Ejercicios Carguio PDF
Ejercicios Carguio PDF
FACULTAD DE INGENIERIA
DEPARTAMENTO DE MINAS
ING. DE EJEC. EN MINAS
DESARROLLO:
Bf = Kr * FCV
FCV= 0.635 / 0.95 = 0.668
DESARROLLO:
FE:FACTOR DE EQUILIBRIO
FE:27/3 * 4/40=9*0.1=0.90 EXESO DE CAPACIDAD DE CARGA, SIGNIFICA QUE LA
EFICIENCIA DE TRANSPORTE ES DE UN 100% MIENTRAS QUE EN EL CARGUI ES DE 90%
ASUMA:
DESARROLLO
TV=(X/35KM/HR)+(X/40KM/HR)=(75/1400)X=0.05357HR/KM=0.0032METROS/MINUTOS
TF+TV=VT/VP *TCRP (n-1) COMO n=3
0.9167+0.0032X=5*0.866*2
X=2423 METROS
4- UNA UNIDAD DE CARGUIO OPERA A RAZON DE TRES TURNOS POR DIA PARA UNA
PRODUCCION MENSUAL DE 42413 TONELADDAS, UN ESTUDIO DE TIEMPO NOS
ARROJO LOS SIGUIENTES DATOS:
SE PIDE:
1- RENDIMIENTO EFECTIVO
2- IOps SEGN ASARCO : COMENTE VALORES
3- FACTOR DE UTILIZACION REAL
DESARROLLO:
U=319.25/(319.25+140)=69.51
KU= 269.25/531.25=50.68%
5- UN CARGADOR FRONTAL DE 6 YARDAS CUBICAS LLEVA UNA CARGA DE 6270 KGS PARA
UN TIEMPO DE CICLO DE 40 SEGUNDOS EN UN TERRENO DE DENSIDAD DE 2.4 TON POR METRO
CUBICO CON UN FACTOR DE ESPONJAMIENTO DE 49.25 %
ASUMA:
SE PIDE:
DESARROLLO:
QHP=CP*NC*S-1 *A*O*BF*P*DESP.
NC=3600/40=90
S-1=1/1,1
A=(8-1.5)/8=0.8125
FO=(6.5-1.3)/6.5=0.80
FCV=1.608/2.4=0.67
P=0.75
2- KC=F(GRANULOMETRIA)
KC 1 100%
1.02 80%
1.10 60%
1.25 40%
EQUIPOS:
- CARGADOR FRONTAL 6 YARDAS CUBICAS
Kr=0.80 TCP=42 SEG
- CAMION 35 TONELADAS
Kll=0.95 CON 4% DE HUMEDAD TF=3.75 MIN
PRODUCCION=175000 TON/MES
DENSIDAD ESP. 1.6 TON/METRO CUBICO
DISTANCIA=1200 METROS
TRABAJA: 2 TURNOS POR DIA
VELOCIDAD MAX: 35 KM/HR CARGADO
40 KM/HR VACIO
HORAS OPERACIONALES:6.3 HR/TURNO
FO:90%
HORAS MANTENCION:0.7 HR/TURNO
DESARROLLO:
TC(CAMION)=TF + TV + TC(PALA)*P
TV=1200/583.33 +1200/666.66
TV=3.857 MINUTOS
TCC=11.807 MINUTOS
FACTOR DE EQUILIBRIO
FE= N * p*TCPR
Xp TCC
DONDE
Xp=617.28TON /HORA
QHP
QHP=4.5876*3600/42*11.34/16*1.6*0.80=356.724TON/HORA
n=TCC
P*TCP=2.81 3 CAMIONES POR CARGADOR
FE=1.067
RENDIMIENTO DE CAMION
CONSIDERE :
DESARROLLO:
HROP=8-1=7HORAS
DF=HROP = 7/8=0.875
HRPROG
FO=HREF/HROP=0.82
HREF=0.82*7*25*12=1722HREF/AO
COSTO FIJO=0.00011614CIF-0.22888
NOTITA: 37.5 KM EN UNA HORA , 70000 KM QUE ES LA VIDA UTIL DE LOS NEUMATICOS, SE
RECORRERAN EN 1866HORAS.(HORAS AL AO)
COSTO VARIABLE=(8.1+0.000092912-0.199104)*1.1
COSTO VARIABLE=8.69+0.00010220CIF
CIF=38235.68US$/HR
ASUMA:
CARGADOR CAMION
DISPONIBILIDAD FISICA 0.70 0.90
FACTOR OPERACIONAL 0.80 ----
FACTOR DE LLENADO 0.85 0.95(C/5%H)
TIEMPO DE CICLO REAL 45 SEG ----
