CRONOGRAMA 05-Feb-24 23:54

Activity ID Activity Name Original Remaining Schedule % Start Finish TotalQtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024
Duration Duration Complete Float
May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar
EX-P1-2 CONSTRUCCION 163 163 0% 13-May-23 22-Oct-23 0 22-Oct-23, EX-P1-2 CONSTRUCCION

EX-P1-2.1 HITOS DE PROYECTO 0 0 0% 0

EX-P1-2.2 MOVILIZACION Y OBRAS PRELIMINARES 163 163 0% 13-May-23 22-Oct-23 0 22-Oct-23, EX-P1-2.2 MOVILIZACION Y OBRAS PRELIMINARES
MOP-1001 MOVILIZACION 6 6 0% 13-May-23 18-May-23 0 MOVILIZACION
MOP-1002 CONSTRUCCION DE OFICINAS, ALMACENES Y COMEDORES 6 6 0% 19-May-23 24-May-23 0 CONSTRUCCION DE OFICINAS, ALMACENES Y COMEDORES
MOP-1003 DESMOVILIZACION 6 6 0% 17-Oct-23 22-Oct-23 0 DESMOVILIZACION
EX-P1-2.3 CONSTRUCCION DE AMPLIACION DE PAD 145 145 0% 25-May-23 16-Oct-23 6 16-Oct-23, EX-P1-2.3 CONSTRUCCION DE AMPLIACI ON DE PAD

