FICHA DE IDENTIFICACION DE OBRA

INFORMACION CONTRACTUAL

ENTIDAD:
: MUNICIPALIDAD PROVINCIAL DE CHINCHA

:
"MANTENIMIENTO PERIODICO Y RUTINARIO DE LAS VIAS VECINALES DE LA PROVINCIA
NOMBRE DEL SERVICIO DE CHINCHA - ICA - ITEM II – TRAMOS EMP. IC-100 (CHAVIN) - SAN FLORIAN - SAN JUAN
DE LUYO – HUIRPINA, DISTRITO DE CHAVIN – CHINCHA – ICA”.

N° DE CONTRATO : CONTRATO N° 27-2020-MPCH/GM

PROCESO : PES N° 001-2020-MPCH-PRIMERA CONVOCATORIA

CONTRATISTA : CONSORCIO SAN MARTIN DE PORRES

RESIDENTE : ING. IVAN ALEXANDER MONROE ESPINOZA

INSPECTOR : ING. FLOR ANICAMA MUÑANTE


MODALIDAD : A COSTOS UNTARIOS
PRESUPUESTO BASE : S/. 2,642,378.00 Inc. IGV
PRESUPUESTO CONTRATADO : S/. 2,113,902.40 Inc. IGV
FACTOR DE RELACION : 0.80000
PRESUPUESTO MANT. PERIODICO : S/. 1,754,538.99 Inc. IGV
PRESUPUESTO MANT. RUTINARIO : S/. 317,085.36 Inc. IGV
PRESUPUESTO PLAN DE TRABAJO : S/. 21,139.02 Inc. IGV
PRESUPUESTO INVENTARIO VIAL : S/. 21,139.02 Inc. IGV
PLAZO PROGRAMADO : 485 Días Calendarios
FECHA DE FIRMA DE CONTRATO : 14-Aug-20
FECHA ENTREGA DE TERRENO : 28-Sep-20
FECHA DE INICIO DE OBRA : 29-Sep-20
FECHA TERMINO CONTRACTUAL : 27-Jan-22
PLAZO DE MANT. PERIODICO : 94 Días Calendarios

UBICACIÓN DE LA OBRA

DEPARTAMENTO : ICA
PROVINCIA : CHINCHA
DISTRITO : CHAVIN
RESUMEN DE VALORIZACION N° 02
OBRA :
"MANTENIMIENTO PERIODICO Y RUTINARIO DE LAS VIAS VECINALES DE LA PROVINCIA DE CHINCHA - ICA - ITEM II –
TRAMOS EMP. IC-100 (CHAVIN) - SAN FLORIAN - SAN JUAN DE LUYO – HUIRPINA, DISTRITO DE CHAVIN – CHINCHA – ICA”.
INSPECCION: : MUNICIPALIDAD PROVINCIAL DE CHINCHA MODALIDAD EJECUCIÓN : PRECIOS UNITARIOS
ING. INSPECTOR : ING. FLOR ANICAMA MUÑANTE PLAZO EJECUCIÓN : 94 DÍAS CALENDARIOS
EJECUTA : CONSORCIO SAN MARTIN DE PORRES PRES. MANT. PERIODICO (INC. IGV) : S/. 1,754,538.99
ING. RESIDENTE : ING. IVAN ALEXANDER MONROE ESPINOZA PRES. MANT. PERIODICO (SIN. IGV) : S/. 1,486,897.45
UBICACIÓN : DEPARTAMENTO : ICA
PROVINCIA : CHINCHA
DISTRITO : CHAVIN

Monto Val. Acum. Valorizacion Val. Acum. % Saldo por


DESCRIPCIÓN
Contratado Anterior Actual Actual Avance Valorizar

1 Valorizacion Contractual ( V ) (sin. IGV)


1.1 Mej. Y ampliación agua y alcantarillado 1,486,897.45 32,415.51 208,208.88 240,624.39 16.18% 1,246,273.06

Total Contractual (SIN IGV) 1,486,897.45 32,415.51 208,208.88 240,624.39 1,246,273.06


