Está en la página 1de 3

VALORIZACION N° 01

SECTOR LAS PRADERAS

: INSTALACION Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO EN EL SECTOR


OBRA PRESUPUESTO BASE : S/. 2,883,089.51
4, DISTRITO DE HUAMACHUCO, PROVINCIA SANCHEZ CARRION, DEPARTAMENTO LA LIBERTAD
PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE SANCHEZ CARRION PRESUPUESTO CONTRATADO : S/. 2,883,089.51
EJECUTOR : CONSORCIO SAGITARIO
MES : JULIO 2014 PLAZO EJECUCION : 195 DIAS CALENDARIOS

METRADO PRESUPUESTO ACUMULADO ANTERIOR AVANCE ACTUAL ACUMULADO TOTAL SALDO


DESCRIPCION
UNID. CANT. P. UNIT. P. TOTAL % CANT. P. TOTAL % CANT. P. TOTAL % CANT. P. TOTAL % CANT. P. TOTAL

03.00 AGUA POTABLE


03.01 OBRAS PROVISIONALES
03.01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 3.60X2.40M Und 1.00 1,058.48 1,058.48 0.00% 0.00 0.00 100.00% 1.00 1,058.48 100.00% 1.00 1058.48 0.00% - -
03.01.02 CASETA DE ALMACEN Y/O GUARDIANIA m2 55.00 59.48 3,271.40 0.00% 0.00 0.00 100.00% 55.00 3,271.40 100.00% 55.00 3271.40 0.00% - -
03.01.03 SEÑALIZACION Y SEGURIDAD EN OBRA LAS PRADERAS Glb 1.00 10,140.88 10,140.88 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 1.00 10,140.88
03.01.04 MOVILIZACION Y DESMOVILIZACION DE EQUIPO A SECTOR LAS PRADERAS Glb 1.00 2,893.57 2,893.57 0.00% 0.00 0.00 50.00% 0.50 1,446.79 50.00% 0.50 1446.79 50.00% 0.50 1,446.78

03.02 TRABAJOS PRELIMINARES


03.02.01 TRAZO Y REPLANTEO GENERAL LINEA DE AGUA m 2,318.00 1.58 3,662.44 0.00% 0.00 0.00 100.00% 2,318.00 3,662.44 100.00% 2,318.00 3662.44 0.00% - -

03.03 LINEA DE MATRIZ (AGUA POTABLE)


03.03.01 LIMPIEZA DE TERRENO MANUAL m 2,318.00 1.66 3,847.88 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 2,318.00 3,847.88
03.03.02 TRAZO, NIVELACION Y REPLANTEO DE ZANJAS/ML m 2,318.00 1.29 2,990.22 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 2,318.00 2,990.22
03.03.03 EXCAVACION MANUAL DE ZANJAS/ML m 1,077.00 20.81 22,412.37 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 1,077.00 22,412.37
03.03.04 ACARREO DE MATERIAL, DISTANCIA MAXIMA= 50 m. m3 107.70 10.57 1,138.39 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 107.70 1,138.39
03.03.05 ELIMINACION DE MATERIAL EXCEDENTE C/ESPONJAMIENTO (DIST 2 Km) m3 134.63 25.99 3,499.03 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 134.63 3,499.03
03.03.06 REFINE, NIVELACION Y FONDOS PARA TUBERIA m 2,318.00 3.50 8,113.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 2,318.00 8,113.00
03.03.07 CAMA DE APOYO PARA TUBERIAS ( ARENA FINA m 2,318.00 10.11 23,434.98 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 2,318.00 23,434.98
03.03.08 TUBERIA PVC SAP CLASE 10,3" m 1,837.00 14.61 26,838.57 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 1,837.00 26,838.57
03.03.09 TUBERIA PVC SAP CLASE 10, 2" m 481.00 9.92 4,771.52 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 481.00 4,771.52
03.03.10 PRUEBA HIDRAULICA m 2,318.00 3.09 7,162.62 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 2,318.00 7,162.62
03.03.11 ACCESORIOS LINEA DE MATRIZ und 1.00 348.45 348.45 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 1.00 348.45
03.03.12 RELLENO Y COMPACTADO DE ZANJAS (MATERIAL ZARANDEADO m 2,318.00 16.87 39,104.66 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 2,318.00 39,104.66
03.03.13 LIMPIEZA FINAL DE OBRA m 2,318.00 1.66 3,847.88 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 2,318.00 3,847.88

