COMPARATIVO PROYECTO CANINOS

presupuesto de Tecnico Plantilla de presupuesto DIFERENCIAS


Item Descripción Und. Metrado Precio (S/.) Parcial (S/.) Metrado Precio (S/.) Parcial (S/.) Metrado Precio (S/.) Parcial (S/.)
OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD,
01 383,797.39 370,663.54 13,133.85
SALUD Y MEDIO AMBIENTE
01.01 OBRAS PROVISIONALES Y TRABAJOS PRELIMINARES 262,374.90 249,241.05
01.01.01 CONSTRUCCIONES PROVISIONALES 95,159.21 82,046.71
01.01.01.02 ALMACEN GENERAL m2 100.00 191.58 19,158.00 50.00 191.58 9,579.00 50.00 - 9,579.00
01.01.01.03 AREA DE TRABAJO DE ACERO m2 100.00 70.67 7,067.00 50.00 70.67 3,533.50 50.00 - 3,533.50
01.01.05 TRAZOS, NIVELES Y REPLANTEO 67,751.72 67,730.36
01.01.05.01 TRAZO, NIVELES Y REPLANTEO PRELIMINAR m2 16,231.50 2.00 32,463.00 16,220.82 2.00 32,441.64 10.68 - 21.36
02 ESTRUCTURAS 4,872,916.31 2,247,126.31 2,625,790.00
02.01.02 EXCAVACIONES 217,921.85 89,921.85
02.01.02.01 EXCAVACIONES MASIVAS m3 24,674.89 6.40 157,919.30 4,674.89 6.40 29,919.30 20,000.00 - 128,000.00
02.01.05 ELIMINACIÓN DE MATERIAL EXCEDENTE 471,393.77 121,393.77
ACARREO INTERNO, MATERIAL PROCEDENTE DE
02.01.05.01 m3 26,026.37 3.40 88,489.66 6,026.37 3.40 20,489.66 20,000.00 - 68,000.00
EXCAVACIONES
02.01.05.02 ELIMINACIÓN DE MATERIAL EXCEDENTE m3 27,156.32 14.10 382,904.11 7,156.32 14.10 100,904.11 20,000.00 - 282,000.00
02.02.03 SOLADOS 188,658.68 46,338.68

02.02.03.01 CONCRETO PRE-MEZCLADO F'C=100 kg/cm², SOLADOS E=10CM m2 5,302.38 35.58 188,658.68 1,302.38 35.58 46,338.68 4,000.00 - 142,320.00

02.02.05 SARDINEL 152,963.79 106,433.79


02.02.05.02 ENCOFRADO Y DESENCOFRADO NORMAL, SARDINEL m2 2,203.56 46.53 102,531.65 1,203.56 46.53 56,001.65 1,000.00 - 46,530.00
02.03.01 ZAPATAS 199,517.42 159,173.42
02.03.01.02 ENCOFRADO Y DESENCOFRADO NORMAL, ZAPATAS m2 983.43 67.24 66,125.83 383.43 67.24 25,781.83 600.00 - 40,344.00
02.03.02 VIGAS DE CIMENTACIÓN 486,186.61 186,286.61

