1) NUEVO PUNTO DE DISEÑO PARA UNA CARGA DE 397kW,22,9kV PARA EL TABLERO GENERAL
PROYECTO: HOTEL HAMPTON
ΔV = K.I.L/1000
ΔV: CAIDA DE TENSION (V)
K: FACTOR DE CAIDA DE TENSION SELECCIÓN DEL INTERRUPTOR ( IEC 60364 )
K= v3(r.cosφ+x.senφTRIFASICO Icarga ≤ In ≤ In (cable)
K= 2(r.cosφ+x.senφ) MONOFASICO
L= LONGITUD (m)
N2XOH
TABLEROS M.D.(W) U (V) cosφ n(%) FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) r(ohm/km) x(ohm/km) K ΔV(V) ΔV(%) ∑ΔV(%)
TG-BT 406244 380 0.85 1.00 3 726.15 907.68 3x 1000 2 240 1050 6 0.084 0.137 0.249 0.68 0.18% 0.18%
TTA-3 (TC-PR1) 12433 380 0.80 1.00 3 23.61 29.52 3x 40 1 10 95 48 1.995 0.166 2.937 4.16 1.09% 1.27%
TTA-4 (TF-MO) 24478 380 0.80 1.00 3 46.49 58.11 3x 60 1 16 125 33 1.247 0.152 1.886 3.62 0.95% 1.13%
TTA-5 (TC-PR2 12433 380 0.80 1.00 3 23.61 29.52 3x 40 1 10 95 72 1.995 0.166 2.937 6.24 1.64% 1.82%
TTA-P (TGE) 369138 380 0.80 1.00 3 701.06 876.32 3x 1000 3 120 1140 6 0.167 0.140 0.377 0.66 0.17% 0.35%
LSOH-90
TABLEROS M.D.(W) U (V) cosφ n(%) FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) r(ohm/km) x(ohm/km) K ΔV(V) ΔV(%) ∑ΔV(%)
TGE 369138 380 0.66 0.17% 0.35%
TD-S1 11059 380 0.80 1.00 3 21.00 26.25 3x 40 1 10 62 39 1.995 0.166 2.937 3.01 0.79% 1.14%
TD-S2 10725 380 0.80 1.00 3 20.37 25.46 3x 40 1 10 62 42 1.995 0.166 2.937 3.14 0.83% 1.18%
TD-OF 8437 380 0.80 1.00 3 16.02 20.03 3x 40 1 10 62 39 1.995 0.166 2.937 2.29 0.60% 0.96%
STG-1P 82289 380 0.80 1.00 3 156.28 195.35 3x 200 1 70 203 12 0.286 0.143 0.545 1.28 0.34% 0.69%
TD-11 4400 380 0.80 1.00 3 8.36 10.45 3x 30 1 10 62 3 1.995 0.166 2.937 0.09 0.02% 0.71%
TD-BAR 15756 380 0.80 1.00 3 29.92 37.40 3x 50 1 10 62 18 1.995 0.166 2.937 1.98 0.52% 1.21%
TD-CO 33589 380 0.80 1.00 3 63.79 79.74 3x 100 1 25 107 17 0.798 0.152 1.264 1.71 0.45% 1.14%
TD-LC 3818 380 0.80 1.00 3 7.25 9.06 3x 30 1 10 62 10 1.995 0.166 2.937 0.27 0.07% 0.76%
TF-1P 6631 380 0.80 1.00 3 12.59 15.74 3x 30 1 10 62 21 1.995 0.166 2.937 0.97 0.26% 0.94%
H-107 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 33 3.325 0.166 5.519 1.48 0.67% 1.36%
H-108 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 36 3.325 0.166 5.519 1.61 0.73% 1.42%
H-109 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 33 3.325 0.166 5.519 1.48 0.67% 1.02%
STG-2P 161170 380 0.80 1.00 3 306.09 382.61 3x 400 2 70 406 18 0.286 0.143 0.545 1.88 0.49% 0.85%
TD-21 23667 380 0.80 1.00 3 44.95 56.18 3x 70 1 16 85 2 1.247 0.152 1.886 0.21 0.06% 0.90%
TD-31 23667 380 0.80 1.00 3 44.95 56.18 3x 70 1 16 85 5 1.247 0.152 1.886 0.53 0.14% 0.99%
TD-41 23667 380 0.80 1.00 3 44.95 56.18 3x 70 1 16 85 8 1.247 0.152 1.886 0.85 0.22% 1.07%
TD-51 23667 380 0.80 1.00 3 44.95 56.18 3x 70 1 16 85 11 1.247 0.152 1.886 1.17 0.31% 1.15%
TD-61 23667 380 0.80 1.00 3 44.95 56.18 3x 70 1 25 107 14 0.798 0.152 1.264 0.99 0.26% 1.11%
TD-71 23667 380 0.80 1.00 3 44.95 56.18 3x 70 1 25 107 17 0.798 0.152 1.264 1.21 0.32% 1.16%
TD-81 23667 380 0.80 1.00 3 44.95 56.18 3x 70 1 25 107 20 0.798 0.152 1.264 1.42 0.37% 1.22%
TD-AZ 17716 380 0.80 1.00 3 33.65 42.06 3x 50 1 10 62 24 1.995 0.166 2.937 2.96 0.78% 1.63%
TF-SH 4352 380 0.80 1.00 3 8.26 10.33 3x 30 1 10 62 24 1.995 0.166 2.937 0.73 0.19% 1.04%
TG-UPS 13800 380 0.80 1.00 3 26.21 32.76 3x 40 1 10 62 15 1.995 0.166 2.937 1.44 0.38% 0.73%