03.04 CONEXIONES DOMICILIARIAS (AGUA POTABLE)


03.04.01 LIMPIEZA DE TERRENO MANUAL m 400.50 1.66 664.83 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 400.50 664.83
03.04.02 TRAZO, NIVELACION Y REPLANTEO DE ZANJAS/ML m 400.50 1.29 516.65 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 400.50 516.65
03.04.03 EXCAVACION MANUAL DE ZANJAS/ML m 400.50 20.81 8,334.41 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 400.50 8,334.41
03.04.04 ACARREO DE MATERIAL, DISTANCIA MAXIMA= 50 m. m3 8.90 10.57 94.07 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 8.90 94.07
03.04.05 ELIMINACION DE MATERIAL EXCEDENTE C/ESPONJAMIENTO (DIST 2 Km) m3 11.13 25.99 289.27 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 11.13 289.27
03.04.06 REFINE, NIVELACION Y FONDOS PARA TUBERIA m 400.50 3.50 1,401.75 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 400.50 1,401.75
03.04.07 CAMA DE APOYO PARA TUBERIAS ( ARENA FINA) m 400.50 10.11 4,049.06 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 400.50 4,049.06
03.04.08 TUBERIA PVC SAP CLASE 10, 1/2" m 400.50 3.23 1,293.62 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 400.50 1,293.62
03.04.09 PRUEBA HIDRAULICA m 400.50 3.09 1,237.55 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 400.50 1,237.55
03.04.10 RELLENO Y COMPACTADO DE ZANJAS (MATERIAL ZARANDEADO m 400.50 16.87 6,756.44 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 400.50 6,756.44
03.04.11 LIMPIEZA FINAL DE OBRA m 400.50 1.66 664.83 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 400.50 664.83

03.05 INST. DOMICILIARIA ACOMETIDA DE AGUA POTABLE


03.05.01 EXCAVACION MANUAL m3 6.23 23.77 148.09 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 6.23 148.09
03.05.02 CONCRETO FC=175 KG/CM2 m3 4.56 392.44 1,789.53 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 4.56 1,789.53
03.05.03 ENCOFRADO Y DESENCOFRADO m2 85.44 35.49 3,032.27 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 85.44 3,032.27
03.05.04 TARRAJEO INTERIOR C/MORTERO 1:5 X 1.5CM m2 46.28 19.25 890.89 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 46.28 890.89
03.05.05 SOLADO C:H E=4" m2 1.07 32.38 34.65 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 1.07 34.65
03.05.06 VALVULA DE PASO PVC 1/2" und 89.00 50.35 4,481.15 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 89.00 4,481.15
03.05.07 ACCESORIOS PARA CAJA DE PASO und 89.00 61.90 5,509.10 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 89.00 5,509.10

03.06 CAJA DE VALVULAS DE CONTROL (AGUA POTABLE


03.06.01 EXCAVACION MANUAL m3 1.40 23.77 33.28 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 1.40 33.28
03.06.02 CONCRETO FC=175 KG/CM2 m3 0.15 392.44 58.87 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 0.15 58.87
03.06.03 ENCOFRADO Y DESENCOFRADO m2 2.88 35.49 102.21 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 2.88 102.21
03.06.04 TARRAJEO INTERIOR C/MORTERO 1:5 X 1.5CM m2 4.32 19.25 83.16 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 4.32 83.16
03.06.05 SOLADO C:H E=4" m2 0.24 32.38 7.77 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 0.24 7.77
03.06.06 VALVULA DE CONTROL DE FIERRO FUNDIDO TIPO MAZZA DE 2" und 3.00 302.93 908.79 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 3.00 908.79
03.06.07 ACCESORIOS PARA CAJA DE VALVULAS, D=2" und 3.00 138.21 414.63 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 3.00 414.63

