ING:
PROYECTO: TECHADO DEL PATIO DE HONOR DE LA I.E RICARDO PALMA SORIANO - PERENE - CHANCHAMAYO - JUNIN.
REGION JUNIN
PROVINCIA CHANCHAMAYO
DISTRITO PERENE
PRESUPUESTO AVANCE
SALDO
PART. DESCRIPCION ACTUAL ACUMULADO
UND METRADO PRECIO $ PARCIAL SUB TOTAL
METRADO VALORIZADO METRADO VALORIZADO (%) METRADO VALORIZADO %
01.00.00 TRABAJOS PROVICIONALES 928.50
01.01.00 ALQUILER DE LOCAL PARA ALMACEN Mes 4.00 100.00 400.00 1.00 100.00 1.00 100.00 25.00% 3.00 300.00 75.00%
01.02.00 INSTALACION DE CARTEL DE OBRA IMPRESIÓN EN BANNER DE 3.60 Und 1.00 528.50 528.50 1.00 528.50 1.00 528.50 100.00% 0.00 0.00 0.00%
02.02.00 TRAZO, NIVELES REPLANTEOS PRELIMINARES M2 984.84 2.65 2,609.83 984.84 2609.83 984.84 2609.83 100.00% 0.00 0.00 0.00%
03.02.00 RELLENO COMPACTADO CON MATERIAL PROPIO M3 86.64 10.71 927.91 86.64 927.91 86.64 927.91 100.00% 0.00 0.00 0.00%
03.03.00 NIVELACION INTERIOR, APISONADO CON EQUIPO M3 86.64 23.90 2,070.70 86.64 2070.70 86.64 2070.70 100.00% 0.00 0.00 0.00%
03.04.00 ACARREO DE MATERIAL EXCEDENTE DIS A 30M M3 88.37 27.30 2,412.50 88.37 2412.50 88.37 2412.50 100.00% 0.00 0.00 0.00%
03.05.00 ELIMINACION DE MATRERIAL EXCEDENTE A 1KM M3 88.37 73.10 6,459.85 - 0.00 - 0.00 0.00% 88.37 6459.85 100.00%
05.02.01 ACERO EN ZAPATAS Fy= 4200Kg/cm2 Kg 1,403.02 5.30 7,436.01 1,403.02 7436.01 1,403.02 7436.01 100.00% 0.00 0.00 0.00%
05.02.01 ACERO EN COLUMNAS Fy= 4200Kg/cm2 KG 3,622.08 5.30 19,197.02 3,622.08 19197.02 3,622.08 19197.02 100.00% 0.00 0.00 0.00%
05.02.03 ENCOFRADO Y DESENCOFRADO DE COLUMNAS M2 215.04 22.16 4,765.29 120.00 2659.20 120.00 2659.20 55.80% 95.04 2106.09 44.20%
05.03.02 ACERO EN VIGAS Fy= 4200Kg/cm2 KG 5,198.26 5.30 27,550.78 5,198.26 27550.78 5,198.26 27550.78 100.00% 0.00 0.00 0.00%
05.03.03 ENCOFRADO Y DESENCOFRADO DE VIGAS M2 971.74 28.72 27,908.37 - 0.00 - 0.00 0.00% 971.74 27908.37 100.00%
06.01.02 COBERTURA CON CALAMINA GALVANIZADA M2 984.84 30.31 29,850.50 - 0.00 - 0.00 0.00% 984.84 29850.50 100.00%
07.02.00 TARRAJEO EN VIGAS Y VIGUETAS M2 204.14 24.43 4,987.14 - 0.00 - 0.00 0.00% 204.14 4987.14 100.00%
TUBERIA DE BAJADA DE DISTRIBUCION PVC DE 3 M 30.00 18.76 562.80 - 0.00 - 0.00 0.00% 30.00 562.80 100.00%
PROYECTO:
TECHADO DEL PATIO DE HONOR DE LA I.E RICARDO PALMA
SORIANO - PERENE - CHANCHAMAYO - JUNIN.
REGION JUNIN
PROVINCIA CHANCHAMAYO
DISTRITO PERENE
05.02.00 COLUMNAS
05.02.01 CONCRETO EN COLUMNA F'c= 210Kg/cm2 M3 18.43
05.03.00 VIGAS
05.03.01 CONCRETO EN VIGAS F'c= 210Kg/cm2 M3 28.40
% DE EJECUCION
25.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
100.00%
0.00%
100.00%
100.00%
100.00%
0.00%
100.00%
55.80%
0.00%
100.00%
0.00%
48.92%
0.00%
0.00%
0.00%
0.00%
0.00%