UPS-S1 7650 380 0.80 1.00 1 25.16 31.46 3x 40 1 6 44 3 3.325 0.166 5.519 0.52 0.14% 0.87%
UPS-11 4200 380 0.80 1.00 1 13.82 17.27 3x 30 1 6 44 8 3.325 0.166 5.519 0.76 0.20% 0.93%
UPS-AZ 1950 380 0.80 1.00 1 6.41 8.02 3x 30 1 6 44 27 3.325 0.166 5.519 1.19 0.31% 1.05%
TC-CH1 106300 380 0.80 1.00 3 201.88 252.35 3x 300 1 150 318 81 0.134 0.141 0.332 6.79 1.79% 2.14%
TC-CH2 106300 380 0.80 1.00 3 201.88 252.35 3x 300 1 150 318 81 0.134 0.141 0.332 6.79 1.79% 2.14%
TF-AZ 82474 380 0.85 1.00 3 147.42 191.65 3x 200 1 70 203 72 0.286 0.143 0.552 7.61 2.00% 2.35%
TF-BA 35228 380 0.80 1.00 3 66.90 86.97 3x 100 1 25 107 24 0.798 0.152 1.264 2.64 0.69% 1.05%
TF-ASC-1 7460 380 0.80 1.00 3 14.17 19.84 3x 40 1 16 85 57 1.247 0.152 1.886 2.13 0.56% 0.91%
TF-ASC-2 7460 380 0.80 1.00 3 14.17 19.84 3x 40 1 16 85 57 1.247 0.152 1.886 2.13 0.56% 0.91%
TF-ASC-3 8289 380 0.80 1.00 3 15.74 22.04 3x 40 1 16 85 57 1.247 0.152 1.886 2.37 0.62% 0.98%
PROYECTO: HOTEL HAMPTON
ΔV = K.I.L/1000
ΔV: CAIDA DE TENSION (V)
K: FACTOR DE CAIDA DE TENSION SELECCIÓN DEL INTERRUPTOR ( IEC 60364 )
K= v3(r.cosφ+x.senφTRIFASICO Icarga ≤ In ≤ In (cable)
K= 2(r.cosφ+x.senφ) MONOFASICO
L= LONGITUD (m)
TF-ASC-4 2487 380 0.80 1.00 3 4.72 6.61 3x 30 1 6 44 27 3.325 0.166 4.780 0.85 0.22% 0.58%
PROYECTO: HOTEL HAMPTON
ΔV = K.I.L/1000
ΔV: CAIDA DE TENSION (V)
K: FACTOR DE CAIDA DE TENSION SELECCIÓN DEL INTERRUPTOR ( IEC 60364 )
K= v3(r.cosφ+x.senφTRIFASICO Icarga ≤ In ≤ In (cable)
K= 2(r.cosφ+x.senφ) MONOFASICO
L= LONGITUD (m)
TABLEROS M.D.(W) U (V) cosφ n(%) FASES I (A) Id (A) ITM TERNAS 18 In (cable) (A) L(m) r(ohm/km) x(ohm/km) K ΔV(V) ΔV(%) ∑ΔV(%)
TD-21 23667 380 0.21 0.06% 0.90%
H-201 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 12 3.325 0.166 5.519 0.54 0.24% 1.15%
H-202 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 13 3.325 0.166 5.519 0.58 0.26% 1.17%
H-203 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 21 3.325 0.166 5.519 0.94 0.43% 1.33%
H-204 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 22 3.325 0.166 5.519 0.99 0.45% 1.35%
H-205 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 29 3.325 0.166 5.519 1.30 0.59% 1.49%
H-206 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 33 3.325 0.166 5.519 1.48 0.67% 1.57%
H-207 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 36 3.325 0.166 5.519 1.61 0.73% 1.63%
H-208 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 35 3.325 0.166 5.519 1.57 0.71% 1.61%
H-209 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 32 3.325 0.166 5.519 1.43 0.65% 1.55%
H-210 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 28 3.325 0.166 5.519 1.25 0.57% 1.47%
H-211 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 22 3.325 0.166 5.519 0.99 0.45% 1.35%
H-212 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 21 3.325 0.166 5.519 0.94 0.43% 1.33%
H-213 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 15 3.325 0.166 5.519 0.67 0.31% 1.21%
H-214 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 9 3.325 0.166 5.519 0.40 0.18% 1.08%
H-215 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 9 3.325 0.166 5.519 0.40 0.18% 1.08%
H-216 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 13 3.325 0.166 5.519 0.58 0.26% 1.17%
H-217 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 13 3.325 0.166 5.519 0.58 0.26% 1.17%