03.07 CAMARA ROMPE PRESION CRP-7


03.07.01 EXCAVACION MANUAL m3 2.00 23.77 47.54 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 2.00 47.54
03.07.02 ENCOFRADO Y DESENCOFRADO m2 12.84 35.49 455.69 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 12.84 455.69

Página 1
VALORIZACION N° 01
SECTOR LAS PRADERAS

: INSTALACION Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO EN EL SECTOR


OBRA PRESUPUESTO BASE : S/. 2,883,089.51
4, DISTRITO DE HUAMACHUCO, PROVINCIA SANCHEZ CARRION, DEPARTAMENTO LA LIBERTAD
PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE SANCHEZ CARRION PRESUPUESTO CONTRATADO : S/. 2,883,089.51
EJECUTOR : CONSORCIO SAGITARIO
MES : JULIO 2014 PLAZO EJECUCION : 195 DIAS CALENDARIOS

METRADO PRESUPUESTO ACUMULADO ANTERIOR AVANCE ACTUAL ACUMULADO TOTAL SALDO


DESCRIPCION
UNID. CANT. P. UNIT. P. TOTAL % CANT. P. TOTAL % CANT. P. TOTAL % CANT. P. TOTAL % CANT. P. TOTAL
03.07.03 CONCRETO SIMPLE FC=140 KG/CM2 m3 0.08 272.29 21.78 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 0.08 21.78
03.07.04 CONCRETO FC=175 KG/CM2 m3 0.56 392.44 219.77 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 0.56 219.77
03.07.05 ACERO FY=4200 KG/CM2 kg 54.02 4.89 264.16 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 54.02 264.16
03.07.06 TARRAJEO CON IMPERMEABILIZANTE (1:2) m2 4.02 39.21 157.62 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 4.02 157.62
03.07.07 TARRAJEO INTERIOR C/MORTERO 1:5 X 1.5CM m2 5.18 19.25 99.72 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 5.18 99.72
03.07.08 PINTURA CON ESMALTE m2 5.18 12.75 66.05 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 5.18 66.05
03.07.09 TAPA SANITARIA DE FIERRO 0.60 x 0.60, E=1/8" und 1.00 534.74 534.74 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 1.00 534.74
03.07.10 ACCESORIOS ENTRA Y SALE 2" CRP -7 und 1.00 251.01 251.01 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 1.00 251.01

03.08 CAMARA DE VALVULAS DE PURGA


03.08.01 EXCAVACION MANUAL m3 0.87 23.77 20.68 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 0.87 20.68
03.08.02 SUMINISTRO DE CAJA PARA VALVULA DE PURGA und 1.00 68.00 68.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 1.00 68.00
03.08.03 TAPA SANITARIA DE FIERRO 0.40 x 0.40, E=1/8" und 1.00 501.12 501.12 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 1.00 501.12
03.08.04 ACCESORIOS PARA CAJA DE VALVULAS, D=2" und 1.00 138.21 138.21 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 1.00 138.21

