ORIGEN: GUANAJUATO
CALCULO DE VOLUMENES
AREAS
ESTACION
A.CARP.A. A.B.A. A.B.H. A.S.R.S. A.S.Y.S. A.CORTE A.TERR. A.COMP A.DESP. A.D.CARP.

11+480.00 0.429 0.881 2.142 3.258 6.042 0.000 47.413 6.061 4.040 0.000
11+500.00 0.429 0.881 2.142 3.258 6.042 0.000 46.626 6.045 4.029 0.000
11+520.00 0.429 0.881 2.142 3.258 6.042 0.000 42.204 5.867 3.910 0.000
11+540.00 0.429 0.881 2.142 3.258 6.042 0.000 37.697 3.830 5.746 0.000
11+560.00 0.429 0.881 2.142 3.258 6.042 0.000 33.582 5.469 3.645 0.000
11+580.00 0.429 0.881 2.142 3.258 6.042 0.000 27.014 5.151 3.434 0.000
11+600.00 0.429 0.881 2.142 3.258 6.042 0.000 25.538 4.997 3.329 0.000
11+620.00 0.429 0.881 2.142 3.258 6.042 0.000 19.337 4.741 3.160 0.000
11+640.00 0.429 0.881 2.142 3.258 6.042 0.000 12.974 4.448 2.965 0.000
11+660.00 0.429 0.881 2.142 3.258 6.042 0.000 7.285 2.740 4.116 0.000
11+680.00 0.429 0.881 2.142 3.258 6.016 0.000 2.170 3.733 2.490 0.000
11+700.00 0.429 0.881 2.142 3.252 5.801 7.722 0.000 3.567 2.378 0.000
A1+A2 D/2
ESTACION
A.CARP.A. A.B.A. A.B.H. A.S.R.S. A.S.Y.S. A.CORTE A.TERR. A.COMP A.DESP. A.D.CARP.

11+480.00 0.858 1.762 4.284 6.516 12.084 0.000 93.655 12.061 8.040 0.000 10.000
11+500.00 0.429 0.881 2.142 3.258 6.042 0.000 46.626 6.045 4.029 0.000 10.000
11+520.00 0.858 1.762 4.284 6.516 12.084 0.000 89.617 11.928 7.950 0.000 10.000
11+540.00 0.858 1.762 4.284 6.516 12.084 0.000 84.323 9.875 9.775 0.000 10.000
11+560.00 0.858 1.762 4.284 6.516 12.084 0.000 75.786 11.336 7.555 0.000 10.000
11+580.00 0.858 1.762 4.284 6.516 12.084 0.000 64.711 8.981 9.180 0.000 10.000
11+600.00 0.858 1.762 4.284 6.516 12.084 0.000 59.120 10.466 6.974 0.000 10.000
11+620.00 0.858 1.762 4.284 6.516 12.084 0.000 46.351 9.892 6.594 0.000 10.000
11+640.00 0.858 1.762 4.284 6.516 12.084 0.000 38.512 9.445 6.294 0.000 10.000
11+660.00 0.858 1.762 4.284 6.516 12.084 0.000 26.622 7.481 7.276 0.000 10.000
11+680.00 0.858 1.762 4.284 6.516 12.058 0.000 15.144 8.181 5.455 0.000 10.000
11+700.00 0.858 1.762 4.284 6.510 11.843 7.722 7.285 6.307 6.494 0.000 10.000
PROYECTO: ADECUACION AL PROYECTO EJECUTIVO DEL DISTRIBUIDOR VIAL EN EL ENTRONQUE CON LA AUTOPISTA
GUANAJUATO - SAN MIGUEL DE ALLENDE Y LA CARRETERA FEDERAL 45
MUNICIPIO: GUANAJUATO TRAMO: KM 100+430.87 SUBTRAMO:
KM: 11+480 A 11+700 ORIGEN: GUANAJUATO
CALCULO DE VOLUMENES
VOLUMENES
ESTACION
V.CARP.A. V.B.A. V.B.H. V.S.R.S. V.S.Y.S. V.CORTE V.TERR. V.COMP V.DESP. V.D.CARP.