% de Avance a la fecha 2.18% 14.00% 16.18% 83.82%

2 Reajustes, Inc. Deducciones ( R )


2.1 Mej. Y ampliación agua y alcantarillado 0.00 0.00 0.00
0.00 0.00 0.00
Total de Reajustes 0.00 0.00 0.00
Valorizacion Bruta ( VB = V + R ) 32,415.51 208,208.88 240,624.39

3 Amortizaciones ( A )
3.1 Adelanto Directo (0%) Anterior Actual Acum.Actual Sald.Amortizar
3.1.1 Mej. Y ampliación agua y alcantarillado 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00

3.2 Adelanto Materiales (0%) Anterior Actual Acum.Actual Sald.Amortizar


3.2.1 Mej. Y ampliación agua y alcantarillado 0.00 0.00 0.00 0.00 0.00
0.00 0.00 0.00 0.00 0.00

Total de Amortizaciones ( A ) 0.00 0.00 0.00 0.00 0.00

Anterior Actual Acum.Actual


Valorizacion Neta ( VN = VB - A ) 32,415.51 208,208.88 240,624.39
I.G.V (18%) 5,834.79 37,477.60 43,312.39
Valorizacion Neta Total 38,250.30 245,686.48 283,936.78

Monto a cancelar al contratista en la presente valorización S/. 245,686.48 (INC. IGV)

SON : DOSCIENTOS CUARENTA Y CINCO MIL SEISCIENTOS OCHENTA Y SEIS CON 48/100 soles
METRADOS EJECUTADOS - VALORIZACION N°2
DEL 01 AL 30 DE NOVIEMBRE DEL 2020
Entidad: MUNICIPALIDAD PROVINCIAL DE CHINCHA
Proceso: PES N° 001-2020-MPCH-PRIMERA CONVOCATORIA
MANTENIMIENTO PERIODICO Y RUTINARIO DE LAS VIAS VECINALES DE LA
PROVINCIA DE CHINCHA - ICA - ITEM II – TRAMOS EMP. IC-100 (CHAVIN)
Obra:
- SAN FLORIAN - SAN JUAN DE LUYO – HUIRPINA, DISTRITO DE CHAVIN –
CHINCHA – ICA”.
Contratista: CONSORCIO SAN MARTIN DE PORRES
Residente: ING. IVAN ALEXANDER MONROE ESPINOZA
Inspector: ING. FLOR ANICAMA MUÑANTE

Item Descripcion Und. Metrado

1 OBRAS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 0.00
1.02 TRAZO Y REPLANTEO KM 7.25
2 PAVIMENTOS
2.01 CAPA NIVELANTE E=0.05 M M3 625.80
2.02 MATERIAL GRANULAR DE CANTERA E=0.15 M M3 1,877.40
3 TRANSPORTE
3.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1 KM M3K 3,129.00
3.02 TRANSPORTE DE MATERIAL GRANULAR MAYOR A 1 KM M3K 28,161.00
3.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 KM M3K 217.00
3.04 TRANSPORTE DE MATERIAL EXCEDENTE MAYOR A 1KM M3K 2,039.80
4 OBRAS DE ARTE Y DRENAJE
4.01 RECONFORMACION DE CUNETAS ML 900.00
5 SEÑALIZACION
5.01 INSTALACION DE POSTES KILOMETRICOS UND 0.00
5.02 SEÑALES PREVENTIVAS UND 0.00
5.03 SEÑALES REGLAMENTARIAS UND 0.00
5.04 SEÑALES INFORMATIVAS UND 0.00
6 IMPACTO AMBIENTAL
6.01 RECUPERACION AMBIENTAL DE AREAS OCUPADAS HA 0.00
7 EMERGENCIA SANITARIA
7.01 EMERGENCIA SANITARIA COVID 19 GLB 0.33
SUSTENTO DE METRADOS EJECUTADOS- VALORIZACION N°2
DEL 01 AL 30 DE NOVIEMBRE DEL 2020
Entidad: MUNICIPALIDAD PROVINCIAL DE CHINCHA
Proceso: PES N° 001-2020-MPCH-PRIMERA CONVOCATORIA
MANTENIMIENTO PERIODICO Y RUTINARIO DE LAS VIAS VECINALES DE LA PROVINCIA DE CHINCHA - ICA - ITEM II – TRAMOS EMP. IC-100 (CHAVIN) - SAN FLORIAN - SAN JUAN DE LUYO –
Obra:
HUIRPINA, DISTRITO DE CHAVIN – CHINCHA – ICA”.
Contratista: CONSORCIO SAN MARTIN DE PORRES
Residente: ING. IVAN ALEXANDER MONROE ESPINOZA
Inspector: ING. FLOR ANICAMA MUÑANTE

