Está en la página 1de 1

PRESUPUESTO TOTAL DE OBRA

PLAN PARA LA
SEGURIDAD Y PLAN DE PLAN DE
OBRAS TRABAJOS MOVIMIENTO DE VIGILANCIA,
DESCRIPCION SALUD EN EL ENROCADO MONITOREO MONITOREO
PROVISIONALES PRELIMINARES TIERRAS PREVENCION DE COVID-
TRABAJO ARQUELOGICO AMBIENTAL
19 EN EL TRABAJO
COSTO DIRECTO S/ 92,470.55 S/ 187,248.68 S/ 22,562.50 S/ 2,828,374.97 S/ 12,801,153.70 S/ 63,000.00 S/ 193,181.67 S/ 199,743.28
GASTOS GENERALES 10.00% C.D S/ 9,247.06 S/ 18,724.87 S/ 2,256.25 S/ 282,837.50 S/ 1,280,115.37 S/ 6,300.00 S/ 19,318.17 S/ 19,974.33
UTILIDAD 9.46% C.D S/ 8,746.14 S/ 17,710.53 S/ 2,134.03 S/ 267,515.99 S/ 1,210,770.60 S/ 5,958.72 S/ 18,271.69 S/ 18,892.30
SUB TOTAL S/ 110,463.74 S/ 223,684.08 S/ 26,952.78 S/ 3,378,728.45 S/ 15,292,039.67 S/ 75,258.72 S/ 230,771.53 S/ 238,609.91
I.G.V. 18.00% S/ 19,883.47 S/ 40,263.13 S/ 4,851.50 S/ 608,171.12 S/ 2,752,567.14 S/ 13,546.57 S/ 41,538.87 S/ 42,949.78
PRESUPUESTO TOTAL S/ 130,347.21 S/ 263,947.21 S/ 31,804.28 S/ 3,986,899.58 S/ 18,044,606.82 S/ 88,805.29 S/ 272,310.40 S/ 281,559.70
VALOR CONTRACTUAL S/ 23,100,280.49
SUPERVISION S/ 704,181.30
EXPEDIENTE TECNICO S/ 149,680.28
CAPACITACION S/ 28,320.00
GESTION DEL PROYECTO S/ 404,740.00
TOTAL S/ 24,387,202.07