11+480.00 8.580 17.620 42.840 65.160 120.840 0.000 936.550 120.610 80.400 0.000
11+500.00 4.290 8.810 21.420 32.580 60.420 0.000 466.260 60.450 40.290 0.000
11+520.00 8.580 17.620 42.840 65.160 120.840 0.000 896.170 119.280 79.500 0.000
11+540.00 8.580 17.620 42.840 65.160 120.840 0.000 843.230 98.750 97.750 0.000
11+560.00 8.580 17.620 42.840 65.160 120.840 0.000 757.860 113.360 75.550 0.000
11+580.00 8.580 17.620 42.840 65.160 120.840 0.000 647.110 89.810 91.800 0.000
11+600.00 8.580 17.620 42.840 65.160 120.840 0.000 591.200 104.660 69.740 0.000
11+620.00 8.580 17.620 42.840 65.160 120.840 0.000 463.510 98.920 65.940 0.000
11+640.00 8.580 17.620 42.840 65.160 120.840 0.000 385.120 94.450 62.940 0.000
11+660.00 8.580 17.620 42.840 65.160 120.840 0.000 266.220 74.810 72.760 0.000
11+680.00 8.580 17.620 42.840 65.160 120.580 0.000 151.440 81.810 54.550 0.000
11+700.00 8.580 17.620 42.840 65.100 118.430 77.220 72.850 63.070 64.940 0.000
TOTAL 98.670 202.630 492.660 749.280 1 386.990 77.220 6 477.520 1 119.980 856.160 0.000
SIMBOLOGIA
A.CARP.A. ÁREA DE CARPETA ASFÁLTICA.
A.B.A AREA DE BASE ASFALTCA
A.B.H. AREA DE BASE HIDRAULICA
A.S.R.S. AREA DE SUBRASANTE
A.S.Y.S. AREA DE SUBYACENTE
A.CORTE. AREA DE CORTE
A.TERR. AREA DE TERRAPLEN
A.COMPACT. AREA DE COMPACTACION
A.DESP. AREA DE DESPALME
A.ESC.L. AREA DE ESCALON DE LIGA
A.D.CARP. AREA DE DEMOLICION DE CARPETA
EMULSION PARA RIEGO DE IMPREGNACIÓN = 2960.100 LT
BARRIDO DE LA SUPERFICIE A TRATAR = 0.197 HA
ARENA PARA CUBRIR LA BASE IMPREGNADA = 15.787 M3

VOLUMEN DE CARPETA ASFÁLTICA. V.CARP.A.= 98.670 m³


VOLUMEN DE BASE ASFALTCA V.B.A= 202.630 m³
VOLUMEN DE BASE HIDRAULICA V.B.H.= 492.660 m³
VOLUMEN DE SUBRASANTE V.S.R.S.= 749.280 m³
VOLUMEN DE SUBYACENTE V.S.Y.S.= 1386.990 m³
VOLUMEN DE CORTE V.CORTE.= 77.220 m³
VOLUMEN DE TERRAPLEN V.TERR.= 6477.520 m³
VOLUMEN DE COMPACTACION V.COMPACT.= 1119.980 m³
VOLUMEN DE DESPALME V.DESP. = 856.160 m³
VOLUMEN DE ESCALON DE LIGA V.ESC.L.= 0.000 m³
VOLUMEN DE DEMOLICION DE CARPETA V.D.CARP.= 0.000 m³
PROYECTO: ADECUACION AL PROYECTO EJECUTIVO DEL DISTRIBUIDOR VIAL EN EL ENTRONQUE CON LA AUTOPISTA
GUANAJUATO - SAN MIGUEL DE ALLENDE Y LA CARRETERA FEDERAL 45
MUNICIPIO: GUANAJUATO TRAMO: KM 100+430.87 SUBTRAMO:
KM: 11+720 A 12+009.14 ORIGEN: GUANAJUATO
CALCULO DE VOLUMENES
AREAS
ESTACION
A.CARP.A. A.B.A. A.B.H. A.S.R.S. A.S.Y.S. A.CORTE A.TERR. A.COMP A.DESP. A.D.CARP.

