G03-Informe Memoria de Calculo
G03-Informe Memoria de Calculo
Santa María
Facultad de Arquitectura e Ingeniería Civil y del Ambiente
Escuela Profesional de Ingeniería Civil
Perú – Arequipa
2022
Tabla de contenido
INTRODUCCION............................................................................................................................................4
CAPITULO I: CONSIDERACIONES PARA EL DISEÑO GEOMETRICO.................................................................4
1.1. NORMATIVA.................................................................................................................................4
CAPITULO II: PROCEDIMIENTO DESCRIPTIVO...............................................................................................8
CAPÍTULO III: CÁLCULOS DE LAS DISTANCIAS DE TRANSPORTE..................................................................19
3.1. MOVIMIENTO DE TIERRAS EN CORTE Y TERRAPLÉN............................................................................19
3.1.1. volumen entre secciones del mismo tipo método de las áreas medias....................................19
3.2 MOVIMIENTO DEL MATERIAL EXTRAÍDO DEL TÚNEL.......................................................................28
3.2.1. DETERMINAR LA CANTIDAD DE SUELOS PARA PAVIMENTO (SUBBASE) EN M3...........................28
3.2. Determinar el ancho de la carpeta subbase...............................................................................28
3.2.2. Determinar la longitud total del proyecto................................................................................29
3.2.3. Determinar el área de la subbase.............................................................................................30
3.2.5. Determinar el volumen de la subbase en estado suelto...........................................................30
3.3. DETERMINAR LA CANTIDAD DE ASFALTO EN M2............................................................................31
3.4. METRADO DE OBRAS DE ARTE(CUNETA).........................................................................................32
3.3. DIAGRAMA DE MASAS.....................................................................................................................33