EX-P1-2.3.1 MOVIMIENTO DE TIERRAS 63 63 0% 25-May-23 26-Jul-23 88 26-Jul-23, EX-P1-2.3.1 MOVIMIENTO DE TIERRAS


EX-P1-2.3.1.1 TRABAJOS EN MATERIAL ORGANICO (TOP S0IL) 4 4 0% 25-May-23 28-May-23 0 28-May-23, EX-P1-2.3.1.1 TRABAJOS EN MATERIAL ORGANICO (TOP S0IL)
MT-1001 DESBROCE DE MATERIAL ORGANICO (TOP SOIL) 4 4 0% 25-May-23 28-May-23 0 DESBROCE DE MATERIAL ORGANICO (TOP SOIL)
MT-1002 CARGUIO DE MATERIAL ORGANICO (TOP SOIL) 4 4 0% 25-May-23 28-May-23 0 CARGUIO DE MATERIAL ORGANICO (TOP SOIL)
EX-P1-2.3.1.2 TRABAJOS EN MATERIAL INORGANICO (PEAT) 26 26 0% 29-May-23 23-Jun-23 0 23-Jun-23, EX-P1-2.3.1.2 TRABAJOS EN MATERIAL INORGANICO (PEAT)
MT-1003 CORTE DE MATERIAL INORGÁNICO 26 26 0% 29-May-23 23-Jun-23 0 CORTE DE MATERIAL INORGÁNICO
MT-1004 CARGUÍO DE MATERIAL INORGÁNICO 21 21 0% 03-Jun-23 23-Jun-23 0 CARGUÍO DE MATERIAL INORGÁNICO
EX-P1-2.3.1.3 TRABAJOS EN MATERIAL ROCA FIJA 33 33 0% 24-Jun-23 26-Jul-23 88 26-Jul-23, EX-P1-2.3.1.3 TRABAJOS EN MATERIAL R OCA FIJA
MT-1005 CARGUIO DE ROCA VOLADA 25 25 0% 24-Jun-23 18-Jul-23 88 CARGUIO DE ROCA VOLADA
MT-1006 EXTENDIDO DE MATERIAL EN BOTADERO (ROCA VOLADA) 29 29 0% 28-Jun-23 26-Jul-23 88 EXTENDIDO DE MATERIAL EN BOTADERO (ROCA VOLADA)
EX-P1-2.3.2 SISTEMA DE SUB DRENAJE 50 50 0% 13-Jun-23 01-Aug-23 0 01-Aug-23, EX-P1-2.3.2 SISTEMA DE SUB DRENAJE
EX-P1-2.3.2.1 INSTALACION DE TUBERIA DE SUB DRENAJE 45 45 0% 13-Jun-23 27-Jul-23 0 27-Jul-23, EX-P1-2.3.2.1 INSTALACION DE TUBERIA DE SUB DRENAJE
SD-1001 EXCAVACION PARA SUB-DRENAJE (ROCA SUELTA) 32 32 0% 13-Jun-23 14-Jul-23 0 EXCAVACION PARA SUB-DRENAJE (ROCA SUELTA)
SD-1002 TUBERIA PERFORADA CPT-HDPE DE SUB-DRENAJE PARED DOBLE 200mm 21 21 0% 29-Jun-23 19-Jul-23 0 TUBERIA PERFORADA CPT-HDPE DE SUB-DRENAJE PARED DOBLE 200mm
SD-1003 TUBERIA PERFORADA CPT-HDPE DE SUB-DRENAJE PARED DOBLE 300mm 8 8 0% 20-Jul-23 27-Jul-23 0 TUBERIA PERFORADA CPT-HDPE DE SUB-DRENAJE PARED DOBLE 300mm
SD-1004 GEOTEXTIL NO TEJIDO DE 270 gr/cm2 EN SUB DRENAJE 27 27 0% 01-Jul-23 27-Jul-23 0 GEOTEXTIL NO TEJIDO DE 270 gr/cm2 EN SUB DRENAJE
SD-1005 COLOCACION DE GRAVA (3/4"- 3") EN SUB DRENES 21 21 0% 07-Jul-23 27-Jul-23 0 COLOCACION DE GRAVA (3/4"- 3") EN SUB DRENES
EX-P1-2.3.2.2 RELLENO ESTRUCTURAL 47 47 0% 16-Jun-23 01-Aug-23 0 01-Aug-23, EX-P1-2.3.2.2 RELLENO ESTRUCTURAL
SD-1006 PRODUCCION DE RELLENO ESTRUCTURAL 47 47 0% 16-Jun-23 01-Aug-23 0 PRODUCCION DE RELLENO ESTRUCTURAL
SD-1007 COLOCACION DE MATERIAL CLASIFICADO PARA RELLENO ESTRUCTURAL 38 38 0% 25-Jun-23 01-Aug-23 0 COLOCACION DE MATERIAL CLASIFICADO PARA RELLENO ESTRUCTURAL
EX-P1-2.3.3 SISTEMA DE REVESTIMIENTO 82 82 0% 25-Jun-23 14-Sep-23 38 14-Sep-23, EX-P1-2.3.3 SISTEMA DE REVESTIMIENTO
EX-P1-2.3.3.1 CAPA IMPERMEABLE (CLAY) 78 78 0% 25-Jun-23 10-Sep-23 0 10-Sep-23, EX-P1-2.3.3.1 CAPA I MPERMEABLE (CLAY)
SR-1001 EXTRACCION DE CLAY 27 27 0% 25-Jun-23 21-Jul-23 0 EXTRACCION DE CLAY
SR-1002 CONFORMACION DE CAPA IMPERMEABLE (C LAY) E=0.30m 48 48 0% 15-Jul-23 31-Aug-23 0 CONFORMACION DE CAPA IMPERMEABLE (C LAY) E=0.30m
SR-1003 REFINE DE MATERIAL CLASIFICADO 35 35 0% 07-Aug-23 10-Sep-23 0 REFINE DE MATERIAL CLASIFICADO
EX-P1-2.3.3.2 BERMAS PERIMETRICAS 26 26 0% 22-Jul-23 16-Aug-23 0 16-Aug-23, EX-P1-2.3.3.2 BERMAS PERIMETRICAS
SR-1004 PRODUCCION DE CLAY 9 9 0% 22-Jul-23 30-Jul-23 0 PRODUCCION DE CLAY
SR-1005 CONFORMACION DE BERMAS 13 13 0% 31-Jul-23 12-Aug-23 0 CONFORMACION DE BERMAS
SR-1006 REFINE DE MATERIAL CLASIFICADO 4 4 0% 13-Aug-23 16-Aug-23 0 REFINE DE MATERIAL CLASIFICADO
EX-P1-2.3.3.3 GEOMEMBRANA 35 35 0% 11-Aug-23 14-Sep-23 38 14-Sep-23, EX-P1-2.3.3.3 GEOMEMBRANA
SR-1007 EXCAVACION DE ZANJA DE ANCLAJE P/GEOMEMBRANA 6 6 0% 11-Aug-23 16-Aug-23 0 EXCAVACION DE ZANJA DE ANCLAJE P/GEOMEMBRANA
SR-1008 INSTALACION DE GEOMEMBRANA HDPE e= 2mm EN PAD Y BERMAS 29 29 0% 17-Aug-23 14-Sep-23 0 INSTALACION DE GEOMEMBRANA HDPE e= 2mm EN PAD Y BERMAS
SR-1009 RELLENO DE ZANJA DE ANCLAJE 21 21 0% 25-Aug-23 14-Sep-23 38 RELLENO DE ZANJA DE ANCLAJE
EX-P1-2.3.4 SISTEMA DE COLECCIÓN DE SOLUCION LIXIVIADA 18 18 0% 10-Sep-23 27-Sep-23 25 27-Sep-23, EX-P1-2.3.4 SISTEMA DE COLECCIÓN D E SOLUCION LIXIVIADA
EX-P1-2.3.4.1 INSTALACION DE TUBERIA DE SUB DRENAJE 18 18 0% 10-Sep-23 27-Sep-23 25 27-Sep-23, EX-P1-2.3.4.1 INSTALACION DE TUBERIA DE SUB DRENAJE
SCSL-1001 TUBERIA PERFORADA CPT-HDPE PARED DOBLE 100 MM 18 18 0% 10-Sep-23 27-Sep-23 25 TUBERIA PERFORADA CPT-HDPE PARED DOBLE 100 MM
SCSL-1002 TUBERIA PERFORADA CPT-HDPE PARED DOBLE 300mm 6 6 0% 22-Sep-23 27-Sep-23 25 TUBERIA PERFORADA CPT-HDPE PARED DOBLE 300mm
SCSL-1003 GEOTEXTIL NO TEJIDO DE 270 gr/cm2 EN DRENAJE 13 13 0% 15-Sep-23 27-Sep-23 0 GEOTEXTIL NO TEJIDO DE 270 gr/cm2 EN DRENAJE
SCSL-1004 COLOCACION DE GRAVA (3/4"- 3") EN SUB- DRENES 10 10 0% 18-Sep-23 27-Sep-23 0 COLOCACION DE GRAVA (3/4"- 3") EN SUB- DRENES
EX-P1-2.3.5 CAPA PROTECTORA (OVER LINER) 19 19 0% 28-Sep-23 16-Oct-23 0 16-Oct-23, EX-P1-2.3.5 CAPA PROTECTORA (OVER LINER)
CP-1001 EXTENDIDO DE OVERLINER SOBRE REVESTIMIENTO DE GEOMEMBRANA 19 19 0% 28-Sep-23 16-Oct-23 0 EXTENDIDO DE OVERLINER SOBRE REVESTIMIENTO DE GEOMEMBRANA

Actual Level of Effort Remaining Work Milestone Page 1 of 1 TASK filter: Normal.
Actual Work Critical Remaining Work summary © Oracle Corporation