CONCRETO PRE-MEZCLADO F'C=210 kg/cm², VIGAS DE


02.03.02.01 m3 528.20 300.50 158,724.10 328.20 300.50 98,624.10 200.00 - 60,100.00
CIMENTACION

ENCOFRADO Y DESENCOFRADO NORMAL, VIGAS DE


02.03.02.02 m2 3,106.74 71.60 222,442.58 1,106.74 71.60 79,242.58 2,000.00 - 143,200.00
CIMENTACIÓN

02.03.02.03 ACERO CORRUGADO F'Y=4200 kg/cm² kg 21,085.34 4.83 101,842.19 1,085.34 4.83 5,242.19 20,000.00 - 96,600.00

02.03.04 MUROS DE CONTENCION 1,372,391.68 123,607.68


CONCRETO PRE-MEZCLADO F'C=210 kg/cm², MUROS DE
02.03.04.01 m3 1,867.50 319.52 596,703.60 167.50 319.52 53,519.60 1,700.00 - 543,184.00
CONTENCION
ENCOFRADO Y DESENCOFRADO NORMAL, MURO DE
02.03.04.02 m2 6,381.89 61.25 390,890.76 381.89 61.25 23,390.76 6,000.00 - 367,500.00
CONTENCION
02.03.04.03 ACERO CORRUGADO F'Y=4200 kg/cm² kg 78,307.24 4.83 378,223.97 8,307.24 4.83 40,123.97 70,000.00 - 338,100.00
02.03.05 COLUMNAS 321,906.81 166,694.81
02.03.05.01 CONCRETO PRE-MEZCLADO F'C=210 kg/cm², COLUMNAS m3 166.32 319.52 53,142.57 66.32 319.52 21,190.57 100.00 - 31,952.00
02.03.05.02 ENCOFRADO Y DESENCOFRADO NORMAL, COLUMNAS m2 2,249.88 74.96 168,651.00 1,249.88 74.96 93,691.00 1,000.00 - 74,960.00
02.03.05.03 ACERO CORRUGADO F'Y=4200 kg/cm² kg 20,247.59 4.83 97,795.86 10,247.59 4.83 49,495.86 10,000.00 - 48,300.00
02.03.06 VIGAS 210,752.69 130,952.69
02.03.06.02 ENCOFRADO Y DESENCOFRADO NORMAL, VIGAS m2 1,436.05 79.80 114,596.79 436.05 79.80 34,796.79 1,000.00 - 79,800.00
02.03.07.02 LOSA ALIGERADA CONVENCIONAL 01 DIRECCIÓN, H=0.25M 229,841.96 176,161.96
03 ARQUITECTURA 2,379,217.59 1,719,437.87 659,779.72
03.01 MUROS Y TABIQUES DE ALBAÑILERIA 257,402.26 180,092.26
MURO DE LADRILLO KK DE ARCILLA DE SOGA, MEZCLA 1:5 JUNTA
03.01.02 m2 2,003.74 77.31 154,909.14 1,003.74 77.31 77,599.14 1,000.00 - 77,310.00
1,5 cm
03.02 REVOQUES Y REVESTIMIENTOS 350,860.82 253,660.82

03.02.02 TARRAJEO EN MUROS INTERIORES, E=1.5 cm, C:A 1:5 m2 3,322.59 27.48 91,304.77 1,322.59 27.48 36,344.77 2,000.00 - 54,960.00

TARRAJEO EN COLUMNAS CON C:A - 1:5 E=1.5 CM INCL.


03.02.05 m2 1,175.09 42.24 49,635.80 175.09 42.24 7,395.80 1,000.00 - 42,240.00
VESTIDURA DE ARISTAS

03.04 PISOS Y PAVIMENTOS 415,317.10 273,747.10

03.04.01 CONTRAPISOS 222,039.11 80,469.11

CONTRAPISO DE CONCRETO SIMPLE E=5 cm CON


03.04.01.02 m2 1,850.87 52.57 97,300.24 850.87 52.57 44,730.24 1,000.00 - 52,570.00
IMPERMEABILIZANTE

03.04.01.03 CONTRAPISO DE 50 mm MEZC. 1:5 ACAB. 1CM PASTA 1:2 m2 2,285.00 44.50 101,682.50 285.00 44.50 12,682.50 2,000.00 - 89,000.00

03.07.02 VENTANAS 214,927.24 65,459.32


VENTANA V-01 (2.40m x 1.94m) SISTEMA CORREDIZO MAS
03.07.02.01 VITROVEN CON MARCO DE ALUMINIO, INC. VIDRIO 6mm LAMINADO und 8.00 2,784.00 22,272.00 1.00 2,784.00 2,784.00 7.00 - 19,488.00
S/DISEÑO

VENTANA V-02 (2.40m X 1.34m) SISTEMA CORREDIZO CON


03.07.02.02 MARCO DE PERFIL DE ALUMINIO INC. VIDRIO LAMINADO 6 mm S/ und 1.00 2,393.00 2,393.00 1.00 2,393.00 2,393.00 - - -
DISEÑO

VENTANA VA-01 (1.00m X 0.44m) SISTEMA SOBRELUZ CON


03.07.02.03 MARCO DE PERFIL DE ALUMINIO INC. VIDRIO 6mm LAMINADO und 18.00 1,000.00 18,000.00 1.00 1,000.00 1,000.00 17.00 - 17,000.00
S/DISEÑO

VENTANA VA-02 (1.00m X 0.64m) SISTEMA SOBRELUZ CON


03.07.02.04 MARCO DE PERFIL DE ALUMINIO INC. VIDRIO 6 mm LAMINADO und 2.00 1,000.00 2,000.00 1.00 1,000.00 1,000.00 1.00 - 1,000.00
S/DISEÑO

VENTANA VA-03 (1.00m X 0.34m) SISTEMA SOBRELUZ CON


03.07.02.05 MARCO DE PERFIL DE ALUMINIO INC. VIDRIO 6mm LAMINADO und 3.00 1,000.00 3,000.00 1.00 1,000.00 1,000.00 2.00 - 2,000.00
S/DISEÑO
VENTANA VA-04 (0.80m X 0.57m) SISTEMA SOBRELUZ CON
03.07.02.06 MARCO DE PERFIL DE ALUMINIO INC. VIDRIO 6mm LAMINADO und 4.00 870.00 3,480.00 1.00 870.00 870.00 3.00 - 2,610.00
S/DISEÑO