03.09 PASES AEREOS 01 (UNIDAD)


03.09.01 EXCAVACION MANUAL m3 4.00 23.77 95.08 0.00% 0.00 0.00 100.00% 4.00 95.08 100.00% 4.00 95.08 0.00% - -
03.09.02 CONCRETO FC=175 KG/CM2 m3 4.29 392.44 1,683.57 0.00% 0.00 0.00 100.00% 4.29 1,683.57 100.00% 4.29 1683.57 0.00% - -
03.09.03 ACERO FY=4200 KG/CM2 kg 284.83 4.89 1,392.82 0.00% 0.00 0.00 100.00% 284.83 1,392.82 100.00% 284.83 1392.82 0.00% - -
03.09.04 ENCOFRADO Y DESENCOFRADO m2 19.84 35.49 704.12 0.00% 0.00 0.00 100.00% 19.84 704.12 100.00% 19.84 704.12 0.00% - -
03.09.05 TARRAJEO EXTERIOR C/MORTERO 1:5 X 1.5CM m2 30.72 33.57 1,031.27 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 30.72 1,031.27
03.09.06 CABLE DE ACERO TIPO BOA 5/8" m 25.00 94.02 2,350.50 0.00% 0.00 0.00 100.00% 25.00 2,350.50 100.00% 25.00 2350.50 0.00% - -
03.09.07 TEMPLADORES DE FIERRO und 2.00 328.27 656.54 0.00% 0.00 0.00 100.00% 2.00 656.54 100.00% 2.00 656.54 0.00% - -
03.09.08 GRAPAS PARA CABLE DE ACERO und 30.00 71.42 2,142.60 0.00% 0.00 0.00 100.00% 30.00 2,142.60 100.00% 30.00 2142.60 0.00% - -
03.09.09 PENDOLAS DE FIERRO und 15.00 166.21 2,493.15 0.00% 0.00 0.00 100.00% 15.00 2,493.15 100.00% 15.00 2493.15 0.00% - -
03.09.10 TUBERIA HDPE ISO-4427 PN-10 3" m 21.00 104.47 2,193.87 0.00% 0.00 0.00 100.00% 21.00 2,193.87 100.00% 21.00 2193.87 0.00% - -

04.00 ALCANTARILLADO
04.01 TRABAJOS PRELIMINARES
04.01.01 DEMOLICION DE BUZONES EXISTENTES m3 23.11 816.32 18,865.16 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 23.11 18,865.16
04.01.02 RETIRO DE TUBERIA DAÑADA m 395.00 11.29 4,459.55 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 395.00 4,459.55
04.01.03 ACARREO DE MATERIAL, DISTANCIA MAXIMA= 50 m. m3 23.11 10.57 244.27 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 23.11 244.27
04.01.04 ELIMINACION DE MATERIAL EXCEDENTE C/ESPONJAMIENTO (DIST 2 Km) m3 21.20 25.99 550.99 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 21.20 550.99

04.02 MOVIMIENTO DE TIERRAS


04.02.01 TRAZO, NIVELACION Y REPLANTEO DE ZANJAS/ML m 395.00 1.29 509.55 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 395.00 509.55
04.02.02 EXCAVACION C/EQUIPO DE ZANJAS/ML, H = 1.20 - 1.50 M m 395.00 10.81 4,269.95 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 395.00 4,269.95
04.02.03 REFINE Y NIVELACION ZANJA TERR.NORMAL-ALCANTARILLADO m 395.00 1.83 722.85 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 395.00 722.85
04.02.04 RELLENO Y COMPACTADO DE ZANJAS (MATERIAL ZARANDEADO m 395.00 16.87 6,663.65 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 395.00 6,663.65
04.02.05 ACARREO DE MATERIAL, DISTANCIA MAXIMA= 50 m. m3 39.50 10.57 417.52 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 39.50 417.52
04.02.06 ELIMINACION DE MATERIAL EXCEDENTE C/ESPONJAMIENTO (DIST 2 Km m3 49.38 23.41 1,155.99 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 49.38 1,155.99

