Está en la página 1de 40

RESUMEN DE VALORIZACIONES TRAMITADAS

“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO –
OBRA: RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS –
HUARI – ANCASH”

CLIENTE: MUNICIPALIDAD DISTRITAL DE SAN MARCOS

LUGAR: C.P MOSNA - SAN MARCOS - HUARI - ANCASH

EMPRESA
CONSORCIO SAN JUAN
EJECUTORA.
RESIDENTE: ING. Wilson Leyva Vasquez
SUPERVISOR: ING. BILLY RONALD MEJIA GARCIA Periodo: 01 al 30 jun 2021

GARANTIA POR
MONTO LIQUIDO A MONTO A
VALORIZACIÓN FIEL VALORIZACIÓN AVANCE
DESCRIPCIÓN IGV (18%) PAGAR AL FACTURAR POR EL AVANCE FÍSICO
BRUTA S/. CUMPLIMIENTO NETA S/. PROGRAMADO
CONTRATISTA S/. CONTRATISTA S/.
10% SIN IGV

VALORIZACIÓN N°01 410,304.05 0.00 410,304.05 73,854.73 484,158.78 484,158.78 100.00% 100.00%

TOTAL VALORIZADO 410,304.05 0.00 410,304.05 73,854.73 484,158.78 484,158.78 100.00%


RESUMEN DE VALORIZACION N° 01 DE ADICIONAL DE OBRA N° 02
“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC
Obra:
– MOSNA CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”

Ubicación MUNICIPALIDAD DISTRITAL DE SAN MARCOS


Contratista: CONSORCIO SAN JUAN
Residente: ING. WILSON LEYVA VASQUEZ
Supervisor : ING. BILLY RONALD MEJIA GARCIA
Periodo: 01 al 30 junio 2021

Presupuesto de Obra (S/.) S/. 484,158.78 C/IGV

ACUMULADO
ACTUAL AVANCE ACUMULADO SALDO POR EJECUTAR
MONTO ANTERIOR
ESPECIALIDAD
CONTRATO
S/. S/. % S/. % S/. %

VAL N° 01 347,715.30 347,715.30

COSTO DIRECTO 347,715.30 347,715.30 100.00% 347,715.30 100.00% - 0.00%

GASTOS GENERALES (8%) 27,817.22 27,817.22 27,817.22 -

UTILIDAD (10%) 34,771.53 34,771.53 34,771.53 -

SUBTOTAL 410,304.05 410,304.05 100.00% 410,304.05 100.00% - 0.00%

IGV (18%) 73,854.73 73,854.73 73,854.73 -

TOTAL 484,158.78 484,158.78 100.00% 484,158.76 100.00% - 0.00%


RESUMEN DE VALORIZACIÓN N° 01 DE ADICIONAL DE OBRA Nº 02

Obra:
“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA
CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC –
MOSNA CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN
MARCOS – HUARI – ANCASH”

Propietario MUNICIPALIDAD DISTRITAL DE SAN MARCOS


Contratista CONSORCIO SAN JUAN
Residente ING. WILSON LEYVA VASQUEZ
Supervisor ING. BILLY RONALD MEJIA GARCIA
Fecha JUNIO DEL 2021

Monto Contrato 484,158.78 C/IGV


410,304.05 S/IGV

Periodo: 01 al 30 jun 2021

MONTO VALORIZACION VALORIZACION VALORIZACION


ITEM DESCRIPCION
CONTRATADO ANTERIOR ACTUAL ACUMULADA

A VALORIZACION CONTRACTUAL (V)


MONTO FORMULA 410,304.05 410,304.05 410,304.05
TOTAL CONTRACTUAL (SIN IGV) 410,304.05 0.00 410,304.05 410,304.05

PORCENTAJE DE AVANCE DE OBRA A LA


FECHA 0.00% 100.00% 100.00%

B REAJUSTES 0.00 0.00 0.00

C DEDUCCIONES 0.00 0.00 0.00

D VALORIZACION BRUTA (VB = V + S - D) 0.00 410,304.05 410,304.05

E AMORTIZACIONES (A)
AMORTIZACION ADELANTO EFECTIVO 0.00 0.00 0.00
AMORTIZACION DE MATERIALES 0.00 0.00 0.00
TOTAL AMORTIZACIONES 0.00 0.00 0.00

F VALORIZACION NETA (VN = VB - A) 0.00 410,304.05 410,304.05


MULTA POR ATRASO DE OBRA (M) 0.00 0.00 0.00
MONTOS A PAGAR AL CONTRATISTA
REINTEGRO POR PAGO EN EXCESO DE
ADELANTO DE MATERIALES
EN EFECTIVO ( VN - M ) 0.00 410,304.05 410,304.05
EN I.G.V.( VN * 0.18 ) 0.00 73,854.73 73,854.73
MONTO TOTAL CON I.G.V. 0.00 484,158.78 484,158.78

TOTAL COMPROMISO 0.00 484,158.78 484,158.78


VALORIZACION N° 01 DEL ADICIONAL DE OBRA N° 02

“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI –
OBRA:
ANCASH”

CLIENTE: MUNICIPALIDAD DISTRITAL DE SAN MARCOS

LUGAR: C.P MOSNA - SAN MARCOS - HUARI - ANCASH


EMPRESA
CONSORCIO SAN JUAN
EJECUTORA.

RESIDENTE: ING. WILSON LEYVA VASQUEZ

SUPERVISOR: ING. BILLY RONALD MEJIA GARCIA

PERIODO: 01 al 30 junio 2021

METRADO AVANCE ACTUAL AVANCE ACUMULADO SALDO


ITEM DESCRIPCION UND PRECIO S/. PARCIAL S/.
BASE METRADO VALORIZ. METRADO VALORIZ. % METRADO VALORIZ. %

PARTIDAS DE LA OBRA PRINCIPAL


04 MOVIMIENTO DE TIERRAS 36,864.55 36,864.55 36,864.55 0.00

04.01 CORTE EN TERRENO CONGLOMERADO CON MAQUINARIA m3 270.20 10.98 2,966.80 270.20 2,966.80 270.20 2,966.80 100.00% 0.00 0.00 0.00%

04.03 CORTE ROCA FIJA CON MAQUINARIA m3 513.00 44.64 22,900.32 513.00 22,900.32 513.00 22,900.32 100.00% 0.00 0.00 0.00%

04.07 RELLENO CON MATERIAL PROPIO C/EQUIPO m3 206.97 8.83 1,827.55 206.97 1,827.55 206.97 1,827.55 100.00% 0.00 0.00 0.00%

04.10 ELIMINACION DE MATERIAL EXCEDENTE A MAS DE 5 KM m3 666.90 13.75 9,169.88 666.90 9,169.88 666.90 9,169.88 100.00% 0.00 0.00 0.00%

07 OBRAS COMPLEMENTARIAS - 278,487.69 278,487.69 278,487.69 0.00


07.01 MUROS DE SOSTENIMIENTO DE PIEDRA CON CONCRETO (220 ML) - 166,711.98 166,711.98 166,711.98 0.00

07.01.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 495.92 47.11 23,362.79 495.92 23,362.79 495.92 23,362.79 100.00% 0.00 0.00 0.00%
07.01.02 NIVELACION Y REFINE PARA ESTRUCTURA m2 340.57 8.81 3,000.42 340.57 3,000.42 340.57 3,000.42 100.00% 0.00 0.00 0.00%

07.01.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 475.83 49.71 23,653.51 475.83 23,653.51 475.83 23,653.51 100.00% 0.00 0.00 0.00%
07.01.04 CONCRETO CICLOPEO C-175 + 70% PG m3 381.13 203.08 77,399.88 381.13 77,399.88 381.13 77,399.88 100.00% 0.00 0.00 0.00%

07.01.05 RELLENO COMPACTADO CON MATERIAL PROPIO EN ESTRUCTURAS m3 624.43 62.93 39,295.38 624.43 39,295.38 624.43 39,295.38 100.00% 0.00 0.00 0.00%
07.02 MUROS DE CONTENCION (180 ML) - 111,775.71 111,775.71 111,775.70 0.00

07.02.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 216.22 47.11 10,186.12 216.22 10,186.12 216.22 10,186.12 100.00% 0.00 0.00 0.00%

07.02.02 NIVELACION Y REFINE PARA ESTRUCTURA m2 112.22 8.81 988.66 112.22 988.66 112.22 988.66 100.00% 0.00 0.00 0.00%

07.02.03 ELIMINACION MATERIAL EXCEDENTE m3 68.20 30.68 2,092.38 68.20 2,092.38 68.20 2,092.38 100.00% 0.00 0.00 0.00%

07.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO EN ESTRUCTURAS m3 165.86 62.93 10,437.57 165.86 10,437.57 165.86 10,437.57 100.00% 0.00 0.00 0.00%

07.02.05 SOLADOS CONCRETO DE 4" m2 120.11 17.14 2,058.69 120.11 2,058.69 120.11 2,058.69 100.00% 0.00 0.00 0.00%

07.02.06 ACERO DE REFUERZO, EN MURO CONTENCION kg 3,948.74 5.14 20,296.52 3,948.74 20,296.52 3,948.74 20,296.52 100.00% 0.00 0.00 0.00%

07.02.07 ENCOFRADO Y DESENCOFRADO DE MURO DE CONTENCIÓN m2 104.87 49.71 5,213.09 104.87 5,213.09 104.87 5,213.09 100.00% 0.00 0.00 0.00%

07.02.08 CONCRETO C-210 EN MURO DE CONTENCIÓN m3 120.80 500.85 60,502.68 120.80 60,502.68 120.80 60,502.68 100.00% 0.00 0.00 0.00%

PARTIDAS DEL ADICIONAL CON DEDUCTIVO VINCULANTE

7.03 GAVIONES 32,363.06 32,363.06 32,363.06 0.00

7.03.03 RELLENO CON MATERIAL (AFIRMADO) m3 102.60 104.65 10,737.09 102.60 10,737.09 102.60 10,737.09 100.00% 0.00 0.00 0.00%

7.03.05 GAVION CAJA 5 X 1.0 0 X 1.00 M, MALLA 10 X 12, DIAM 3.4 (ZN - 5AL - MM + PVC) m3 109.20 198.04 21,625.97 109.20 21,625.97 109.20 21,625.97 100.00% 0.00 0.00 0.00%

COSTO DIRECTO 347,715.30 347,715.30 347,715.30 0.00

G.G (8%) 27,817.22 27,817.22 27,817.22 -


UTILIDAD (10%) 34,771.53 34,771.53 34,771.53 -

SUBTOTAL 410,304.05 410,304.05 410,304.05 -

IMPUESTO (IGV) 18% 73,854.73 73,854.73 73,854.73 -

PRESUPUESTO TOTAL 484,158.78 484,158.78 484,158.78 -

PORCENTAJE DE AVANCE 100.00% 100.00% 100.00% 0.00%


METRADO MENSUAL DE AVANCE DE OBRA

“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC –
OBRA:
MOSNA CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”

CLIENTE: MUNICIPALIDAD DISTRITAL DE SAN MARCOS

LUGAR: C.P MOSNA - SAN MARCOS - HUARI - ANCASH

EMPRESA
CONSORCIO SAN JUAN
EJECUTORA:

RESIDENTE: ING. WILSON LEYVA VASQUEZ Periodo: 01 al 30 junio 2021

SUPERVISOR: ING. BILLY RONALD MEJIA GARCIA

METRADO
METRADO
ITEM DESCRIPCION UND ADICIONAL Jun-21 SALDO
ACUMULADO
DEDUCTIVO 02

PARTIDAS DE LA OBRA PRINCIPAL

04 MOVIMIENTO DE TIERRAS

04.01 CORTE EN TERRENO CONGLOMERADO CON MAQUINARIA m3 270.20 270.20 270.20 0.00
04.03 CORTE ROCA FIJA CON MAQUINARIA m3 513.00 513.00 513.00 0.00
04.07 RELLENO CON MATERIAL PROPIO C/EQUIPO m3 206.97 206.97 206.97 0.00
04.10 ELIMINACION DE MATERIAL EXCEDENTE A MAS DE 5 KM m3 666.90 666.90 666.90 0.00
07 OBRAS COMPLEMENTARIAS

07.01 MUROS DE SOSTENIMIENTO DE PIEDRA CON CONCRETO (220 ML)

07.01.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 495.92 495.92 495.92 0.00


07.01.02 NIVELACION Y REFINE PARA ESTRUCTURA m2 340.57 340.57 340.57 0.00
07.01.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 475.83 475.83 475.83 0.00
07.01.04 CONCRETO CICLOPEO C-175 + 70% PG m3 381.13 381.13 381.13 0.00
07.01.05 RELLENO COMPACTADO CON MATERIAL PROPIO EN ESTRUCTURAS m3 624.43 624.43 624.43 0.00
07.02 MUROS DE CONTENCION (180 ML)

07.02.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 216.22 216.22 216.22 0.00


07.02.02 NIVELACION Y REFINE PARA ESTRUCTURA m2 112.22 112.22 112.22 0.00
07.02.03 ELIMINACION MATERIAL EXCEDENTE m3 68.20 68.20 68.20 0.00
07.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO EN ESTRUCTURAS m3 165.86 165.86 165.86 0.00
07.02.05 SOLADOS CONCRETO DE 4" m2 120.11 120.11 120.11 0.00
07.02.06 ACERO DE REFUERZO, EN MURO CONTENCION kg 3,948.74 3,948.74 3,948.74 0.00
07.02.07 ENCOFRADO Y DESENCOFRADO DE MURO DE CONTENCIÓN m2 104.87 104.87 104.87 0.00
07.02.08 CONCRETO C-210 EN MURO DE CONTENCIÓN m3 120.80 120.80 120.80 0.00
PARTIDAS DEL ADICIONAL CON DEDUCTIVO VINCULANTE

7.03 GAVIONES

7.03.03 RELLENO CON MATERIAL (AFIRMADO) m3 102.60 102.60 102.60 0.00


7.03.05 GAVION CAJA 5 X 1.0 0 X 1.00 M, MALLA 10 X 12, DIAM 3.4 (ZN - 5AL - MM + PVC) m3 109.20 109.20 109.20 0.00
SUSTENTO DE METRADOS VALORIZACION N° 01 DE ADICIONAL DE OBRA N° 02

“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL
OBRA
CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”

ENTIDAD MUNICIPALIDAD DISTRITAL DE SAN MARCOS RESIDENCIA ING. WILSON LEYVA VASQUEZ
UBICACIÓN CENTRO POBLADO SANTA CRUZ DE MOSNA SUPERVISIÓN: CONSORCIO BMG
CONTRATISTA CONSORCIO SAN JUAN MES: Periodo: 01 al 30 junio 2021

Metrado AVANCE ACTUAL


ITEM DESCRIPCION PARTIDA Und. Adicional ACUMULADO
N° Largo Ancho Alto Factor Producto Parcial
N°02
04 MOVIMIENTO DE TIERRAS
04.01 CORTE EN TERRENO CONGLOMERADO CON MAQUINARIA m3 270.20 270.20 270.20
Tramo acceso al estadio 0+140 a 0+300 270.20 270.20
04.03 CORTE ROCA FIJA CON MAQUINARIA m3 513.00 513.00 513.00
0+150 - 0+162 12.00 3.60 2.00 86.40
0+162 - 0+180 18.00 3.60 2.00 129.60
0+180 - 0+205 25.00 2.75 1.80 123.75
0+205 - 0+240 35.00 2.75 1.80 173.25
04.07 RELLENO CON MATERIAL PROPIO C/EQUIPO m3 206.97 206.97 206.97
159.21 1.30 206.97
04.10 ELIMINACION DE MATERIAL EXCEDENTE A MAS DE 5 KM m3 666.90 666.90 666.90
AREA
0+00 1.760 20.45 36.00
0+020 1.840 19.62 36.10
0+040 1.770 20.17 35.70
0+060 1.800 20.28 36.50
0+080 1.850 20.54 38.00
0+100 1.950 19.58 38.18
0+120 1.868 21.78 40.68
0+140 2.200 22.64 49.80
0+160 2.780 18.83 52.35
0+180 2.455 18.89 46.37
0+200 2.182 20.72 45.22
0+220 2.340 21.24 49.70
0+240 2.630 20.46 53.80
0+260 2.750 17.64 48.50
0+280 2.100 19.29 40.50
0+300 1.950 10.00 19.50