H-218 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 10 3.325 0.166 5.519 0.45 0.20% 1.11%
H-219 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 8 3.325 0.166 5.519 0.36 0.16% 1.06%
H-220 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 8 3.325 0.166 5.519 0.36 0.16% 1.06%
H-221 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 13 3.325 0.166 5.519 0.58 0.26% 1.17%
H-222 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 14 3.325 0.166 5.519 0.63 0.29% 1.19%
H-223 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 20 3.325 0.166 5.519 0.90 0.41% 1.31%
H-224 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 20 3.325 0.166 5.519 0.90 0.41% 1.31%
H-225 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 14 3.325 0.166 5.519 0.63 0.29% 1.19%
PROYECTO: HOTEL HAMPTON
ΔV = K.I.L/1000
ΔV: CAIDA DE TENSION (V)
K: FACTOR DE CAIDA DE TENSION SELECCIÓN DEL INTERRUPTOR ( IEC 60364 )
K= v3(r.cosφ+x.senφTRIFASICO Icarga ≤ In ≤ In (cable)
K= 2(r.cosφ+x.senφ) MONOFASICO
L= LONGITUD (m)
TABLEROS M.D.(W) U (V) cosφ n(%) FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) r(ohm/km) x(ohm/km) K ΔV(V) ΔV(%) ∑ΔV(%)
TD-31 23667 380 0.53 0.14% 0.99%
H-301 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 16 3.325 0.166 5.519 0.72 0.33% 1.31%
H-302 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 17 3.325 0.166 5.519 0.76 0.35% 1.33%
H-303 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 25 3.325 0.166 5.519 1.12 0.51% 1.49%
H-304 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 26 3.325 0.166 5.519 1.17 0.53% 1.51%
H-305 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 33 3.325 0.166 5.519 1.48 0.67% 1.66%
H-306 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 37 3.325 0.166 5.519 1.66 0.75% 1.74%
H-307 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 40 3.325 0.166 5.519 1.79 0.81% 1.80%
H-308 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 39 3.325 0.166 5.519 1.75 0.79% 1.78%
H-309 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 36 3.325 0.166 5.519 1.61 0.73% 1.72%
H-310 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 32 3.325 0.166 5.519 1.43 0.65% 1.64%
H-311 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 26 3.325 0.166 5.519 1.17 0.53% 1.51%
H-312 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 25 3.325 0.166 5.519 1.12 0.51% 1.49%
H-313 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 19 3.325 0.166 5.519 0.85 0.39% 1.37%
H-314 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 13 3.325 0.166 5.519 0.58 0.26% 1.25%
H-315 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 13 3.325 0.166 5.519 0.58 0.26% 1.25%
H-316 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 17 3.325 0.166 5.519 0.76 0.35% 1.33%
H-317 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 17 3.325 0.166 5.519 0.76 0.35% 1.33%
H-318 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 14 3.325 0.166 5.519 0.63 0.29% 1.27%
H-319 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 12 3.325 0.166 5.519 0.54 0.24% 1.23%
H-320 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 12 3.325 0.166 5.519 0.54 0.24% 1.23%
H-321 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 17 3.325 0.166 5.519 0.76 0.35% 1.33%
H-322 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 18 3.325 0.166 5.519 0.81 0.37% 1.35%
