Calculo-Muro-de-Contencion
Calculo-Muro-de-Contencion
DATOS:
A GEOMETRIA DEL MURO
D FACTOR DE SEGURIDAD A
E SOBRECARGA ZAPATA d
1.- PREDIMENSIONAMIENTO:
a = 20 a 30 → Asumido = 0.30 m
b = H H
a
12 10
b = 6.70 6.70
ó
12 10
B = 0.5 H a 0.8 H
B = 0.5 6.70 ó 0.8 6.70
c = 1
B - 1/2 b 1.20
3
c = 1.20 → Asumido = 1.20 m
= b =
= b+5
d = = b + 10 0.70 → Asumido = 0.70 m
= b +15
= b + 20
e = B-c-b
4.50 - 1.20 - 0.60
e = 2.70 m
0.30
W1
W3
6.00
6.70 F1
W5 Empuje
Activo
W2
h F2
W4 2
Empuje
Pasivo 1.20 0.3 0.30 2.70 H ⅓
W6 0.70
4.50
O g . H
Punto
de Volteo
2
W5 = 2,400 kg/cm2 x 0.3 x 2.60 x 1.00 = 1,872 kg
Ka = tg ² ( 45 º - Ø )
2
Ka = tg ² ( 45 º - 30 ) = 30.00 0.5236
2
Ka = 0.333
F1 = 1,000 Kg/cm2
UBICACIÓN : F 1
F1 = H 6.00
2 = 2 = 3 m
F2 = ( vol ) D . P
F2 = [ 1 (ү H ) (H) x 1.00 ] Ka
2
F2 = 1 ү h² x 1.00 x Ka
2
6.76
F2 = 1 30 kg/cm2 2.60 ² 1.00 0.333
2
F2 = 33.80 Kg
UBICACIÓN : F 2
F2 = 1 H
3
1F2 6.00 = = 2 m
3
3.- ESTABILIDAD DEL MURO AL VOLTEO
∑ MFy
Fs V =
∑ MFh ≥ 1.75
W3 12 1.650 19.31
F2 34 2.00 67.60
26,745.89 kg/m
Fs V = 8.72 > 1.75 OK CUMPLE
3,067.60 kg/m
ų∑ Fv ƒ Empuje
Fs D =
∑ Fh
≥ 1.25
= ƒ Rozamiento
ų = tg Ø ≤ 0.60
0.58 12,090
Fs D = 6.75 > 1.25 OK CUMPLE
1,033.80
26,745.89 - 3,067.60
x =
12,090
x = 1.96
R
£
e 4.50
2.25 2.25
1.50 1.50 1.50
2.25
x = 1.96
OK CUMPLE
2ro EXENTRICIDAD
B
e = - x
2
e = Exentricidad
R
£
e 4.50
B/3 B/3 B/3
B/6 B/6
4.50
e = - 1.96 e = 0.292
2
B 4.50
6 = = 0.75
6
3ro CALCULO DE LA PRESION ACTUANTE
ΣFy 6 e
q = ( 1 ± )
A B B
12,090 6 0.292
q = 1.00 4.50 ( 1 ± )
4.50
q = 2,686.73 1 ± 0.3887293
W1
1,500 kg
W3
12 kg
W2
211 kg
q1 = 0.06 kg/cm2
q2 = 0.29 kg/cm2
q3= 0.70 kg/cm2
qmax = 0.37 kg/cm2
q = w1 + w2 + w3 q = 1,500 + 211 + 12
A talón 2.70 x 1.00
4.1.- EN LA PANTALLA
1.00 m
DIAGRAMA DE PRESIONES
q = tn-m
F1
6.00
F2
Y1
Y2
a) MOMENTO FLECTOR
En
F1 = ( q.h.1.00 m) . ka
F1 = 1,116.67 kg.