07 OBRAS COMPLEMENTARIAS
07.01 MUROS DE SOSTENIMIENTO DE PIEDRA CON CONCRETO (220 ML) 0.00
07.01.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 495.92 495.92 495.92
muro ciclopeo 23 6.00 3.00 0.40 7.20
6.00 1.70 4.00 40.80
muro ciclopeo 24 6.00 3.00 0.40 7.20
6.00 1.50 3.60 32.40
muro ciclopeo 25 5.90 3.00 0.40 7.08
5.90 1.70 3.90 39.12
muro ciclopeo 26 5.95 3.00 0.40 7.14
5.95 1.70 3.90 39.45
muro ciclopeo 27 5.90 3.00 0.40 7.08
5.90 1.70 3.90 39.12
muro ciclopeo 28 6.05 3.00 0.40 7.26
5.90 1.80 3.90 41.42
muro ciclopeo 29 6.00 3.00 0.40 7.20
6.00 1.60 3.50 33.60
muro ciclopeo 30 5.95 3.00 0.40 7.14
5.95 1.60 3.60 34.27
muro ciclopeo 39 Muñoz 8.50 3.00 0.60 15.30
8.50 1.60 3.00 40.80
muro ciclopeo 1A 6.00 1.10 1.50 9.90
6.00 1.10 1.50 9.90
muro ciclopeo 2B 6.95 1.10 1.50 11.47
6.95 1.10 1.50 11.47
muro ciclopeo 3C 6.00 1.10 1.50 9.90
6.00 1.10 1.50 9.90
muro ciclopeo 4D 6.00 1.10 1.50 9.90
SUSTENTO DE METRADOS VALORIZACION N° 01 DE ADICIONAL DE OBRA N° 02

“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL
OBRA
CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”

ENTIDAD MUNICIPALIDAD DISTRITAL DE SAN MARCOS RESIDENCIA ING. WILSON LEYVA VASQUEZ
UBICACIÓN CENTRO POBLADO SANTA CRUZ DE MOSNA SUPERVISIÓN: CONSORCIO BMG
CONTRATISTA CONSORCIO SAN JUAN MES: Periodo: 01 al 30 junio 2021

Metrado AVANCE ACTUAL


ITEM DESCRIPCION PARTIDA Und. Adicional ACUMULADO
N° Largo Ancho Alto Factor Producto Parcial
N°02

6.00 1.10 1.50 9.90


07.01.02 NIVELACION Y REFINE PARA ESTRUCTURA m2 340.57 340.57 340.57
muro ciclopeo 04 7.00 3.00 21.00
muro ciclopeo 05 5.80 3.00 17.40
muro ciclopeo 18 6.10 3.00 18.30
muro ciclopeo 19 3.00 3.00 9.00
muro ciclopeo 20 2.70 3.00 8.10
muro ciclopeo 21 6.10 3.00 18.30
muro ciclopeo 22 6.00 3.00 18.00
muro ciclopeo 23 6.00 3.00 18.00
muro ciclopeo 24 6.00 3.00 18.00
muro ciclopeo 25 5.90 3.00 17.70
muro ciclopeo 26 5.95 3.00 17.85
muro ciclopeo 27 5.90 3.00 17.70
muro ciclopeo 28 6.05 3.00 18.15
muro ciclopeo 29 6.00 3.00 18.00
muro ciclopeo 30 5.95 3.00 17.85
SUSTENTO DE METRADOS VALORIZACION N° 01 DE ADICIONAL DE OBRA N° 02

“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL
OBRA
CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”

ENTIDAD MUNICIPALIDAD DISTRITAL DE SAN MARCOS RESIDENCIA ING. WILSON LEYVA VASQUEZ
UBICACIÓN CENTRO POBLADO SANTA CRUZ DE MOSNA SUPERVISIÓN: CONSORCIO BMG
CONTRATISTA CONSORCIO SAN JUAN MES: Periodo: 01 al 30 junio 2021

Metrado AVANCE ACTUAL


ITEM DESCRIPCION PARTIDA Und. Adicional ACUMULADO
N° Largo Ancho Alto Factor Producto Parcial
N°02

muro ciclopeo 35 6.50 2.50 16.25


muro ciclopeo 36 3.00 2.50 7.50
muro ciclopeo 37 3.40 2.50 8.50
muro ciclopeo 38 6.30 2.50 15.75
muro ciclopeo 39 Muñoz 8.50 3.00 25.50
muro ciclopeo 1A 6.00 0.55 3.30
muro ciclopeo 2B 6.95 0.55 3.82
muro ciclopeo 3C 6.00 0.55 3.30
muro ciclopeo 4D 6.00 0.55 3.30
07.01.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 475.83 475.83 475.83
muro ciclopeo 04 7.00 0.60 4.20
7.00 4.00 28.00
muro ciclopeo 05 5.80 0.60 3.48
5.80 4.00 23.20
muro ciclopeo 18 6.10 0.60 3.66
6.10 3.70 22.57
muro ciclopeo 19 3.00 0.60 1.80
3.00 4.50 13.50
muro ciclopeo 20 2.70 0.60 1.62
2.70 3.65 9.86
muro ciclopeo 21 6.10 0.60 3.66
6.10 4.20 25.62
muro ciclopeo 22 6.00 0.60 3.60
6.00 4.50 27.00
muro ciclopeo 23 6.00 0.60 3.60
6.00 4.30 25.80
muro ciclopeo 24 6.00 0.60 3.60
6.00 3.80 22.80
muro ciclopeo 25 5.90 0.60 3.54
5.90 4.00 23.60
muro ciclopeo 26 5.95 0.60 3.57
5.95 4.00 23.80
muro ciclopeo 27 5.90 0.60 3.54
5.90 4.00 23.60
muro ciclopeo 28 6.05 0.60 3.63
5.90 4.10 24.19
muro ciclopeo 29 6.00 0.60 3.60
6.00 3.60 21.60
muro ciclopeo 30 5.95 0.60 3.57
5.95 3.50 20.83
muro ciclopeo 39 Muñoz 8.50 0.60 5.10
8.50 3.00 25.50
muro ciclopeo 1A 6.00 1.50 9.00
6.00 1.00 6.00
muro ciclopeo 2B 6.95 2.00 13.90
6.95 0.30 2.09
muro ciclopeo 3C 6.00 2.00 12.00
6.00 0.30 1.80
muro ciclopeo 4D 6.00 2.00 12.00
6.00 0.30 1.80
SUSTENTO DE METRADOS VALORIZACION N° 01 DE ADICIONAL DE OBRA N° 02

“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL
OBRA
CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”

ENTIDAD MUNICIPALIDAD DISTRITAL DE SAN MARCOS RESIDENCIA ING. WILSON LEYVA VASQUEZ
UBICACIÓN CENTRO POBLADO SANTA CRUZ DE MOSNA SUPERVISIÓN: CONSORCIO BMG
CONTRATISTA CONSORCIO SAN JUAN MES: Periodo: 01 al 30 junio 2021

Metrado AVANCE ACTUAL


ITEM DESCRIPCION PARTIDA Und. Adicional ACUMULADO
N° Largo Ancho Alto Factor Producto Parcial
N°02

07.01.04 CONCRETO CICLOPEO C-175 + 70% PG m3 381.13 381.13 381.13


muro ciclopeo 04 7.00 3.00 0.60 12.60
7.00 4.00 0.55 15.40
muro ciclopeo 05 5.80 3.00 0.60 10.44
5.80 4.00 0.55 12.76
muro ciclopeo 18 6.10 3.00 0.60 10.98
6.10 3.70 0.55 12.41
muro ciclopeo 19 3.00 3.00 0.60 5.40
3.00 4.50 0.55 7.43
muro ciclopeo 20 2.70 3.00 0.60 4.86
2.70 3.65 0.55 5.42
muro ciclopeo 21 6.10 3.00 0.60 10.98
6.10 4.20 0.55 14.09
muro ciclopeo 22 6.00 3.00 0.60 10.80
6.00 4.50 0.55 14.85
muro ciclopeo 23 6.00 3.00 0.60 10.80
6.00 4.30 0.55 14.19
muro ciclopeo 24 6.00 3.00 0.60 10.80
6.00 3.80 0.55 12.54
muro ciclopeo 25 5.90 3.00 0.60 10.62
5.90 4.00 0.55 12.98
muro ciclopeo 26 5.95 3.00 0.60 10.71
5.95 4.00 0.55 13.09
muro ciclopeo 27 5.90 3.00 0.60 10.62
5.90 4.00 0.55 12.98
muro ciclopeo 28 6.05 3.00 0.60 10.89
5.90 4.10 0.55 13.30
muro ciclopeo 29 6.00 3.00 0.60 10.80
6.00 3.60 0.55 11.88
muro ciclopeo 30 5.95 3.00 0.60 10.71
5.95 3.50 0.55 11.45
muro ciclopeo 39 Muñoz 8.50 3.00 0.60 15.30
8.50 3.00 0.55 14.03
muro ciclopeo 1A 6.00 1.60 0.20 1.92
6.00 0.30 0.55 0.99
muro ciclopeo 2B 6.95 1.15 0.50 4.00
6.95 0.30 0.45 0.94
muro ciclopeo 3C 6.00 1.60 0.20 1.92
6.00 0.30 0.55 0.99
muro ciclopeo 4D 6.00 1.15 0.50 3.45
6.00 0.30 0.45 0.81
07.01.05 RELLENO COMPACTADO CON MATERIAL PROPIO EN ESTRUCTURAS m3 624.43 604.03 604.03
muro ciclopeo 04 7.00 1.70 3.35 39.87
muro ciclopeo 05 5.80 1.70 3.35 33.03
muro ciclopeo 18 6.10 1.70 2.65 27.48
muro ciclopeo 19 3.00 1.70 3.35 17.09
muro ciclopeo 20 2.70 1.70 2.90 13.31
muro ciclopeo 21 6.10 1.70 3.35 34.74
muro ciclopeo 22 6.00 1.70 3.35 34.17
muro ciclopeo 23 6.00 1.80 3.90 42.12
muro ciclopeo 24 6.00 1.70 3.45 35.19
muro ciclopeo 25 5.90 1.70 3.60 36.11
muro ciclopeo 26 5.95 1.70 3.60 36.41
SUSTENTO DE METRADOS VALORIZACION N° 01 DE ADICIONAL DE OBRA N° 02

“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL
OBRA
CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”

ENTIDAD MUNICIPALIDAD DISTRITAL DE SAN MARCOS RESIDENCIA ING. WILSON LEYVA VASQUEZ
UBICACIÓN CENTRO POBLADO SANTA CRUZ DE MOSNA SUPERVISIÓN: CONSORCIO BMG
CONTRATISTA CONSORCIO SAN JUAN MES: Periodo: 01 al 30 junio 2021

Metrado AVANCE ACTUAL


ITEM DESCRIPCION PARTIDA Und. Adicional ACUMULADO
N° Largo Ancho Alto Factor Producto Parcial
N°02

muro ciclopeo 27 5.90 1.70 3.60 36.11


muro ciclopeo 28 5.90 1.80 3.70 39.29
muro ciclopeo 29 6.00 1.70 3.35 34.17
muro ciclopeo 30 5.95 1.70 3.35 33.89
muro ciclopeo 39 Muñoz 8.50 2.30 3.00 58.65
muro ciclopeo 1A 6.00 1.50 1.40 12.60
muro ciclopeo 2B 6.95 1.50 1.40 14.60
muro ciclopeo 3C 6.00 1.50 1.40 12.60
muro ciclopeo 4D 6.00 1.50 1.40 12.60
07.02 MUROS DE CONTENCION (180 ML)
07.02.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 216.22 216.22 216.2192
Pantalla- tramo 1 5.32 1.70 2.10 18.99
Zapata-muro1 5.32 2.80 0.55 8.19
Pantalla- tramo 5 3.00 1.70 1.95 9.95
Zapata-muro5 3.92 3.00 0.55 6.47
Pantalla- tramo 6 6.00 1.70 2.15 21.93
Zapata-muro6 3.92 3.00 0.55 6.47
Pantalla- tramo 7 3.00 1.70 2.05 10.46
Zapata-muro7 3.92 3.00 0.55 6.47
Pantalla- tramo 8 3.00 1.70 1.90 9.69
Zapata-muro8 3.92 3.00 0.55 6.47
Pantalla- tramo 41 6.10 2.50 3.90 59.48
Zapata-muro41 6.10 3.35 0.60 12.26
Pantalla- tramo 43 3.35 2.50 3.90 32.66
Zapata-muro43 3.35 3.35 0.60 6.73
07.02.02 NIVELACION Y REFINE PARA ESTRUCTURA m2 112.22 112.22 112.22
Pantalla- tramo 1 5.32 2.80 14.90
Pantalla- tramo 5 3.00 2.80 8.40
Pantalla- tramo 6 6.00 2.80 16.80
Pantalla- tramo 7 3.00 2.80 8.40
Pantalla- tramo 8 3.00 2.80 8.40
Pantalla- tramo 9 5.40 2.80 15.12
Pantalla- tramo 41 6.00 3.35 20.10
Pantalla- tramo 43 6.00 3.35 20.10
07.02.03 ELIMINACION MATERIAL EXCEDENTE m3 68.20 68.20 68.20
68.20 68.20
07.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO EN ESTRUCTURAS m3 165.86 165.86 165.86
Pantalla- tramo 1 5.32 1.70 1.80 16.28
Pantalla- tramo 5 3.00 1.70 1.65 8.42
Pantalla- tramo 6 6.00 1.70 1.90 19.38
Pantalla- tramo 7 3.00 1.70 1.80 9.18
Pantalla- tramo 8 3.00 1.70 1.60 8.16
Pantalla- tramo 9 5.40 1.70 1.70 15.61
Pantalla- tramo 41 6.00 2.50 3.80 57.00
Pantalla- tramo 43 3.35 2.50 3.80 31.83
07.02.05 SOLADOS CONCRETO DE 4" m2 120.11 120.11 120.11
tramo 1 5.32 3.00 15.96
tramo 4 3.92 3.00 11.76
tramo 5 3.00 3.00 9.00
tramo 6 6.00 3.00 18.00
tramo 7 3.00 3.00 9.00
tramo 8 3.00 3.00 9.00
tramo 9 5.40 3.00 16.20
tramo 41 6.10 3.30 20.13
tramo 43 3.35 3.30 11.06
SUSTENTO DE METRADOS VALORIZACION N° 01 DE ADICIONAL DE OBRA N° 02

“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL
OBRA
CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”

ENTIDAD MUNICIPALIDAD DISTRITAL DE SAN MARCOS RESIDENCIA ING. WILSON LEYVA VASQUEZ
UBICACIÓN CENTRO POBLADO SANTA CRUZ DE MOSNA SUPERVISIÓN: CONSORCIO BMG
CONTRATISTA CONSORCIO SAN JUAN MES: Periodo: 01 al 30 junio 2021

Metrado AVANCE ACTUAL


ITEM DESCRIPCION PARTIDA Und. Adicional ACUMULADO
N° Largo Ancho Alto Factor Producto Parcial
N°02

07.02.06 ACERO DE REFUERZO, EN MURO CONTENCION kg 3,948.74


3,948.74 3,948.74
ZAPATA
Acero: Longitudinal Ø 1/2"
Paño 7 24 3.00 0.99 71.28
Paño 8 24 3.00 0.99 71.28
Paño 9 24 5.40 0.99 128.30
Paño 41 24 3.00 0.99 71.28
Acero: Transversal Ø 5/8"
Paño 7 18 6.50 1.55 181.35
Paño 8 24 6.50 1.55 241.80
Paño 9 24 6.50 1.55 241.80
Paño 41 36 7.50 1.55 418.50
Paño 42 18 7.50 1.55 209.25
Paño 43 24 3.00 1.55 111.60
PANTALLA
Paño 5 nº - L= 3.00
Vertical Ø 5/8" 1 14.000 3.47 1.55 75.25
Vertical Ø 5/8" 1 14.000 2.75 1.55 59.68
Horizontal Ø 5/8" 1 9.000 3.00 1.55 41.85
Horizontal Ø 1/2" 1 18.000 3.00 0.99 53.46
Paño 7 nº - L= 3.00
Vertical Ø 5/8" 1 14.000 3.50 1.55 75.95
Vertical Ø 5/8" 1 14.000 2.75 1.55 59.68
Horizontal Ø 5/8" 1 9.000 3.00 1.55 41.85
Horizontal Ø 1/2" 1 18.000 3.00 0.99 53.46
Paño 8 nº - L= 3.00
Vertical Ø 5/8" 1 14.000 3.35 1.55 72.70
Vertical Ø 5/8" 1 14.000 2.75 1.55 59.68
Horizontal Ø 5/8" 1 9.000 3.00 1.55 41.85
Horizontal Ø 1/2" 1 18.000 3.00 0.99 53.46
Paño 9 nº - L= 5.40
Vertical Ø 5/8" 1 26.000 3.45 1.55 139.04
Vertical Ø 5/8" 1 26.000 2.75 1.55 110.83
Horizontal Ø 5/8" 1 9.000 5.40 1.55 75.33
Horizontal Ø 1/2" 1 18.000 5.40 0.99 96.23
Paño 41 nº - L= 6.10
Vertical Ø 5/8" 1 27.000 5.64 1.55 236.03
Vertical Ø 5/8" 1 27.000 3.15 1.55 131.83
Horizontal Ø 5/8" 1 9.000 6.10 1.55 85.10
Horizontal Ø 1/2" 1 28.000 6.10 0.99 169.09
Paño 43 nº - L= 3.35
Vertical Ø 5/8" 1 16.000 5.55 1.55 137.64
Vertical Ø 5/8" 1 16.000 3.15 1.55 78.12
Horizontal Ø 5/8" 1 9.000 6.10 1.55 85.10
Horizontal Ø 1/2" 1 28.000 6.10 0.99 169.09
07.02.07 ENCOFRADO Y DESENCOFRADO DE MURO DE CONTENCIÓN m2 104.87 104.87 104.87
ZAPATA
tramo 5 3.00 0.60 1.80
3.00 0.60 1.80
tramo 6 6.00 0.60 3.60
3.00 0.60 1.80
tramo 41 6.10 0.60 3.66
3.00 0.60 1.80
tramo 43 3.35 0.60 2.01
3.00 0.60 1.80
SUSTENTO DE METRADOS VALORIZACION N° 01 DE ADICIONAL DE OBRA N° 02

