AVANCE COMPARATIVO - ESTRUCTURAS

DEL 01 AL 29 ENERO 2016.


OBRA: REFACCION Y ACONDICIONAMIENTO DE LA SEDE INTENDENCIA DE ADUANA PAITA
UBICACIÓN : Reg. Piura, Prov. Piura, Dist. Paita
Contratista Consorcio Zavaleta
Supervisor Consorcio Supervisor Paita MES.VAL : FEBRERO 2016.

AVANCE FISICO AVANCE FISICO (%)


Programado Contractual Real Programado Contractual Real
Valorizacion
Parcial Acumulado Parcial Acumulado Parcial Acumulado Parcial Acumulado
VAL-01 171,282.12 171,282.12 157,043.65 157,043.65 10.58% 10.58% 9.70% 9.70%
VAL-02 460,421.92 631,704.04 348,523.26 505,566.91 28.44% 39.02% 21.53% 0.00%
VAL-03 57,574.83 689,278.87 0.00 3.56% 42.58% 0.00% 0.00%
VAL-04 593,123.43 1,282,402.30 0.00 36.64% 79.21% 0.00% 0.00%
VAL-05 330,116.39 1,612,518.69 0.00 20.39% 99.60% 0.00% 0.00%
VAL-06 6,211.29 1,618,729.98 0.00 0.38% 99.99% 0.00% 0.00%
VAL-07 238.26 1,618,968.24 0.00 0.01% 100.00% 0.00% 0.00%

1,618,968.24 505,566.91 100.00%


VALORES AFECTADOS POR EL FACTOR DE RELACION 0.95000, SIN IGV

AVANCES FISICOS PARCIALES AVANCES FISICOS ACUMULADOS

40.00% 120.00%

35.00%
100.00%
30.00%
80.00%
PORCENTAJE

25.00% PORCENTAJE
Programado
20.00% 60.00% Programado Real
Real

15.00%
40.00%
10.00%
20.00%
5.00%

0.00% 0.00%

MESES MESES
AVANCE COMPARATIVO - ARQUITECTURA
DEL 01 AL 29 ENERO 2016.

OBRA: REFACCION Y ACONDICIONAMIENTO DE LA SEDE INTENDENCIA DE ADUANA PAITA


UBICACIÓN : Reg. Piura, Prov. Piura, Dist. Paita
Contratista Consorcio Zavaleta
Supervisor Consorcio Supervisor Paita MES VAL : FEBRERO 2016.

AVANCE FISICO AVANCE FISICO (%)


Programado Contractual Real Programado Contractual Real
Valorizacion
Parcial Acumulado Parcial Acumulado Parcial Acumulado Parcial Acumulado
VAL-01 72.29 72.29 13,686.57 13,686.57 0.00% 0.00% 0.67% 0.67%
VAL-02 170,265.11 170,337.40 158,229.82 171,916.39 8.34% 8.35% 7.75% 8.42%
VAL-03 278,512.65 448,850.05 0.00 13.65% 21.99% 0.00% 0.00%
VAL-04 22,831.64 471,681.68 0.00 1.12% 23.11% 0.00% 0.00%
VAL-05 582,141.80 1,053,823.48 0.00 28.52% 51.63% 0.00% 0.00%
VAL-06 773,903.90 1,827,727.38 0.00 37.92% 89.55% 0.00% 0.00%
VAL-07 213,310.65 2,041,038.03 0.00 10.45% 100.00% 0.00% 0.00%

2,041,038.03 171,916.39 100.00%


VALORES AFECTADO POR FACTOR DE RELACION 0.95000 (SIN IGV)

AVANCE FISICOS ACUMULADOS


AVANCE FISICOS PARCIALES
40.00% 120.00%
37.92%
PROGRAMADO ACUMULADO
35.00% REAL ACUMULADO 100.00%
100.00%
89.55%
30.00% 28.52%
80.00%
25.00%

20.00% PROGRAMADO 60.00%


51.63%
EJECUTADO
15.00% 13.65%
40.00%
10.45%
10.00% 21.99% 23.11%
8.34%
20.00%
5.00%
0.67% 1.12%
0.00%
0.00%
0.00% 1
8.35% 2 3 4 5 6 7 8 9
1 2 3 4 5 6 7 8 9 10
0.00%
MESES
MESES
OBRA:
REFACCION
Y
ACONDICION
AMIENTO DE AVANCE COMPARATIVO - INSTALACIONES ELECTRICAS
LA SEDE
INTENDENCI DEL 01 AL 29 ENERO 2016.
A DE
OBRA: REFACCION Y ACONDICIONAMIENTO DE LA SEDE INTENDENCIA DE ADUANA PAITA
ADUANA
PAITA Reg. Piura, Prov. Piura, Dist. Paita
UBICACIÓN : Consorcio Zavaleta
Contratista Consorcio Supervisor Paita MES VAL. : FEBRERO 2016.