h 6.70
y1 = = = 3.35
2 2
y1 = 3.35 m
En
F2 = 1 ( g .h². 1.00m) Ka
2
6.76
F2 = 1 30 2.60 17 1.00 0.333 = 33.80 kg
2
F2 = 0.03 tn-m
1 1
y2 = 3 h y2 = 3 6.00
y2 = 2.00 m
MOMENTO ULTIMO
b) FUERZA CORTANTE
V = F1 + F2
V = 1,116.67 + 33.80
V = 1,150.47 kg
V = 1,150.47
µ = V b = 1.00
b d d = 0.56
1,150.47
µ = = 0.21
100 56
µ = 0.21 kg/cm2
µc = Ø 0.53 √ f 'c
Empotramiento
a) MOMENTO FLECTOR
En:
F1 = 0.70 x 1.20 x 1.00
F1 = 8,371 Kg
X1 = 1.20 =
2 0.60 m
En
F2 = 1 120 -0.32 100 = -1946.71 Kg
2
F2 = -1946.71 kg
X2 = 2 1.20 =
3
X2 = 0.80 mt
MOMENTO MAXIMO
V = F1 + F2
V = 8,371 + -1946.71
V = 6,424.08 kg
ų = V
b d
ų = 6,424.08
120 56
ų = 0.96 kg/cm2
Vc = Ø 0.53 √ f'c
Vc = 6.53
4.3.- EN EL TALON F1
X1
q1 = 0.06 kg/cm2
2.70 h = 0.70
0.13 kg/cm2
F1 = 1,722.30 kg
X1 = 2.70
2
X1 = 1.35 m
F2 = 4,434.27 kg
X2 = 2.70
2
X2 = 1.35 m
F3 = 1,691.95 kg
X3 = 1 2.70
3
X3 = 0.90 m
a. MOMENTO FLECTOR
M = (F2.X2)+(F3.X3)-(F1.X1)
M = 9,834.1 kg/cm2
b. FUERZA CORTANTE
>
V = F1 - F2 - F3
µ = V µ = -4,403.92
b d 100 56
µ = -0.79 kg/cm2
Vc = Ø 0.53 √ f'c
210
Vc = 0.9 0.53 14.491
2 As h 1 As h
3 3
Mu
Ku = b d² As = ρ b d
Mu = 8.6
Mu = 32,753 kg/m
Acero principal:
As = ρ b d
S = 1.27
x 100
7.60
Asumimos un Ø ≤ 5/8"
As min = 0.0020 b d
1) Arriba: (h = 0.3 )
a) Cara Interior
1 = 1
Ash 6.00 = 2.00 cm2/m
3 3
S = 1.27
x 100
6.33
b) Cara Exterior:
2 = 2
Ash 6 = 4.00 cm2/m
3 3
S = 1.27
x 100
5.07
2) Cara Intermedia ( h= 60 + 30 ) = 45 cm
2
As min (Horizontal) = 0.0020 100 45 = 9.00 cm2
a) Cara Interior:
1 = 1
Ash 9.00 = 3.00 cm2/m
3 3
S = 1.98
x 100
9.90
b) Cara Exterior:
2 = 2
Ash 9.0 = 6.00 cm2/m
3 3
S = 1.27
x 100
6.33
a) Cara Interior:
1 = 1
Ash 12.00 = 4.00 cm2/m
3 3
S = 1.27
x 100
5.07
b) Cara Exterior:
2 = 2
Ash 12.0 = 8.00 cm2/m
3 3
S = 1.27
x 100
8.87
Resumen
Acero Horizontal
Para Exterior:
Entonces:
C.I = Ø 5/8 @ 0.177 ≈ 0.20
C.E = Ø 1/2 @ 0.200 ≈ 0.25
5 DISEÑO DE LA ZAPATA.
a) MOMENTO ULTIMO
b = 1.00 mt
d = hz - (r + Ø vlla)
2
d = 70 - 7.5 + 1.58
2
d = 61.71
Acero principal:
As = ρ b d
Acero mínimo:
ZAPATA POSTERIOR
b = 1.00 mt
d = 61.71
Acero principal:
As = ρ b d
S = 1.98
x 100
7.92
S = 1.98
x 100
13.86
0.5 t = 0.5 70 = 35
S ≤ 45 cm
SE TOMA EL MENOR:
1.- PANTALLA:
* ACERO VERTICAL
Φ
CLASES DE TERRENOS DE CIMENTACION Y CONSTANTES DE DISEÑO
Clases de Esfuerzo ###
Coeficiente de
terrenos permisible del friccion para###
terreno
paracimentación ###
Desplazamiento
s t = (kg/cm2) ų ###
Roca dura ###
uniforme con 10 0.7 ###
pocas grietas ###
ROCOSO Roca dura ###
con muchas 6 0.7 ###
fisuras
Roca blanda 3 0.7
ESTRATO Densa 6 0.6
DE GRAVA No densa 3 0.6
TERRENO Densa 3 0.6
ARENOSO Media 2 0.5
TERRENO Muy dura 2 0.5
COHESIVO Dura 1 0.45
ARCILLAS Media 0.5 0.45
CONSISTENCI
TIPO DE SUELO
A Φ
Arena gruesa o arena Compacto 40º
con grava Suelto 35º
Arena media Compacto 40º
Arena limosa fina o Suelto 30º
limo arenoso Compacto 25º
Suelto 30º
Limo uniforme
Compacto 25º
Arcilla - Limo Suave a mediano 20º
Arcilla limosa Suave a mediano 15º
Arcilla Suave a mediano 0 - 10º
TIPO DE TERRENO g =(kg/m3) Φ
Arcilla suave 1440 a 1920 0º a 15º
Arcilla mediana 1600 a 1920 15º a 30º
Limo seco suelto 1600 a 1920 27º a 30º
Limo denso 1760 a 1920 30º a 35º
Arena suelta y grava 1600 a 2100 30º a 40º
Arena densa y grava 1920 a 2100 25º a 35º
Arena suelta y bien graduada 1840 a 2100 33º a 35º
Arna densa y bien graduada 1920 a 2100 42º a 46º
PESO ESP. Y ANG DE FRIC INTERNA DE ALGUNOS TIPOS DESUELOS
Nº Nº 3 y es retenido en lamalla Nº
% de Matrial que pasa la % de Matrial que pasa la malla
GW
>50 % pasa
GRAVAS
la malla 3" y GP
es retenido
Malla Nº 4 GM
GC
200
SW
>50 % pasa
ARENAS
la malla Nº 6 SP
y es retenido SM
Malla Nº 200
SC
LIMITE
CL
LIMOS Y ARCILLAS
LIQUIDO ML
< 50%
OL
200 >50%
CH
LIMITE MH
malla
LIQUIDO
> 50% OH
PI
1,500
17482.323
17.482323
10,590
17.10
16.24
0.86
0.75
3
3/8" 0
1/2" 1
5/8" 2
3/4" 3
1" 4
0 3/8
1 1/2
2 5/8
3 3/4
4 1
0.5
1
1/2" 1
5/8" 2
3/4" 3
1" 4
1 1/2
2 5/8
3 3/4
4 1
0.5
2
0.5
2
3/8" 1
1/2" 2
5/8" 3
3/4" 4
1" 5
1 3/8
2 1/2
3 5/8
4 3/4
5 1
3/8" 1
1/2" 2
0.625 5/8" 3
3 3/4" 4
1" 5
1 3/8
2 1/2
3 5/8
4 3/4
5 1
0.5
2
3/8" 1
1/2" 2
5/8" 3
3/4" 4
1" 5
1 3/8
2 1/2
3 5/8
4 3/4
5 1
3/8" 1
1/2" 2
0.5 5/8" 3
2 3/4" 4
1" 5
1 3/8
2 1/2
3 5/8
4 3/4
5 1
0.5
2
3/8" 1
1/2" 2
5/8" 3
3/4" 4
1" 5
1 3/8
2 1/2
3 5/8
4 3/4
5 1
3/8" 1
1/2" 2
5/8" 3
3/4" 4
1" 5
1 3/8
2 1/2
3 5/8
4 3/4
5 1
0.625
2
1/2" 1
5/8" 2
3/4" 3
1" 4
1 1/2
2 5/8
3 3/4
4 1
0.625
2
0.625 1/2" 1
2 5/8" 2
3/4" 3
1" 4
1 1/2
2 5/8
3 3/4
4 1
1/2" 1
5/8" 2
3/4" 3
1" 4
1 1/2
2 5/8
3 3/4
4 1
0.30
NIVEL DE RELLENO
6.00
Ø 3/4 @ 0.36 0.36 0.36 0.36
6.70 Ø 1/2 @ 0.18 Intercalado
Ø 3/4 @ 0.18
Ø 3/4 @ 0.180
NIVEL ACTUAL
2.60 0.180 0.180 0.180 0.180 0.180 0.180
Ø 5/8 @ 0.25
1.00
0.70
0.30 0.30 0.30
4.50
Proyecto: MEJORAMIENTO DE LA CARRETERA POMATA -
YOROHOCO
Lugar: Propiet:
HP
POMATA GOBIERNO REGIONAL DE PUNO
RECUBRIMIENTOS:
Pantalla 4 cm
Zapata 7.5
Cara Interior 7.5 cm
Cara superior 5 cm