“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL
OBRA
CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”

ENTIDAD MUNICIPALIDAD DISTRITAL DE SAN MARCOS RESIDENCIA ING. WILSON LEYVA VASQUEZ
UBICACIÓN CENTRO POBLADO SANTA CRUZ DE MOSNA SUPERVISIÓN: CONSORCIO BMG
CONTRATISTA CONSORCIO SAN JUAN MES: Periodo: 01 al 30 junio 2021

Metrado AVANCE ACTUAL


ITEM DESCRIPCION PARTIDA Und. Adicional ACUMULADO
N° Largo Ancho Alto Factor Producto Parcial
N°02

PANTALLA
Pantalla- tramo 41 2 6.10 4.20 51.24
2 0.48 4.20 3.99
Pantalla- tramo 43 2 3.35 4.10 27.47
2 0.48 4.10 3.90
07.02.08 CONCRETO C-210 EN MURO DE CONTENCIÓN m3 120.80 120.80 120.80
ZAPATA
tramo 1 5.32 2.80 0.60 8.94
tramo 5 3.00 2.80 0.60 5.04
tramo 6 6.00 3.00 0.60 10.80
tramo 7 3.00 2.80 0.60 5.04
tramo 8 3.00 2.80 0.60 5.04
tramo 9 5.40 2.80 0.60 9.07
tramo 41 6.10 3.30 0.60 12.08
tramo 43 3.35 3.30 0.60 6.63
UÑA

35.17 0.60 0.55 11.61


PANTALLA
Pantalla- tramo 1 5.32 0.48 2.10 5.31
Pantalla- tramo 5 3.00 0.48 1.95 2.78
Pantalla- tramo 6 6.00 0.48 2.15 6.13
Pantalla- tramo 7 3.00 0.48 2.05 2.92
Pantalla- tramo 8 3.00 0.48 1.90 2.71
Pantalla- tramo 9 5.40 0.48 2.00 5.13
Pantalla- tramo 41 6.10 0.48 4.19 12.14
Pantalla- tramo 42 Altura de pantalla 3.45, se valorizó 1.65 3.00 0.45 1.80 2.43
Pantalla- tramo 43 3.35 0.48 4.10 6.52
7.03 GAVIONES
7.03.03 RELLENO CON MATERIAL (AFIRMADO) m3 102.60 102.60 102.60
57.00 0.90 2.00 102.60

7.03.05 GAVION CAJA 5 X 1.0 0 X 1.00 M, MALLA 10 X 12, DIAM 3.4 (ZN - 5AL - MM + P m3 109.20 109.20 109.20
2 54.60 1.00 1.00 109.20
SUSTENTO DE METRADOS CORRESPONDIENTE AL MES DE SETIEMBRE

OBRA “CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”
ENTIDAD MUNICIPALIDAD DISTRITAL DE SAN MARCOS
UBICACIÓN SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA
CONTRATISTA CONSORCIO SAN JUAN RESIDENCIA ING. VICENTE BARRERA BULNES SUPERVISIÓN CONSORCIO BMG

Metrado AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL


ITEM DESCRIPCION PARTIDA Und. ACUMULADO
Base N° Largo Ancho Alto Factor Producto Parcial N° Largo Ancho Alto Factor Producto Parcial
01 OBRAS PROVISIONALES
01.01 CAMPAMENTO PROVISIONAL DE LA OBRA 9x5 m glb 1.00 - - 1.00 1.00 1.00 1.00
01.02 CERCO PROVISIONAL m 250.00 - - 1.00 112.50 112.50 112.50 112.50
01.03 CARTEL DE OBRA u 1.00 - - 1.00 1.00 1.00 1.00
01.04 SERVICIO DE BAÑO PORTATIL (INODORO Y LAVATORIO) TIPO DISAL O SIMILAR mes 6.00 - - 1.00 1.00 1.00 1.00
02 SEGURIDAD Y SALUD - - - - -
02.01 ELAB, IMPLEM Y ADMINIS. DEL PLAN DE SEGURIDAD Y SALUD EN EL TRABAJO glb 1.00 - - 0.33 0.33 0.33 0.33
02.02 EQUIPOS DE PROTECCIÓN INDIVIDUAL glb 1.00 0.2 0.20 0.20 0.17 0.17 0.17 0.37
02.03 EQUIPOS DE PROTECCIÓN COLECTIVA glb 1.00 - - 0.17 0.17 0.17 0.17
02.04 SEÑALIZACIÓN TEMPORAL DE SEGURIDAD glb 1.00 - - 0.50 0.50 0.50 0.50
02.05 CAPACITACIÓN EN SEGURIDAD Y SALUD glb 1.00 - - 0.17 0.17 0.17 0.17
02.06 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SST evto 1.00 - - 0.50 0.50 0.50 0.50
03 TRABAJOS PRELIMINARES - - - - -
03.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO glb 1.00 - - 0.50 0.50 0.50 0.50
03.02 TOPOGRAFÍA Y GEOREFERENCIACIÓN EN CARRETERAS km 2.00 1 1.00 1.00 - - 1.00
03.03 TRAZO, NIVELACIÓN Y REPLANTEO EN OBRAS COMPLEMENTARIAS m2 2,300.00 - - - 450.00 450.00
Puente Shirauco 45.00 10.00 450.00 450.00
Muro de Sostenimiento
Muro de Contencion
Alcantarillas
Alcantarillado Pluvial
03.04 TRABAJOS PREVENTIVOS DE SEGURIDAD m 360.00 - - -
Tramo 0+440 a 0+800
04 MOVIMIENTO DE TIERRAS - - -
04.01 CORTE EN TERRENO CONGLOMERADO CON MAQUINARIA m3 6,445.53 - 1.00 2,950.70 2,950.70 2,950.70
04.02 CORTE EN ROCA SUELTA (PERF. Y DISPARO) CON MAQUINARIA m3 699.20 - - -
04.03 CORTE ROCA FIJA CON MAQUINARIA m3 7,565.28 - 1.00 3,359.10 3,359.10 3,359.10
04.04 PERFILADO Y COMPACTADO EN TRAMOS DE CORTE Y RELLENO m2 8,260.00 - - -
04.05 CONFORMACION DE TERRAPLENES R= 650 m3/día m3 2450.02 - - 1,850.00 1,850.00
Tramo 0+140 a 0+220 1.00 1,850.00
04.06 PERFILADO, DESQUINCHE y PEINADO DE TALUDES m2 5747.42 - - -
04.07 RELLENO CON MATERIAL PROPIO C/EQUIPO m3 3,860.14 - 1,831.40 1,831.40 1,831.40
04.08 TRASPORTE DE PIEDRA PARA ENROCADO R=240 m3/día m3 468.00 - - -
04.09 ACOMODO DE PIEDRA EN ENROCADO R=120 m3/día m3 468.00 - -
04.10 ELIMINACION DE MATERIAL EXCEDENTE A MAS DE 5 KM m3 13,253.60 - 1.00 1,590.43 1,590.43 1,590.43
04.11 MEJORAMIENTO SUPERFICIE DE RODADURA CON MATERIAL AFIRMADO m2 8,560.00 - - -
05 OBRAS DE ARTE - - -

13
SUSTENTO DE METRADOS CORRESPONDIENTE AL MES DE SETIEMBRE

OBRA “CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”
ENTIDAD MUNICIPALIDAD DISTRITAL DE SAN MARCOS
UBICACIÓN SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA
CONTRATISTA CONSORCIO SAN JUAN RESIDENCIA ING. VICENTE BARRERA BULNES SUPERVISIÓN CONSORCIO BMG

Metrado AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL


ITEM DESCRIPCION PARTIDA Und. ACUMULADO
Base N° Largo Ancho Alto Factor Producto Parcial N° Largo Ancho Alto Factor Producto Parcial
05.01 CUNETAS - - -
05.01.01 CONFORMACIÓN DE CUNETAS EN MATERIAL SIN CLASIFICAR m 1,380.00 - - -
05.01.02 CONFORMACIÓN DE CUNETAS LATERALES EN ROCA m 460.00 - - -
05.01.03 CUNETA LATERAL REVESTIDO DE CONCRETO m 300.00 - - -
05.02 ALCANTARILLA TIPO TMC (05 UNID.) - - -
05.02.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 86.03 - - -
05.02.02 NIVELACION Y REFINE PARA ESTRUCTURA m2 68.25 - - -
05.02.03 ENCOFRADO y DESENCOFRADO DEL INGRESO Y SALIDA m2 78.00 - - -
05.02.04 CONCRETO C-175 EN INGRESO Y SALIDA m3 12.86 - - -
05.02.05 REVESTIMIENTO DE CAUCES DE ALCANTARILLA m2 56.00 - - -
05.02.06 ALCANTARILLA TMC 0=24" C=16 R=12 m/día m 25.00 - - -
05.03 ALCANTANTARILLADO PLUVIAL (260 ML) - - -
05.03.01 DEMOLICION DE PAVIMENTO EXISTENTE m3 28 - - -
05.03.02 EXCAVACION EN SUELO CONGLOMERADO m3 338.00 - - -
05.03.03 REFINE, NIVELACION Y COMPACTADO FONDO DE ZANJA m2 260.00 - - -
05.03.04 SOLADO CONCRETO DE 4" m2 260.00 - - -
05.03.05 HABILITADO Y ARMADO DE ACERO Fy=4200 Kg/cm2 kg 9,862.48 - - -
05.03.06 ENCOFRADO Y DESENCOFRADO EN ALCANTARILLADO PLUVIAL m2 624 - - -
05.03.07 CONCRETO C-210 EN ALCANTARILLADO PLUVIAL m3 197.60 - - -
05.03.08 DRENAJE COLECTOR SUMIDERO DE RIELES m 16.00 - - -
05.03.09 JUNTA TRANSVERSAL CONTRACCION 1.0" a 3.00 M m 309.60 - - -
06 PUENTE DE ACERO Y CONCRETO - - -
06.01 MOVIMIENTO DE TIERRAS - - -
06.01.01 EXCAVACION NO CLASIFICADA PARA ESTRIBOS DE PUENTE m3 152.38 - 1 152.38 152.38 152.38
6.40 4.00 2.50 64.00
10.10 3.50 2.50 88.38
06.01.02 CORTE EN ROCA FIJA m3 54.60 - 1 7.00 3.00 2.60 54.60 54.60 54.60
06.01.03 RELLENO COMPACTADO CON MATERIAL PROPIO m3 148.68 - 1 5.90 3.50 7.20 148.68 148.68 148.68
06.01.04 ELIMINACION DE MATERIAL EXCEDENTE A MAS DE 5 KM m3 58.30 - 1 58.30 58.30 58.30
06.01.05 LIMPIEZA DE CAUCE DE RIO m2 900 - 1 30.00 30.00 900.00 900.00 900.00
06.02 OBRAS DE CONCRETO SIMPLE - - -
06.02.01 FALSA ZAPATA C=140 PARA ESTRIBO DE PUENTE m3 127.65 - 1 Area 87.95 87.95 87.95
1 79.95 1.10 87.95
-
06.03 OBRAS DE CONCRETO ARMADO - - -
06.03.01 ACERO DE REFUERZO ZAPATAS kg 6,918.97 - 1 6,918.97 6,918.97 6,918.97
Pantalla

14
SUSTENTO DE METRADOS CORRESPONDIENTE AL MES DE SETIEMBRE

OBRA “CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”
ENTIDAD MUNICIPALIDAD DISTRITAL DE SAN MARCOS
UBICACIÓN SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA
CONTRATISTA CONSORCIO SAN JUAN RESIDENCIA ING. VICENTE BARRERA BULNES SUPERVISIÓN CONSORCIO BMG

Metrado AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL


ITEM DESCRIPCION PARTIDA Und. ACUMULADO
Base N° Largo Ancho Alto Factor Producto Parcial N° Largo Ancho Alto Factor Producto Parcial
Longitudinal 1/2" 1 74.00 6.30 0.99 462.94
Transversal 1" 1 98.00 8.60 3.97 3,348.44
Aletas -
Longitudinal 1/2" 2 52.00 3.50 0.99 361.45
Transversal 1" 2 54.00 6.40 3.97 2,746.14
06.03.02 ENCOFRADO y DESENCOFRADO DE ZAPATAS m2 45.50 - 45.50 45.50 45.50
Pantalla
2 4.00 - 1.30 10.40
1 6.40 - 1.30 8.32
Aletas -
4 1.80 1.30 9.36
2 3.50 1.30 9.10
1 6.40 1.30 8.32
06.03.03 CONCRETO C-210 PARA ZAPATAS m3 110.63 - 1 110.63 110.63 110.63
Pantalla 1 6.40 7.50 1.30 62.40
Aletas 2 3.50 5.30 1.30 48.23
06.03.04 ACERO DE REFUERZO EN PANTALLA Y ALEROS kg 4562.39 - 4,562.39 4,562.39 4,562.39
Pantalla
Vertical 1" 43.00 4.00 3.97 683.36
Vertical 1" 43.00 7.30 3.97 1,247.12
Verical 5/8" 22.00 7.30 1.55 249.25
Horizontal 5/8" 2 17.00 6.60 1.55 348.27

Aletas
Vertical 1/2" 2 18.00 3.90 0.99 139.42
Vertical 1" 2 18.00 9.00 3.97 1,287.25
Verical 1/2" 2 18.00 9.00 0.99 321.73
Horizontal 1/2" 2 36.00 4.00 0.99 285.98
06.03.05 ENCOFRADO Y DESENCOFRADO DE PANTALLA Y ALEROS m2 163.52 - - -
06.03.06 CONCRETO C=210 EN PANTALLA Y ALEROS m3 48.10 - - -
06.03.07 ANCLAJE CON EPÓXICO u 12.00 - - -
06.03.08 ACERO DE REFUERZO EN CAJUELAS kg 3,015.76 - - -
06.03.09 ENCOFRADO Y DESENCOFRADO EN CAJUELAS m2 84.8 - - -
06.03.10 CONCRETO C=210 EN CAJUELAS m3 31.53 - - -
06.03.11 ENCOFRADO Y DESENCOFRADO EN LOSA Y VEREDAS m2 216.00 - - -
06.03.12 ACERO DE REFUERZO EN LOSA Y VEREDAS kg 8,752.86 - - -
06.03.13 CONCRETO C=280 EN LOSA m3 28.20 - - -

15
SUSTENTO DE METRADOS CORRESPONDIENTE AL MES DE SETIEMBRE

OBRA “CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”
ENTIDAD MUNICIPALIDAD DISTRITAL DE SAN MARCOS
UBICACIÓN SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA
CONTRATISTA CONSORCIO SAN JUAN RESIDENCIA ING. VICENTE BARRERA BULNES SUPERVISIÓN CONSORCIO BMG