AVANCE FISICO AVANCE FISICO (%)


Programado Contractual Real Programado Contractual Real
Valorizacion
Parcial Acumulado Parcial Acumulado Parcial Acumulado Parcial Acumulado
VAL-01 0.00 0.00 0.00 0.00 0.00% 0.00% 0.00% 0.00%
VAL-02 14,262.38 14,262.38 412,954.89 412,954.89 0.71% 0.71% 20.58% 20.58%
VAL-03 320,597.74 334,860.12 0.00 15.98% 16.69% 0.00% 20.58%
VAL-04 402,063.88 736,924.00 0.00 20.04% 36.73% 0.00% 20.58%
VAL-05 444,490.10 1,181,414.09 0.00 22.16% 58.89% 0.00% 20.58%
VAL-06 739,430.86 1,920,844.96 0.00 36.86% 95.75% 0.00% 20.58%
VAL-07 85,352.11 2,006,197.07 0.00 4.25% 100.00% 0.00% 0.00%

2,006,197.07 412,954.89 100.00%


VALORES AFECTADO POR FACTOR DE RELACION 0.95000 (SIN IGV)

AVANCES FISICOS PARCIALES


AVANCE FISICO ACUMULADOS
40.00% 120.00%
36.86%

35.00% PROGRAMADO PARCIAL PROGRAMADO 100.00%


100.00% ACUMULADO 95.75%
REAL PARCIAL
30.00% REAL ACUMULADO

80.00%
25.00%
22.16%
20.04%
20.00% 58.89%
60.00%
15.98%
15.00%
40.00% 36.73%

10.00%

20.00%
5.00% 4.25%
16.69%
0.71%
0.00%
0.00% 0.00%
0.71%
1 2 3 4 5 6 7 8 9 0.00%
1 2 3 4 5 6 7 8 9
OBRA:
REFACCION
Y
ACONDICION
AMIENTO DE AVANCE COMPARATIVO - INSTALACIONES SANITARIAS
LA SEDE
INTENDENCI
DEL 01 AL 29 ENERO 2016.
A DE
OBRA: REFACCION Y ACONDICIONAMIENTO DE LA SEDE INTENDENCIA DE ADUANA PAITA
ADUANA
PAITA Reg. Piura, Prov. Piura, Dist. Paita
UBICACIÓN : Consorcio Zavaleta
Contratista Consorcio Supervisor Paita MES VAL. : FEBRERO 2016.

AVANCE FISICO AVANCE FISICO (%)


Programado Contractual Real Programado Contractual Real
Valorizacion
Parcial Acumulado Parcial Acumulado Parcial Acumulado Parcial Acumulado
VAL-01 3,511.21 3,511.21 0.00 0.00 0.57% 0.57% 0.00% 0.00%
VAL-02 194,442.03 197,953.24 103,190.24 103,190.24 31.60% 32.17% 16.77% 16.77%
VAL-03 261,068.90 459,022.14 0.00 42.42% 74.59% 0.00% 16.77%
VAL-04 38,142.21 497,164.35 0.00 6.20% 80.79% 0.00% 16.77%
VAL-05 49,887.67 547,052.02 0.00 8.11% 88.90% 0.00% 16.77%
VAL-06 68,334.48 615,386.50 0.00 11.10% 100.00% 0.00% 16.77%
VAL-07 0.00 615,386.50 0.00% 100.00% 0.00% 16.77%

615,386.50 103,190.24 100.00%

VALORES AFECTADO POR FACTOR DE RELACION 0.95000 (SIN IGV)

AVANCES FISICOS PARCIALES AVANCE FISICOS ACUMU-


LADOS
120.00%
45.00% 42.42% PROGRAMADO ACUMULADO

40.00% REAL ACUMULADO 100.00% 100.00%


100.00%
88.90%
35.00% PROGRAMADO PARCIAL
31.60% 80.79%
REAL PARCIAL 80.00% 74.59%
30.00%

25.00%
60.00%
20.00%

15.00% 40.00%
32.17%
11.10%
10.00% 8.11%
6.20% 20.00%
5.00%
0.57% 0.00% 0.57%
0.00% 0.00%
1 2 3 4 5 6 7 8 9 1 2 3 4 5 6 7 8 9

MESES MESES
OBRA:
REFACCION
Y
ACONDICION RESUMEN DE AVANCE FISICO GENERAL
AMIENTO DE
LA SEDE DEL 01 AL 29 ENERO 2016.
INTENDENCI
A DE
OBRA:
ADUANAREFACCION Y ACONDICIONAMIENTO DE LA SEDE INTENDENCIA DE ADUANA PAITA
PAITA Reg. Piura, Prov. Piura, Dist. Paita
UBICACIÓN : Consorcio Zavaleta
Contratista Consorcio Supervisor Paita MES VAL. : FEBRERO 2016.