H-323 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 24 3.325 0.166 5.519 1.08 0.49% 1.47%
H-324 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 24 3.325 0.166 5.519 1.08 0.49% 1.47%
H-325 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 18 3.325 0.166 5.519 0.81 0.37% 1.35%
PROYECTO: HOTEL HAMPTON
ΔV = K.I.L/1000
ΔV: CAIDA DE TENSION (V)
K: FACTOR DE CAIDA DE TENSION SELECCIÓN DEL INTERRUPTOR ( IEC 60364 )
K= v3(r.cosφ+x.senφTRIFASICO Icarga ≤ In ≤ In (cable)
K= 2(r.cosφ+x.senφ) MONOFASICO
L= LONGITUD (m)
TABLEROS M.D.(W) U (V) cosφ n(%) FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) r(ohm/km) x(ohm/km) K ΔV(V) ΔV(%) ∑ΔV(%)
TD-41 23667 380 0.85 0.22% 1.07%
H-401 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 20 3.325 0.166 5.519 0.90 0.41% 1.48%
H-402 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 21 3.325 0.166 5.519 0.94 0.43% 1.50%
H-403 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 29 3.325 0.166 5.519 1.30 0.59% 1.66%
H-404 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 30 3.325 0.166 5.519 1.34 0.61% 1.68%
H-405 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 37 3.325 0.166 5.519 1.66 0.75% 1.82%
H-406 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 41 3.325 0.166 5.519 1.84 0.84% 1.90%
H-407 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 44 3.325 0.166 5.519 1.97 0.90% 1.97%
H-408 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 43 3.325 0.166 5.519 1.93 0.88% 1.94%
H-409 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 40 3.325 0.166 5.519 1.79 0.81% 1.88%
H-410 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 36 3.325 0.166 5.519 1.61 0.73% 1.80%
H-411 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 30 3.325 0.166 5.519 1.34 0.61% 1.68%
H-412 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 29 3.325 0.166 5.519 1.30 0.59% 1.66%
H-413 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 23 3.325 0.166 5.519 1.03 0.47% 1.54%
H-414 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 17 3.325 0.166 5.519 0.76 0.35% 1.42%
H-415 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 17 3.325 0.166 5.519 0.76 0.35% 1.42%
H-416 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 21 3.325 0.166 5.519 0.94 0.43% 1.50%
H-417 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 21 3.325 0.166 5.519 0.94 0.43% 1.50%
H-418 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 18 3.325 0.166 5.519 0.81 0.37% 1.44%
H-419 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 16 3.325 0.166 5.519 0.72 0.33% 1.39%
H-420 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 16 3.325 0.166 5.519 0.72 0.33% 1.39%
H-421 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 21 3.325 0.166 5.519 0.94 0.43% 1.50%
H-422 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 22 3.325 0.166 5.519 0.99 0.45% 1.52%
H-423 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 28 3.325 0.166 5.519 1.25 0.57% 1.64%
H-424 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 28 3.325 0.166 5.519 1.25 0.57% 1.64%
H-425 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 22 3.325 0.166 5.519 0.99 0.45% 1.52%
PROYECTO: HOTEL HAMPTON
ΔV = K.I.L/1000
ΔV: CAIDA DE TENSION (V)
K: FACTOR DE CAIDA DE TENSION SELECCIÓN DEL INTERRUPTOR ( IEC 60364 )