11+720.00 0.609 1.248 2.931 3.916 6.590 13.787 0.000 3.949 2.633 0.345
11+740.00 0.487 1.004 2.372 3.172 5.312 11.235 0.000 3.183 2.122 0.338
11+760.00 0.536 0.875 2.057 2.273 4.232 9.796 0.000 2.536 1.691 0.336
11+768.76 0.216 0.550 1.324 1.641 2.736 6.385 0.000 1.641 1.094 0.050
11+780.00 0.248 0.531 1.278 1.559 2.598 5.914 0.000 1.558 1.039 0.050
11+800.00 0.229 0.493 1.191 1.441 2.402 5.537 0.000 1.441 0.960 0.050
11+820.00 0.199 0.433 1.054 1.306 2.182 4.777 0.000 1.309 0.873 0.050
11+840.00 0.178 0.379 0.872 0.987 1.645 4.200 0.000 0.987 0.658 0.050
11+860.00 0.155 0.334 0.768 0.852 1.420 3.621 0.000 0.852 0.568 0.050
11+880.00 0.134 0.292 0.672 0.726 1.210 3.076 0.000 0.726 0.484 0.050
11+900.00 0.141 0.300 0.690 0.597 0.995 2.526 0.000 0.597 0.398 0.050
11+920.00 0.091 0.205 0.472 0.465 0.775 1.997 0.000 0.465 0.310 0.050
11+940.00 0.067 0.158 0.363 0.324 0.540 1.380 0.000 0.324 0.216 0.050
11+960.00 0.045 0.114 0.262 0.192 0.320 0.812 0.000 0.192 0.128 0.050
11+980.00 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
12+000.00 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
12+009.14 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
A1+A2 D/2
ESTACION
A.CARP.A. A.B.A. A.B.H. A.S.R.S. A.S.Y.S. A.CORTE A.TERR. A.COMP A.DESP. A.D.CARP.

11+720.00 1.038 2.129 5.073 7.168 12.391 21.509 0.000 7.516 5.011 0.345 10.000
11+740.00 1.096 2.252 5.303 7.088 11.902 25.022 0.000 7.132 4.755 0.683 10.000
11+760.00 1.023 1.879 4.429 5.445 9.544 21.031 0.000 5.719 3.813 0.674 10.000
11+768.76 0.752 1.425 3.381 3.914 6.968 16.181 0.000 4.177 2.785 0.386 4.380
11+780.00 0.464 1.081 2.602 3.200 5.334 12.299 0.000 3.199 2.133 0.100 5.620
11+800.00 0.477 1.024 2.469 3.000 5.000 11.451 0.000 2.999 1.999 0.100 10.000
11+820.00 0.428 0.926 2.245 2.747 4.584 10.314 0.000 2.750 1.833 0.100 10.000
11+840.00 0.377 0.812 1.926 2.293 3.827 8.977 0.000 2.296 1.531 0.100 10.000
11+860.00 0.333 0.713 1.640 1.839 3.065 7.821 0.000 1.839 1.226 0.100 10.000
11+880.00 0.289 0.626 1.440 1.578 2.630 6.697 0.000 1.578 1.052 0.100 10.000
11+900.00 0.275 0.592 1.362 1.323 2.205 5.602 0.000 1.323 0.882 0.100 10.000
11+920.00 0.232 0.505 1.162 1.062 1.770 4.523 0.000 1.062 0.708 0.100 10.000
11+940.00 0.158 0.363 0.835 0.789 1.315 3.377 0.000 0.789 0.526 0.100 10.000
11+960.00 0.112 0.272 0.625 0.516 0.860 2.192 0.000 0.516 0.344 0.100 10.000
11+980.00 0.045 0.114 0.262 0.192 0.320 0.812 0.000 0.192 0.128 0.050 10.000
12+000.00 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 10.000
12+009.14 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 4.570
PROYECTO: ADECUACION AL PROYECTO EJECUTIVO DEL DISTRIBUIDOR VIAL EN EL ENTRONQUE CON LA AUTOPISTA
GUANAJUATO - SAN MIGUEL DE ALLENDE Y LA CARRETERA FEDERAL 45
MUNICIPIO: GUANAJUATO TRAMO: KM 100+430.87 SUBTRAMO:
KM: 11+720 A 12+009.14 ORIGEN: GUANAJUATO
CALCULO DE VOLUMENES

VOLUMENES
ESTACION
V.CARP.A. V.B.A. V.B.H. V.S.R.S. V.S.Y.S. V.CORTE V.TERR. V.COMP V.DESP. V.D.CARP.

