ANALISIS DE COSTOS

FACULTAD DE ARQUITECTURA
EMPRESA: TLEYD ARQUITECTS S.A. DE C.V
DESCRIPCION : CONJ-01 MAESTRO
(MAESTRO, 2 ALBAIL ,2 UNIDAD JORNAL
PEONES) PEONES

Clave Concepto Unidad Cantidad Precio Unitario Importe

MSTR-019 MAESTRO JORNAL 1 $564.98 $564.98


MSTR-015 PEON JORNAL 2 $251.48 $502.96

SUMA PARCIAL $1,067.94

MANDO
CJNT-01 %MANO DE OBRA 0.1 $1,067.94 $106.79
INTERMEDIO

SUMA PARCIAL $106.79

HERRAMIENTA
CNJT-01 %MANO DE OBRA 0.3 $1,174.73 $35.24
MENOR

SUMA PARCIAL $35.24

SUMA TOTAL
$1,209.98

UNIDAD JORNAL

Clave Concepto Unidad Cantidad Precio Unitario Importe

OF. CARPINTERO
MSTR-03 JORNAL 1 $500.32 $500.32
OBRA BLANCA

MSTR-015 PEON JORNAL 2 $251.48 $502.96

SUMA PARCIAL $1,003.28


MANDO
CJNT-01 %MANO DE OBRA 0.1 $1,003.28 $100.33
INTERMEDIO

SUMA PARCIAL $100.33

HERRAMIENTA
CNJT-01 %MANO DE OBRA 0.3 $1,103.61 $33.11
MENOR

SUMA PARCIAL $33.11

SUMA TOTAL
$ 1136.72

DESCRIPCION CONJ-03 (2OFICIAL YESERO, 2 PEONES) UNIDAD JORNAL

Clave Concepto Unidad Cantidad Precio Unitario Importe

MSTR-005 OF. YESERO JORNAL 2 $437.14 $874.28


MSTR-015 PEON JORNAL 2 $251.48 $502.96

SUMA PARCIAL $1,377.24

MANDO
CJNT-01 %MANO DE OBRA 0.1 $1,377.24 $137.72
INTERMEDIO

SUMA PARCIAL $137.72

HERRAMIENTA
CNJT-01 %MANO DE OBRA 0.3 $1,514.96 $45.45
MENOR

SUMA PARCIAL $45.45

SUMA TOTAL
$1,560.41
DESCRIPCION CONJ-04 (2OFICIAL CARPINTERO DE OBRA NEGRA, 2 PEONES)
UNIDAD JORNAL

Clave Concepto Unidad Cantidad Precio Unitario Importe

MSTR-001 OFICIAL ALBAIL JORNAL 1 $412.65 $412.65

MSTR-015 PEON JORNAL 8 $251.48 $2,011.84


SUMA PARCIAL $2,424.49
MANDO
CJNT-01 %MANO DE OBRA 0.1 $2,424.49 $242.45
INTERMEDIO
SUMA PARCIAL $242.45

HERRAMIENTA
CNJT-01 %MANO DE OBRA 0.3 $2,666.94 $80.01
MENOR

SUMA PARCIAL $80.01


SUMA TOTAL
$2746.95

DESCRIPCION CONJ-05 (2 OFICIAL CARPINTERO OBRA NEGRA, 2 PEONES)


UNIDAD JORNAL

Clave Concepto Unidad Cantidad Precio Unitario Importe

OF. CARPINTERO
MSTR-002 JORNAL 2 $412.65 $825.30
DE OBRA NEGRA
MSTR-015 PEON JORNAL 2 $251.48 $502.96
SUMA PARCIAL $1,328.26
MANDO
CJNT-01 %MANO DE OBRA 0.1 $1,328.26 $132.83
INTERMEDIO
SUMA PARCIAL $132.83
HERRAMIENTA
CNJT-01 %MANO DE OBRA 0.3 $1,461.09 $43.83
MENOR

