Está en la página 1de 12

N° PLACAS CANTIDAD/PLACA LOG.

PLACA
GONZALES PRADA 8 6 2
MICAELA BASTIDAS 4 6 2
LUTERKING 1 6 2
TUPAC 7 6 2
ML DE ACERO
KG DE ACERO
PARCIAL
96
48
12
84
240
134.4
ACERO SIN USAR "ALMACEN ACCIONA" VARILLAS DE 9m
ITEM DESCRIPCIONTOTAL (ml)
1 ACERO 1/2" 36.00
2 ACERO 3/8" 1152.00
TOTAL Kg

ACERO SINUSAR "ALMACEN ACCIONA" CORTADAS


ITEM DESCRIPCIONTOTAL (ml)
1 ACERO 1/2" 711.15
2 ACERO 3/8" 224.40
TOTAL Kg

ACERO TOTAL SIN USAR


ITEM DESCRIPCIONTOTAL (ml)
1 ACERO 1/2" 747.15
2 ACERO 3/8" 1376.40
TOTAL Kg
"ALMACEN ACCIONA" VARILLAS DE 9m
TOTAL USADO (kg) TOTAL VARILLAS
35.78 4
645.12 128 ACERO USADO "ALMACEN ACCIONA" VARILLAS DE 9m
680.90 ITEM DESCRIPCIOTOTAL (ml) TOTAL USADO
1 ACERO 1/2" 1521.00 1511.87
2 ACERO 3/8" 603.00 337.68
TOTAL Kg 1849.55
AR "ALMACEN ACCIONA" CORTADAS
TOTAL USADO (kg) TOTAL VARILLAS
706.88 80 ACERO USADO
125.66 25 Ꝋ1/2"
832.55 CALLE DESCRIPCION MRO DE CONTENCION ml kg
ACERO EN ALMACEN - - 1,420.50 1,411.98
TOTAL ACERO CORRUGADO EN "ALMACEN ACCIONA" 1,420.50 1,411.98
ACERO TOTAL SIN USAR
TOTAL USADO (kg) TOTAL VARILLAS
742.67 84
770.78 153
1513.45
IONA" VARILLAS DE 9m
TOTAL VARILLAS
169
67

ACERO USADO EN OBRA


Ꝋ1/2" Ꝋ3/8"
CION ml kg ml kg
- 1,420.50 1,411.98 1,979.40 1,108.46
1,420.50 1,411.98 1,979.40 1,108.46
ACERO USADO "ALMACEN ACCIONA" VARILLAS DE 9m
ITEM DESCRIPCION TOTAL (ml) TOTAL USADO (kg)
1 ACERO 1/2" 1521.00 1511.87
2 ACERO 3/8" 603.00 337.68
TOTAL Kg 1849.55
VARILLAS DE 9m
TOTAL VARILLAS
169
67
CUADRO DE RESUMEN GONZALES PRADA

ACERO USADO EN OBRA


Ꝋ1/2" Ꝋ3/8" Ꝋ5/8"
CALLE DESCRIPCION MRO DE CONTENCION ml kg ml kg ml kg
MURO 01 114.67 113.98 22.30 12.42 24.20 37.75
MURO 02 191.65 190.50 76.00 42.33 25.00 39.00
MURO 03 190.55 189.41 74.10 41.27 33.50 52.26
MURO 04 199.26 198.06 68.80 38.32 18.20 28.39
GONZALES PRADA MURO HORIZONTAL
MURO 05 108.83 108.18 19.90 11.08 17.80 27.77
MURO 06 187.19 186.07 67.32 37.50 17.30 26.99
MURO 07 196.35 195.17 73.80 41.11 12.50 19.50
MURO 08 188.03 186.90 65.60 36.54 22.50 35.10
TOTAL ACERO CORRUGADO EN "GONZALES PRADA" 1,376.53 1,368.27 467.82 260.58 171.00 266.76

ACERO USADO EN OBRA


Ꝋ1/2" Ꝋ3/8"
CALLE DESCRIPCION MRO DE CONTENCION ml kg ml kg
MURO 09 54.90 54.57 10.50 5.85
MURO 10 138.67 137.84 45.60 25.40
MURO 11 73.20 72.76 20.96 11.67
MURO 12 128.77 128.00 - -
MURO 13 128.93 128.16 - -
MURO 14 70.10 69.68 - -
MURO 15 234.65 233.24 - -
MURO 16 118.99 118.28 - -
MURO 17 61.44 61.07 - -
GONZALES PRADA MURO TRANSVERSAL
MURO 18 54.90 54.57 - -
MURO 19 175.81 174.76 47.20 26.29
MURO 20 167.59 166.59 68.60 38.21
MURO 21 51.92 51.61 16.50 9.19
MURO 22 156.39 155.45 - -
MURO 23 75.40 74.94 - -
MURO 24 119.07 118.36 - -
MURO 25 148.59 147.70 - -
MURO 26 59.40 59.04 - -
TOTAL ACERO CORRUGADO EN "GONZAlES PRADA" 2,018.71 2,006.60 209.36 116.61