Metrado AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL


ITEM DESCRIPCION PARTIDA Und. ACUMULADO
Base N° Largo Ancho Alto Factor Producto Parcial N° Largo Ancho Alto Factor Producto Parcial
06.03.14 CONCRETO F'C=280 KG/CM2 EN VEREDAS m3 9 - - -
06.04 FALSO PUENTE - - -
06.04.01 MUROS DE PIEDRA C:H 1:8 + 70% PG m3 57.60 - - -
06.04.02 FALSO PUENTE DE MADERA EUCALIPTO m2 180.00 - - -
06.05 VIGAS Y DIAFRAGMAS METÁLICOS - - -
06.05.01 VIGA PRINCIPAL TIPO I DE 1.068 X 0.417 X 30 M m 2 - - -
06.05.02 VIGA DIAFRAGMA PERFIL C DE 0.381 X 0.10 X 2.70 pza 11.00 - - -
06.05.03 LANZAMIENTO Y MONTAJE DE VIGAS METÁLICAS pza 2.00 - - -
06.05.04 INSTALACIÓN Y MONTAJE DE DIAFRAGMAS METÁLICOS pza 11.00 - - -
06.06 APOYOS - - -
06.06.01 APOYO MOVIL u 2.00 - - -
06.06.02 APOYO FIJO u 2.00 - - -
06.07 BARANDA METÁLICA - - -
06.07.01 ALINEACIÓN Y COLOCACIÓN DE BASE METÁLICA u 42.00 - - -
06.07.02 INSTALACIÓN DE BARANDA METALICA (L=9.00 M/BARANDA) m 60.00 - - -
06.07.03 PINTURA DE ALTO TRÁNSITO, BASE ANTICORROSIVA m 60.00 - - -
06.08 JUNTAS - - -
06.08.01 JUNTAS DE DILATACION E=0.05 M m 9.40 - - -
06.08.02 COLOCADO DE ANGULO 4" X 4" X 1/4" UNION MURO LOSA m 9.40 - - -
07 OBRAS COMPLEMENTARIAS - - -
07.01 MUROS DE SOSTENIMIENTO DE PIEDRA CON CONCRETO (220 ML) - - -
07.01.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 356.4 - - -
07.01.02 NIVELACION Y REFINE PARA ESTRUCTURA m2 396.00 - - -
07.01.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 682.00 - - -
07.01.04 CONCRETO CICLOPEO C-175 + 70% PG m3 485.10 - - -
07.01.05 RELLENO COMPACTADO CON MATERIAL PROPIO EN ESTRUCTURAS m3 577.50 - - -
07.02 MUROS DE CONTENCION (180 ML) - - -
07.02.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 1,722.60 - - -
07.02.02 NIVELACION Y REFINE PARA ESTRUCTURA m2 594.00 - - -
07.02.03 ELIMINACION MATERIAL EXCEDENTE m3 37.80 - - -
07.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO EN ESTRUCTURAS m3 1,684.80 - - -
07.02.05 SOLADOS CONCRETO DE 4" m2 594 - - -
07.02.06 ACERO DE REFUERZO, EN MURO CONTENCION kg 32,875.20 - - -
07.02.07 ENCOFRADO Y DESENCOFRADO DE MURO DE CONTENCIÓN m2 1,512.00 - - -
07.02.08 CONCRETO C-210 EN MURO DE CONTENCIÓN m3 637.20 - - -
07.02.09 RELLENO MATERIAL FILTRANTE DE 3" m3 351.00 - - -
08 SEÑALIZACION Y SEGURIDAD VIAL (18 UND) - - -

16
SUSTENTO DE METRADOS CORRESPONDIENTE AL MES DE SETIEMBRE

OBRA “CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”
ENTIDAD MUNICIPALIDAD DISTRITAL DE SAN MARCOS
UBICACIÓN SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA
CONTRATISTA CONSORCIO SAN JUAN RESIDENCIA ING. VICENTE BARRERA BULNES SUPERVISIÓN CONSORCIO BMG

Metrado AVANCE ACUMULADO ANTERIOR AVANCE ACTUAL


ITEM DESCRIPCION PARTIDA Und. ACUMULADO
Base N° Largo Ancho Alto Factor Producto Parcial N° Largo Ancho Alto Factor Producto Parcial
08.01 SEÑALES PREVENTIVAS u 4.00 - - -
08.02 SEÑALES INFORMATIVAS u 5.00 - - -
08.03 BARANDAS METALICA H=0.90 M m 220.00 - - -
09 MITIGACIÓN DE IMPACTO AMBIENTAL - - -
09.01 IMPLEMENTACIÓN DEL PLAN DE MANEJO AMBIENTAL glb 1.00 - - -
10 MONITOREO ARQUEOLÓGICO - - -
10.01 ELABORACIÓN DE PLAN DE MONITOREO ARQUEOLÓGICO u 1.00 - - -
10.02 EJECUCIÓN DEL PLAN DE MONITOREO ARQUEOLÓGICO mes 6.00 - - -
11 VARIOS - - -
11.01 REPOSICIÓN DE LINEA DE CONDUCCIÓN DE AGUA POTABLE AFECTADO m 828.00 - - -
11.02 REPOSICIÓN DE SERVICIOS EXISTENTES AFECTADOS pza 28.00 - - -
11.03 CAPACITACIÓN EN MANTENIMIENTO RUTINARIO Y PERIODICO glb 1.00 - - -
12 FLETE - - -
12.02 FLETE RURAL DE MATERIALES VARIOS glb 1.00 - 0 0.40 -

17
Proyecto “CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO
– RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN
MARCOS – HUARI – ANCASH”

Metrados actuales al mes de noviembre

Medidas Perimetro,
Nro
Item DESCRIPCION DE PARTIDAS UND Area o TOTAL
Veces LARGO ANCHO ALTO Parcial
07.02.00 MURO DE CONTENCIÓN
07.02.01 Excavación no Clasificada para Estructuras m3 L= 34.10 326.34 326.34
Tramo 1+360 a 1+540 1 34.10 1.10 0.90 33.76
1 34.10 2.20 3.90 292.58
L= 0.00
07.02.02 Nivelación y Refine para Estructuras m2 1 0.00 3.30 0.00 0.00

07.02.03 Eliminación de Material Excedente a más de 5 Km m3 0.00 0.00

07.02.04 Relleno Compactado con Material Propio m3 1 0.00 2.40 3.90 0.00 0.00
L= 46.10
07.02.05 Solado Concreto de 4" m2 1 46.10 3.30 152.13 152.13

07.02.06 Acero de Refuerzo, en Muro de Contención kg 6,636.47


3,756.91
ZAPATA MES OCT 2,146.63
MES NOV L= 64.10 5,903.53

Zapata: Longitudinal Ø 1/2" 26 64.10 0.993 1,654.93


Zapata: Transversal Ø 5/8" 365 7.50 1.552 4,248.60

PANTALLA 2,879.57
MES OCT 2,108.62
MES NOV 4,988.19

Pantalla (completa: acero, encofrado y concreto) nº L= 6.00 2,155.94


Paño 1, paño 2. paño3, paño4
Vertical Ø 5/8" 4 27 5.10 1.552 854.84
Vertical Ø 5/8" 4 27 2.35 1.552 393.90
Horizontal Ø 5/8" 4 9 6.00 1.552 335.23
Horizontal Ø 1/2" 4 24 6.00 0.993 571.97

Pantalla (enconfrado y acero) nº L= 6.00 538.98


Paño 5
Vertical Ø 5/8" 1 27 5.10 1.552 213.71
Vertical Ø 5/8" 1 27 2.35 1.552 98.47
Horizontal Ø 5/8" 1 9 6.00 1.552 83.81
Horizontal Ø 1/2" 1 24 6.00 0.993 142.99

Pantalla (completa: acero, encofrado y concreto) nº L= 3.00 275.27


Paño 6-A
Vertical Ø 5/8" 1 14 5.10 1.552 110.81
Vertical Ø 5/8" 1 14 2.35 1.552 51.06
Horizontal Ø 5/8" 1 9 3.00 1.552 41.90
Horizontal Ø 1/2" 1 24 3.00 0.993 71.50

Pantalla ( acero) nº L= 3.00 275.27


Paño 6-B
Vertical Ø 5/8" 1 14 5.10 1.552 110.81
Vertical Ø 5/8" 1 14 2.35 1.552 51.06
Horizontal Ø 5/8" 1 9 3.00 1.552 41.90
Horizontal Ø 1/2" 1 24 3.00 0.993 71.50

Pantalla (enconfrado y acero) nº L= 6.00 538.98


Paño 7
Vertical Ø 5/8" 1 27 5.10 1.552 213.71
Vertical Ø 5/8" 1 27 2.35 1.552 98.47
Horizontal Ø 5/8" 1 9 6.00 1.552 83.81
Horizontal Ø 1/2" 1 24 6.00 0.993 142.99

Pantalla ( acero) nº L= 6.00 269.49


Paño 8
Vertical Ø 5/8" 0.5 27 5.10 1.552 106.86
Vertical Ø 5/8" 0.5 27 2.35 1.552 49.24
Horizontal Ø 5/8" 0.5 9 6.00 1.552 41.90
Horizontal Ø 1/2" 0.5 24 6.00 0.993 71.50

Pantalla ( acero) nº L= 6.00 485.09


Paño 9
Vertical Ø 5/8" 0.9 27 5.10 1.552 192.34
Vertical Ø 5/8" 0.9 27 2.35 1.552 88.63
Horizontal Ø 5/8" 0.9 9 6.00 1.552 75.43
Horizontal Ø 1/2" 0.9 24 6.00 0.993 128.69

Pantalla ( acero) nº L= 6.00 269.49


Paño 10
Vertical Ø 5/8" 0.5 27 5.10 1.552 106.86
Vertical Ø 5/8" 0.5 27 2.35 1.552 49.24
Horizontal Ø 5/8" 0.5 9 6.00 1.552 41.90
Horizontal Ø 1/2" 0.5 24 6.00 0.993 71.50

Pantalla ( acero) nº L= 4.00 179.66


Paño 11
Vertical Ø 5/8" 0.5 18 5.10 1.552 71.24
Vertical Ø 5/8" 0.5 18 2.35 1.552 32.82
Horizontal Ø 5/8" 0.5 9 4.00 1.552 27.94
Horizontal Ø 1/2" 0.5 24 4.00 0.993 47.66

L= 40.10
07.02.07 Encofrado y Desencofrado de Muro de Contención m2 1 251.91 251.91
Zapata 1 40.10 0.60 24.06

Pantalla
2.25 227.85
Pantalla- tramo 1 1.7 2 6.00 1.975 23.70

2.85

Pantalla- tramo 2 2.5 2 6.00 2.675 32.10


3.15

Pantalla- tramo 3 2.8 2 6.00 2.975 35.70

3.25

Pantalla- tramo 4 2.85 2 6.00 3.050 36.60

3.45

Pantalla- tramo 5 3.05 2 6.00 3.250 39.00

3.4

Pantalla- tramo 6-A 3.35 2 3.00 3.375 20.25

Pantalla- tramo 6-B 0.000 0.00

3.45

Pantalla- tramo 7 3.3 2 6.00 3.375 40.50

Pantalla- tramo 8 0.000 0.00

Pantalla- tramo 9 0.000 0.00

Pantalla- tramo 10 0.000 0.00

Pantalla- tramo 11 0.000 0.00

07.02.08 Concreto C-210 en Muros de Contención m3 203.15 203.15


L= 64.100
Zapata 1 64.10 3.35 0.60 128.84
Uña 1 64.10 0.53 0.60 20.19
L= 64.100
Pantalla 54.11

2.25
Pantalla- tramo 1 1.7 1 6.00 0.48 1.975 5.63
2.85
Pantalla- tramo 2 2.5 1 6.00 0.48 2.675 7.62
3.15
Pantalla- tramo 3 2.8 1 6.00 0.48 2.975 8.48
3.25
Pantalla- tramo 4 2.85 1 6.00 0.48 3.050 8.69
3.45
Pantalla- tramo 5 3.05 1 6.00 0.48 3.250 9.26
3.4
Pantalla- tramo 6-A 3.35 1 3.00 0.48 3.375 4.81

Pantalla- tramo 6-B 0.000 0.00


3.45
Pantalla- tramo 7 3.3 1 6.00 0.48 3.375 9.62

L= 0.000
07.02.09 Relleno Material Filtrante de 3/4" m3 1 0.00 0.50 0.00 0.00 0.00
VALORIZACION N° 003

“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO
OBRA:
DE SAN MARCOS – HUARI – ANCASH”
CLIENTE: MUNICIPALIDAD DISTRITAL DE SAN MARCOS

LUGAR: C.P MOSNA - SAN MARCOS - HUARI - ANCASH


EMPRESA
CONSORCIO SAN JUAN
EJECUTORA.
RESIDENTE: ING. VICENTE BARRERA BULNES

SUPERVISOR: ING. BILLY RONALD MEJIA GARCIA

AVANCE ANTERIOR AVANCE ACTUAL AVANCE ACUMULADO SALDO


ITEM DESCRIPCION UND METRADO PRECIO S/. PARCIAL S/.
METRADO VALORIZ. METRADO VALORIZ. METRADO VALORIZ. % METRADO VALORIZ. %

01 OBRAS PROVISIONALES 16,152.54 7,683.29 605.25 8,288.54 51.31% - 7,864.00 48.69%

01.01 CAMPAMENTO PROVISIONAL DE LA OBRA 9x5 m glb 1.00 3,616.07 3,616.07 1.00 3,616.07 0.00 0.00 1.00 3,616.07 100.00% - - 0.00%

01.02 CERCO PROVISIONAL m 250.00 16.14 4,035.00 112.50 1,815.75 37.50 605.25 150.00 2,421.00 60.00% 100.00 1,614.00 40.00%
01.03 CARTEL DE OBRA u 1.00 1,001.47 1,001.47 1.00 1,001.47 0.00 0.00 1.00 1,001.47 100.00% - - 0.00%

01.04 SERVICIO DE BAÑO PORTATIL (INODORO Y LAVATORIO) TIPO DISAL O S mes 6.00 1,250.00 7,500.00 1.00 1,250.00 0.00 0.00 1.00 1,250.00 16.67% 5.00 6,250.00 83.33%
02 SEGURIDAD Y SALUD 43,625.03 14,336.72 6,604.12 20,940.84 48.00% - 22,684.19 52.00%

02.01 ELAB, IMPLEM Y ADMINIS. DEL PLAN DE SEGURIDAD Y SALUD EN EL TR glb 1.00 13,840.25 13,840.25 0.33 4,567.28 0.16 2,214.44 0.49 6,781.72 49.00% 0.51 7,058.53 51.00%
02.02 EQUIPOS DE PROTECCIÓN INDIVIDUAL glb 1.00 16,990.98 16,990.98 0.37 6,286.66 0.17 2,888.47 0.54 9,175.13 54.00% 0.46 7,815.85 46.00%

02.03 EQUIPOS DE PROTECCIÓN COLECTIVA glb 1.00 4,330.68 4,330.68 0.17 736.22 0.17 736.22 0.34 1,472.44 34.00% 0.66 2,858.25 66.00%

02.04 SEÑALIZACIÓN TEMPORAL DE SEGURIDAD glb 1.00 2,317.54 2,317.54 0.50 1,158.77 0.00 0.00 0.50 1,158.77 50.00% 0.50 1,158.77 50.00%
02.05 CAPACITACIÓN EN SEGURIDAD Y SALUD glb 1.00 4,500.00 4,500.00 0.17 765.00 0.17 765.00 0.34 1,530.00 34.00% 0.66 2,970.00 66.00%

02.06 RECURSOS PARA RESPUESTAS ANTE EMERGENCIAS EN SST evto 1.00 1,645.58 1,645.58 0.50 822.79 0.00 0.00 0.50 822.79 50.00% 0.50 822.79 50.00%

03 TRABAJOS PRELIMINARES 65,006.48 17,754.44 5,845.30 23,599.74 36.30% - 41,406.74 63.70%

03.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO glb 1.00 28,993.88 28,993.88 0.50 14,496.94 0.00 0.00 0.50 14,496.94 50.00% 0.50 14,496.94 50.00%

03.02 TOPOGRAFÍA Y GEOREFERENCIACIÓN EN CARRETERAS km 2.00 2,074.00 4,148.00 1.00 2,074.00 0.30 622.20 1.30 2,696.20 65.00% 0.70 1,451.80 35.00%
03.03 TRAZO, NIVELACIÓN Y REPLANTEO EN OBRAS COMPLEMENTARIAS m2 2,300.00 2.63 6,049.00 450.00 1,183.50 350.00 920.50 800.00 2,104.00 34.78% 1,500.00 3,945.00 65.22%

03.04 TRABAJOS PREVENTIVOS DE SEGURIDAD m 360.00 71.71 25,815.60 0.00 0.00 60.00 4,302.60 60.00 4,302.60 16.67% 300.00 21,513.00 83.33%
04 MOVIMIENTO DE TIERRAS 926,379.58 251,871.01 105,528.96 357,399.97 38.58% - 568,979.61 61.42%

04.01 CORTE EN TERRENO CONGLOMERADO CON MAQUINARIA m3 6,445.53 10.98 70,771.92 2,950.70 32,398.69 0.00 0.00 2,950.70 32,398.69 45.78% 3,494.83 38,373.23 54.22%

04.02 CORTE EN ROCA SUELTA (PERF. Y DISPARO) CON MAQUINARIA m3 699.20 42.37 29,625.10 0.00 0.00 350.47 14,849.41 350.47 14,849.41 50.12% 348.73 14,775.69 49.88%
04.03 CORTE ROCA FIJA CON MAQUINARIA m3 7,565.28 44.64 337,714.10 3,359.10 149,950.22 1,483.61 66,228.35 4,842.71 216,178.57 64.01% 2,722.57 121,535.52 35.99%