K= v3(r.cosφ+x.senφTRIFASICO Icarga ≤ In ≤ In (cable)
K= 2(r.cosφ+x.senφ) MONOFASICO
L= LONGITUD (m)
TABLEROS M.D.(W) U (V) cosφ n(%) FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) r(ohm/km) x(ohm/km) K ΔV(V) ΔV(%) ∑ΔV(%)
TD-51 23667 380 1.17 0.31% 1.15%
H-501 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 24 3.325 0.166 5.519 1.08 0.49% 1.64%
H-502 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 25 3.325 0.166 5.519 1.12 0.51% 1.66%
H-503 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 33 3.325 0.166 5.519 1.48 0.67% 1.82%
H-504 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 34 3.325 0.166 5.519 1.52 0.69% 1.85%
H-505 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 41 3.325 0.166 5.519 1.84 0.84% 1.99%
H-506 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 45 3.325 0.166 5.519 2.02 0.92% 2.07%
H-507 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 48 3.325 0.166 5.519 2.15 0.98% 2.13%
H-508 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 47 3.325 0.166 5.519 2.11 0.96% 2.11%
H-509 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 44 3.325 0.166 5.519 1.97 0.90% 2.05%
H-510 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 40 3.325 0.166 5.519 1.79 0.81% 1.97%
H-511 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 34 3.325 0.166 5.519 1.52 0.69% 1.85%
H-512 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 33 3.325 0.166 5.519 1.48 0.67% 1.82%
H-513 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 27 3.325 0.166 5.519 1.21 0.55% 1.70%
H-514 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 21 3.325 0.166 5.519 0.94 0.43% 1.58%
H-515 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 21 3.325 0.166 5.519 0.94 0.43% 1.58%
H-516 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 25 3.325 0.166 5.519 1.12 0.51% 1.66%
H-517 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 25 3.325 0.166 5.519 1.12 0.51% 1.66%
H-518 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 22 3.325 0.166 5.519 0.99 0.45% 1.60%
H-519 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 20 3.325 0.166 5.519 0.90 0.41% 1.56%
H-520 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 20 3.325 0.166 5.519 0.90 0.41% 1.56%
H-521 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 25 3.325 0.166 5.519 1.12 0.51% 1.66%
H-522 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 26 3.325 0.166 5.519 1.17 0.53% 1.68%
H-523 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 32 3.325 0.166 5.519 1.43 0.65% 1.80%
H-524 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 32 3.325 0.166 5.519 1.43 0.65% 1.80%
H-525 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 26 3.325 0.166 5.519 1.17 0.53% 1.68%
PROYECTO: HOTEL HAMPTON
ΔV = K.I.L/1000
ΔV: CAIDA DE TENSION (V)
K: FACTOR DE CAIDA DE TENSION SELECCIÓN DEL INTERRUPTOR ( IEC 60364 )
K= v3(r.cosφ+x.senφTRIFASICO Icarga ≤ In ≤ In (cable)
K= 2(r.cosφ+x.senφ) MONOFASICO
L= LONGITUD (m)
TABLEROS M.D.(W) U (V) cosφ n(%) FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) r(ohm/km) x(ohm/km) K ΔV(V) ΔV(%) ∑ΔV(%)
TD-61 23667 380 0.99 0.26% 1.11%
H-601 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 28 3.325 0.166 5.519 1.25 0.57% 1.68%
H-602 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 29 3.325 0.166 5.519 1.30 0.59% 1.70%