Item Descripcion Und. Cant. Largo (m) Ancho (m) Alto (m) Parcial Metrado

1 OBRAS PRELIMINARES
1.02 TRAZO Y REPLANTEO KM 7.25
7.25
2 PAVIMENTOS
2.01 CAPA NIVELANTE E=0.05 M M3 625.80
Progresiva
Del Km Al Km
0+000 0+500 500.00 3.10 0.05 77.50
0+500 1+000 500.00 3.25 0.05 81.25
1+000 1+500 500.00 2.90 0.05 72.50
1+500 2+000 500.00 2.80 0.05 70.00
2+000 2+500 500.00 2.95 0.05 73.75
2+500 3+000 500.00 3.20 0.05 80.00
3+000 3+500 500.00 2.80 0.05 70.00
3+500 4+000 480.00 2.40 0.05 57.60
6+000 7+000 360.00 2.40 0.05 43.20

2.02 MATERIAL GRANULAR DE CANTERA E=0.15 M M3 1,877.40


Progresiva
Del Km Al Km
0+000 0+500 500.00 3.10 0.15 232.50
0+500 1+000 500.00 3.25 0.15 243.75
1+000 1+500 500.00 2.90 0.15 217.50
1+500 2+000 500.00 2.80 0.15 210.00
2+000 2+500 500.00 2.95 0.15 221.25
2+500 3+000 500.00 3.20 0.15 240.00
3+000 3+500 500.00 2.80 0.15 210.00
3+500 4+000 480.00 2.40 0.15 172.80
6+000 7+000 360.00 2.40 0.15 129.60

3 TRANSPORTE
3.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1 KM M3K 3,129.00
1.25 2,503.20 3,129.00

3.02 TRANSPORTE DE MATERIAL GRANULAR MAYOR A 1 KM M3K 28,161.00


1.25 2,503.20 28,161.00

3.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 KM M3K 217.00


4,340.00 0.05 217.00

3.04 TRANSPORTE DE MATERIAL EXCEDENTE MAYOR A 1KM M3K 2,039.80


4,340.00 0.05 2,039.80

4 OBRAS DE ARTE Y DRENAJE


4.01 RECONFORMACION DE CUNETAS ML 900.00
900.00
7 EMERGENCIA SANITARIA
7.01 EMERGENCIA SANITARIA COVID 19 GLB 0.33
VALORIZACION DE AVANCE DE OBRA N° 02
DEL 01 AL 30 DE NOVIEMBRE DEL 2020
Entidad: MUNICIPALIDAD PROVINCIAL DE CHINCHA
Proceso: PES N° 001-2020-MPCH-PRIMERA CONVOCATORIA Ppto de Contrato : S/. 2,642,378.00 (Inc. I.G.V.)
MANTENIMIENTO PERIODICO Y RUTINARIO DE LAS VIAS VECINALES DE LA PROVINCIA DE CHINCHA - ICA - ITEM II – TRAMOS EMP. IC-100 (CHAVIN) - SAN
Obra: Ppto de Mant. Periodico : S/. 1,754,538.99 (Inc. I.G.V.)
FLORIAN - SAN JUAN DE LUYO – HUIRPINA, DISTRITO DE CHAVIN – CHINCHA – ICA”.
Contratista: CONSORCIO SAN MARTIN DE PORRES Plazo de Ejecución : 485 días calendario
Residente: ING. IVAN ALEXANDER MONROE ESPINOZA Fecha de Inicio de Obra : 29/09/2020
Inspector: ING. FLOR ANICAMA MUÑANTE Fecha de Termino de Obra : 27/01/2022