04.04 PERFILADO Y COMPACTADO EN TRAMOS DE CORTE Y RELLENO m2 8,260.00 3.12 25,771.20 0.00 0.00 0.00 0.00 0.00 0.00% 8,260.00 25,771.20 100.00%
04.05 CONFORMACION DE TERRAPLENES R= 650 m3/día m3 2450.02 12.18 29,841.24 1,850.00 22,533.00 0.00 0.00 1,850.00 22,533.00 75.51% 600.02 7,308.24 24.49%
04.06 PERFILADO, DESQUINCHE y PEINADO DE TALUDES m2 5747.42 7.55 43,393.02 1,804.56 13,624.43 0.00 0.00 1,804.56 13,624.43 31.40% 3,942.86 29,768.59 68.60%
04.07 RELLENO CON MATERIAL PROPIO C/EQUIPO m3 3,860.14 8.83 34,085.04 1,831.40 16,171.26 0.00 0.00 1,831.40 16,171.26 47.44% 2,028.74 17,913.77 52.56%

04.08 TRASPORTE DE PIEDRA PARA ENROCADO R=240 m3/día m3 468.00 43.36 20,292.48 0.00 0.00 360.00 15,609.60 360.00 15,609.60 76.92% 108.00 4,682.88 23.08%
04.09 ACOMODO DE PIEDRA EN ENROCADO R=120 m3/día m3 468.00 24.56 11,494.08 0.00 0.00 360.00 8,841.60 360.00 8,841.60 76.92% 108.00 2,652.48 23.08%

04.10 ELIMINACION DE MATERIAL EXCEDENTE A MAS DE 5 KM m3 13,253.60 13.75 182,237.00 1,250.43 17,193.41 0.00 1,250.43 17,193.41 9.43% 12,003.17 165,043.59 90.57%
04.11 MEJORAMIENTO SUPERFICIE DE RODADURA CON MATERIAL AFIRMADO m2 8,560.00 16.49 141,154.40 0.00 0.00 0.00 0.00 0.00 0.00% 8,560.00 141,154.40 100.00%

05 OBRAS DE ARTE 291,429.76 0.00 0.00 0.00 0.00% - 291,429.76 100.00%

05.01 CUNETAS 50,448.20 0.00 0.00 0.00 0.00% - 50,448.20 100.00%


05.01.01 CONFORMACIÓN DE CUNETAS EN MATERIAL SIN CLASIFICAR m 1,380.00 2.97 4,098.60 0.00 0.00 0.00 0.00 0.00 0.00% 1,380.00 4,098.60 100.00%

05.01.02 CONFORMACIÓN DE CUNETAS LATERALES EN ROCA m 460.00 29.66 13,643.60 0.00 0.00 0.00 0.00 0.00 0.00% 460.00 13,643.60 100.00%

05.01.03 CUNETA LATERAL REVESTIDO DE CONCRETO m 300.00 109.02 32,706.00 0.00 0.00 0.00 0.00 0.00 0.00% 300.00 32,706.00 100.00%

05.02 ALCANTARILLA TIPO TMC (05 UNID.) 25,164.99 0.00 0.00 0.00 0.00% - 25,164.99 100.00%

05.02.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 86.03 47.11 4,052.87 0.00 0.00 0.00 0.00 0.00 0.00% 86.03 4,052.87 100.00%
05.02.02 NIVELACION Y REFINE PARA ESTRUCTURA m2 68.25 8.81 601.28 0.00 0.00 0.00 0.00 0.00 0.00% 68.25 601.28 100.00%

05.02.03 ENCOFRADO y DESENCOFRADO DEL INGRESO Y SALIDA m2 78.00 51.75 4,036.50 0.00 0.00 0.00 0.00 0.00 0.00% 78.00 4,036.50 100.00%
05.02.04 CONCRETO C-175 EN INGRESO Y SALIDA m3 12.86 420.08 5,402.23 0.00 0.00 0.00 0.00 0.00 0.00% 12.86 5,402.23 100.00%

05.02.05 REVESTIMIENTO DE CAUCES DE ALCANTARILLA m2 56.00 28.81 1,613.36 0.00 0.00 0.00 0.00 0.00 0.00% 56.00 1,613.36 100.00%
05.02.06 ALCANTARILLA TMC 0=24" C=16 R=12 m/día m 25.00 378.35 9,458.75 0.00 0.00 0.00 0.00 0.00 0.00% 25.00 9,458.75 100.00%

05.03 ALCANTANTARILLADO PLUVIAL (260 ML) 215,816.57 0.00 0.00 0.00 0.00% - 215,816.57 100.00%

05.03.01 DEMOLICION DE PAVIMENTO EXISTENTE m3 28 41.39 1,158.92 0.00 0.00 0.00 0.00 0.00 0.00% 28.00 1,158.92 100.00%
05.03.02 EXCAVACION EN SUELO CONGLOMERADO m3 338.00 41.33 13,969.54 0.00 0.00 0.00 0.00 0.00 0.00% 338.00 13,969.54 100.00%

05.03.03 REFINE, NIVELACION Y COMPACTADO FONDO DE ZANJA m2 260.00 10.74 2,792.40 0.00 0.00 0.00 0.00 0.00 0.00% 260.00 2,792.40 100.00%

05.03.04 SOLADO CONCRETO DE 4" m2 260.00 36.47 9,482.20 0.00 0.00 0.00 0.00 0.00 0.00% 260.00 9,482.20 100.00%

05.03.05 HABILITADO Y ARMADO DE ACERO Fy=4200 Kg/cm2 kg 9,862.48 5.14 50,693.15 0.00 0.00 0.00 0.00 0.00 0.00% 9,862.48 50,693.15 100.00%

05.03.06 ENCOFRADO Y DESENCOFRADO EN ALCANTARILLADO PLUVIAL m2 624 78.12 48,746.88 0.00 0.00 0.00 0.00 0.00 0.00% 624.00 48,746.88 100.00%
05.03.07 CONCRETO C-210 EN ALCANTARILLADO PLUVIAL m3 197.60 421.60 83,308.16 0.00 0.00 0.00 0.00 0.00 0.00% 197.60 83,308.16 100.00%

05.03.08 DRENAJE COLECTOR SUMIDERO DE RIELES m 16.00 211.86 3,389.76 0.00 0.00 0.00 0.00 0.00 0.00% 16.00 3,389.76 100.00%
05.03.09 JUNTA TRANSVERSAL CONTRACCION 1.0" a 3.00 M m 309.60 7.35 2,275.56 0.00 0.00 0.00 0.00 0.00 0.00% 309.60 2,275.56 100.00%

06 PUENTE DE ACERO Y CONCRETO 936,047.99 132,988.99 80,304.50 213,293.49 22.79% - 722,754.49 77.21%

06.01 MOVIMIENTO DE TIERRAS 34,343.20 34,343.20 0.00 34,343.20 100.00% - 0.00 0.00%
06.01.01 EXCAVACION NO CLASIFICADA PARA ESTRIBOS DE PUENTE m3 152.38 34.98 5,330.25 152.38 5,330.25 0.00 0.00 152.38 5,330.25 100.00% - - 0.00%

06.01.02 CORTE EN ROCA FIJA m3 54.60 38.79 2,117.93 54.60 2,117.93 0.00 0.00 54.60 2,117.93 100.00% - - 0.00%
06.01.03 RELLENO COMPACTADO CON MATERIAL PROPIO m3 148.68 42.51 6,320.39 148.68 6,320.39 0.00 0.00 148.68 6,320.39 100.00% - - 0.00%

06.01.04 ELIMINACION DE MATERIAL EXCEDENTE A MAS DE 5 KM m3 58.30 13.75 801.63 58.30 801.63 0.00 0.00 58.30 801.63 100.00% - - 0.00%
06.01.05 LIMPIEZA DE CAUCE DE RIO m2 900 21.97 19,773.00 900.00 19,773.00 0.00 0.00 900.00 19,773.00 100.00% - - 0.00%

06.02 OBRAS DE CONCRETO SIMPLE 42,305.76 29,148.39 0.00 29,148.39 68.90% - 13,157.37 31.10%
06.02.01 FALSA ZAPATA C=140 PARA ESTRIBO DE PUENTE m3 127.65 331.42 42,305.76 87.95 29,148.39 0.00 0.00 87.95 29,148.39 68.90% 39.70 13,157.37 31.10%
06.03 OBRAS DE CONCRETO ARMADO 259,625.70 69,497.40 78,714.16 148,211.56 57.09% - 111,414.13 42.91%

06.03.01 ACERO DE REFUERZO ZAPATAS kg 6,918.97 5.14 35,563.51 6,918.97 35,563.51 0.00 0.00 6,918.97 35,563.51 100.00% - - 0.00%
06.03.02 ENCOFRADO y DESENCOFRADO DE ZAPATAS m2 45.50 51.75 2,354.63 45.50 2,354.63 0.00 0.00 45.50 2,354.63 100.00% - - 0.00%

06.03.03 CONCRETO C-210 PARA ZAPATAS m3 110.63 500.85 55,409.04 0.00 0.00 103.04 51,607.58 103.04 51,607.58 93.14% 7.59 3,801.45 6.86%
06.03.04 ACERO DE REFUERZO EN PANTALLA Y ALEROS kg 4562.39 5.14 23,450.68 4,562.39 23,450.68 0.00 0.00 4,562.39 23,450.68 100.00% - - 0.00%

06.03.05 ENCOFRADO Y DESENCOFRADO DE PANTALLA Y ALEROS m2 163.52 49.71 8,128.58 163.52 8,128.58 0.00 0.00 163.52 8,128.58 100.00% - - 0.00%

06.03.06 CONCRETO C=210 EN PANTALLA Y ALEROS m3 48.10 500.85 24,090.89 0.00 0.00 35.47 17,765.15 35.47 17,765.15 73.74% 12.63 6,325.74 26.26%
06.03.07 ANCLAJE CON EPÓXICO u 12.00 39.37 472.44 0.00 0.00 0.00 0.00 0.00 0.00% 12.00 472.44 100.00%

06.03.08 ACERO DE REFUERZO EN CAJUELAS kg 3,015.76 5.03 15,169.27 0.00 0.00 1,434.50 7,215.54 1,434.50 7,215.54 47.57% 1,581.26 7,953.74 52.43%

06.03.09 ENCOFRADO Y DESENCOFRADO EN CAJUELAS m2 84.8 55.71 4,724.21 0.00 0.00 38.16 2,125.89 38.16 2,125.89 45.00% 46.64 2,598.31 55.00%

06.03.10 CONCRETO C=210 EN CAJUELAS m3 31.53 500.85 15,791.80 0.00 0.00 0.00 0.00 0.00 0.00% 31.53 15,791.80 100.00%

06.03.11 ENCOFRADO Y DESENCOFRADO EN LOSA Y VEREDAS m2 216.00 55.71 12,033.36 0.00 0.00 0.00 0.00 0.00 0.00% 216.00 12,033.36 100.00%
06.03.12 ACERO DE REFUERZO EN LOSA Y VEREDAS kg 8,752.86 5.03 44,026.89 0.00 0.00 0.00 0.00 0.00 0.00% 8,752.86 44,026.89 100.00%

06.03.13 CONCRETO C=280 EN LOSA m3 28.20 500.85 14,123.97 0.00 0.00 0.00 0.00 0.00 0.00% 28.20 14,123.97 100.00%
06.03.14 CONCRETO F'C=280 KG/CM2 EN VEREDAS m3 9 476.27 4,286.43 0.00 0.00 0.00 0.00 0.00 0.00% 9.00 4,286.43 100.00%

06.04 FALSO PUENTE 35,537.69 0.00 1,590.34 1,590.34 4.48% - 33,947.35 95.52%
06.04.01 MUROS DE PIEDRA C:H 1:8 + 70% PG m3 57.60 220.88 12,722.69 0.00 0.00 7.20 1,590.34 7.20 1,590.34 12.50% 50.40 11,132.35 87.50%

06.04.02 FALSO PUENTE DE MADERA EUCALIPTO m2 180.00 126.75 22,815.00 0.00 0.00 0.00 0.00 0.00 0.00% 180.00 22,815.00 100.00%

06.05 VIGAS Y DIAFRAGMAS METÁLICOS 522,805.70 0.00 0.00 0.00 0.00% - 522,805.70 100.00%
06.05.01 VIGA PRINCIPAL TIPO I DE 1.068 X 0.417 X 30 M m 2 192372.82 384,745.64 0.00 0.00 0.00 0.00 0.00 0.00% 2.00 384,745.64 100.00%

06.05.02 VIGA DIAFRAGMA PERFIL C DE 0.381 X 0.10 X 2.70 pza 11.00 11,016.95 121,186.45 0.00 0.00 0.00 0.00 0.00 0.00% 11.00 121,186.45 100.00%

06.05.03 LANZAMIENTO Y MONTAJE DE VIGAS METÁLICAS pza 2.00 3,235.07 6,470.14 0.00 0.00 0.00 0.00 0.00 0.00% 2.00 6,470.14 100.00%

06.05.04 INSTALACIÓN Y MONTAJE DE DIAFRAGMAS METÁLICOS pza 11.00 945.77 10,403.47 0.00 0.00 0.00 0.00 0.00 0.00% 11.00 10,403.47 100.00%

06.06 APOYOS 2,217.76 0.00 0.00 0.00 0.00% - 2,217.76 100.00%


06.06.01 APOYO MOVIL u 2.00 554.44 1,108.88 0.00 0.00 0.00 0.00 0.00 0.00% 2.00 1,108.88 100.00%

06.06.02 APOYO FIJO u 2.00 554.44 1,108.88 0.00 0.00 0.00 0.00 0.00 0.00% 2.00 1,108.88 100.00%
06.07 BARANDA METÁLICA 30,346.38 0.00 0.00 0.00 0.00% - 30,346.38 100.00%

06.07.01 ALINEACIÓN Y COLOCACIÓN DE BASE METÁLICA u 42.00 217.39 9,130.38 0.00 0.00 0.00 0.00 0.00 0.00% 42.00 9,130.38 100.00%

06.07.02 INSTALACIÓN DE BARANDA METALICA (L=9.00 M/BARANDA) m 60.00 334.95 20,097.00 0.00 0.00 0.00 0.00 0.00 0.00% 60.00 20,097.00 100.00%
06.07.03 PINTURA DE ALTO TRÁNSITO, BASE ANTICORROSIVA m 60.00 18.65 1,119.00 0.00 0.00 0.00 0.00 0.00 0.00% 60.00 1,119.00 100.00%

06.08 JUNTAS 8,865.80 0.00 0.00 0.00 0.00% - 8,865.80 100.00%


06.08.01 JUNTAS DE DILATACION E=0.05 M m 9.40 10.47 98.42 0.00 0.00 0.00 0.00 0.00 0.00% 9.40 98.42 100.00%

06.08.02 COLOCADO DE ANGULO 4" X 4" X 1/4" UNION MURO LOSA m 9.40 932.70 8,767.38 0.00 0.00 0.00 0.00 0.00 0.00% 9.40 8,767.38 100.00%
07 OBRAS COMPLEMENTARIAS 995,412.58 0.00 80,032.89 80,032.89 8.04% - 915,379.69 91.96%

07.01 MUROS DE SOSTENIMIENTO DE PIEDRA CON CONCRETO (220 ML) 189,037.17 0.00 0.00 0.00 0.00% - 189,037.17 100.00%
07.01.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 356.4 47.11 16,790.00 0.00 0.00 0.00 0.00 0.00 0.00% 356.40 16,790.00 100.00%
07.01.02 NIVELACION Y REFINE PARA ESTRUCTURA m2 396.00 8.81 3,488.76 0.00 0.00 0.00 0.00 0.00 0.00% 396.00 3,488.76 100.00%

07.01.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 682.00 49.71 33,902.22 0.00 0.00 0.00 0.00 0.00 0.00% 682.00 33,902.22 100.00%
07.01.04 CONCRETO CICLOPEO C-175 + 70% PG m3 485.10 203.08 98,514.11 0.00 0.00 0.00 0.00 0.00 0.00% 485.10 98,514.11 100.00%

07.01.05 RELLENO COMPACTADO CON MATERIAL PROPIO EN ESTRUCTURAS m3 577.50 62.93 36,342.08 0.00 0.00 0.00 0.00 0.00 0.00% 577.50 36,342.08 100.00%

07.02 MUROS DE CONTENCION (180 ML) 806,375.41 0.00 80,032.89 80,032.89 9.93% - 726,342.52 90.07%
07.02.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 1,722.60 47.11 81,151.69 0.00 0.00 1,148.40 54,101.12 1,148.40 54,101.12 66.67% 574.20 27,050.56 33.33%