H-603 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 37 3.325 0.166 5.519 1.66 0.75% 1.86%
H-604 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 38 3.325 0.166 5.519 1.70 0.77% 1.88%
H-605 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 45 3.325 0.166 5.519 2.02 0.92% 2.02%
H-606 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 49 3.325 0.166 5.519 2.20 1.00% 2.11%
H-607 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 52 3.325 0.166 5.519 2.33 1.06% 2.17%
H-608 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 51 3.325 0.166 5.519 2.29 1.04% 2.15%
H-609 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 48 3.325 0.166 5.519 2.15 0.98% 2.09%
H-610 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 44 3.325 0.166 5.519 1.97 0.90% 2.00%
H-611 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 38 3.325 0.166 5.519 1.70 0.77% 1.88%
H-612 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 37 3.325 0.166 5.519 1.66 0.75% 1.86%
H-613 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 31 3.325 0.166 5.519 1.39 0.63% 1.74%
H-614 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 25 3.325 0.166 5.519 1.12 0.51% 1.62%
H-615 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 25 3.325 0.166 5.519 1.12 0.51% 1.62%
H-616 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 29 3.325 0.166 5.519 1.30 0.59% 1.70%
H-617 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 29 3.325 0.166 5.519 1.30 0.59% 1.70%
H-618 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 26 3.325 0.166 5.519 1.17 0.53% 1.64%
H-619 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 24 3.325 0.166 5.519 1.08 0.49% 1.60%
H-620 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 24 3.325 0.166 5.519 1.08 0.49% 1.60%
H-621 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 29 3.325 0.166 5.519 1.30 0.59% 1.70%
H-622 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 30 3.325 0.166 5.519 1.34 0.61% 1.72%
H-623 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 36 3.325 0.166 5.519 1.61 0.73% 1.84%
H-624 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 36 3.325 0.166 5.519 1.61 0.73% 1.84%
H-625 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 30 3.325 0.166 5.519 1.34 0.61% 1.72%
PROYECTO: HOTEL HAMPTON
ΔV = K.I.L/1000
ΔV: CAIDA DE TENSION (V)
K: FACTOR DE CAIDA DE TENSION SELECCIÓN DEL INTERRUPTOR ( IEC 60364 )
K= v3(r.cosφ+x.senφTRIFASICO Icarga ≤ In ≤ In (cable)
K= 2(r.cosφ+x.senφ) MONOFASICO
L= LONGITUD (m)
TABLEROS M.D.(W) U (V) cosφ n(%) FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) r(ohm/km) x(ohm/km) K ΔV(V) ΔV(%) ∑ΔV(%)
TD-71 23667 380 1.21 0.32% 1.16%
H-701 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 32 3.325 0.166 5.519 1.43 0.65% 1.82%
H-702 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 33 3.325 0.166 5.519 1.48 0.67% 1.84%
H-703 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 41 3.325 0.166 5.519 1.84 0.84% 2.00%
H-704 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 42 3.325 0.166 5.519 1.88 0.86% 2.02%
H-705 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 49 3.325 0.166 5.519 2.20 1.00% 2.16%
H-706 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 53 3.325 0.166 5.519 2.38 1.08% 2.24%
H-707 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 56 3.325 0.166 5.519 2.51 1.14% 2.30%