Acumulado Anterior Valorizacion del Mes Actual Acumulado Actual Saldo por Valorizar
Costo
Item Descripcion Und. Metrado Costo Parcial
Unitario Metrado Costo Parcial % Metrado Costo Parcial % Metrado Costo Parcial % Metrado Costo Parcial %

1 OBRAS PRELIMINARES
1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 S/16,892.45 S/16,892.45 0.40 S/6,756.98 40.00% 0.00 S/0.00 0.00% 0.40 6,756.98 40.00% 0.60 10,135.47 60.00%
1.02 TRAZO Y REPLANTEO KM 31.00 S/916.73 S/28,418.63 3.50 S/3,208.56 11.29% 7.25 S/6,646.29 23.39% 10.75 9,854.85 34.68% 20.25 18,563.78 65.32%
2 PAVIMENTOS
2.01 CAPA NIVELANTE E=0.05 M M3 4,129.75 S/19.38 S/80,034.56 0.00 S/0.00 0.00% 625.80 S/12,128.00 15.15% 625.80 12,128.00 15.15% 3,503.95 67,906.56 84.85%
2.02 MATERIAL GRANULAR DE CANTERA E=0.15 M M3 12,389.25 S/34.75 S/430,526.44 185.54 S/6,447.52 1.50% 1,877.40 S/65,239.65 15.15% 2,062.94 71,687.17 16.65% 10,326.31 358,839.28 83.35%
3 TRANSPORTE
3.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1 KM M3K 19,822.80 S/7.75 S/153,626.70 0.00 S/0.00 0.00% 3,129.00 S/24,249.75 15.78% 3,129.00 24,249.75 15.78% 16,693.80 129,376.95 84.22%
3.02 TRANSPORTE DE MATERIAL GRANULAR MAYOR A 1 KM M3K 178,405.20 S/1.73 S/308,641.00 0.00 S/0.00 0.00% 28,161.00 S/48,718.53 15.78% 28,161.00 48,718.53 15.78% 150,244.20 259,922.47 84.22%
3.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 KM M3K 1,550.00 S/4.81 S/7,455.50 0.00 S/0.00 0.00% 217.00 S/1,043.77 14.00% 217.00 1,043.77 14.00% 1,333.00 6,411.73 86.00%
3.04 TRANSPORTE DE MATERIAL EXCEDENTE MAYOR A 1KM M3K 14,570.00 S/2.38 S/34,676.60 0.00 S/0.00 0.00% 2,039.80 S/4,854.72 14.00% 2,039.80 4,854.72 14.00% 12,530.20 29,821.88 86.00%
4 OBRAS DE ARTE Y DRENAJE
4.01 RECONFORMACION DE CUNETAS ML 31,000.00 S/3.15 S/97,650.00 0.00 S/0.00 0.00% 900.00 S/2,835.00 2.90% 900.00 2,835.00 2.90% 30,100.00 94,815.00 97.10%
5 SEÑALIZACION
5.01 INSTALACION DE POSTES KILOMETRICOS UND 31.00 S/173.59 S/5,381.29 0.00 S/0.00 0.00% 0.00 S/0.00 0.00% 0.00 0.00 0.00% 31.00 5,381.29 100.00%
5.02 SEÑALES PREVENTIVAS UND 85.00 S/541.04 S/45,988.40 0.00 S/0.00 0.00% 0.00 S/0.00 0.00% 0.00 0.00 0.00% 85.00 45,988.40 100.00%
5.03 SEÑALES REGLAMENTARIAS UND 3.00 S/457.49 S/1,372.47 0.00 S/0.00 0.00% 0.00 S/0.00 0.00% 0.00 0.00 0.00% 3.00 1,372.47 100.00%
5.04 SEÑALES INFORMATIVAS UND 6.00 S/1,359.48 S/8,156.88 0.00 S/0.00 0.00% 0.00 S/0.00 0.00% 0.00 0.00 0.00% 6.00 8,156.88 100.00%
6 IMPACTO AMBIENTAL
6.01 RECUPERACION AMBIENTAL DE AREAS OCUPADAS HA 2.48 S/3,523.78 S/8,738.97 0.00 S/0.00 0.00% 0.00 S/0.00 0.00% 0.00 0.00 0.00% 2.48 8,738.97 100.00%
7 EMERGENCIA SANITARIA
7.01 EMERGENCIA SANITARIA COVID 19 GLB 1.00 S/32,522.69 S/32,522.69 0.34 S/11,057.71 34.00% 0.33 S/10,732.49 33.00% 0.67 21,790.20 67.00% 0.33 10,732.49 33.00%
COSTO DIRECTO S/. 1,260,082.58 S/. 27,470.77 S/. 176,448.20 S/. 203,918.98 S/. 1,056,163.60
GASTOS GENERALES 10.00% 126,008.26 2,747.08 17,644.82 20,391.90 105,616.36
UTILIDAD 8.00% 100,806.61 2,197.66 14,115.86 16,313.52 84,493.09
-------------- --------------- --------------- ---------------- ----------------
SUB TOTAL S/. 1,486,897.45 S/. 32,415.51 S/. 208,208.88 S/. 240,624.40 S/. 1,246,273.05
IGV 18% 18.00% 267,641.54 5,834.79 37,477.60 43,312.39 224,329.15
TOTAL S/. 1,754,538.99 S/. 38,250.30 2.18% S/. 245,686.48 14.00% S/. 283,936.80 16.18% S/. 1,470,602.20 83.82%
CONTROL DE ACTIVIDADES EJECUTADAS VS. PROGRAMADAS - VALORIZACION N° 2
DEL 01 AL 30 DE NOVIEMBRE DEL 2020
Entidad: MUNICIPALIDAD PROVINCIAL DE CHINCHA Presupuesto de Contrato : S/. 2,642,378.00 (Inc. I.G.V.)
Proceso: PES N° 001-2020-MPCH-PRIMERA CONVOCATORIA Presupuesto Mant. Periodico : S/. 1,754,538.99 (Inc. I.G.V.)