11+720.00 10.380 21.290 50.730 71.680 123.910 215.090 0.000 75.160 50.110 3.450
11+740.00 10.960 22.520 53.030 70.880 119.020 250.220 0.000 71.320 47.550 6.830
11+760.00 10.230 18.790 44.290 54.450 95.440 210.310 0.000 57.190 38.130 6.740
11+768.76 3.290 6.240 14.810 17.140 30.520 70.870 0.000 18.300 12.200 1.690
11+780.00 2.610 6.080 14.620 17.980 29.980 69.120 0.000 17.980 11.990 0.560
11+800.00 4.770 10.240 24.690 30.000 50.000 114.510 0.000 29.990 19.990 1.000
11+820.00 4.280 9.260 22.450 27.470 45.840 103.140 0.000 27.500 18.330 1.000
11+840.00 3.770 8.120 19.260 22.930 38.270 89.770 0.000 22.960 15.310 1.000
11+860.00 3.330 7.130 16.400 18.390 30.650 78.210 0.000 18.390 12.260 1.000
11+880.00 2.890 6.260 14.400 15.780 26.300 66.970 0.000 15.780 10.520 1.000
11+900.00 2.750 5.920 13.620 13.230 22.050 56.020 0.000 13.230 8.820 1.000
11+920.00 2.320 5.050 11.620 10.620 17.700 45.230 0.000 10.620 7.080 1.000
11+940.00 1.580 3.630 8.350 7.890 13.150 33.770 0.000 7.890 5.260 1.000
11+960.00 1.120 2.720 6.250 5.160 8.600 21.920 0.000 5.160 3.440 1.000
11+980.00 0.450 1.140 2.620 1.920 3.200 8.120 0.000 1.920 1.280 0.500
12+000.00 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
12+009.14 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
TOTAL 64.730 134.390 317.140 385.520 654.630 1 433.270 0.000 393.390 262.270 28.770
PROYECTO: ADECUACION AL PROYECTO EJECUTIVO DEL DISTRIBUIDOR VIAL EN EL ENTRONQUE CON LA AUTOPISTA
GUANAJUATO - SAN MIGUEL DE ALLENDE Y LA CARRETERA FEDERAL 45
MUNICIPIO: GUANAJUATO TRAMO: KM 100+430.87 SUBTRAMO:
KM: 11+720 A 12+009.14 ORIGEN: GUANAJUATO
SIMBOLOGIA CALCULO DE VOLUMENES
A.CARP.A. ÁREA DE CARPETA ASFÁLTICA.
A.B.A AREA DE BASE ASFALTCA
A.B.H. AREA DE BASE HIDRAULICA
A.S.R.S. AREA DE SUBRASANTE
A.S.Y.S. AREA DE SUBYACENTE
A.CORTE. AREA DE CORTE
A.TERR. AREA DE TERRAPLEN
A.COMPACT. AREA DE COMPACTACION
A.DESP. AREA DE DESPALME
A.ESC.L. AREA DE ESCALON DE LIGA
A.D.CARP. AREA DE DEMOLICION DE CARPETA

EMULSION PARA RIEGO DE IMPREGNACIÓN = 1941.900 LT


BARRIDO DE LA SUPERFICIE A TRATAR = 0.129 HA
ARENA PARA CUBRIR LA BASE IMPREGNADA = 10.357 M3

VOLUMEN DE CARPETA ASFÁLTICA. V.CARP.A.= 64.730 m³


VOLUMEN DE BASE ASFALTCA V.B.A= 134.390 m³
VOLUMEN DE BASE HIDRAULICA V.B.H.= 317.140 m³
VOLUMEN DE SUBRASANTE V.S.R.S.= 385.520 m³
VOLUMEN DE SUBYACENTE V.S.Y.S.= 654.630 m³
VOLUMEN DE CORTE V.CORTE.= 1433.270 m³
VOLUMEN DE TERRAPLEN V.TERR.= 0.000 m³
VOLUMEN DE COMPACTACION V.COMPACT.= 393.390 m³
VOLUMEN DE DESPALME V.DESP. = 262.270 m³
VOLUMEN DE ESCALON DE LIGA V.D.CARP.= 28.770 m³
VOLUMEN DE DEMOLICION DE CARPETA V.ESC.L.= 0.000 m³
PROYECTO: ADECUACION AL PROYECTO EJECUTIVO DEL DISTRIBUIDOR VIAL EN EL ENTRONQUE CON LA AUTOPISTA
GUANAJUATO - SAN MIGUEL DE ALLENDE Y LA CARRETERA FEDERAL 45
MUNICIPIO: GUANAJUATO TRAMO: KM 100+430.87 SUBTRAMO:
KM: 11+260 A 12+009.14 ORIGEN: GUANAJUATO

AREAS
ESTACION
A.CARP.A. A.B.A. A.B.H. A.S.R.S. A.S.Y.S. A.CORTE A.TERR. A.COMP A.DESP. A.D.CARP.