TIEMPO DE DESCARGA ----- 1.20MIN
TIEMPO DE MANIOBRA ---- 0.80MIN
DIATANCIA RECORRIDO ---- 2800METROS
VIDA UTIL 12 AOS 6 AOS
FACTOR M Y R 0.70 0.80
NEUMATICOS (UNIDAD) 10000US$/HR 5000US$/HR(80000KM)
MANO DE OBRA 5US$/HR 5US$/HR
COSTO COMBUSTIBLE 4.8US$/HR 5US$/HR
COSTO OPERACIN 22.50 3.00
SE PIDE:
DESARROLLO:
HREFECT (CARGADOR)=FO*DF*HRPROG=0.70*0,80*16=8,96HREFECT/DIA
224HREF/MES
2688HREF/AO
PRODUCCION HORARIA=330.000(TON/MES)*1(MES/25DIAS)*1(DIA/8,96HREF)
=1.473,214(TON/HR)
F.C.V=1/(1+E%)=DE/DRDE=1.71(TON/M3)
P(NPALADAS)=100(TON)*0.95*0.95 =8.121269PALADAS
10(YD^3)*0.85*1.17(TON/M^3)
TCC(TIEMPO CICLO CAMION)=TF+TV+TCPR*P (TV=T IDA + VUELTA)
=1,20(MIN)+0,80(MIN) +2800 +_ 2800 +45(SEG)*1(MIN)*9
40(KM/HR) 35(KM/HR) 60(SEG)
=17,75(MIN)
TF=TM+TD+TE+TCD
NCAMIONES=TCC/TCPR*P
=17,75(MIN) =2,6296(CAMIONES/CARGADOR)3 CAMIONES/CARG
45(SEG)*1(MIN)*9
60(SEG)
QH(CARGADOR)=CP(M^3)*NC*DE*DF*FO*KR
=10(YD^3)*0.7646*(3600/45)*1.71(TON/M^3)*0.7*0.8*0.85
=494,94223(TON/HR)
3 CARGADORES9CAMIONES
=1.473,214(TON/HR)/9=163,694(TON/HR)
QH(CAMION)=CP(TON)*NC*KU*KR*% HUMEDAD
=57.29US$/HR
CF=CIF-(5000*6) + 0.1*(6+1)*CIF
6*16*0.52*300 2*6*300*16*0.52
CV=(5+5+2.5+(6.677350*10E-5CIF-2.0032)0.80+(6*5000*37.5/80000))1.1
CV=0.00005876CIF+27.4559
CIF = 213810.62US$/HR
DESARROLLO
FCV=DE/DR
DE=0.67*2.567TON/M3
DE=1.72 TON/M3
PALADAS=TON TOLVA*KR
TON BALDE*KR
PALADAS=100*0.9464
10*0.7646*0.90*1.72
PALADAS=7.998 PALADAS
TCC= 1.35+0.50+(1000/35*1000/60)+(1000/40*1000/60)+40*8/60
TCC=10.3976MIN
N=10.3976MIN/40*8=2CAMIONES/CARGADOR
QH(CARGADOR)= 7.6455M3*(3600/40)*1.72*54.6/60*0.8125*0.90
QH(CARGADOR)=787.56 TON/HR
= 1.45
= 2 CARGADORES
=295.21TON/HR*0.112US$/TON
=33.0635US$/HR
CF=CIF-(500*6) + 0.1(6.5+1)CIF
6.5*16*0.54055*300 2*6.5*300*16*0.54055
CF=0.00005929CIF-0.1778 + 0.000022235
COSTO VARIABLE=23.804+5.217E-5
LUBRICACION=50%COMBUSTIBLE
INSUMOS=6*500*37.5/8000=14.0625
CIF=9.43/1.336E-4
CIF=70583
10-EN UNA FAENA CIELO ABIERTO OPERA UN CARGADOR FRONTAL DE 6 YARDAS CUBICAS
CON CAMIONES DE 50 TONELADAS PARA UNA PRODUCCION DE 330300 TONELADAS AL MES
PARA UN MATERIAL DE DENSIDAD 1,60 TONELADAS POR METRO CUBICO A RAZON DE 2
TURNOS DIARIOS:
DETERMINAR:
DESARROLLO.
HREFEC= 16*0,75= 12 HR
TCC= 10,507[MIN]
QH(CAMION)=1101[TON/HR] /6 = 183,5[TON/M^3]
EL VALOR 1,1992 (VER GRAFICA) IMPLICA QUE EL CARGUIO ESTA TRABAJANDO A UN 100%
PERO LOS CAMIONES NO, ENTONCES TIENEN Q ESPERAR.
QH(CAMION)=CP(TON)*NC*KU
CIF=82013,65[US$/HR]