SUMA PARCIAL $43.83

SUMA TOTAL
$ 1504.92

DESCRIPCION C ONJ.06 2 Of . Ebanerista,2 Ayudantes UNIDAD JORNAL


CLAVE 5 CONCEPTO UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE

MSTR-001 OF.EBANERISTA JORNAL 2 $500.32 $1000.64

MSTR-002 AYUDANTE "B" JORNAL 2 $259.90 $519.80

SUMA PARCIAL $1520.44

MANDO % MANO DE
CJNT-001 0.1 $1520.44 $152.04
INTERMEDIO OBRRA

SUMA PARCIAL $152.04

HERRAMIENTA % MANO DE
CJNT-002 0.03 $1672.48 $50.17
MENOR OBRA
SUMA TOTAL $1722.66

DESCRIPCION CONJ-07 2 Of. Azulejero, 2 Ayudantes UNIDAD JORNAL

CLAVE 6 CONCEPTO UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE

MSRT-003 OF. AZULEJERO JORNAL 2 $437.14 $874.28

MSRT-004 PEON JORNAL 2 %251.48 $502.96

SUMA PARCIAL $1377.24

MANDO % MANO DE
CJNT-003 0.1 $1377.24 $137.72
INTERMEDIO OBRA

SUMA PARCIAL $137.72

HERRAMIENTA % MANO DE
CJNT-004 0.03 $1514.96 $45.45
MENOR OBRA

SUMA TOTAL $1560.41

DESCRIPCION CONJ-08 1 Of. Electricista, 2 Ayudantes UNIDAD JORNAL


CLAVE CONCEPTO UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE
MSRT-005 OF. ELECTRICISTA JORNAL 1 $500.32 $500.32

AYUDANTE"A"P/IN
MSRT-006 JORNAL 2 $292.94 $585.88
ST.

SUMA PARCIAL $1086.20

MANO
CJNT-005 %MANO DE OBRA 0.1 $1086.20 $108.62
INTERMEDIO

SUMA PARCIAL $108.62

HERRAMIENTA
CJNT-006 %MANO DE OBRA 0.03 $1194.82 $35.84
MENOR
SUMA TOTAL $1230.66

DESCRIPCION CONJ-09 Encargado de Bode jornal UNIDAD JORNAL

CLAVE CONCEPTO UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE

ENCARGADO DE
MSRT-007 JORNAL 1 $212.56 $212.56
BODEGA

SUMA PARCIAL $212.56

MANDO
CNJT-007 %MANO DE OBRA 0.1 $212.56 $21.26
INTERMEDIO

SUMA PARCIAL $21.26

HERRAMIENTA % MANO DE
CNJT-008 0.03 $233.82 $7.01
MENOR OBRA
SUMA TOTAL $240.83
DESCRIPCIN CONJ-10 (2OFICIAL HERRERO, 3 AYUDANTE "B" UNIDAD JORNAL