07.02.02 NIVELACION Y REFINE PARA ESTRUCTURA m2 594.00 8.81 5,233.14 0.00 0.00 264.00 2,325.84 264.00 2,325.84 44.44% 330.00 2,907.30 55.56%
07.02.03 ELIMINACION MATERIAL EXCEDENTE m3 37.80 30.68 1,159.70 0.00 0.00 0.00 0.00 0.00 0.00% 37.80 1,159.70 100.00%

07.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO EN ESTRUCTURAS m3 1,684.80 62.93 106,024.46 0.00 0.00 0.00 0.00 0.00 0.00% 1,684.80 106,024.46 100.00%

07.02.05 SOLADOS CONCRETO DE 4" m2 594 17.14 10,181.16 0.00 0.00 59.40 1,018.12 59.40 1,018.12 10.00% 534.60 9,163.04 90.00%
07.02.06 ACERO DE REFUERZO, EN MURO CONTENCION kg 32,875.20 5.14 168,978.53 0.00 0.00 4,255.25 21,871.99 4,255.25 21,871.99 12.94% 28,619.95 147,106.54 87.06%

07.02.07 ENCOFRADO Y DESENCOFRADO DE MURO DE CONTENCIÓN m2 1,512.00 49.71 75,161.52 0.00 0.00 14.40 715.82 14.40 715.82 0.95% 1,497.60 74,445.70 99.05%
07.02.08 CONCRETO C-210 EN MURO DE CONTENCIÓN m3 637.20 500.85 319,141.62 0.00 0.00 0.00 0.00 0.00 0.00% 637.20 319,141.62 100.00%

07.02.09 RELLENO MATERIAL FILTRANTE DE 3" m3 351.00 112.09 39,343.59 0.00 0.00 0.00 0.00 0.00 0.00% 351.00 39,343.59 100.00%
08 SEÑALIZACION Y SEGURIDAD VIAL (18 UND) 10,400.96 0.00 0.00 0.00 0.00% - 10,400.96 100.00%

08.01 SEÑALES PREVENTIVAS u 4.00 521.59 2,086.36 0.00 0.00 0.00 0.00 0.00 0.00% 4.00 2,086.36 100.00%

08.02 SEÑALES INFORMATIVAS u 5.00 357.88 1,789.40 0.00 0.00 0.00 0.00 0.00 0.00% 5.00 1,789.40 100.00%
08.03 BARANDAS METALICA H=0.90 M m 220.00 29.66 6,525.20 0.00 0.00 0.00 0.00 0.00 0.00% 220.00 6,525.20 100.00%

09 MITIGACIÓN DE IMPACTO AMBIENTAL 26,480.00 0.00 0.00 0.00 0.00 0.00% - 26,480.00 100.00%
09.01 IMPLEMENTACIÓN DEL PLAN DE MANEJO AMBIENTAL glb 1.00 26,480.00 26,480.00 0.00 0.00 0.00 0.00 0.00 0.00% 1.00 26,480.00 100.00%

10 MONITOREO ARQUEOLÓGICO 20,000.00 0.00 0.00 0.00 0.00% - 20,000.00 100.00%

10.01 ELABORACIÓN DE PLAN DE MONITOREO ARQUEOLÓGICO u 1.00 5,000.00 5,000.00 0.00 0.00 0.00 0.00 0.00 0.00% 1.00 5,000.00 100.00%
10.02 EJECUCIÓN DEL PLAN DE MONITOREO ARQUEOLÓGICO mes 6.00 2,500.00 15,000.00 0.00 0.00 0.00 0.00 0.00 0.00% 6.00 15,000.00 100.00%

11 VARIOS 22,892.44 0.00 0.00 0.00 0.00% - 22,892.44 100.00%


11.01 REPOSICIÓN DE LINEA DE CONDUCCIÓN DE AGUA POTABLE AFECTADO m 828.00 9.23 7,642.44 0.00 0.00 0.00 0.00 0.00 0.00% 828.00 7,642.44 100.00%

11.02 REPOSICIÓN DE SERVICIOS EXISTENTES AFECTADOS pza 28.00 500.00 14,000.00 0.00 0.00 0.00 0.00 0.00 0.00% 28.00 14,000.00 100.00%

11.03 CAPACITACIÓN EN MANTENIMIENTO RUTINARIO Y PERIODICO glb 1.00 1,250.00 1,250.00 0.00 0.00 0.00 0.00 0.00 0.00% 1.00 1,250.00 100.00%
12 FLETE 70,506.86 24,677.40 10,576.03 35,253.43 50.00% - 35,253.43 50.00%

12.02 FLETE RURAL DE MATERIALES VARIOS glb 1.00 70,506.86 70,506.86 0.35 24,677.40 0.15 10,576.03 0.50 35,253.43 50.00% 0.50 35,253.43 50.00%

3,424,334.22 449,311.85 289,497.05 738,808.90 2,685,525.32


GASTOS GENERALES(8%) 273,946.74 35,944.95 23,159.76 59,104.71 214,842.03

UTILIDAD (10%) 342,433.42 44,931.19 28,949.71 73,880.89 268,552.53

SUBTOTAL 4,040,714.38 530,187.98 341,606.52 871,794.51 3,168,919.88

IMPUESTO (IGV) 18% 727,328.59 95,433.84 61,489.17 156,923.01 570,405.58


PRESUPUESTO TOTAL DE OBRA 4,768,042.97 625,621.82 403,095.69 1,028,717.52 3,739,325.46

PORCENTAJE DE AVANCE DE
100.00% 13.12% 8.45% 21.57% 78.43%
OBRA
CALCULO DE COEFICIENTES DE REAJUSTE (K) FORMULA DE AGUA POTABLE
VALORIZACION N° 002 SISTEMA DE AGUA POTABLE

OBRA: “CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCAS
PROPIETARIO: MUNICIPALIDAD DISTRITAL DE SAN MARCOS
CONTRATISTA: CONSORCIO SAN JUAN
RESIDENTE: ING. VICENTE BARRERA BULNES
SUPERVISOR: ING. BILLY RONALD MEJIA GARCIA
FECHA: SETIEMBRE DEL 2018

K = 0.100*(Ar / Ao) + 0.140*(Cr / Co) + 0.160*(Ir / Io) + 0.170*(Mr / Mo) + 0.190*(Mr / Mo) + 0.240*(Ar / Ao)

COEF. PARTICIP. Ki (FECHA ELABOR. VALORIZ.)

INDICES INDICES INDICES INDICES INDICES INDICES


INDICES
(AGOSTO (SETIEMBRE (OCTUBRE (OCTUBRE (NVIEMBRE (DICIEMBRE
INDICE BASE (ENERO 2018)
2018) DEL 2018) 2018) 2018) 2018) 2018)
MONOMIO DESCRIPCION I.U. INCIDENCIA PORCENTUAL (DIC 2017) K1 K2 K3 K4 K5 K6 K7

(1) (2) (3) AGOSTO 2018 SETIEMBRE 2018 OCTUBRE 2018 NOVIEMBRE 2018 DICIEMBRE 2018 ENERO 2018 FEBRERO 2018

1 AGREGADO GRUESO 5 0.402 100.000% 544.59 544.12 544.12 0.402 0.402 0.000 0.000 0.000 0.000 0.000
2 CEMENTO PORTLAND TIPO I 21 0.124 100.000% 409.93 417.65 409.29 0.126 0.124 0.000 0.000 0.000 0.000 0.000
3 INDICE GENERAL DEL PRECIO AL CONSUMIDOR 39 0.088 100.000% 443.28 443.98 441.35 0.088 0.088 0.000 0.000 0.000 0.000 0.000
4 MAQUINARIA Y EQUIPO NACIONAL 48 0.061 100.000% 291.08 305.19 295.61 0.064 0.062 0.000 0.000 0.000 0.000 0.000
5 MANO DE OBRA 47 0.060 100.000% 459.40 462.57 462.57 0.060 0.060 0.000 0.000 0.000 0.000 0.000
6 ACERO DE CONSTRUCCION CORRUGADO 3 0.057 100.000% 461.49 459.71 442.8 0.057 0.055 0.000 0.000 0.000 0.000 0.000

K 0.797 0.791 0.000 0.000 0.000 0.000 0.000


CALCULO AMORTIZACION DE ADELANTO PARA MATERIALES
VALORIZACION N° 01 - MES DE AGOSTO 2018

“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO
OBRA:
SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”

PROPIETARIO: MUNICIPALIDAD DISTRITAL DE SAN MARCOS

CONTRATISTA: CONSORCIO SAN JUAN

RESIDENTE: ING. VICENTE BARRERA BULNES


SUPERVISOR: ING. BILLY RONALD MEJIA GARCIA
FECHA: Aug-18

DATOS GENERALES:
Monto del Cotrato (1): S/. 4,768,042.97
Fecha Presupuesto: diciembre-18
Monto del A. Materiales (2): S/. 0.00 S/IGV
Monto del A. Materiales (2): S/. 0.00 C/IGV
F. Pago del Adelanto:

Ci = Coeficiente de incidencia del material motivo de adelanto


V= Valorización del mes (inc. F.R. Sin IGV)
Ima= Indice a la fecha de otorgamiento del adelanto (Abril-2016) - INDICE UTILIZADO PARA AMORTIZAR (MARZO-2016)
Imo= Indice de la fecha del Presupuesto base del mismo material (Octubre 2015)

Material: TUBERIA PVC PARA AGUA I.U.= 72


Monto Otorgado S/. 345,873.96 con IGV
S/. 293,113.53 sin IGV
Monto Valor. Ci Ima Imo Amortización Monto a Saldo por
Val Nº Mes
(A) (B) (C) (D) (E)=(B)*(A)*(C)/(D) Amortizar Amortizar
1 Agosto 2018 259,465.54 0.124 417.65 409.93 32,779.64 32,779.64 260,333.89
2 Set 2018 #REF! 0.124 417.65 409.93 #REF! #REF! #REF!
3 Oct 2018
4 Nov 2018
5 Dic 2018
6 Ene 2019
7 Feb 2019

AMORTIZACION DEL ADELANTO PARA MATERIALES PARA EL PRESENTE MES S/. #REF! #REF!

Material: AGREGADO GRUESO I.U.= 05


Monto Otorgado S/. 48,816.79 con IGV
S/. 41,370.16 sin IGV
Monto Valor. Ci Ima Imo Amortización Monto a Saldo por
Val Nº Mes
(A) (B) (C) (D) (E)=(B)*(A)*(C)/(D) Amortizar Amortizar
1 Apr-16 259,465.54 0.088 443.98 443.28 22,869.02 22,869.02 18,501.14
2 May-16 #REF! 0.088 443.98 443.28 #REF! 18,501.14 0.00
3 Jun-16
4 Jul-16
5 Aug-16
6 Sep-16
7 Oct-16

AMORTIZACION DEL ADELANTO PARA MATERIALES PARA EL PRESENTE MES S/. 18,501.14 0.00

Material: CEMENTO PORTLAND TIPO MS I.U.= 21


Monto Otorgado S/. 62,304.55 con IGV
S/. 52,800.47 sin IGV
Monto Valor. Ci Ima Imo Amortización Monto a Saldo por
Val Nº Mes
(A) (B) (C) (D) (E)=(B)*(A)*(C)/(D) Amortizar Amortizar
1 Apr-16 259,465.54 0.060 462.57 459.40 15,675.36 15,675.36 37,125.11
2 May-16 #REF! 0.060 462.57 459.40 #REF! 37,125.11 0.00
3 Jun-16
4 Jul-16
5 Aug-16
6 Sep-16
7 Oct-16

AMORTIZACION DEL ADELANTO PARA MATERIALES PARA EL PRESENTE MES S/. 37,125.11 0.00
CALCULO AMORTIZACION DE ADELANTO PARA MATERIALES
VALORIZACION N° 01 - MES DE AGOSTO 2018

“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO
OBRA:
SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”

PROPIETARIO: MUNICIPALIDAD DISTRITAL DE SAN MARCOS

CONTRATISTA: CONSORCIO SAN JUAN

RESIDENTE: ING. VICENTE BARRERA BULNES


SUPERVISOR: ING. BILLY RONALD MEJIA GARCIA
FECHA: Aug-18

DATOS GENERALES:
Monto del Cotrato (1): S/. 4,768,042.97
Fecha Presupuesto: diciembre-18
Monto del A. Materiales (2): S/. 0.00 S/IGV
Monto del A. Materiales (2): S/. 0.00 C/IGV
F. Pago del Adelanto:

Ci = Coeficiente de incidencia del material motivo de adelanto


V= Valorización del mes (inc. F.R. Sin IGV)
Ima= Indice a la fecha de otorgamiento del adelanto (Abril-2016) - INDICE UTILIZADO PARA AMORTIZAR (MARZO-2016)
Imo= Indice de la fecha del Presupuesto base del mismo material (Octubre 2015)

Material: ACERO CORRUGADO PARA CONSTRUCCION I.U.= 03


Monto Otorgado S/. 90,562.16 con IGV
S/. 76,747.59 sin IGV
Monto Valor. Ci Ima Imo Amortización Monto a Saldo por
Val Nº Mes
(A) (B) (C) (D) (E)=(B)*(A)*(C)/(D) Amortizar Amortizar
1 Apr-16 259,465.54 0.057 459.71 461.49 14,732.49 14,732.49 62,015.10
2 May-16 #REF! 0.057 459.71 461.49 #REF! #REF! #REF!
3 Jun-16
4 Jul-16
5 Aug-16
6 Sep-16
7 Oct-16

AMORTIZACION DEL ADELANTO PARA MATERIALES PARA EL PRESENTE MES S/. #REF! #REF!

FORMULA SISTEMA DE DESAGÜE

Material: AGREGADO GRUESO I.U.= 05


Monto Otorgado S/. 27,753.44 con IGV
S/. 23,519.86 sin IGV
Monto Valor. Ci Ima Imo Amortización Monto a Saldo por
Val Nº Mes
(A) (B) (C) (D) (E)=(B)*(A)*(C)/(D) Amortizar Amortizar
1 Apr-16 48,208.06 #REF! #REF! #REF! #REF! #REF! #REF!
2 May-16 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3 Jun-16
4 Jul-16
5 Aug-16
6 Sep-16
7 Oct-16

AMORTIZACION DEL ADELANTO PARA MATERIALES PARA EL PRESENTE MES S/. #REF! #REF!

Material: CEMENTO PORTLAND TIPO MS I.U.= 21


Monto Otorgado S/. 15,439.22 con IGV
S/. 13,084.08 sin IGV
Monto Valor. Ci Ima Imo Amortización Monto a Saldo por
Val Nº Mes
(A) (B) (C) (D) (E)=(B)*(A)*(C)/(D) Amortizar Amortizar
1 Apr-16 48,208.06 #REF! #REF! #REF! #REF! #REF! #REF!
2 May-16 #REF! #REF! #REF! #REF! #REF! 9,451.17 #REF!
3 Jun-16
4 Jul-16
5 Aug-16
6 Sep-16
7 Oct-16

AMORTIZACION DEL ADELANTO PARA MATERIALES PARA EL PRESENTE MES S/. 9,451.17 #REF!
CALCULO AMORTIZACION DE ADELANTO PARA MATERIALES
VALORIZACION N° 01 - MES DE AGOSTO 2018

“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO
OBRA:
SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”

PROPIETARIO: MUNICIPALIDAD DISTRITAL DE SAN MARCOS

CONTRATISTA: CONSORCIO SAN JUAN

RESIDENTE: ING. VICENTE BARRERA BULNES


SUPERVISOR: ING. BILLY RONALD MEJIA GARCIA
FECHA: Aug-18

DATOS GENERALES:
Monto del Cotrato (1): S/. 4,768,042.97
Fecha Presupuesto: diciembre-18
Monto del A. Materiales (2): S/. 0.00 S/IGV
Monto del A. Materiales (2): S/. 0.00 C/IGV
F. Pago del Adelanto:

Ci = Coeficiente de incidencia del material motivo de adelanto


V= Valorización del mes (inc. F.R. Sin IGV)
Ima= Indice a la fecha de otorgamiento del adelanto (Abril-2016) - INDICE UTILIZADO PARA AMORTIZAR (MARZO-2016)
Imo= Indice de la fecha del Presupuesto base del mismo material (Octubre 2015)

Material: ACERO CORRUGADO PARA CONSTRUCCION I.U.= 03


Monto Otorgado S/. 5,225.22 con IGV
S/. 4,428.15 sin IGV
Monto Valor. Ci Ima Imo Amortización Monto a Saldo por
Val Nº Mes
(A) (B) (C) (D) (E)=(B)*(A)*(C)/(D) Amortizar Amortizar
1 Apr-16 48,208.06 #REF! #REF! #REF! #REF! 4,428.15 0.00
2 May-16 #REF! #REF! #REF! #REF! #REF! 0.00 0.00
3 Jun-16
4 Jul-16
5 Aug-16
6 Sep-16
7 Oct-16

AMORTIZACION DEL ADELANTO PARA MATERIALES PARA EL PRESENTE MES S/. 0.00 0.00

Material: MATERIAL DE RELLENO I.U.= 38


Monto Otorgado S/. 17,159.60 con IGV
S/. 14,542.03 sin IGV
Monto Valor. Ci Ima Imo Amortización Monto a Saldo por
Val Nº Mes
(A) (B) (C) (D) (E)=(B)*(A)*(C)/(D) Amortizar Amortizar
1 Apr-16 48,208.06 #REF! #REF! #REF! #REF! #REF! #REF!
2 May-16 #REF! #REF! #REF! #REF! #REF! 10,344.18 #REF!
3 Jun-16
4 Jul-16
5 Aug-16
6 Sep-16
7 Oct-16

AMORTIZACION DEL ADELANTO PARA MATERIALES PARA EL PRESENTE MES S/. 10,344.18 #REF!