MANTENIMIENTO PERIODICO Y RUTINARIO DE LAS VIAS VECINALES DE LA PROVINCIA DE CHINCHA - ICA - ITEM II –
Obra: Presupuesto Mant. Periodico : S/. 1,486,897.45 (Inc. I.G.V.)
TRAMOS EMP. IC-100 (CHAVIN) - SAN FLORIAN - SAN JUAN DE LUYO – HUIRPINA, DISTRITO DE CHAVIN – CHINCHA – ICA”.

Contratista: CONSORCIO SAN MARTIN DE PORRES Plazo de Ejecución : 485 días calendario
Residente: ING. IVAN ALEXANDER MONROE ESPINOZA Fecha de Inicio de Obra : 29/09/2020
Inspector: ING. FLOR ANICAMA MUÑANTE Fecha de Termino de Obra : 27/01/2022

METRADO PROGRAMADO METRADO EJECUTADO


ESTADO DE
ITEM DESCRIPCION UND META AVANCE AVANCE SERVICIO DE
AVANCE AVANCE PORCENTAJE AVANCE AVANCE PORCENTAJE
ACUMULADO MES ACUMULADO MES ACTIVIDAD
MENSUAL ACUMULADO ACUMULADO MENSUAL ACUMULADO ACUMULADO
ANTERIOR ANTERIOR