VENTANA VA-05 (2.14m X 0.55m) SISTEMA VITROVEN CON


03.07.02.07 MARCO DE PERFIL DE ALUMINIO INC. VIDRIO 6mm LAMINADO und 5.00 1,146.00 5,730.00 1.00 1,146.00 1,146.00 4.00 - 4,584.00
S/DISEÑO

VENTANA VA-06 (1.20m X 0.55m) SISTEMA VITROVEN CON


03.07.02.08 MARCO DE PERFIL DE ALUMINIO INC. VIDRIO 6mm LAMINADO und 3.00 725.00 2,175.00 1.00 725.00 725.00 2.00 - 1,450.00
S/DISEÑO
VENTANA VA-09 (2.40m X 0.44m) SISTEMA SOBRELUZ CON
03.07.02.11 MARCO DE PERFIL DE ALUMINIO INC. VIDRIO 6mm LAMINADO und 4.00 1,267.20 5,068.80 1.00 1,267.20 1,267.20 3.00 - 3,801.60
S/DISEÑO
VENTANA VA-10 (1.00m X 0.59m) SISTEMA SOBRELUZ CON
03.07.02.12 MARCO DE PERFIL DE ALUMINIO INC. VIDRIO 6mm LAMINADO und 5.00 708.00 3,540.00 1.00 708.00 708.00 4.00 - 2,832.00
S/DISEÑO

VENTANA V-04 (3.43m X 1.34m) SISTEMA CORREDIZO MAS


03.07.02.14 VITROVEN CON MARCO DE ALUMINIO, INC. VIDRIO LAMINADO 6 mm und 2.00 5,370.72 10,741.44 1.00 5,370.72 5,370.72 1.00 - 5,370.72
S/DISEÑO

VENTANA V-05 (3.60m X 1.34m) SISTEMA CORREDIZO MAS


03.07.02.15 VITROVEN CON MARCO DE ALUMINIO, INC. VIDRIO LAMINADO 6 mm und 2.00 5,788.80 11,577.60 1.00 5,788.80 5,788.80 1.00 - 5,788.80
S/DISEÑO

VENTANA VA-11 (1.80m X 0.55m) SISTEMA VITROVEN CON


03.07.02.17 MARCO DE PERFIL DE ALUMINIO INC. VIDRIO 6mm LAMINADO und 8.00 1,188.00 9,504.00 1.00 1,188.00 1,188.00 7.00 - 8,316.00
S/DISEÑO

VENTANA VA-12 (3.00m X 0.55m) SISTEMA VITROVEN CON


03.07.02.18 MARCO DE PERFIL DE ALUMINIO INC. VIDRIO 6mm LAMINADO und 2.00 1,980.00 3,960.00 1.00 1,980.00 1,980.00 1.00 - 1,980.00
S/DISEÑO

VENTANA V-08 (1.80m X 1.34m) SISTEMA CORREDIZO MAS


03.07.02.19 VITROVEN CON MARCO DE ALUMINIO, INC. VIDRIO LAMINADO 6 mm und 21.00 2,894.40 60,782.40 1.00 2,894.40 2,894.40 20.00 - 57,888.00
S/DISEÑO

VENTANA VA-15 (1.00m X 0.94m) SISTEMA SOBRELUZ CON


03.07.02.23 MARCO DE PERFIL DE ALUMINIO INC. VIDRIO 6mm LAMINADO und 2.00 1,128.00 2,256.00 1.00 1,128.00 1,128.00 1.00 - 1,128.00
S/DISEÑO
VENTANA VA-16 (1.00m X 1.09m) SISTEMA SOBRELUZ CON
03.07.02.24 MARCO DE PERFIL DE ALUMINIO INC. VIDRIO 6mm LAMINADO und 4.00 1,308.00 5,232.00 1.00 1,308.00 1,308.00 3.00 - 3,924.00
S/DISEÑO

VENTANA VA-18 (1.34m X 0.55m) SISTEMA VITROVEN CON


03.07.02.26 MARCO DE PERFIL DE ALUMINIO INC. VIDRIO 6mm LAMINADO und 8.00 884.40 7,075.20 1.00 884.40 884.40 7.00 - 6,190.80
S/DISEÑO

VENTANA VA-19 (1.00m X 0.49m) SISTEMA SOBRELUZ CON


03.07.02.27 MARCO DE PERFIL DE ALUMINIO INC. VIDRIO 6mm LAMINADO und 8.00 588.00 4,704.00 1.00 588.00 588.00 7.00 - 4,116.00
S/DISEÑO
03.07.03 PUERTA 94,907.63 10,791.83

PUERTA P-03 (1.60m X 2.10m) DE VIDRIO DOBLE LAMINADO DE 8


03.07.03.01 und 14.00 1,566.60 21,932.40 1.00 1,566.60 1,566.60 13.00 - 20,365.80
MM CON PERFILES DE ALUMINIO INCL. ACCESORIOS E INST.