CONTROL DE LA AMORTIZACION DEL ADELANTO ESPECIFICO PARA MATERIALES

MONTO PARA AMORTIZAR EN VALORIZACION Nº 02 MES DE MAYO DE 2016 DE ACUERDO A NORMA #REF!

AMORTIZACION TOTAL POR ADELANTO PARA MATERIALES SOLICITADA POR EL CONTRATISTA -104,973.02
CALCULO DE LA DEDUCCION DEL REAJUSTE QUE NO CORRESPONDE POR ADELANTO
DIRECTO

“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO –
RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI –
OBRA: ANCASH”

PROPIETARIO: MUNICIPALIDAD DISTRITAL DE SAN MARCOS

CONTRATISTA: CONSORCIO SAN JUAN

RESIDENTE: ING. VICENTE BARRERA BULNES

SUPERVISOR: ING. BILLY RONALD MEJIA GARCIA

FECHA: September-18

Adelanto en efectivo - C/IGV


- S/IGV
Monto Contrato 4,768,042.97 C/IGV
4,040,714.38 S/IGV

FORMULA:
De = A * V / C * ( K / Ka - 1 )

DONDE:
De : Deduccion del Reajuste generado por el Adelanto Directo
A : Monto del Adelanto Directo otorgado
V : Monto de la Valorizacion Mensual
C : Saldo del contrato por Valorizar a la fecha del Adelanto
K : Coeficiente de reajuste obtenido por la aplicacion de la Fórmula Polinómica
Ka : Coeficiente de reajuste correspondiente al mes en que se canceló el Adelanto

DATOS:
A= 0.00 ( ADELANTO OTORGADO SIN IGV ABRIL 2016 )

C= 4,040,714.38 ( MONTO CONTRATADO SIN I.G.V.)

VALORIZACION V A * V / C K Ka DEDUCCION
Nº MES FORMULA Abr. 2016 De
1 Agosto 2018 6,457.20 0.00 0.797 0.797 0.00
2 Set 2018
3 Oct 2018
4 Nov 2018
5 Dic 2018
6 Ene 2019
7 Feb 2019

TOTALES 6,457.20 0.00 0.00


DEDUCCION DEL REAJUSTE QUE NO CORRESPONDE POR
ADELANTO ESPECIFICO PARA MATERIALES

OBRA: “CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO
PROPIETARIO: MUNICIPALIDAD DISTRITAL DE SAN MARCOS
CONTRATISTACONSORCIO SAN JUAN
SUPERVISOR: ING. BILLY RONALD MEJIA GARCIA
FECHA: August-18

Adelanto para Materiale 1,044,027.96 C/IGV


884,769.46 S/IGV
Monto Contrato 5,220,139.81 C/IGV
4,423,847.30 S/IGV

D.S. Nº 017-79-VC

D = ci x Val x [ (Imr - Ima) / Imo ]

donde :

D = Deducción de reintegro que no corresponde


ci = coeficiente de incidencia del material del adelanto
V = valorización del mes
Imr = Indice del material al mes del reajuste (Mayo 2016) indice utilizado Abril -2016
Ima = Indice del material al mes del adelanto ( El adelanto se otorgó enAbril 2016)
Imo = Indice del material al mes del P.B. ( Octubre 2015)

Material : TUBERÍA PVC PARA AGUA IU = 72


Adelanto para Materiale 345,873.96 C/IGV
293,113.53 S/IGV
Valorizacion Monto Valoriz. c.i. Monto Otorg. Imr Ima Imo Adelanto Deflactado c.i. x Valoriz. Monto utilizado Deducción
S/. material (SIN IGV) Abr. 2016 Abr. 2016 Oct. 2015 Adel.Otorg. x Imo/Ima para la deducción
Nº Mes
a b c d e f g=cxf/e h=axb j k = j x (d -e)/f

1.00 Agosto 2018 259,465.54 0.124 293,113.53 417.65 417.65 409.93 287,695.51 32,173.73 32,173.73 0.00
2.00 Set 2018 #REF! 0.124 293,113.53 409.29 417.65 409.93 287,695.51 #REF! #REF! #REF!
3.00 Oct 2018
4.00 Nov 2018
5.00 Dic 2018
6.00 Ene 2019
7.00 Feb 2019

TOTAL #REF! #REF! #REF!

TOTAL DEDUCCION DEL PRESENTE MES S/. #REF!

Material : AGREGADO GRUESO IU = 38


Adelanto para Materiale 48,816.79 C/IGV
41,370.16 S/IGV
Valorizacion Monto Valoriz. c.i. Monto Otorg. Imr Ima Imo Adelanto Deflactado c.i. x Valoriz. Monto utilizado Deducción
S/. material (SIN IGV) Abr. 2016 Abr. 2016 Oct. 2015 Adel.Otorg. x Imo/Ima para la deducción
Nº Mes
a b c d e f g=cxf/e h=axb j k = j x (d -e)/f

1.00 Abr 2016 259,465.54 0.088 41,370.16 443.98 443.98 443.28 41,304.93 22,832.97 22,832.97 0.00
2.00 May 2016 #REF! 0.088 41,370.16 441.35 443.98 443.28 41,304.93 #REF! #REF! #REF!
3.00 Jun 2016
4.00 Jul 2016
5.00 Ago 2016
6.00 Sep 2016
7.00 Oct 2016

TOTAL #REF! #REF! #REF!

TOTAL DEDUCCION DEL PRESENTE MES S/. #REF!


DEDUCCION DEL REAJUSTE QUE NO CORRESPONDE POR
ADELANTO ESPECIFICO PARA MATERIALES

OBRA: “CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO
PROPIETARIO: MUNICIPALIDAD DISTRITAL DE SAN MARCOS
CONTRATISTACONSORCIO SAN JUAN
SUPERVISOR: ING. BILLY RONALD MEJIA GARCIA
FECHA: August-18

Adelanto para Materiale 1,044,027.96 C/IGV


884,769.46 S/IGV
Monto Contrato 5,220,139.81 C/IGV
4,423,847.30 S/IGV

D.S. Nº 017-79-VC

D = ci x Val x [ (Imr - Ima) / Imo ]

donde :

D = Deducción de reintegro que no corresponde


ci = coeficiente de incidencia del material del adelanto
V = valorización del mes
Imr = Indice del material al mes del reajuste (Mayo 2016) indice utilizado Abril -2016
Ima = Indice del material al mes del adelanto ( El adelanto se otorgó enAbril 2016)
Imo = Indice del material al mes del P.B. ( Octubre 2015)

Material : CEMENTO PORTLAND TIPO MS IU = 21


Adelanto para Materiale 62,304.55 C/IGV
52,800.47 S/IGV
Valorizacion Monto Valoriz. c.i. Monto Otorg. Imr Ima Imo Adelanto Deflactado c.i. x Valoriz. Monto utilizado Deducción
S/. material (SIN IGV) Abr. 2016 Abr. 2016 Oct. 2015 Adel.Otorg. x Imo/Ima para la deducción
Nº Mes
a b c d e f g=cxf/e h=axb j k = j x (d -e)/f

1.00 Abr 2016 259,465.54 0.060 52,800.47 462.57 462.57 459.40 52,438.63 15,567.93 15,567.93 0.00
2.00 May 2016 #REF! 0.060 52,800.47 462.57 462.57 459.40 52,438.63 #REF! #REF! #REF!
3.00 Jun 2016
4.00 Jul 2016
5.00 Ago 2016
6.00 Sep 2016
7.00 Oct 2016

TOTAL #REF! #REF! #REF!

TOTAL DEDUCCION DEL PRESENTE MES S/. #REF!

Material : ACERO CORRUGADO PARA CONSTRUCCION IU = 03


Adelanto para Materiale 90,562.16 C/IGV
76,747.59 S/IGV
Valorizacion Monto Valoriz. c.i. Monto Otorg. Imr Ima Imo Adelanto Deflactado c.i. x Valoriz. Monto utilizado Deducción
S/. material (SIN IGV) Abr. 2016 Abr. 2016 Oct. 2015 Adel.Otorg. x Imo/Ima para la deducción
Nº Mes
a b c d e f g=cxf/e h=axb j k = j x (d -e)/f

1.00 Abr 2016 259,465.54 0.057 76,747.59 459.71 459.71 461.49 77,044.76 14,789.54 14,789.54 0.00
2.00 May 2016 #REF! 0.057 76,747.59 442.80 459.71 461.49 77,044.76 #REF! #REF! #REF!
3.00 Jun 2016
4.00 Jul 2016
5.00 Ago 2016
6.00 Sep 2016
7.00 Oct 2016

TOTAL #REF! #REF! #REF!

TOTAL DEDUCCION DEL PRESENTE MES S/. #REF!


DEDUCCION DEL REAJUSTE QUE NO CORRESPONDE POR
ADELANTO ESPECIFICO PARA MATERIALES

OBRA: “CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO
PROPIETARIO: MUNICIPALIDAD DISTRITAL DE SAN MARCOS
CONTRATISTACONSORCIO SAN JUAN
SUPERVISOR: ING. BILLY RONALD MEJIA GARCIA
FECHA: August-18

Adelanto para Materiale 1,044,027.96 C/IGV


884,769.46 S/IGV
Monto Contrato 5,220,139.81 C/IGV
4,423,847.30 S/IGV

D.S. Nº 017-79-VC

D = ci x Val x [ (Imr - Ima) / Imo ]

donde :

D = Deducción de reintegro que no corresponde


ci = coeficiente de incidencia del material del adelanto
V = valorización del mes
Imr = Indice del material al mes del reajuste (Mayo 2016) indice utilizado Abril -2016
Ima = Indice del material al mes del adelanto ( El adelanto se otorgó enAbril 2016)
Imo = Indice del material al mes del P.B. ( Octubre 2015)

SISTEMA DE DESAGÜE

Material : AGREGADO GRUESO IU = 38


Adelanto para Materiale 27,753.44 C/IGV
23,519.86 S/IGV
Valorizacion Monto Valoriz. c.i. Monto Otorg. Imr Ima Imo Adelanto Deflactado c.i. x Valoriz. Monto utilizado Deducción
S/. material (SIN IGV) Abr. 2016 Abr. 2016 Oct. 2015 Adel.Otorg. x Imo/Ima para la deducción
Nº Mes
a b c d e f g=cxf/e h=axb j k = j x (d -e)/f

1.00 Abr 2016 48,208.06 0.086 23,519.86 #REF! #REF! #REF! #REF! 4,145.89 4,145.89 #REF!
2.00 May 2016 #REF! 0.086 23,519.86 462.57 #REF! #REF! #REF! #REF! #REF! #REF!
3.00 Jun 2016
4.00 Jul 2016
5.00 Ago 2016
6.00 Sep 2016
7.00 Oct 2016

TOTAL #REF! #REF! #REF!

TOTAL DEDUCCION DEL PRESENTE MES S/. #REF!

Material : CEMENTO PORTLAND TIPO MS IU = 21


Adelanto para Materiale 15,439.22 C/IGV
13,084.08 S/IGV
Valorizacion Monto Valoriz. c.i. Monto Otorg. Imr Ima Imo Adelanto Deflactado c.i. x Valoriz. Monto utilizado Deducción
S/. material (SIN IGV) Abr. 2016 Abr. 2016 Oct. 2015 Adel.Otorg. x Imo/Ima para la deducción
Nº Mes
a b c d e f g=cxf/e h=axb j k = j x (d -e)/f

1.00 Abr 2016 48,208.06 0.117 13,084.08 #REF! #REF! #REF! #REF! 5,640.34 5,640.34 #REF!
2.00 May 2016 #REF! 0.117 13,084.08 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.00 Jun 2016
4.00 Jul 2016
5.00 Ago 2016
6.00 Sep 2016
7.00 Oct 2016

TOTAL #REF! #REF! #REF!

TOTAL DEDUCCION DEL PRESENTE MES S/. #REF!


DEDUCCION DEL REAJUSTE QUE NO CORRESPONDE POR
ADELANTO ESPECIFICO PARA MATERIALES

OBRA: “CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO
PROPIETARIO: MUNICIPALIDAD DISTRITAL DE SAN MARCOS
CONTRATISTACONSORCIO SAN JUAN
SUPERVISOR: ING. BILLY RONALD MEJIA GARCIA
FECHA: August-18

Adelanto para Materiale 1,044,027.96 C/IGV


884,769.46 S/IGV
Monto Contrato 5,220,139.81 C/IGV
4,423,847.30 S/IGV

D.S. Nº 017-79-VC

D = ci x Val x [ (Imr - Ima) / Imo ]

donde :

D = Deducción de reintegro que no corresponde


ci = coeficiente de incidencia del material del adelanto
V = valorización del mes
Imr = Indice del material al mes del reajuste (Mayo 2016) indice utilizado Abril -2016
Ima = Indice del material al mes del adelanto ( El adelanto se otorgó enAbril 2016)
Imo = Indice del material al mes del P.B. ( Octubre 2015)

Material : ACERO CORRUGADO PARA CONSTRUCCION IU = 03


Adelanto para Materiale 5,225.22 C/IGV
4,428.15 S/IGV
Valorizacion Monto Valoriz. c.i. Monto Otorg. Imr Ima Imo Adelanto Deflactado c.i. x Valoriz. Monto utilizado Deducción
S/. material (SIN IGV) Abr. 2016 Abr. 2016 Oct. 2015 Adel.Otorg. x Imo/Ima para la deducción
Nº Mes
a b c d e f g=cxf/e h=axb j k = j x (d -e)/f

1.00 Abr 2016 48,208.06 0.186 4,428.15 #REF! #REF! #REF! #REF! 8,966.70 8,966.70 #REF!
2.00 May 2016 #REF! 0.186 4,428.15 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.00 Jun 2016
4.00 Jul 2016
5.00 Ago 2016
6.00 Sep 2016
7.00 Oct 2016

TOTAL #REF! #REF! #REF!

TOTAL DEDUCCION DEL PRESENTE MES S/. #REF!

Material : MATERIAL DE RELLENO IU = 38


Adelanto para Materiale 17,159.60 C/IGV
14,542.03 S/IGV
Valorizacion Monto Valoriz. c.i. Monto Otorg. Imr Ima Imo Adelanto Deflactado c.i. x Valoriz. Monto utilizado Deducción
S/. material (SIN IGV) Abr. 2016 Abr. 2016 Oct. 2015 Adel.Otorg. x Imo/Ima para la deducción
Nº Mes
a b c d e f g=cxf/e h=axb j k = j x (d -e)/f

1.00 Abr 2016 48,208.06 0.086 14,542.03 #REF! #REF! #REF! #REF! 4,145.89 4,145.89 #REF!
2.00 May 2016 #REF! 0.086 14,542.03 #REF! #REF! #REF! #REF! #REF! #REF! #REF!
3.00 Jun 2016
4.00 Jul 2016
5.00 Ago 2016
6.00 Sep 2016
7.00 Oct 2016

TOTAL #REF! #REF! #REF!

TOTAL DEDUCCION DEL PRESENTE MES S/. #REF!

TOTAL DE DEDUCCIONES POR ADELANTO PARA MATERIALES

MONTO PARA DEDUCIR POR ADELANTO PARA MATERIALES EN VALORIZACION Nº #REF!

TOTAL DEDUCIDO #REF!