4.EXPLOSIVOS.........................................................................................................................................35
REFERENCIAS..............................................................................................................................................37
Seguiremos revisando el manual de túneles donde de acuerdo a la longitud del túnel se tendrá
una pendiente máxima, la longitud del túnel que realizamos es de 280m donde nos
correspondería una pendiente máxima de 5%
Teniendo en cuenta que este túnel se realizara en zona rural tomaremos un ancho de vereda
mínimo de 75.00 cm
Ilustración 6: Ancho de veredas
Luego conectaremos a los datos del cad mapper para poder hacer las curvas de nivel, donde el
nivel de detalle lo pondremos al máximo para que las curvas sean mejores,
Tendremos una seria de opciones donde se ira a dibujar una caja para delimitar las curvas de
nivel.
Esta opción nos dará un archivo de texto con las alturas y coordenadas.
Ilustración 14: formato en el que se guardara las curvas de nivel
Para importar los puntos del civil3d primero verificamos la zona este en categoría de UTM,
WSG 84 DATUM y validando el sistema de coordenadas.
(8.29 + 22.91) 3
𝑉5 = 2 ∗ 10 = 156 𝑚
(22.91 + 40.6)
𝑉6 = ∗ 10 = 317.55 𝑚3
2
(40.6 + 93.91)
𝑉7 = ∗ 10 = 672.55 𝑚3
2
(93.91 + 63.49) 3
𝑉8 = 2 ∗ 10 = 787 𝑚
(63.49 + 71.11) 3
𝑉9 = 2 ∗ 20 = 1346 𝑚
(71.11 + 91.55)
𝑉10 = ∗ 20 = 1626.6 𝑚3
2
(91.55 + 111.32)
𝑉11 = ∗ 20 = 2028.7 𝑚3
2
(111.32 + 95.68) 3
𝑉12 = 2 ∗ 20 = 2070 𝑚
(95.68 + 49.2)
𝑉13 = ∗ 20 = 1448.8 𝑚3
2
(49.2 + 0.53)
𝑉14 = ∗ 20 = 497.3 𝑚3
2
(0.53 + 0)
𝑉15 = ∗ 20 = 5.3 𝑚3
2
(0 + 0)
𝑉16 = ∗ 20 = 0 𝑚3
2
(0 + 0)
𝑉17 = ∗ 20 = 0
2
(0 + 0)
𝑉18 = ∗ 20 = 0 𝑚3
2
(0 + 0)
𝑉19 = ∗ 20 = 0 𝑚3
2
𝑡𝑢𝑛𝑒𝑙 𝑑𝑒 0 + 340𝑚 𝑎 0 + 620𝑚
(0 + 0)
𝑉21 = ∗ 20 = 0 𝑚3
2
(0 + 0)
𝑉22 = ∗ 20 = 0 𝑚3
2
(0 + 0)
𝑉23 = ∗ 20 = 0 𝑚3
2
(0 + 0)
𝑉24 = ∗ 20 = 0 𝑚3
2
(0 + 0)
𝑉25 = ∗ 10 = 0 𝑚3
2
(0 + 0)
𝑉26 = ∗ 10 = 0 𝑚3
2
(0 + 0.72)
𝑉27 = ∗ 10 = 3.6 𝑚3
2
(0.72 + 8.85)
𝑉28 = ∗ 10 = 47.85 𝑚3
2
(8.85 + 13.57)
𝑉29 = ∗ 10 = 224.2 𝑚3
2
(13.57 + 16.46)
𝑉30 = ∗ 20 = 300.3 𝑚3
2
(16.46 + 26.6)
𝑉31 = ∗ 20 = 430.6 𝑚3
2
(26.6 + 45.11)
𝑉32 = ∗ 20 = 717.1 𝑚3
2
(45.11 + 51.67)
𝑉33 = ∗ 20 = 967.8 𝑚3
2
(51.67 + 31.67)
𝑉34 = ∗ 20 = 833.4 𝑚3
2
(31.67 + 11.49)
𝑉35 = ∗ 20 = 431.6 𝑚3
2
(11.49 + 0.11)
𝑉36 = ∗ 16.75 = 97.15 𝑚3
2
3.1.1.2 Corte
(51.55 + 56.86)
𝑉1 = ∗ 20 = 1084.1 𝑚3
2
(56.86 + 47.55)
