PARTIDAS 

PARA DESTAJO
HOJA DE TAREO POR DESTAJO
CONVENIO: 032‐2021‐JUN/VMVU/PNVR
PERIODO: 20/10/2021 AL 15/11/2021

N° DE NOMBRE Y DOCUMENTO DE AVANCE ACTUAL DEL                


FECHA PARTIDAS Y/O SUBPARTIDAS AVANCE ANTERIOR ACUMULADO  AVANCE ACUMULADO SALDO
ORDEN APELLIDOS IDENTIFICACION UND METRADO PARCIAL 20/10/2021 ‐ 15/11/2021
JULIO MIGUEL  MET. VALOR. % MET. VALOR. % MET. VALOR. % MET. VALOR. %
47092882
AGUIRRE  OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y SALUD
   TRAZO NIVELES Y REPLANTEO PRELIMINAR
      LIMPIEZA, TRAZOS, NIVELES  (REPLANTEO PRELIMINAR) m2 332.85 386.08 332.85 386.08 100.00% 0.00 0.00 0.00% 332.85 386.08 100.00% 0.00 0.00 0.00%
OBRAS DE CONCRETO SIMPLE
   CIMIENTO
SOLADO 1:10, E=10cm m2 20.48 161.36 20.48 161.36 100.00% 0.00 0.00 0.00% 20.48 161.36 100.00% 0.00 0.00 0.00%
CIMIENTO CORRIDO DE  CONCRETO CICLOPEO MEZCLA  CEMENTO HORMIGON 1:10 + 50% P.G. m3 20.97 583.92 20.97 583.92 100.00% 0.00 0.00 0.00% 20.97 583.92 100.00% 0.00 0.00 0.00%
   SOBRECIMIENTO
      SOBRECIMIENTOS MEZCLA CEMENTO‐HORMIGON 1:8 + 30% PM m3 12.76 668.64 12.76 668.64 100.00% 0.00 0.00 0.00% 12.76 668.64 100.00% 0.00 0.00 0.00%
      ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO h=0.35m m2 133.11 1,569.44 133.11 1569.44 100.00% 0.00 0.00 0.00% 133.11 1,569.44 100.00% 0.00 0.00 0.00%
CONCRETO ARMADO
   COLUMNAS
      CONCRETO COLUMNAS  F´c = 175 kg/cm2  m3 16.99 654.32 16.77 645.87 98.71% 0.22 8.45 1.29% 16.99 654.32 100.00% 0.00 0.00 0.00%
      ENCOFRADO Y DESENCOFRADO EN COLUMNAS m2 127.15 1,398.64 116.19 1278.07 91.38% 10.96 120.57 8.62% 127.15 1,398.64 100.00% 0.00 0.00 0.00%
      ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 COLUMNAS kg 1,463.04 965.60 1463.04 965.60 100.00% 0.00 0.00 0.00% 1,463.04 965.60 100.00% 0.00 0.00 0.00%
   VIGAS
      CONCRETO VIGAS f'c=175 kg/cm2 m3 12.58 605.84 12.58 605.84 100.00% 0.00 0.00 0.00% 12.58 605.84 100.00% 0.00 0.00 0.00%
      ENCOFRADO Y DESENCOFRADO EN VIGAS m2 131.09 2,163.04 131.09 2163.04 100.00% 0.00 0.00 0.00% 131.09 2,163.04 100.00% 0.00 0.00 0.00%
      ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 PARA VIGAS kg 715.20 522.08 715.20 522.08 100.00% 0.00 0.00 0.00% 715.20 522.08 100.00% 0.00 0.00 0.00%
MUROS
      MURO DE LADRILLO MEDIDAS SEGUN PLANO, A= 10cm m2 615.65 7,584.72 590.56 7275.73 95.93% 25.08 308.99 4.07% 615.65 7,584.72 100.00% 0.00 0.00 0.00%
      SUMINISTRO E INSTALACION DE POLIESTIRENO DE 1"  DENSIDAD 10 m2 436.21 1,343.52 436.21 1343.52 100.00% 0.00 0.00 0.00% 436.21 1,343.52 100.00% 0.00 0.00 0.00%
      BRUÑAS DE MUROS DE LADRILLO m 2,279.70 3,328.32 1722.33 2514.57 75.55% 557.37 813.75 24.45% 2,279.70 3,328.32 100.00% 0.00 0.00 0.00%
REVOQUES
      BOTA AGUA EN VANO DE VENTANA CON CORTA GOTERA. CON MORTERO 1:4 E= 1.5 CM m2 5.62 98.16 0.00 0.00 0.00% 5.62 98.16 100.00% 5.62 98.16 100.00% 0.00 0.00 0.00%
ENLUCIDO DE YESO
      ENLUCIDO DE YESO EN MURO DE LADRILLO m2 492.30 6,774.00 0.00 0.00 0.00% 492.30 6,774.00 100.00% 492.30 6,774.00 100.00% 0.00 0.00 0.00%
      DERRAMES DE VANOS CON YESO E=1.5CM m 232.64 1,616.88 0.00 0.00 0.00% 232.64 1,616.88 100.00% 232.64 1,616.88 100.00% 0.00 0.00 0.00%
PISOS 
   ACERO DE TEMPERATURA DE 6MM kg 162.88 104.24 101.80 65.15 0.00% 61.08 39.09 100.00% 162.88 104.24 100.00% 0.00 0.00 0.00%
   PISO DE CEMENTO PULIDO E:4" ACAB. CON OCRE INC. BRUÑADO m2 159.20 1,564.96 99.50 978.10 0.00% 59.70 586.86 100.00% 159.20 1,564.96 100.00% 0.00 0.00 0.00%
VEREDAS
      VEREDA DE CONCRETO SIMPLE F'C=140 KG/CM2 E= 10 CM ACABADO FROTACHADO INCLUYE BRUÑADO m2 19.85 185.84 0.00 0.00 0.00% 19.85 185.84 100.00% 19.85 185.84 100.00% 0.00 0.00 0.00%
      ENCOFRADO Y DESENCOFRADO  DE VEREDAS m2 5.60 115.60 0.00 0.00 0.00% 5.60 115.60 100.00% 5.60 115.60 100.00% 0.00 0.00 0.00%
ZOCALOS Y CONTRAZOCALOS
      ZOCALO DE CEMENTO SOBRE MURO EXTERIOR H=60CM INC/BRUÑAS m2 91.45 1,476.08 0.00 0.00 0.00% 91.45 1,476.08 100.00% 91.45 1,476.08 100.00% 0.00 0.00 0.00%
      CONTRAZOCALO DE MADERA CON RODON, DE 5.80 CM X 1.90 CM X 2.40 M m 134.32 208.16 0.00 0.00 0.00% 134.32 208.16 100.00% 134.32 208.16 100.00% 0.00 0.00 0.00%
INSTALACIONES ELECTRICAS 
      INSTALACION ELECTRICA EN MÓDULO  glb 8.00 617.12 0.00 0.00 0.00% 8.00 617.12 100.00% 8.00 617.12 100.00% 0.00 0.00 0.00%

TOTAL PRESUPUESTO S/34,696.56 21,727.00 62.62% 12,969.56 37.38% 34,696.56 100.00% 0.00 0.00%