11+260.00 0.429 0.880 2.138 3.257 6.033 0.000 25.031 5.051 3.367 0.000
11+280.00 0.429 0.880 2.138 3.258 6.036 0.000 25.394 5.071 3.380 0.000
11+300.00 0.429 0.880 2.138 3.258 6.036 0.000 24.295 5.036 3.358 0.000
11+308.97 0.429 0.880 2.138 3.258 6.036 0.000 25.990 5.112 3.409 0.000
11+320.00 0.429 0.880 2.138 3.256 6.037 0.000 26.739 5.170 3.448 0.000
11+340.00 0.429 0.881 2.142 3.258 6.042 0.000 27.931 5.215 3.477 0.000
11+360.00 0.429 0.881 2.142 3.258 6.042 0.000 28.285 5.242 3.496 0.000
11+380.00 0.429 0.881 2.142 3.258 6.042 0.000 32.242 5.467 3.646 0.000
11+400.00 0.429 0.881 2.142 3.258 6.042 0.000 60.206 6.601 4.401 0.000
11+420.00 0.429 0.881 2.142 3.258 6.042 0.000 40.528 5.785 3.857 0.000
11+440.00 0.429 0.881 2.142 3.258 6.042 0.000 44.190 5.936 3.957 0.000
11+460.00 0.429 0.881 2.142 3.258 6.042 0.000 46.242 6.000 4.000 0.000
11+480.00 0.429 0.881 2.142 3.258 6.042 0.000 47.413 6.061 4.040 0.000
11+500.00 0.429 0.881 2.142 3.258 6.042 0.000 46.626 6.045 4.029 0.000
11+520.00 0.429 0.881 2.142 3.258 6.042 0.000 42.204 5.867 3.910 0.000
11+540.00 0.429 0.881 2.142 3.258 6.042 0.000 37.697 3.830 5.746 0.000
11+560.00 0.429 0.881 2.142 3.258 6.042 0.000 33.582 5.469 3.645 0.000
11+580.00 0.429 0.881 2.142 3.258 6.042 0.000 27.014 5.151 3.434 0.000
11+600.00 0.429 0.881 2.142 3.258 6.042 0.000 25.538 4.997 3.329 0.000
11+620.00 0.429 0.881 2.142 3.258 6.042 0.000 19.337 4.741 3.160 0.000
11+640.00 0.429 0.881 2.142 3.258 6.042 0.000 12.974 4.448 2.965 0.000
11+660.00 0.429 0.881 2.142 3.258 6.042 0.000 7.285 2.740 4.116 0.000
11+680.00 0.429 0.881 2.142 3.258 6.016 0.000 2.170 3.733 2.490 0.000
11+700.00 0.429 0.881 2.142 3.252 5.801 7.722 0.000 3.567 2.378 0.000
11+720.00 0.609 1.248 2.931 3.916 6.590 13.787 0.000 3.949 2.633 0.345
11+740.00 0.487 1.004 2.372 3.172 5.312 11.235 0.000 3.183 2.122 0.338
11+760.00 0.536 0.875 2.057 2.273 4.232 9.796 0.000 2.536 1.691 0.336
11+768.76 0.216 0.550 1.324 1.641 2.736 6.385 0.000 1.641 1.094 0.050
11+780.00 0.248 0.531 1.278 1.559 2.598 5.914 0.000 1.558 1.039 0.050
11+800.00 0.229 0.493 1.191 1.441 2.402 5.537 0.000 1.441 0.960 0.050
11+820.00 0.199 0.433 1.054 1.306 2.182 4.777 0.000 1.309 0.873 0.050
11+840.00 0.178 0.379 0.872 0.987 1.645 4.200 0.000 0.987 0.658 0.050
11+860.00 0.155 0.334 0.768 0.852 1.420 3.621 0.000 0.852 0.568 0.050
11+880.00 0.134 0.292 0.672 0.726 1.210 3.076 0.000 0.726 0.484 0.050
11+900.00 0.141 0.300 0.690 0.597 0.995 2.526 0.000 0.597 0.398 0.050
11+920.00 0.091 0.205 0.472 0.465 0.775 1.997 0.000 0.465 0.310 0.050
11+940.00 0.067 0.158 0.363 0.324 0.540 1.380 0.000 0.324 0.216 0.050
11+960.00 0.045 0.114 0.262 0.192 0.320 0.812 0.000 0.192 0.128 0.050
11+980.00 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
12+000.00 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
12+009.14 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
NOTA. LA VOLUMETRIA DE LOS CADENAMIENTOS 11+000 AL 11+260 SE CUANTIFICAN CON EL EJE 100
PROYECTO: ADECUACION AL PROYECTO EJECUTIVO DEL DISTRIBUIDOR VIAL EN EL ENTRONQUE CON LA AUTOPISTA
GUANAJUATO - SAN MIGUEL DE ALLENDE Y LA CARRETERA FEDERAL 45
MUNICIPIO: GUANAJUATO TRAMO: KM 100+430.87 SUBTRAMO:
KM: 100+000 A 101+539.91 ORIGEN: GUANAJUATO
CURVA MASA
A1+A2
ESTACION D/2
A.CARP.A. A.B.A. A.B.H. A.S.R.S. A.S.Y.S. A.CORTE A.TERR. A.COMP A.DESP. A.D.CARP.