𝑉2 = ∗ 20 = 1044.1 𝑚3
2
(47.55 + 29.72) 3
𝑉3 = 2 ∗ 20 = 772.7 𝑚
(29.72 + 9.45)
𝑉4 = ∗ 20 = 391.7 𝑚3
2
(9.45 + 3.15) 3
𝑉5 = 2 ∗ 10 = 63 𝑚
(3.15 + 0)
𝑉6 = ∗ 10 = 15.75 𝑚3
2
(0 + 0)
𝑉7 = ∗ 10 = 0 𝑚3
2
(0 + 0)
𝑉8 = ∗ 10 = 0 𝑚3
2
(0 + 0)
𝑉9 = ∗ 20 = 0 𝑚3
2
(0 + 0)
𝑉10 = ∗ 20 = 0 𝑚3
2
(0 + 0)
𝑉11 = ∗ 20 = 0 𝑚3
2
(0 + 0)
𝑉12 = ∗ 20 = 0 𝑚3
2
(0 + 6.52)
𝑉13 = ∗ 20 = 65.2 𝑚3
2
(6.52 + 113.04)
𝑉14 = ∗ 20 = 1195.6 𝑚3
2
(113.04 + 362.39) 3
𝑉15 = 2 ∗ 20 = 4754.3 𝑚
(362.39 + 637.48) 3
𝑉16 = 2 ∗ 20 = 9998.7 𝑚
(637.48 + 838.27)
𝑉17 = ∗ 20 = 14757.5 𝑚3
2
(838.27 + 1066.96) 3
𝑉18 = 2 ∗ 20 = 19052.3 𝑚
(1066.96 + 1351.09) 3
𝑉19 = 2 ∗ 20 = 24180.5 𝑚
𝑡𝑢𝑛𝑒𝑙 𝑑𝑒 0 + 340𝑚 𝑎 0 + 620𝑚
(1247.17 + 1037.17) 3
𝑉21 = 2 ∗ 20 = 22843.4 𝑚
(1037.17 + 780.68) 3
𝑉22 = 2 ∗ 20 = 18178.5 𝑚
(780.68 + 523.24)
𝑉23 = ∗ 20 = 13039.2 𝑚3
2
(523.24 + 280.28) 3
𝑉24 = 2 ∗ 20 = 8035.2 𝑚
(280.28 + 175.45)
𝑉25 = ∗ 10 = 2278.65 𝑚3
2
(175.45 + 99.27)
𝑉26 = ∗ 10 = 1373.6 𝑚3
2
(99.27 + 54.59)
𝑉27 = ∗ 10 = 769.3 𝑚3
2
(54.59 + 40.62)
𝑉28 = ∗ 10 = 476.05 𝑚3
2
(40.62 + 34.26)
𝑉29 = ∗ 10 = 748.8 𝑚3
2
(34.26 + 24.29)
𝑉30 = ∗ 20 = 585.5 𝑚3
2
(24.29 + 9.74)
𝑉31 = ∗ 20 = 340.3 𝑚3
2
(9.74 + 0)
𝑉32 = ∗ 20 = 97.4 𝑚3
2
(0 + 0)
𝑉33 = ∗ 20 = 0 𝑚3
2
(0 + 0)
𝑉34 = ∗ 20 = 0 𝑚3
2
(0 + 3.7)
𝑉35 = ∗ 20 = 37 𝑚3
2
(3.7 + 9.61)
𝑉36 = ∗ 16.75 = 111.47125 𝑚3
2
𝑉 = 175.024𝑚2 ∗ 280𝑚
𝑉 = 49006.72 𝑚3
La subbase será 0.50m para cada lado entonces el ancho de la carpeta subbase será de
9.20
Ancho total de la carpeta subbase = 9.20m
3.2.2. Determinar la longitud total del proyecto
El espesor que tendrá la subbase según la norma para carreteras con un IMDA alto es un
máximo de 0.30m
Entonces
Volumen = 0.30*9078.1 =2723.43m3
3.2.5. Determinar el volumen de la subbase en estado suelto
El factor de esponjamiento es de 1.10
Entonces
Volumen = 2723.43*1.10=2995.773m3
2995.773m3 se traerán desde la cantera hasta la obra para construir la subbase.
Ilustración 28: volquete
(Depositphotos, 2020)
𝐸𝑗𝑒𝑚𝑝𝑙𝑜:
𝑃𝑟𝑜𝑔𝑟𝑒𝑠𝑖𝑣𝑎: 0 + 040.00
51.80
𝑉𝑟𝑎 = 57.56
0.9
=
𝑃𝑟𝑜𝑔𝑟𝑒𝑠𝑖𝑣𝑎: 0 + 740.00
47.85
𝑉𝑟𝑎 = 53.17
0.9
=
𝐷𝑖𝑓𝑒𝑟𝑒𝑛𝑐𝑖𝑎 𝑑𝑒 𝑣𝑜𝑙𝑢𝑚𝑒𝑛 = 𝑉𝑜𝑙𝑐𝑜𝑟𝑡𝑒 − 𝑉𝑜𝑙𝑟𝑒𝑙𝑙𝑒𝑛𝑜 𝑎𝑗𝑢𝑠𝑡𝑎𝑑𝑜
4.EXPLOSIVOS
Alivio Consideramos 1
Ayudas 12 Taladros
Arrastres 5 Taladros
Cuadradores 10 Taladros
Corona 6 Taladros
Stoping 2 Taladros
6 ∗ 0.3048 = 1.83𝑚
𝐸𝑛 𝑒𝑠𝑡𝑒 𝑐𝑎𝑠𝑜 𝑙𝑎 𝑒𝑓𝑖𝑐𝑖𝑒𝑛𝑐𝑖𝑎 𝑠𝑒𝑟𝑎 𝑑𝑒 93%
1.83 ∗ 0.93 = 1.70𝑚 𝑝𝑎𝑟𝑎 𝑙𝑎 𝑑𝑒𝑓𝑜𝑟𝑚𝑎𝑐𝑖𝑜𝑛 𝑟𝑒𝑎𝑙