AVANCE FISICO AVANCE FISICO (%)


Programado Contractual Real Programado Contractual Real
Valorizacion
Parcial Acumulado Parcial Acumulado Parcial Acumulado Parcial Acumulado
VAL-01 174,865.61 174,865.61 170,730.22 170,730.22 2.78% 2.78% 2.72% 2.72%
VAL-02 839,391.44 1,014,257.05 1,022,898.21 1,193,628.43 13.36% 16.15% 16.28% 19.00%
VAL-03 917,754.13 1,932,011.18 0.00 14.61% 30.76% 0.00% 0.00%
VAL-04 1,056,161.15 2,988,172.33 0.00 16.81% 47.57% 0.00% 0.00%
VAL-05 1,406,635.96 4,394,808.29 0.00 22.39% 69.96% 0.00% 0.00%
VAL-06 1,587,880.53 5,982,688.82 0.00 25.28% 95.24% 0.00% 0.00%
VAL-07 298,901.02 6,281,589.85 0.00 4.76% 100.00% 0.00%

6,281,589.85 1,193,628.43 100.00% 19.00%


VALORES CON AFECTACION DE FACTOR DE RELACION 0.95000,(SIN IGV)

AVANCES FISICOS PARCIALES AVANCES FISICOS ACUMULADOS EN %

30.00% 120.00%

25.00% 100.00%

20.00% 80.00%
PORCENTAJE

PORCENTAJE
PROGRAMADO PROGRAMADO
15.00% 60.00%
EJECUTADO EJECUTADO

10.00% 40.00%

5.00% 20.00%

0.00% 0.00%

MESES MESES
CURVA "S"
AVANCE PROGRAMADO VS EJECUTADO (GENERAL)
DEL 01 AL 29 ENERO 2016.
OBRA REFACCION Y ACONDICIONAMIENTO DE LA SEDE INTENDENCIA DE ADUANA PAITA MES VAL. : FEBRERO 2016.

CONCURSO LICITACION PUBLICA Nº 000010-2015-SUNAT/610600-PRIMERA CONVOCATORIA PRESUPÙESTO REFERENCIAL S/. 7,802,395.81 INCL. IGV
CONTRATO Nº 455-2015/SUNAT- EJECUCION DE OBRAS PRESUPUESTO CONTRATADO S/. 7,412,276.02 INCL. IGV
FINANCIA SUPERINTENDENCIA NACIONAL DE ADMINISTRACIÓN TRIBUTARIA PRESUPUESTO CONTRATADO S/. 6,281,589.85 SIN. IGV
UBICACIÓN PIURA - PAITA - PAITA FACTOR DE RELACION 0.95000
CONTRATISTA CONSORCIO ZAVALETA ADELANTO DIRECTO S/. 1,482,455.20 INCL. IGV
SUPERVISOR ING. JOSE ALCIDES GALVEZ PAREDES ADELANTO POR MATERIALES S/. 0.00 INCL. IGV
RESIDENTE ING. GILMER JULIO SILVA CHOLAN

GRAFICO DE AVANCE FISICO - FINANCIERO PROGRAMADO Vs EJECUTADO

8,000,000.00

7,500,000.00 7412276.007808

7,000,000.00 7059572.80878

6,500,000.00

6,000,000.00
MONTO EN NUEVOS SOLES

5,500,000.00
5185873.780548
5,000,000.00

4,500,000.00

4,000,000.00

3,500,000.00 3526043.35176

3,000,000.00
POROGRAMADO
2,500,000.00
2279773.19358 EJECUTADO
2,000,000.00

1,500,000.00 1,408,481.55

1,000,000.00 1196823.323484

206341.425228
500,000.00
201,461.66
0.00 0
05/01/2016 31/01/2016 29/02/2016 31/03/2016 30/04/2016 31/05/2016 30/06/2016 02/07/2016

PLAZO DE EJECUCION 180


DIAS CALENDARIOS

MONTOS VALORIZADOS PROGRAMADOS MONTOS VALORIZADOS EJECUTADOS

MONTOS (Inc IGV) PORCENTAJES MONTOS (Inc IGV) PORCENTAJES


MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES PARCIAL ACUMUL. PARCIAL ACUMUL.
S/. S/. % % S/. S/. % %
05/01/2016 0.00 0.00 0.00% 0.00% 05/01/2016 0.00 0 0 0
31/01/2016 206,341.43 206,341.43 2.78% 2.78% 31/01/2016 201,461.66 201,461.66 2.72% 2.72%
29/02/2016 990,481.90 1,196,823.3 13.36% 16.15% 29/02/2016 1,207,019.89 1,408,481.55 16.28% 19.00%
31/03/2016 1,082,949.87 2,279,773.19 14.61% 30.76% 31/03/2016
30/04/2016 1,246,270.16 3,526,043.35 16.81% 47.57% 30/04/2016
31/05/2016 1,659,830.43 5,185,873.78 22.39% 69.96% 31/05/2016
30/06/2016 1,873,699.03 7,059,572.81 25.28% 95.24% 30/06/2016
02/07/2016 352,703.20 7,412,276.01 4.76% 100.00% 02/07/2016

TOTAL 7,412,276.01 100.00% TOTAL 1,408,481.55 19.00%