Precios Unitarios de La Construccion 2014
Precios Unitarios de La Construccion 2014
FECHA: JULIO/2014
DESCRIPCION
DOS PLANTAS:
180 m2
AREA LIBRE:
CANTIDAD
P. UNITARIO
OBRAS PRELIMINARES
Limpieza
m2
150
0.97
1.2
Replanteo y Nivelacion
m2
43.56
1.92
1.3
Terreno
m2
150
42
1.1
CIMENTACION
2.1
m3
23.16
8.31
2.2
m3
3.08
102.18
3. 1
m3
2.78
128.69
3.2
m3
6.14
110.74
3.3
m3
5.94
131.24
3.4
m2
80.16
144.76
3.5
m3
4.42
139.76
3.6
m3
0.78
157.99
3.7
Acero de refuerzo 8- I 2 mm
Kg
1,780.08
1.74
4.1
m2
37.78
14.41
4.2
m2
159.61
12.38
4.3
m2
240.22
7.39
4.4
m2
102.27
6.72
4.5
m2
153.12
5.53
4.6
29.82
4.7
400
7,63
4.8
Alambre (Rollo)
Roll.
24.73
4.9
Arena(M3)
m3
8.78
4.10
BLOQUE MACIZO DE 10
2250
0.28
4.11
BLOQUE HUECO DE 12
860
0.3
5
5. 1
INSTALACIONES HIDROSANITARIAS
Punto de agua potable HG 0 1/2"
Pto.
15
10.41
5.2
Pto
31.05
5.3
Pto
56.11
5.4
64.1
5.5
84.98
5.6
134.78
5.7
49.01
5.8
Valvula De Compuerta3/4"
3.01
5.9
252
1.23
5.10
Llave De Paso
5.11
Valvula De Chek
1.23
5.12
49.89
2.33
5.13
15
5.14
26.07
5.15
14
10.8
5.16
6
6.1
Tuberias Afria
18
8.33
INSTALACIONES ELECTRICAS
Tomacorrientes 110 V
Pto.
13
15.37
6.2
Pto.
10
14.25
6.3
24.42
6.4
CABLEADO (m)
35
0.41
6.5
249
CARPINTERIA DE MADERA
7. I
66.23
7.2
71.26
2.3
124.93
7.3
7.4
2.3
138.89
7.5
Closet (Lacado)
7.5
100.43
69.22
16.29
19.73
8.1
m2
8.3
Piso de Cermica
m2
7.59
8.3
m2
240.22
4.42
8.4
m2
16.41
19.06
8.5
m2
20
16.29
9
9.1
ALUMINIO Y VIDRIO
Ventana de Hierro
m2
24.88
61.69
9.2
m2
24.88
10.92
lO
BAJANTES
m
7.56
16.42
10.1
SUBTOTAL
12% IVA
TOTAL
P.TOTAL
145.5
83.6352
6300
192.4596
314.7144
357.7582
679.9436
779.5656
11603.9616
617.7392
123.2322
3097.3392
544.4098
1975.9718
1775.2258
687.2544
846.7536
89.46
#VALUE!
197.84
70.24
630
258
156.15
279.45
112.22
128.2
169.96
134.78
98.02
3.01
504
4.92
2.46
99.78
34.95
26.07
151.2
149.94
199.81
142.5
24.42
14.35
249
331.15
142.52
287.339
319.447
753.225
1127.5938
149.7507
1061.7724
312.7746
325.8
1534.8472
271.6896
124.1352
#VALUE!
#VALUE!
#VALUE!
ELABORACION:
FECHA: JULIO/2014
RUBRO
1
DESCRIPCION
DOS PLANTAS:
180 m2
AREA LIBRE:
CANTIDAD
P. UNITARIO
ESTRUCTURA ORGANIZATIVA
1.1
GERENTE
1200
1.2
SECRETARIA
340
1.3
BODEGERO
340
1.4
1.5
CHOFER
1.6
OPERADOR DE MAQUINARIA
372.3
1.7
OBREROS
347.14
1.8
RESIDENTE DE OBRA
394.06
372.3
512.35
1.9
INGENIEROS CIVILES
1.10
ARQUITECTO
1.11
PLOMERO
351.7
1.12
PINTOR
351.7
1.13
ELECTRICISTA
351.7
IMPLANTACION DE LA EMPRESA
2.1
INFRAESTRUCTURA
90000
2.2
CONCRETERAS
1500
2.3
ELEVADORES
1800
2.4
VOLQUETA
70000
2.5
30000
2.6
PLOTER
4000
2.7
MUEBLES
5500
COMPUTADORAS
800
2.9
IMPRESORA/COPIADORA
1000
2.10
TERRENO (m2)
1200
42
2.8
m2
SUBTOTAL
12% IVA
TOTAL
P.TOTAL
1200
340
340
0
512.35
372.3
1735.7
394.06
744.6
0
351.7
351.7
351.7
90000
3000
3600
70000
30000
4000
5500
4000
1000
50400
268194.11
32183.2932
300377.4032