04.03 INSTALACION Y SUMINISTRO DE TUBERIA


04.03.01 LIMPIEZA DE TERRENO MANUAL m 395.00 1.66 655.70 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 395.00 655.70
04.03.02 CAMA DE APOYO PARA TUBERIAS-ALCANTARILLADO C/MAT. PRESTAMO m 395.00 8.15 3,219.25 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 395.00 3,219.25
04.03.03 TUBERIA PVC-U S 20 Ø 200 mm DOBLE PARED (UNION FLEXIBLE) m 395.00 46.24 18,264.80 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 395.00 18,264.80
04.03.04 PRUEBA HIDRAULICA DE TUBERIAS DE ALCANTARILLADO m 395.00 6.89 2,721.55 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 395.00 2,721.55
04.03.05 EMPALME DE TUBERIA MATRIZ A BUZON NUEVO und 170.00 70.99 12,068.30 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 170.00 12,068.30
04.03.06 EMPALME DE TUBERIA MATRIZ A BUZON EXISTENTE und 5.00 100.73 503.65 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 5.00 503.65
04.03.07 REPOSICION Y EMPALMES DE TUBERIA DOMICILIARIA ALCANTARILLADO und 100.00 88.20 8,820.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 100.00 8,820.00
04.03.08 LIMPIEZA FINAL DE OBRA m 395.00 1.66 655.70 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 395.00 655.70

04.04 CONSTRUCCION DE BUZONES


04.04.01 TRAZO DE NIVELES Y REPLANTEO m2 22.11 1.45 32.06 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 22.11 32.06
04.04.02 NIVELACION Y COMPACTACION DE SUBRASANTE m2 22.11 16.92 374.10 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 22.11 374.10
04.04.03 EXCAVACION MANUAL EN BUZONES m3 34.77 27.17 944.70 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 34.77 944.70
04.04.04 BUZON DE CONCRETO H=1.20M, D=1.20M, TAPA C°A° und 3.00 1,327.67 3,983.01 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 3.00 3,983.01
04.04.05 BUZON DE CONCRETO H=1.30M, D=1.20M, TAPA C°A° und 1.00 1,368.40 1,368.40 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 1.00 1,368.40
04.04.06 BUZON DE CONCRETO H=1.60M, D=1.20M, TAPA C°A° und 5.00 1,600.70 8,003.50 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 5.00 8,003.50
04.04.07 BUZON DE CONCRETO H=2.20M, D=1.20M, TAPA C°A° und 2.00 2,049.04 4,098.08 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 2.00 4,098.08

Página 2
VALORIZACION N° 01
SECTOR LAS PRADERAS

: INSTALACION Y MEJORAMIENTO DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO EN EL SECTOR


OBRA PRESUPUESTO BASE : S/. 2,883,089.51
4, DISTRITO DE HUAMACHUCO, PROVINCIA SANCHEZ CARRION, DEPARTAMENTO LA LIBERTAD
PROPIETARIO : MUNICIPALIDAD PROVINCIAL DE SANCHEZ CARRION PRESUPUESTO CONTRATADO : S/. 2,883,089.51
EJECUTOR : CONSORCIO SAGITARIO
MES : JULIO 2014 PLAZO EJECUCION : 195 DIAS CALENDARIOS

METRADO PRESUPUESTO ACUMULADO ANTERIOR AVANCE ACTUAL ACUMULADO TOTAL SALDO


DESCRIPCION
UNID. CANT. P. UNIT. P. TOTAL % CANT. P. TOTAL % CANT. P. TOTAL % CANT. P. TOTAL % CANT. P. TOTAL
04.04.08 CONCRETO FC=175 KG/CM2 (BLOQUE DE ANCLAJE BUZON) m3 1.38 390.49 538.88 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 1.38 538.88
04.04.09 ELIMINACION DE MATERIAL EXCEDENTE C/ESPONJAMIENTO (DIST 2 Km) m3 45.20 23.41 1,058.13 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 45.20 1,058.13
04.04.10 MEJORAMIENTO DE MEDIA CAÑA EN BUZONES EXISTENTES und 5.00 85.12 425.60 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 5.00 425.60