CALENDARIO DE AVANCE DE OBRA (PROGRAMADO VS EJECUTADO)

ADICIONAL CON DEDUCTIVO VINCULANTE N° 02

“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA,
OBRA:
RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”

CLIENTE: MUNICIPALIDAD DISTRITAL DE SAN MARCOS

LUGAR: C.P MOSNA - SAN MARCOS - HUARI - ANCASH

CONTRATISTAS CONSORCIO SAN JUAN

RESIDENTE: ING. WILSON LEYVA VASQUEZ

SUPERVISOR: ING. BILLY RONALD MEJIA GARCIA

PERIODO: 01 al 30 junio 2021

PRO VS EJEC
Item DESCRIPCIÓN Und. Metrado Precio S/. Parcial S/. 01 AL 30 JUN 2021
PROG. EJEC.
PARTIDAS DE LA OBRA PRINCIPAL
04 MOVIMIENTO DE TIERRAS 36,864.55 36,864.55 36,864.55
04.01 CORTE EN TERRENO CONGLOMERADO CON MAQUINARIA m3 270.20 10.98 2,966.80 2,966.80 2,966.80
04.03 CORTE ROCA FIJA CON MAQUINARIA m3 513.00 44.64 22,900.32 22,900.32 22,900.32
04.07 RELLENO CON MATERIAL PROPIO C/EQUIPO m3 206.97 8.83 1,827.55 1,827.55 1,827.55
04.10 ELIMINACION DE MATERIAL EXCEDENTE A MAS DE 5 KM m3 666.90 13.75 9,169.88 9,169.88 9,169.88
07 OBRAS COMPLEMENTARIAS - 278,487.69 278,487.69 278,487.69
07.01 MUROS DE SOSTENIMIENTO DE PIEDRA CON CONCRETO (220 ML) - 166,711.98 166,711.98 166,711.98
07.01.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 495.92 47.11 23,362.79 23,362.79 23,362.79
07.01.02 NIVELACION Y REFINE PARA ESTRUCTURA m2 340.57 8.81 3,000.42 3,000.42 3,000.42
07.01.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 475.83 49.71 23,653.51 23,653.51 23,653.51
07.01.04 CONCRETO CICLOPEO C-175 + 70% PG m3 381.13 203.08 77,399.88 77,399.88 77,399.88
07.01.05 RELLENO COMPACTADO CON MATERIAL PROPIO EN ESTRUCTURAS m3 624.43 62.93 39,295.38 39,295.38 39,295.38
07.02 MUROS DE CONTENCION (180 ML) - 111,775.71 111,775.71 111,775.71
07.02.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 216.22 47.11 10,186.12 10,186.12 10,186.12
07.02.02 NIVELACION Y REFINE PARA ESTRUCTURA m2 112.22 8.81 988.66 988.66 988.66
07.02.03 ELIMINACION MATERIAL EXCEDENTE m3 68.20 30.68 2,092.38 2,092.38 2,092.38
07.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO EN ESTRUCTURAS m3 165.86 62.93 10,437.57 10,437.57 10,437.57
07.02.05 SOLADOS CONCRETO DE 4" m2 120.11 17.14 2,058.69 2,058.69 2,058.69
07.02.06 ACERO DE REFUERZO, EN MURO CONTENCION kg 3,948.74 5.14 20,296.52 20,296.52 20,296.52
07.02.07 ENCOFRADO Y DESENCOFRADO DE MURO DE CONTENCIÓN m2 104.87 49.71 5,213.09 5,213.09 5,213.09
07.02.08 CONCRETO C-210 EN MURO DE CONTENCIÓN m3 120.80 500.85 60,502.68 60,502.68 60,502.68
PARTIDAS DEL ADICIONAL CON DEDUCTIVO VINCULANTE

7.03 GAVIONES 32,363.06 32,363.06 32,363.06

7.03.03 RELLENO CON MATERIAL (AFIRMADO) m3 102.60 104.65 10,737.09 10,737.09 10,737.09

7.03.05 GAVION CAJA 5 X 1.0 0 X 1.00 M, MALLA 10 X 12, DIAM 3.4 (ZN - 5AL - MM + PVC) m3 109.20 198.04 21,625.97 21,625.97 21,625.97

TOTAL COSTO DIRECTO 347,715.30 347,715.30 347,715.30


GASTOS GENERALES 8.00% C.D. 27,817.22 27,817.22 27,817.22
UTILIDAD 10.00% C.D. 34,771.53 34,771.53 34,771.53
SUB TOTAL PROGRAMADO MENSUAL SIN IGV 410,304.05 410,304.05 410,304.05
IGV 18.00%SUB-TOTAL 73,854.73 73,854.73 73,854.73
TOTAL PROGRAMADO MENSUAL 484,158.78 484,158.78 484,158.78
% DE AVANCE MENSUAL 100.00% 100.00%
% DE AVANCE ACUMULADO 100.00% 100.00%
AVANCE PROGRAMADO VS AVANCE EJECUTADO
“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA
OBRA:
CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”
ENTIDAD EJECUTORA: MUNICIPALIDAD DISTRITAL DE SAN MARCOS
CONTRATISTA: CONSORCIO SAN JUAN
ING. RESIDENTE: ING. WILSON LEYVA VASQUEZ
ING. SUPERVISOR: ING. BILLY RONALD MEJIA GARCIA
MONTO CONTRATADO: S/. 484,158.78

PORCENTAJES DE AVANCE PROGRAMADO VS AVANCE EJECUTADO

110%

100%
100.00%

90%

80%
AVANCE MENSUAL ACUMULADO (%)

70%

60%

50%

40%

30%

20%

10%
0.00%

0%
01 JUN 2021 30 JUN 2021

PLAZO DE EJECUCION MENSUAL

MONTOS VALORIZADOS PROGRAMADOS MONTOS VALORIZADOS EJECUTADOS

Periodo: 01 al 30 junio 2021

MONTOS (Inc/ IGV) PORCENTAJES MONTOS (Inc/ IGV) PORCENTAJES


MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES PARCIAL ACUMUL. PARCIAL ACUMUL.
S/. S/. % % S/. S/. % %
01 JUN 2021 0.00 0.00% 01 JUN 2021 0.00 0.00%

30 JUN 2021 484,158.78 484,158.78 100.00% 100.00% 30 JUN 2021 484,158.78 484,158.78 100.00% 100.00%

TOTAL 484,158.78 100.00% TOTAL 484,158.78 100.00%


CALENDARIO VALORIZADO DE AVANCE DE OBRA (PROGRAMADO VS EJECUTADO)

ADICIONAL CON DEDUCTIVO VINCULANTE N° 02

OBRA:
“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA
CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”
CLIENTE: MUNICIPALIDAD DISTRITAL DE SAN MARCOS
LUGAR: C.P MOSNA - SAN MARCOS - HUARI - ANCASH
CONTRATISTAS CONSORCIO SAN JUAN
RESIDENTE: ING. WILSON LEYVA VASQUEZ
SUPERVISOR: ING. BILLY RONALD MEJIA GARCIA

CRONOGRAMA
Item DESCRIPCIÓN Und. Metrado Precio S/. Parcial S/. 23 AL 30 SET. DL 1 AL 31 OCT. 1 AL 30 NOV. 1 AL 21 DIC. DEL 06-30
2019 DEL 2019 DEL 2019 2019 NOVIEMBRE

PARTIDAS DE LA OBRA PRINCIPAL

04 MOVIMIENTO DE TIERRAS 624,808.06 145.18 0.00 0.00 0.00 0.00


04.01 CORTE EN TERRENO CONGLOMERADO CON MAQUINARIA m3 6,445.53 10.98 70,771.92 145.18 0.00 0.00 0.00 0.00
04.03 CORTE ROCA FIJA CON MAQUINARIA m3 7,565.28 44.64 337,714.10 75,587.12 9,038.79 0.00 4,500.00 14,239.36
04.07 RELLENO CON MATERIAL PROPIO C/EQUIPO m3 3,860.14 8.83 34,085.04 30,759.92 0.00 0.00 0.00 0.00
04.10 ELIMINACION DE MATERIAL EXCEDENTE A MAS DE 5 KM m3 13,253.60 13.75 182,237.00 0.00 9,038.79 0.00 0.00 0.00
07 OBRAS COMPLEMENTARIAS 956,068.99 0.00 0.00 0.00 500.00 873.60
07.01 MUROS DE SOSTENIMIENTO DE PIEDRA CON CONCRETO (220 ML) 189,037.17 0.00 0.00 0.00 4,000.00 8,748.56
07.01.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 356.4 47.11 16,790.00 28,617.60 0.00 0.00 0.00 0.00
07.01.02 NIVELACION Y REFINE PARA ESTRUCTURA m2 396.00 8.81 3,488.76 16,209.60 0.00 0.00 0.00 0.00
07.01.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 682.00 49.71 33,902.22 0.00 0.00 0.00 0.00 4,617.20
07.01.04 CONCRETO CICLOPEO C-175 + 70% PG m3 485.10 203.08 98,514.11 1,071.60 1,071.60 178.60 357.20 0.00
07.01.05 RELLENO COMPACTADO CON MATERIAL PROPIO EN ESTRUCTURAS m3 577.50 62.93 36,342.08 1,071.60 1,071.60 178.60 357.20 0.00
07.02 MUROS DE CONTENCION (180 ML) 767,031.82 0.00 0.00 0.00 0.00 0.00
07.02.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 1,722.60 47.11 81,151.69 0.00 0.00 0.00 1,789.38 0.00
07.02.02 NIVELACION Y REFINE PARA ESTRUCTURA m2 594.00 8.81 5,233.14 0.00 0.00 0.00 1,789.38 0.00
07.02.03 ELIMINACION MATERIAL EXCEDENTE m3 37.80 30.68 1,159.70 0.00 0.00 3,000.00 0.00 0.00
07.02.04 RELLENO COMPACTADO CON MATERIAL PROPIO EN ESTRUCTURAS m3 1,684.80 62.93 106,024.46 0.00 0.00 3,000.00 0.00 0.00
07.02.05 SOLADOS CONCRETO DE 4" m2 594 17.14 10,181.16 0.00 0.00 0.00 0.00 248,333.88
07.02.06 ACERO DE REFUERZO, EN MURO CONTENCION kg 32,875.20 5.14 168,978.53 0.00 0.00 0.00 0.00 1,104.60
07.02.07 ENCOFRADO Y DESENCOFRADO DE MURO DE CONTENCIÓN m2 1,512.00 49.71 75,161.52 0.00 0.00 0.00 0.00 24,534.97
07.02.08 CONCRETO C-210 EN MURO DE CONTENCIÓN m3 637.20 500.85 319,141.62 0.00 0.00 0.00 0.00 42,634.41
PARTIDAS DEL ADICIONAL CON DEDUCTIVO VINCULANTE 0.00 0.00 0.00 0.00 71,479.80
7.03 GAVIONES 98,085.61 0.00 0.00 0.00 0.00 55,451.20
7.03.03 RELLENO CON MATERIAL (AFIRMADO) m3 407.40 104.65 42,634.41 0.00 0.00 0.00 0.00 34,155.80
CALENDARIO VALORIZADO DE AVANCE DE OBRA (PROGRAMADO VS EJECUTADO)

ADICIONAL CON DEDUCTIVO VINCULANTE N° 02

OBRA:
“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA
CENTRO, EN EL CENTRO POBLADO SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”
CLIENTE: MUNICIPALIDAD DISTRITAL DE SAN MARCOS
LUGAR: C.P MOSNA - SAN MARCOS - HUARI - ANCASH
CONTRATISTAS CONSORCIO SAN JUAN
RESIDENTE: ING. WILSON LEYVA VASQUEZ
SUPERVISOR: ING. BILLY RONALD MEJIA GARCIA

CRONOGRAMA
Item DESCRIPCIÓN Und. Metrado Precio S/. Parcial S/. 23 AL 30 SET. DL 1 AL 31 OCT. 1 AL 30 NOV. 1 AL 21 DIC. DEL 06-30
2019 DEL 2019 DEL 2019 2019 NOVIEMBRE

7.03.05 GAVION CAJA 5 X 1.0 0 X 1.00 M, MALLA 10 X 12, DIAM 3.4 (ZN - 5AL - MM + PVC) m3 280.00 198.04 55,451.20 0.00 0.00 0.00 0.00 11,573.10

TOTAL COSTO DIRECTO 347,715.30 #REF! #REF! #REF! #REF! #REF!


GASTOS GENERALES 8.00% C.D. 27,817.22 #REF! #REF! #REF! #REF! #REF!
UTILIDAD 10.00% C.D. 34,771.53 #REF! #REF! #REF! #REF! #REF!
SUB TOTAL PROGRAMADO MENSUAL SIN IGV 410,304.05 #REF! #REF! #REF! #REF! #REF!
IGV 18.00%SUB-TOTAL 410,304.05 #REF! #REF! #REF! #REF! #REF!
TOTAL PROGRAMADO MENSUAL 484,158.78 #REF! #REF! #REF! #REF! #REF!
% DE AVANCE MENSUAL #REF! #REF! #REF! #REF! #REF!
% DE AVANCE ACUMULADO #REF! #REF! #REF! #REF! #REF!
HOJA DE METRADOS

“CREACIÓN DE LOS SERVICIOS DE TRANSITABILIDAD A NIVEL DE TROCHA CARROZABLE DESDE


OBRA: SHIRAUCRO – AÑAS POTRERO – RANRACUTA, RAYANPATAC – MOSNA CENTRO, EN EL CENTRO POBLADO
SANTA CRUZ DE MOSNA, DISTRITO DE SAN MARCOS – HUARI – ANCASH”

CLIENTE: MUNICIPALIDAD DISTRITAL DE SAN MARCOS

LUGAR: C.P MOSNA - SAN MARCOS - HUARI - ANCASH


EMPRESA
CONSORCIO SAN JUAN
EJECUTORA.
RESIDENTE: ING. VICENTE BARRERA BULNES
M
SUPERVISOR: ING. BILLY RONALD MEJIA GARCIA E
T

O
AVANCE ACTUALC
ITEM DESCRIPCION UND METRADO T
METRADO

01 OBRAS PROVISIONALES ###

01.02 CERCO PROVISIONAL m 250.00 Err:509

02 SEGURIDAD Y SALUD ###

02.01 ELAB, IMPLEM Y ADMINIS. DEL PLAN DE SEGURIDAD Y SALUD EN EL TRAB glb 1.00 Err:509

02.02 EQUIPOS DE PROTECCIÓN INDIVIDUAL glb 1.00 Err:509

02.03 EQUIPOS DE PROTECCIÓN COLECTIVA glb 1.00 Err:509

02.05 CAPACITACIÓN EN SEGURIDAD Y SALUD glb 1.00 Err:509


03 TRABAJOS PRELIMINARES ###

03.02 TOPOGRAFÍA Y GEOREFERENCIACIÓN EN CARRETERAS km 2.00 270.20

03.03 TRAZO, NIVELACIÓN Y REPLANTEO EN OBRAS COMPLEMENTARIAS m2 2,300.00 Err:509

03.04 TRABAJOS PREVENTIVOS DE SEGURIDAD m 360.00 Err:509

04 MOVIMIENTO DE TIERRAS ###

04.02 CORTE EN ROCA SUELTA (PERF. Y DISPARO) CON MAQUINARIA m3 699.20 513.00

04.03 CORTE ROCA FIJA CON MAQUINARIA m3 7,565.28 Err:509

04.08 TRASPORTE DE PIEDRA PARA ENROCADO R=240 m3/día m3 468.00 0.00

04.09 ACOMODO DE PIEDRA EN ENROCADO R=120 m3/día m3 468.00 475.83

05 OBRAS DE ARTE ###


06 PUENTE DE ACERO Y CONCRETO ###

06.03 OBRAS DE CONCRETO ARMADO ###

06.03.03 CONCRETO C-210 PARA ZAPATAS m3 110.63 Err:509

06.03.06 CONCRETO C=210 EN PANTALLA Y ALEROS m3 48.10 Err:509

06.03.08 ACERO DE REFUERZO EN CAJUELAS kg 3,015.76 Err:509

06.03.09 ENCOFRADO Y DESENCOFRADO EN CAJUELAS m2 84.8 Err:509


06.04 FALSO PUENTE ###
06.04.01 MUROS DE PIEDRA C:H 1:8 + 70% PG m3 57.60 Err:509

07 OBRAS COMPLEMENTARIAS ###

07.02 MUROS DE CONTENCION (180 ML) ###

07.02.01 EXCAVACION NO CLASIFICADA PARA ESTRUCTURAS m3 1,722.60 Err:509

07.02.02 NIVELACION Y REFINE PARA ESTRUCTURA m2 594.00 Err:509

07.02.05 SOLADOS CONCRETO DE 4" m2 594 Err:509

07.02.06 ACERO DE REFUERZO, EN MURO CONTENCION kg 32,875.20 Err:509

07.02.07 ENCOFRADO Y DESENCOFRADO DE MURO DE CONTENCIÓN m2 1,512.00 Err:509

12 FLETE ###

12.02 FLETE RURAL DE MATERIALES VARIOS glb 1.00 Err:509

También podría gustarte