TOTAL ACERO CORRUGADO CALLE GONZALES PRADA


ACERO Ꝋ1/2" ACERO Ꝋ3/8" ACERO Ꝋ5/8" TOTAL
ml kg ml kg ml kg kg
3,395.24 3,374.87 677.18 377.19 171.00 266.76 4,018.82
CUADRO DE RESUMEN MICAELA BASTIDAS

ACERO USADO EN OBRA


Ꝋ1/2" Ꝋ3/8"
CALLE DESCRIPCION MRO DE CONTENCION ml kg ml kg
MURO 01 86.64 86.12 23.40 13.03
MURO 02 87.33 86.81 21.00 11.70
MURO 03 127.33 126.57 45.50 25.34
MURO 04 151.63 150.72 54.60 30.41
MURO 05 124.79 124.04 32.80 18.27
MURO 06 142.55 141.70 50.70 28.24
MURO 07 187.41 186.29 67.68 37.70
MICAELA BASTIDAS MURO HORIZONTAL
MURO 08 125.79 125.04 40.26 22.42
MURO 09 107.75 107.11 31.20 17.38
MURO 10 117.17 116.47 29.82 16.61
MURO 11 181.61 180.52 60.80 33.87
MURO 12 206.52 205.28 74.46 41.47
MURO 13 216.62 215.32 81.00 45.12
MURO 14 194.34 193.17 64.40 35.87
TOTAL ACERO CORRUGADO EN "MICAELA BASTIDAS" 2,057.50 2,045.16 677.62 377.43
CUADRO DE RESUMEN LUTERKING

ACERO USADO EN OBRA


Ꝋ1/2" Ꝋ3/8"
CALLE DESCRIPCION MRO DE CONTENCION ml kg ml kg

MURO 02 138.02 137.19 50.00 27.85


MURO 03 117.40 116.70 - -
MURO 04 173.27 172.23 57.40 31.97
LUTERKING MURO HORIZONTAL
MURO 05 125.75 125.00 32.80 18.27
MURO 06 114.43 113.75 39.60 22.06
MURO 07 104.33 103.71 28.98 16.14
TOTAL ACERO CORRUGADO EN "LUTERKING" 773.21 768.57 208.78 116.29
CUADRO DE RESUMEN TUPAC AMARU II

ACERO USADO EN OBRA


Ꝋ1/2" Ꝋ3/8"
CALLE DESCRIPCION MRO DE CONTENCION ml kg ml kg
MURO 01 103.80 103.17 39.00 21.72
MURO 02 261.53 259.96 97.20 54.14
MURO 03 318.67 316.75 115.90 64.56
MURO 04 233.48 232.08 77.56 43.20
MURO 05 153.39 152.47 37.10 20.66
MURO 06 215.29 214.00 75.00 41.78
TUPAC AMARU II MURO HORIZONTAL
MURO 07 131.67 130.88 41.40 23.06
MURO 08 154.97 154.04 52.32 29.14
MURO 09 211.57 210.30 79.20 44.11
MURO 10 182.22 181.13 59.64 33.22 Ꝋ5/8"
MURO 11 146.81 145.93 34.58 19.26 ml kg
MURO 12 211.29 210.02 70.00 38.99 171.00 265.39
TOTAL ACERO CORRUGADO EN "TUPAC AMARU II" 2,324.68 2,310.74 778.90 433.85 171.00 265.39

CUADRO DE RESUMEN ACERO EN ALMACEN DE ACCIONA


19
19

ACERO EN ALMACEN ACCIONA


Ꝋ1/2" Ꝋ3/8"
CALLE DESCRIPCION MRO DE CONTENCION ml kg ml kg
ACERO EN ALMACEN - - 747.15 742.67 1,376.40 770.78
ACCIONA
TOTAL ACERO CORRUGADO EN "ALMACEN ACCIONA" 747.15 742.67 1,376.40 770.78
TOTAL KG 1,513.45
CUADRO DE RESUMEN GONZALES PRADA

TOTAL ACERO EN OBRA HASTA LA FECHA 07/05/18


ACERO Ꝋ1/2" ACERO Ꝋ3/8" ACERO Ꝋ5/8" TOTAL
ml # varillas kg ml # varillas kg ml # varillas kg ml # varillas kg
10,818.79 1,203.00 10,753.88 4,561.88 507.00 2,547.63 171.00 19.00 266.76 15,551.67 1,728.00 13,568.26