04.05 CONEXIONES DOMICILIARIAS


04.05.01 LIMPIEZA DE TERRENO MANUAL m 400.50 1.66 664.83 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 400.50 664.83
04.05.02 TRAZO, NIVELACION Y REPLANTEO DE ZANJAS/ML m 400.50 1.29 516.65 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 400.50 516.65
04.05.03 EXCAVACION MANUAL DE ZANJAS/ML, H = 1.20 - 1.50 M m 400.50 21.63 8,662.82 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 400.50 8,662.82
04.05.04 REFINE Y NIVELACION ZANJA TERR.NORMAL-ALCANTARILLADO m 400.50 1.83 732.92 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 400.50 732.92
04.05.05 CAMA DE APOYO PARA TUBERIAS ( ARENA FINA m 400.50 10.11 4,049.06 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 400.50 4,049.06
04.05.06 TUBERIA PVC-U S 20 Ø 160 mm DOBLE PARED (UNION FLEXIBLE) m 400.50 29.44 11,790.72 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 400.50 11,790.72
04.05.07 RELLENO Y COMPACTADO DE ZANJAS (MATERIAL ZARANDEADO m 400.50 16.87 6,756.44 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 400.50 6,756.44
04.05.08 ACARREO DE MATERIAL, DISTANCIA MAXIMA= 50 m. m3 40.05 10.57 423.33 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 40.05 423.33
04.05.09 ELIMINACION DE MATERIAL EXCEDENTE C/ESPONJAMIENTO (DIST 2 Km m3 50.06 23.41 1,171.90 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 50.06 1,171.90
04.05.10 CONEXION DOMICILIARIA CACHIMBA UPVC 6" und 89.00 103.84 9,241.76 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 89.00 9,241.76
04.05.11 CAJA DE REGISTRO 12" X 24" TAPA DE CONCRETO und 89.00 99.68 8,871.52 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 89.00 8,871.52
04.05.12 TARRAJEO EN CAJA DE REGISTRO m2 341.76 23.49 8,027.94 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 341.76 8,027.94
04.05.13 SOLADO C:H E=4" m2 11.57 32.38 374.64 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 11.57 374.64
04.05.14 CONCRETO FC=175 KG/CM2 (BLOQUE DE ANCLAJE CAJA DE REGISTRO m3 0.67 373.17 250.02 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 0.67 250.02
04.05.15 PRUEBA HIDRAULICA DE TUBERIAS DE ALCANTARILLADO m 400.50 6.89 2,759.45 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 400.50 2,759.45
04.05.16 REJILLA METALICA EN SALIDA DE CAJA DE CONCRETO und 89.00 49.02 4,362.78 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 89.00 4,362.78
04.05.17 LIMPIEZA FINAL DE OBRA m 400.50 1.66 664.83 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 400.50 664.83

04.06 FLETE A SECTOR LAS PRADERAS


04.06.01 FLETE TERRESTRE SC LAS PRADERAS Glb 1.00 4,968.43 4,968.43 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 100.00% 1.00 4,968.43

COSTO DIRECTO S/. 408,807.75 S/. - S/. 23,151.36 S/. 23,151.36 S/. 385,656.39
GASTOS GENERALES (10%) S/. 40,880.78 S/. - S/. 2,315.14 S/. 2,315.14 S/. 38,565.64
UTILIDAD (5%) S/. 20,440.39 S/. - S/. 1,157.57 S/. 1,157.57 S/. 19,282.82

SUB-TOTAL S/. 470,128.92 S/. - S/. 26,624.07 S/. 26,624.07 S/. 424,222.03
FACTOR RELACION 1.0000000 1.0000000 1.0000000 1.0000000 1.0000000
VALORIZACION BRUTA S/. 470,128.92 S/. - S/. 26,624.07 S/. 26,624.07 S/. 424,222.03

Página 3

También podría gustarte