ANALISIS DE PRECIO UNITARIO

CAPUTULO: BASES
ITEM: BASICO DE CONCRETO DE 3000 PSI UNIDAD: M3

I. EQUIPO
DESCRIPCIÓN UND CAN TARIFA/HORA RENDIMIENTO VR. UNITARIO
Herramienta menor 10% M.O 4,796.43
MEZCLADORA DIA 1 65,000.0 2.8 23,214.29 SUBTOTAL
28,010.71
II. MATERIALES EN OBRA
DESCRIPCIÓN UNIDAD PRECIO UNITARIO CANTIDAD VR.UNITARIO
ARENA M3 38,000.0 0.56 21,280.00
CEMENTO KG 560.0 350.00 196,000.00
TRITURADO M3 65,000.0 0.84 54,600.00

DESPERDICIO 5% 13,594.00 SUB TOTAL


285,474.00
III. TRANSPORTES
CONCEPTO M3-TON-KM TARIFA CAN VOL-PES VR. UNITARIO
CEMENTO 10 1,100.0 0.35 3,850.00
ARENA 10 1,100.0 0.56 6,160.00
TRITURADO 10 1,100.0 0.84 9,240.00 SUB TOTAL
19,250.00
IV. MANO DE OBRA
TRABAJADOR JORNAL %PRES JORNAL TOTAL REND. VR. UNITARIO
OFICIAL 45,000.00 0.7 76,500.0 2.8 27,321.43
AYUDANTE 34,000.00 0.7 57,800.0 2.8 20,642.86

SUB TOTAL
47,964.29
TOTAL COSTO DIRECTO 380,699

PRECIO UNITARIO TOTAL $ 380,699.00

ANALISIS DE PRECIO UNITARIO

CAPITULO: BASES
ITEM: CORTE FIGURADO Y AMRRE DE ACERO DE REFUERZO DE 60000 PSI UNIDAD: KG

I. EQUIPO
DESCRIPCIÓN UND CAN TARIFA/HORA RENDIMIENTO VR. UNITARIO
Herramienta menor 10% M.O 67.15
TRONZADORA DIA 1 60,000.0 200 300.00 SUBTOTAL
367.15
II. MATERIALES EN OBRA
DESCRIPCIÓN UNIDAD PRECIO UNITARIO CANTIDAD VR.UNITARIO
ALAMBRE NEGRO KG 8,500.0 0.10 850.00
ACERO CORRUGADA KG 5,975.0 1.00 5,975.00

DESPERDICIO 5% 341.25 SUB TOTAL


7,166.25
III. TRANSPORTES
CONCEPTO M3-TON-KM TARIFA CAN VOL-PES VR. UNITARIO
ACERO 10 1,100.0 0.01 110.00

SUB TOTAL
110.00
IV. MANO DE OBRA
TRABAJADOR JORNAL %PRES JORNAL TOTAL REND. VR. UNITARIO
OFICIAL 45,000.00 0.7 76,500.0 200 382.50
AYUDANTE 34,000.00 0.7 57,800.0 200 289.00

SUB TOTAL
671.50
TOTAL COSTO DIRECTO 8,315

PRECIO UNITARIO TOTAL $ 8,314.90


ANALISIS DE PRECIO UNITARIO

CAPITULO: BASES
ITEM: CONCRETO CICLOPEO DE 3000 PSI UNIDAD: M3

I. EQUIPO
DESCRIPCIÓN UND CAN TARIFA/HORA RENDIMIENTO VR. UNITARIO
Herramienta menor 10% M.O 3,357.50
SUBTOTAL
3,357.50
II. MATERIALES EN OBRA
DESCRIPCIÓN UNIDAD PRECIO UNITARIO CANTIDAD VR.UNITARIO
CONCRETO DE 30000 PSI M3 380,699.0 0.60 228,419.40
PIEDRA TAMA MAX 4 " M3 28,600.0 0.40 11,440.00

DESPERDICIO 5% 11,992.97 SUB TOTAL


251,852.37
III. TRANSPORTES
CONCEPTO M3-TON-KM TARIFA CAN VOL-PES VR. UNITARIO
PIEDRA 10 1,100.0 0.4 4,400.00

SUB TOTAL
4,400.00
IV. MANO DE OBRA
TRABAJADOR JORNAL %PRES JORNAL TOTAL REND. VR. UNITARIO
OFICIAL 45,000.00 0.7 76,500.0 4 19,125.00
AYUDANTE 34,000.00 0.7 57,800.0 4 14,450.00

SUB TOTAL
33,575.00
TOTAL COSTO DIRECTO 293,185

PRECIO UNITARIO TOTAL $ 293,184.87