11+260.00 0.429 0.880 2.138 3.257 6.033 0.000 25.031 5.051 3.367 0.000 10.000
11+280.00 0.858 1.760 4.276 6.515 12.069 0.000 50.425 10.122 6.747 0.000 10.000
11+300.00 0.858 1.760 4.276 6.516 12.072 0.000 49.689 10.107 6.738 0.000 10.000
11+308.97 0.858 1.760 4.276 6.516 12.072 0.000 50.285 10.148 6.767 0.000 4.485
11+320.00 0.858 1.760 4.276 6.514 12.073 0.000 52.729 10.282 6.857 0.000 5.515
11+340.00 0.858 1.761 4.280 6.514 12.079 0.000 54.670 10.385 6.925 0.000 10.000
11+360.00 0.858 1.762 4.284 6.516 12.084 0.000 56.216 10.457 6.973 0.000 10.000
11+380.00 0.858 1.762 4.284 6.516 12.084 0.000 60.527 10.709 7.142 0.000 10.000
11+400.00 0.858 1.762 4.284 6.516 12.084 0.000 92.448 12.068 8.047 0.000 10.000
11+420.00 0.858 1.762 4.284 6.516 12.084 0.000 100.734 12.386 8.258 0.000 10.000
11+440.00 0.858 1.762 4.284 6.516 12.084 0.000 84.718 11.721 7.814 0.000 10.000
11+460.00 0.858 1.762 4.284 6.516 12.084 0.000 78.484 11.467 7.646 0.000 10.000
11+480.00 0.858 1.762 4.284 6.516 12.084 0.000 93.655 12.061 8.040 0.000 10.000
11+500.00 0.429 0.881 2.142 3.258 6.042 0.000 46.626 6.045 4.029 0.000 10.000
11+520.00 0.858 1.762 4.284 6.516 12.084 0.000 89.617 11.928 7.950 0.000 10.000
11+540.00 0.858 1.762 4.284 6.516 12.084 0.000 84.323 9.875 9.775 0.000 10.000
11+560.00 0.858 1.762 4.284 6.516 12.084 0.000 75.786 11.336 7.555 0.000 10.000
11+580.00 0.858 1.762 4.284 6.516 12.084 0.000 64.711 8.981 9.180 0.000 10.000
11+600.00 0.858 1.762 4.284 6.516 12.084 0.000 59.120 10.466 6.974 0.000 10.000
11+620.00 0.858 1.762 4.284 6.516 12.084 0.000 46.351 9.892 6.594 0.000 10.000
11+640.00 0.858 1.762 4.284 6.516 12.084 0.000 38.512 9.445 6.294 0.000 10.000
11+660.00 0.858 1.762 4.284 6.516 12.084 0.000 26.622 7.481 7.276 0.000 10.000
11+680.00 0.858 1.762 4.284 6.516 12.058 0.000 15.144 8.181 5.455 0.000 10.000
11+700.00 0.858 1.762 4.284 6.510 11.843 7.722 7.285 6.307 6.494 0.000 10.000
11+720.00 1.038 2.129 5.073 7.168 12.391 21.509 0.000 7.516 5.011 0.345 10.000
11+740.00 1.096 2.252 5.303 7.088 11.902 25.022 0.000 7.132 4.755 0.683 10.000
11+760.00 1.023 1.879 4.429 5.445 9.544 21.031 0.000 5.719 3.813 0.674 10.000
11+768.76 0.752 1.425 3.381 3.914 6.968 16.181 0.000 4.177 2.785 0.386 4.380
11+780.00 0.464 1.081 2.602 3.200 5.334 12.299 0.000 3.199 2.133 0.100 5.620
11+800.00 0.477 1.024 2.469 3.000 5.000 11.451 0.000 2.999 1.999 0.100 10.000
11+820.00 0.428 0.926 2.245 2.747 4.584 10.314 0.000 2.750 1.833 0.100 10.000
11+840.00 0.377 0.812 1.926 2.293 3.827 8.977 0.000 2.296 1.531 0.100 10.000
11+860.00 0.333 0.713 1.640 1.839 3.065 7.821 0.000 1.839 1.226 0.100 10.000
11+880.00 0.289 0.626 1.440 1.578 2.630 6.697 0.000 1.578 1.052 0.100 10.000
11+900.00 0.275 0.592 1.362 1.323 2.205 5.602 0.000 1.323 0.882 0.100 10.000
11+920.00 0.232 0.505 1.162 1.062 1.770 4.523 0.000 1.062 0.708 0.100 10.000
11+940.00 0.158 0.363 0.835 0.789 1.315 3.377 0.000 0.789 0.526 0.100 10.000
11+960.00 0.112 0.272 0.625 0.516 0.860 2.192 0.000 0.516 0.344 0.100 10.000
11+980.00 0.045 0.114 0.262 0.192 0.320 0.812 0.000 0.192 0.128 0.050 10.000
12+000.00 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 10.000
12+009.14 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 4.570
NOTA. LA VOLUMETRIA DE LOS CADENAMIENTOS 11+000 AL 11+260 SE CUANTIFICAN CON EL EJE 100
PROYECTO: ADECUACION AL PROYECTO EJECUTIVO DEL DISTRIBUIDOR VIAL EN EL ENTRONQUE CON LA AUTOPISTA
GUANAJUATO - SAN MIGUEL DE ALLENDE Y LA CARRETERA FEDERAL 45
MUNICIPIO: GUANAJUATO TRAMO: KM 100+430.87 SUBTRAMO:
KM: 100+000 A 101+539.91 ORIGEN: GUANAJUATO