1.00 OBRAS PRELIMINARES


1.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 0.40 0.00 0.40 40.00% 0.40 0.00 0.40 40.00% EQUILIBRIO
1.02 TRAZO Y REPLANTEO KM 31.00 3.50 20.15 23.65 76.29% 3.50 7.25 10.75 34.68% ATRASADO
2.00 PAVIMENTOS 0.00
2.01 CAPA NIVELANTE E=0.05 M M3 4,129.75 0.00 0.00 0.00 0.00% 0.00 625.80 625.80 15.15% ADELANTADO
2.02 MATERIAL GRANULAR DE CANTERA E=0.15 M M3 12,389.25 185.54 941.58 1,127.12 9.10% 185.54 1,877.40 2,062.94 16.65% ADELANTADO
3.00 TRANSPORTE
3.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1 KM M3K 19,822.80 0.00 8,920.26 8,920.26 45.00% 0.00 3,129.00 3,129.00 15.78% ATRASADO
3.02 TRANSPORTE DE MATERIAL GRANULAR MAYOR A 1 KM M3K 178,405.20 0.00 89,202.60 89,202.60 50.00% 0.00 28,161.00 28,161.00 15.78% ATRASADO
3.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 KM M3K 1,550.00 0.00 0.00 0.00 0.00% 0.00 217.00 217.00 14.00% ADELANTADO
3.04 TRANSPORTE DE MATERIAL EXCEDENTE MAYOR A 1KM M3K 14,570.00 0.00 0.00 0.00 0.00% 0.00 2,039.80 2,039.80 14.00% ADELANTADO
4.00 OBRAS DE ARTE Y DRENAJE
4.01 RECONFORMACION DE CUNETAS ML 31,000.00 0.00 0.00 0.00 0.00% 0.00 900.00 900.00 2.90% ADELANTADO
5.00 SEÑALIZACION
5.01 INSTALACION DE POSTES KILOMETRICOS UND 31.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00 0.00% EQUILIBRIO
5.02 SEÑALES PREVENTIVAS UND 85.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00 0.00% EQUILIBRIO
5.03 SEÑALES REGLAMENTARIAS UND 3.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00 0.00% EQUILIBRIO
5.04 SEÑALES INFORMATIVAS UND 6.00 0.00 0.00 0.00 0.00% 0.00 0.00 0.00 0.00% EQUILIBRIO
6.00 IMPACTO AMBIENTAL
6.01 RECUPERACION AMBIENTAL DE AREAS OCUPADAS HA 2.48 0.00 0.00 0.00 0.00% 0.00 0.00 0.00 0.00% EQUILIBRIO
7.00 EMERGENCIA SANITARIA
7.01 EMERGENCIA SANITARIA COVID 19 GLB 1.00 0.34 0.33 0.67 67.00% 0.34 0.33 0.67 67.00% EQUILIBRIO
CONTROL DE VALORIZACIONES EJECUTADAS VS. PROGRAMADAS - VALORIZACION N°2
DEL 01 AL 30 DE NOVIEMBRE DEL 2020
Entidad: MUNICIPALIDAD PROVINCIAL DE CHINCHA Presupuesto de Contrato : S/. 2,642,378.00 (Inc. I.G.V.)
Proceso: PES N° 001-2020-MPCH-PRIMERA CONVOCATORIA Presupuesto Mant. Periodico : S/. 1,754,538.99 (Inc. I.G.V.)
MANTENIMIENTO PERIODICO Y RUTINARIO DE LAS VIAS
VECINALES DE LA PROVINCIA DE CHINCHA - ICA - ITEM II –
Obra: Presupuesto Mant. Periodico : S/. 1,486,897.45 (Inc. I.G.V.)
TRAMOS EMP. IC-100 (CHAVIN) - SAN FLORIAN - SAN JUAN DE
LUYO – HUIRPINA, DISTRITO DE CHAVIN – CHINCHA – ICA”.
Contratista: CONSORCIO SAN MARTIN DE PORRES Plazo de Ejecución : 485 días calendario
Residente: ING. IVAN ALEXANDER MONROE ESPINOZA Fecha de Inicio de Obra : 29/09/2020
Inspector: ING. FLOR ANICAMA MUÑANTE Fecha de Termino de Obra : 27/01/2022

PROGRAMADO (Sin. IGV) (*) EJECUTADO (Sin. IGV)


ESTADO DE
MES AVANCE AVANCE PORCENTAJE AVANCE AVANCE PORCENTAJE
VALORIZACIÓN Nº VALORIZACIÓN Nº SERVICIO
MENSUAL ACUMULADO ACUMULADO MENSUAL ACUMULADO ACUMULADO

MES 1 01 S/32,415.51 S/32,415.51 2.18% 01 S/32,415.51 S/32,415.51 2.18% EQUILIBRIO


MES 2 02 S/336,745.00 S/369,160.51 24.83% 02 S/208,208.88 S/240,624.39 16.18% ATRASADO
MES 3 03 S/1,117,736.94 S/1,486,897.45 100.00% -

TOTAL 369,160.51 No Incluye IGV. 240,624.39 No Incluye IGV.