CERRAMIENTO DE JAULA (1.50X1.50) CON MALLA OLIMPICA DE


03.07.03.03 und 9.00 562.50 5,062.50 1.00 562.50 562.50 8.00 - 4,500.00
1"X1" CON CERROJO TIPICO

03.07.03.04 PUERTA P-09 PUERTA DE JAULA CON MALLA OLIMPICA DE 1"X1" und 136.00 430.00 58,480.00 1.00 430.00 430.00 135.00 - 58,050.00

03.07.03.07 PUERTA P-12 (2.00m X 2.44m) CON MALLA OLIMPICA DE 1"X1" und 2.00 1,200.00 2,400.00 1.00 1,200.00 1,200.00 1.00 - 1,200.00

03.07.04 BARANDAS Y PASAMANOS 65,168.34 12,352.34

BARANDA METALICA DE TUBO NEGRO ARENADA SEGUN


03.07.04.01 m 493.55 132.04 65,168.34 93.55 132.04 12,352.34 400.00 - 52,816.00
DISEÑO INCL. INSTLACION

03.07.05 ELEMENTOS METÁLICOS ESPECIALES 46,950.00 21,950.00


03.07.05.01 ESCALERA TIPO GATO 1 SEGÚN DISEÑO und 5.00 4,500.00 22,500.00 1.00 4,500.00 4,500.00 4.00 - 18,000.00
03.07.05.02 ESCALERA TIPO GATO 2 SEGÚN DISEÑO und 2.00 3,000.00 6,000.00 1.00 3,000.00 3,000.00 1.00 - 3,000.00
03.07.05.06 ASTA DE BANDERA S/DISEÑO INC. INSTALACION und 2.00 1,500.00 3,000.00 1.00 1,500.00 1,500.00 1.00 - 1,500.00
SUMINISTRO E INSTALACION DE ARCOS PARA LOSA
03.07.05.07 und 2.00 2,500.00 5,000.00 1.00 2,500.00 2,500.00 1.00 - 2,500.00
DEPORTIVA
03.10 PINTURA 207,953.99 175,653.99
03.10.01 PINTURA EN CIELO RASO, VIGA, COLUMNAS Y MUROS 189,133.79 156,833.79

PINTURA EN MUROS INTERIORES A DOS MANOS C/LATEX


03.10.01.01 m2 3,322.59 16.15 53,659.83 1,322.59 16.15 21,359.83 2,000.00 - 32,300.00
SATINADO LAVABLE BLANCO HUMO

05 INSTALACIONES ELÉCTRICAS 1,014,057.67 790,935.20 223,122.47

SALIDA PARA ALUMBRADO, INTERRUPTORES, TOMACORRIENTES


05.01 164,475.42 110,190.95
Y FUERZA

05.01.01 SALIDA PARA ALUMBRADO E INTERRUPTORES 36,165.70 25,269.43

05.01.01.01 SALIDA PARA CENTRO DE LUZ pto 261.00 47.17 12,311.37 30.00 47.17 1,415.10 231.00 - 10,896.27

05.01.02 SALIDA PARA TOMACORRIENTES 31,542.67 15,569.07

05.01.02.01 SALIDA PARA TOMACORRIENTE BIPOLAR DOBLE 2L+T pto 219.00 78.63 17,219.97 30.00 78.63 2,358.90 189.00 - 14,861.07

SALIDA PARA TOMACORRIENTE ESTABILIZADO BIPOLAR DOBLE


05.01.02.09 pto 28.00 206.78 5,789.84 23.00 206.78 4,755.94 5.00 - 1,033.90
2L+T EN PISO

05.01.04.06 SALIDA PARA CAMARA 270° EN TECHO pto 27.00 1,220.82 32,962.14 7.00 1,220.82 8,545.74 20.00 - 24,416.40

05.01.04.07 SALIDA PARA VOZ Y DATA pto 27.00 149.91 4,047.57 7.00 149.91 1,049.37 20.00 - 2,998.20
05.04 ALIMENTADORES 408,506.78 239,668.78
05.04.03 ALIMENTADOR 3-1x16 mm2 N2XOH (F) + 1x10 mm2 N2XOH (T) m 2,108.52 61.84 130,390.88 108.52 61.84 6,710.88 2,000.00 - 123,680.00
05.04.05 ALIMENTADOR 3-1x35 mm2 N2XOH (F) + 1x25 mm2 N2XOH (T) m 649.76 117.85 76,574.22 529.76 117.85 62,432.22 120.00 - 14,142.00
05.04.06 ALIMENTADOR 3-1x50 mm2 N2XOH (F) + 1x35 mm2 N2XOH (T) m 694.03 155.08 107,630.17 494.03 155.08 76,614.17 200.00 - 31,016.00