VOLUMENES
ESTACION
V.CARP.A. V.B.A. V.B.H. V.S.R.S. V.S.Y.S. V.CORTE V.TERR. V.COMP V.DESP. A.D.CARP.

11+260.00 4.290 8.800 21.380 32.570 60.330 0.000 250.310 50.510 33.670 0.000
11+280.00 8.580 17.600 42.760 65.150 120.690 0.000 504.250 101.220 67.470 0.000
11+300.00 8.580 17.600 42.760 65.160 120.720 0.000 496.890 101.070 67.380 0.000
11+308.97 3.850 7.890 19.180 29.220 54.140 0.000 225.530 45.510 30.350 0.000
11+320.00 4.730 9.710 23.580 35.920 66.580 0.000 290.800 56.710 37.820 0.000
11+340.00 8.580 17.610 42.800 65.140 120.790 0.000 546.700 103.850 69.250 0.000
11+360.00 8.580 17.620 42.840 65.160 120.840 0.000 562.160 104.570 69.730 0.000
11+380.00 8.580 17.620 42.840 65.160 120.840 0.000 605.270 107.090 71.420 0.000
11+400.00 8.580 17.620 42.840 65.160 120.840 0.000 924.480 120.680 80.470 0.000
11+420.00 8.580 17.620 42.840 65.160 120.840 0.000 1007.340 123.860 82.580 0.000
11+440.00 8.580 17.620 42.840 65.160 120.840 0.000 847.180 117.210 78.140 0.000
11+460.00 8.580 17.620 42.840 65.160 120.840 0.000 784.840 114.670 76.460 0.000
11+480.00 8.580 17.620 42.840 65.160 120.840 0.000 936.550 120.610 80.400 0.000
11+500.00 4.290 8.810 21.420 32.580 60.420 0.000 466.260 60.450 40.290 0.000
11+520.00 8.580 17.620 42.840 65.160 120.840 0.000 896.170 119.280 79.500 0.000
11+540.00 8.580 17.620 42.840 65.160 120.840 0.000 843.230 98.750 97.750 0.000
11+560.00 8.580 17.620 42.840 65.160 120.840 0.000 757.860 113.360 75.550 0.000
11+580.00 8.580 17.620 42.840 65.160 120.840 0.000 647.110 89.810 91.800 0.000
11+600.00 8.580 17.620 42.840 65.160 120.840 0.000 591.200 104.660 69.740 0.000
11+620.00 8.580 17.620 42.840 65.160 120.840 0.000 463.510 98.920 65.940 0.000
11+640.00 8.580 17.620 42.840 65.160 120.840 0.000 385.120 94.450 62.940 0.000
11+660.00 8.580 17.620 42.840 65.160 120.840 0.000 266.220 74.810 72.760 0.000
11+680.00 8.580 17.620 42.840 65.160 120.580 0.000 151.440 81.810 54.550 0.000
11+700.00 8.580 17.620 42.840 65.100 118.430 77.220 72.850 63.070 64.940 0.000
11+720.00 10.380 21.290 50.730 71.680 123.910 215.090 0.000 75.160 50.110 3.450
11+740.00 10.960 22.520 53.030 70.880 119.020 250.220 0.000 71.320 47.550 6.830
11+760.00 10.230 18.790 44.290 54.450 95.440 210.310 0.000 57.190 38.130 6.740
11+768.76 3.290 6.240 14.810 17.140 30.520 70.870 0.000 18.300 12.200 1.690
11+780.00 2.610 6.080 14.620 17.980 29.980 69.120 0.000 17.980 11.990 0.560
11+800.00 4.770 10.240 24.690 30.000 50.000 114.510 0.000 29.990 19.990 1.000
11+820.00 4.280 9.260 22.450 27.470 45.840 103.140 0.000 27.500 18.330 1.000
11+840.00 3.770 8.120 19.260 22.930 38.270 89.770 0.000 22.960 15.310 1.000
11+860.00 3.330 7.130 16.400 18.390 30.650 78.210 0.000 18.390 12.260 1.000
11+880.00 2.890 6.260 14.400 15.780 26.300 66.970 0.000 15.780 10.520 1.000
11+900.00 2.750 5.920 13.620 13.230 22.050 56.020 0.000 13.230 8.820 1.000
11+920.00 2.320 5.050 11.620 10.620 17.700 45.230 0.000 10.620 7.080 1.000
11+940.00 1.580 3.630 8.350 7.890 13.150 33.770 0.000 7.890 5.260 1.000
11+960.00 1.120 2.720 6.250 5.160 8.600 21.920 0.000 5.160 3.440 1.000
11+980.00 0.450 1.140 2.620 1.920 3.200 8.120 0.000 1.920 1.280 0.500
12+000.00 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
12+009.14 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000 0.000
TOTAL 253.490 521.950 1 259.300 1 818.920 3 309.910 1 510.490 13 523.270 2 660.320 1 883.170 28.770
PROYECTO:
ADECUACION AL PROYECTO EJECUTIVO DEL DISTRIBUIDOR VIAL EN EL ENTRONQUE CON LA AUTOPISTA
GUANAJUATO - SAN MIGUEL DE ALLENDE Y LA CARRETERA FEDERAL 45
MUNICIPIO:
GUANAJUATO TRAMO: KM 100+430.87 SUBTRAMO:
KM: 100+000 A 101+539.91 ORIGEN: GUANAJUATO