CRONOGRAMA VALORIZADO REPROGRAMADO ACELERADO

SERVICIO : " MANTENIMIENTO PERIODICO DE LAS VIAS VECINALES DE LA PROVINCIA DE CHINCHA - ICA - ITEM II - TRAMOS EMP. IC - 100 (CHAVIN) - SAN FLORIAN - SAN JUAN DE LUYO - HUIRPINA; DISTRITO DE CHAVIN - CHINCHA - ICA "
CLIENTE : MUNICIPALIDAD PROVINCIAL DE CHINCHA
CONTRATISTA : CONSORCIO SAN MARTIN DE PORRES
DURACION : 94 DIAS CALENDARIO

MESES
Unidad de MES 1 MES 2 MES 3
Item Actividad Meta Precio (S/.) Parcial (S/.)
Actividad del 29 de Set. al 31 de Oct. del 01 al 30 de Nov. del 01 al 31 de Dic.
metrado costo % metrado costo % metrado costo %
MANTENIMIENTO PERIODICO
01 OBRAS PRELIMINARES
01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS GLB 1.00 16,892.45 16,892.45 0.40 6,756.98 40.00% - - 0.00% 0.60 10,135.47 60.00%
01.02 TRAZO Y REPLANTEO KM 31.00 916.73 28,418.63 3.50 3,208.56 11.29% 20.15 18,472.11 65.00% 7.35 6,737.97 23.71%
02 PAVIMENTOS -
02.01 CAPA NIVELANTE E=5 CM M3 4,129.75 19.38 80,034.56 - - 0.00% - - 0.00% 4,129.75 80,034.56 100.00%
02.02 MATERIAL GRANULAR DE CANTERA PARA ESTABILIZADO E=15 CM M3 12,389.25 34.75 430,526.44 185.54 6,447.52 1.50% 941.58 32,720.01 7.60% 11,262.13 391,358.91 90.90%
03 TRANSPORTE
03.01 TRANSPORTE DE MATERIAL GRANULAR HASTA 1 KM M3K 19,822.80 7.75 153,626.70 - - 0.00% 8,920.26 69,132.02 45.00% 10,902.54 84,494.69 55.00%
03.02 TRANSPORTE DE MATERIAL GRANULAR MAYOR A 1 KM M3K 178,405.20 1.73 308,641.00 - - 0.00% 89,202.60 154,320.50 50.00% 89,202.60 154,320.50 50.00%
03.03 TRANSPORTE DE MATERIAL EXCEDENTE HASTA 1 KM M3K 1,550.00 4.81 7,455.50 - - 0.00% - - 0.00% 1,550.00 7,455.50 100.00%
03.04 TRANSPORTE DE MATERIAL EXCEDENTE MAYOR A 1 KM M3K 14,570.00 2.38 34,676.60 - - 0.00% - - 0.00% 14,570.00 34,676.60 100.00%
04 OBRAS DE ARTE Y DRENAJE
04.01 RECONFORMACION DE CUNETAS ML 31,000.00 3.15 97,650.00 - - 0.00% - - 0.00% 31,000.00 97,650.00 100.00%
05 SEÑALIZACION
05.01 INSTALACION DE POSTES KILOMETRICOS UND 31.00 173.59 5,381.29 - - 0.00% - - 0.00% 31.00 5,381.29 100.00%
05.02 SEÑALES PREVENTIVAS UND 85.00 541.04 45,988.40 - - 0.00% - - 0.00% 85.00 45,988.40 100.00%
05.03 SEÑALES REGLAMENTARIAS UND 3.00 457.49 1,372.47 - - 0.00% - - 0.00% 3.00 1,372.47 100.00%
05.04 SEÑALES INFORMATIVAS UND 6.00 1,359.48 8,156.88 - - 0.00% - - 0.00% 6.00 8,156.88 100.00%