H-708 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 55 3.325 0.166 5.519 2.46 1.12% 2.28%
H-709 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 52 3.325 0.166 5.519 2.33 1.06% 2.22%
H-710 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 48 3.325 0.166 5.519 2.15 0.98% 2.14%
H-711 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 42 3.325 0.166 5.519 1.88 0.86% 2.02%
H-712 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 41 3.325 0.166 5.519 1.84 0.84% 2.00%
H-713 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 35 3.325 0.166 5.519 1.57 0.71% 1.88%
H-714 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 29 3.325 0.166 5.519 1.30 0.59% 1.75%
H-715 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 29 3.325 0.166 5.519 1.30 0.59% 1.75%
H-716 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 33 3.325 0.166 5.519 1.48 0.67% 1.84%
H-717 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 33 3.325 0.166 5.519 1.48 0.67% 1.84%
H-718 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 30 3.325 0.166 5.519 1.34 0.61% 1.77%
H-719 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 28 3.325 0.166 5.519 1.25 0.57% 1.73%
H-720 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 28 3.325 0.166 5.519 1.25 0.57% 1.73%
H-721 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 33 3.325 0.166 5.519 1.48 0.67% 1.84%
H-722 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 34 3.325 0.166 5.519 1.52 0.69% 1.86%
H-723 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 40 3.325 0.166 5.519 1.79 0.81% 1.98%
H-724 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 40 3.325 0.166 5.519 1.79 0.81% 1.98%
H-725 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 34 3.325 0.166 5.519 1.52 0.69% 1.86%
PROYECTO: HOTEL HAMPTON
ΔV = K.I.L/1000
ΔV: CAIDA DE TENSION (V)
K: FACTOR DE CAIDA DE TENSION SELECCIÓN DEL INTERRUPTOR ( IEC 60364 )
K= v3(r.cosφ+x.senφTRIFASICO Icarga ≤ In ≤ In (cable)
K= 2(r.cosφ+x.senφ) MONOFASICO
L= LONGITUD (m)
TABLEROS M.D.(W) U (V) cosφ n(%) FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) r(ohm/km) x(ohm/km) K ΔV(V) ΔV(%) ∑ΔV(%)
TD-81 23667 380 1.42 0.37% 1.22%
H-801 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 36 3.325 0.166 5.519 1.61 0.73% 1.95%
H-802 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 37 3.325 0.166 5.519 1.66 0.75% 1.97%
H-803 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 45 3.325 0.166 5.519 2.02 0.92% 2.14%
H-804 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 46 3.325 0.166 5.519 2.06 0.94% 2.16%
H-805 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 53 3.325 0.166 5.519 2.38 1.08% 2.30%
H-806 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 57 3.325 0.166 5.519 2.55 1.16% 2.38%
H-807 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 60 3.325 0.166 5.519 2.69 1.22% 2.44%
H-808 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 59 3.325 0.166 5.519 2.64 1.20% 2.42%
H-809 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 56 3.325 0.166 5.519 2.51 1.14% 2.36%
H-810 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 52 3.325 0.166 5.519 2.33 1.06% 2.28%
H-811 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 46 3.325 0.166 5.519 2.06 0.94% 2.16%