SIMBOLOGIA
A.CARP.A. ÁREA DE CARPETA ASFÁLTICA.
A.B.A AREA DE BASE ASFALTCA
A.B.H. AREA DE BASE HIDRAULICA
A.S.R.S. AREA DE SUBRASANTE
A.S.Y.S. AREA DE SUBYACENTE
A.CORTE. AREA DE CORTE
A.TERR. AREA DE TERRAPLEN
A.COMPACT. AREA DE COMPACTACION
A.DESP. AREA DE DESPALME
A.ESC.L. AREA DE ESCALON DE LIGA
A.D.CARP. AREA DE DEMOLICION DE CARPETA

EMULSION PARA RIEGO DE IMPREGNACIÓN = 7 604.700 LT


BARRIDO DE LA SUPERFICIE A TRATAR = 0.507 HA
ARENA PARA CUBRIR LA BASE IMPREGNADA = 40.558 M3

VOLUMEN DE CARPETA ASFÁLTICA. V.CARP.A.= 253.490 m³


VOLUMEN DE BASE ASFALTCA V.B.A= 521.950 m³
VOLUMEN DE BASE HIDRAULICA V.B.H.=1 259.300 m³
VOLUMEN DE SUBRASANTE V.S.R.S.= 1 818.920 m³
VOLUMEN DE SUBYACENTE V.S.Y.S.=3 309.910 m³
VOLUMEN DE CORTE V.CORTE.= 1 510.490 m³
VOLUMEN DE TERRAPLEN V.TERR.= 13 523.270 m³
VOLUMEN DE COMPACTACION V.COMPACT.= 2 660.320 m³
VOLUMEN DE DESPALME V.DESP. = 1 883.170 m³
VOLUMEN DE ESCALON DE LIGA V.ESC.L.= 0.000 m³
VOLUMEN DE DEMOLICION DE CARPETA V.D.CARP.= 28.770 m³
NOTA. LA VOLUMETRIA DE LOS CADENAMIENTOS 11+000 AL 11+260 SE CUANTIFICAN CON EL EJE 100