06 IMPACTO AMBIENTAL
06.01 RECUPERACION AMBIENTAL DE AREAS OCUPADAS HA 2.48 3,523.78 8,738.97 - - 0.00% - - 0.00% 2.48 8,738.97 100.00%
07 EMERGENCIA SANITARIA
07.01 EMERGENCIA SANITARIA COVID 19 GLB 1.00 32,522.69 32,522.69 0.34 11,057.71 34.00% 0.33 10,732.49 33.00% 0.33 10,732.49 33.00%
COSTO DIRECTO 1,260,082.58 27,470.77 285,377.13 947,234.70
GASTOS GENERALES 10% 126,008.26 2,747.08 28,537.71 94,723.47
UTILIDAD 8% 100,806.61 2,197.66 22,830.17 75,778.78
SUBTOTAL 1,486,897.45 32,415.51 336,745.00 1,117,736.94
IMPUESTO (IGV) 18% 267,641.54 5,834.79 60,614.10 201,192.65
TOTAL DEL PRESUPUESTO 1,754,538.99 38,250.30 397,359.10 1,318,929.59
AVANCE MENSUAL % 100.00% 2.18% 22.65% 75.17%
AVANCE ACUMULADO % 100.00% 2.18% 24.83% 100.00%
AVANCE DE OBRA PROGRAMADO VS EJECUTADO – CURVA S
DEL 01 AL 30 DE NOVIEMBRE DEL 2020
Entidad: MUNICIPALIDAD PROVINCIAL DE CHINCHA Presupuesto de Contrato : S/. 2,642,378.00 (Inc. I.G.V.)
Proceso: PES N° 001-2020-MPCH-PRIMERA CONVOCATORIA Presupuesto Mant. Periodico : S/. 1,754,538.99 (Inc. I.G.V.)
MANTENIMIENTO PERIODICO Y RUTINARIO DE LAS VIAS VECINALES
DE LA PROVINCIA DE CHINCHA - ICA - ITEM II – TRAMOS EMP. IC-
Obra: Presupuesto Mant. Periodico : S/. 1,486,897.45 (Inc. I.G.V.)
100 (CHAVIN) - SAN FLORIAN - SAN JUAN DE LUYO – HUIRPINA,
DISTRITO DE CHAVIN – CHINCHA – ICA”.
Contratista: CONSORCIO SAN MARTIN DE PORRES Plazo de Ejecución : 485 días calendario
Residente: ING. IVAN ALEXANDER MONROE ESPINOZA Fecha de Inicio de Obra : 29/09/2020
Inspector: ING. FLOR ANICAMA MUÑANTE Fecha de Termino de Obra : 27/01/2022

GRÁFICO DEL AVANCE FÍSICO PROGRAMADO VS. AVANCE FÍSICO EJECUTADO

100%

90% 100.00%
(%)

80%
AVANCE MENSUAL ACUMULADO

70%

60%

50%

40%

30%
PROGRAMADO
24.83%
20% EJECUTADO
2.18%
10%

2.18% 16.18%
0%
MES 1 MES 2 MES 3
PLAZO DE EJECUCIÓN (Meses)

PROGRAMADO (Sin. IGV) (*) EJECUTADO (Sin. IGV)

MES PORCENTAJE PORCENTAJE


VALORIZACIÓN Nº AVANCE MENSUAL AVANCE ACUMULADO VALORIZACIÓN Nº AVANCE MENSUAL AVANCE ACUMULADO
ACUMULADO ACUMULADO

MES 1 01 S/32,415.51 S/32,415.51 2.18% 01 S/32,415.51 S/32,415.51 2.18%


MES 2 02 S/336,745.00 S/369,160.51 24.83% 02 S/208,208.88 S/240,624.39 16.18%
MES 3 03 S/1,117,736.94 S/1,486,897.45 100.00% -

TOTAL 1,486,897.45 No Incluye IGV. 240,624.39 No Incluye IGV.