CLAVE CONCEPTO UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE

MSTR-010 OF. HERRERO JORNAL 2 $412.65 $825.30

MSTR-018 AYUDANTE "B" JORNAL 3 $259.90 $779.70

SUMA PARCIAL $1,605.00

MANDO % MANO DE
CNJT-01 0.1 $1,605.00 $160.00
INTERMEDIO OBRA

SUMA PARCIAL $160.50

HERRAMIENTA % MANO DE
CNJT-01 0.03 $1,765.50 $52.97
MENOR OBRA

SUMA TOTAL $1,818.47

DESCRIPCIN CONJ-11 (2 OFICIAL MECANICO) UNIDAD JORNAL

CLAVE CONCEPTO UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE

MSTR-011 OF. MECANICO JORNAL 1 $500.32 $500.32

SUMA PARCIAL $500.32

MANDO % MANO DE
CNJT-01 0.1 $500.32 $50.03
INTERMEDIO OBRA

SUMA PARCIAL $50.03

HERRAMIENTA % MANO DE
CNJT-01 0.03 $550.35 $16.51
MENOR OBRA

SUMA TOTAL $566.86

DESCRIPCIN CONJ-12 (1 OFICIAL PINTOR, 1 PEN) UNIDAD JORNAL


CLAVE CONCEPTO UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE

MSTR-012 OF. PINTOR JORNAL 1 $412.65 $412.65


MSTR-015 PEN JORNAL 1 $251.48 $251.48

SUMA PARCIAL $664.13

MANDO % MANO DE
CNJT-01 0.1 $664.13 $66.41
INTERMEDIO OBRA

SUMA PARCIAL $66.41

HERRAMIENTA % MANO DE
CNJT-01 0.03 $730.54 $21.92
MENOR OBRA

SUMA TOTAL
$752.46

DESCRIPCIN CONJ-13 (OFICIAL PLOMERO, 2 PEONES) UNIDAD JORNAL

CLAVE CONCEPTO UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE

MSTR-13 OF. PLOMERO JORNAL 1 $500.32 $500.32


MSTR-15 PEN JORNAL 2 $251.48 $502.96

SUMA PARCIAL $ 1, 003.28

MANDO % MANO DE
CNJT-01 0.1 $1,003.28 $100.33
INTERMEDIO OBRA

SUMA PARCIAL $100.33

HERRAMIENTA % MANO DE
CNJT-01 0,03 $ 1.103.608 $33.11
MENOR OBRA

SUMA TOTAL $1,136.72

DESCRIPCIN CONJ-14 ( VELADOR) UNIDAD JORNAL

CLAVE CONCEPTO UNIDAD CANTIDAD PRECIO UNITARIO IMPORTE


MSTR-014 VELADOR JORNAL 1 $222.07 $222.07

SUMA PARCIAL $222.07

MANDO % MANO DE
CNJT-01 0.1 $222.07 $22.21
INTERMEDIO OBRA

SUMA PARCIAL $22.21

HERRAMIENTA % MANO DE
CNJT-01 0.03 $244.28 $7.33
MENOR OBRA

SUMA TOTAL $251.61

Descripcin : CONJ-15 1 OF.Albail,11 Peones Unidad : Jornal

Clave Concepto Unidad Cantidad Precio Unitario Importe

MTRS-001 OFICIAL ALBAIL JORNAL 1 $412.65 $412.65

MTRS-015 PEON JORNAL 11 $251.48 $2,766.28

SUMA PARCIAL $3,178.85

CNJT-01 Mando intermedio %MANO DE OBRA 0.01 $2,766.28 $276.63

SUMA PARCIAL $276.63

HERRAMIENTA % MANO DE
CNJT-01 0.03 $3,042.91 $91.29
MENOR OBRA
SUMA TOTAL $3,546.77

Descripcin : CONJ-16 1 OF.Albail,2 Peones Unidad : Jornal

Clave Concepto Unidad Cantidad Precio Unitario Importe

MTRS-001 OFICIAL ALBAIL JORNAL 1 $412.65 $412.65

MTRS-015 PEON JORNAL 2 $109.33 $218.66


SUMA PARCIAL $631.31

MANDO
CNJT-01 %MANO DE OBRA 0.1 $631.31 $63.13
INTERMEDIO
SUMA PARCIAL $63.13
HERRAMIENTA % MANO DE
CNJT-01 0.03 $694.44 $20.83
MENOR OBRA
SUMA TOTAL $715.27

Descripcin : CONJ-17 ( 1 OF. Carpintero de obra negra,1 pen) Unidad : Jornal

Clave Concepto Unidad Cantidad Precio Unitario Importe

Of. CARPINTERO
MTRS-002 JORNAL 1 $412.65 $412.65
DE OBRA NEGRA

MTRS-015 PEON JORNAL 1 $251.48 $251.48

SUMA PARCIAL $664.13

MANDO
CNJT-01 %MANO DE OBRA 0.1 $664.13 $66.41
INTERMEDIO

SUMA PARCIAL $66.41

HERRAMIENTA % MANO DE
CNJT-01 0.03 $730.54 $21.92
MENOR OBRA
SUMA TOTAL $752.46

Descripcin : CONJ-18 2 Peones Unidad : Jornal

Clave Concepto Unidad Cantidad Precio Unitario Importe

MTRS-015 PEON JORNAL 2 $251.48 $502.96


SUMA PARCIAL $502.96
MANDO
CNJT-01 %MANO DE OBRA 0.1 $502.96 $50.30
INTERMEDIO
SUMA PARCIAL $50.30
HERRAMIENTA % MANO DE
CNJT-01 0.03 $553.26 $16.60
MENOR OBRA
SUMA TOTAL $569.86