H-812 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 45 3.325 0.166 5.519 2.02 0.92% 2.14%
H-813 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 39 3.325 0.166 5.519 1.75 0.79% 2.01%
H-814 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 33 3.325 0.166 5.519 1.48 0.67% 1.89%
H-815 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 33 3.325 0.166 5.519 1.48 0.67% 1.89%
H-816 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 37 3.325 0.166 5.519 1.66 0.75% 1.97%
H-817 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 37 3.325 0.166 5.519 1.66 0.75% 1.97%
H-818 T-HAB.1 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 34 3.325 0.166 5.519 1.52 0.69% 1.91%
H-819 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 32 3.325 0.166 5.519 1.43 0.65% 1.87%
H-820 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 32 3.325 0.166 5.519 1.43 0.65% 1.87%
H-821 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 37 3.325 0.166 5.519 1.66 0.75% 1.97%
H-822 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 38 3.325 0.166 5.519 1.70 0.77% 1.99%
H-823 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 44 3.325 0.166 5.519 1.97 0.90% 2.12%
H-824 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 44 3.325 0.166 5.519 1.97 0.90% 2.12%
H-825 T-HAB.2 1143 220 0.80 1.00 1 6.50 8.12 1x 20 1 6 44 38 3.325 0.166 5.519 1.70 0.77% 1.99%
N2XOH
TABLEROS M.D.(W) U (V) cosφ n(%) FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) r(ohm/km) x(ohm/km) K ΔV(V) ΔV(%) ∑ΔV(%)
TF-BCI 82889 380 0.80 1.00 3 157 197 3x 200 1 50 230 27 0.399 0.146 0.705 3.74 0.99% 0.99%
BCI 82889 380 0.80 1.00 3 157 157 3x 200 1 50 230 6 0.399 0.146 0.705 0.67 0.18% 1.16%
FUENTE: INDECO
FREETOX NHX-80
Conductor de cobre electrolítico recocido, sólido o cableado. Aislamiento de compuesto termoplástico no halogenado HFFR.
Tensión de servicio: 450/750 V Temperatura de operación: 80ºC
TABLA DE DATOS TECNICOS NH-80
AIRE DUCTO
mm² mm mm mm mm Kg/Km A A
1.5 7 0.52 1.5 0.7 2.9 20 18 14
2.5 7 0.66 1.92 0.8 3.5 31 30 24
4 7 0.84 2.44 0.8 4 46 35 31
6 7 1.02 2.98 0.8 4.6 65 50 39
10 7 1.33 3.99 1 6 110 74 51
16 7 1.69 4.67 1 6.7 167 99 68
25 7 2.13 5.88 1.2 8.3 262 132 88
35 7 2.51 6.92 1.2 9.3 356 165 110
50 19 1.77 8.15 1.4 11 480 204 138
70 19 2.13 9.78 1.4 12.6 678 253 165
95 19 2.51 11.55 1.6 14.8 942 303 198
120 37 2.02 13 1.6 16.2 1174 352 231
150 37 2.24 14.41 1.8 18 1443 413 264
185 37 2.51 16.16 2 20.2 1809 473 303
240 37 2.87 18.51 2.2 22.9 2368 528 352
300 37 3.22 20.73 2.4 25.5 2963 633 391
(*) TEMPERATURA AMBIENTE 30°C.
NO MAS DE TRES CONDUCTORES POR DUCTO.
FUENTE: INDECO
FREETOX NHX-80
Conductor de cobre electrolítico recocido, sólido o cableado. Aislamiento de compuesto termoplástico no halogenado HFFR.
Tensión de servicio: 450/750 V Temperatura de operación: 80ºC
TABLA DE DATOS TECNICOS NH-80
AIRE DUCTO
mm² mm mm mm mm Kg/Km A A
1.5 7 0.52 1.5 0.7 2.9 20 18 14
2.5 7 0.66 1.92 0.8 3.5 31 30 24
4 7 0.84 2.44 0.8 4 46 35 31
6 7 1.02 2.98 0.8 4.6 65 50 39
10 7 1.33 3.99 1 6 110 74 51
16 7 1.69 4.67 1 6.7 167 99 68
25 7 2.13 5.88 1.2 8.3 262 132 88
35 7 2.51 6.92 1.2 9.3 356 165 110
50 19 1.77 8.15 1.4 11 480 204 138
70 19 2.13 9.78 1.4 12.6 678 253 165
95 19 2.51 11.55 1.6 14.8 942 303 198
120 37 2.02 13 1.6 16.2 1174 352 231
150 37 2.24 14.41 1.8 18 1443 413 264
185 37 2.51 16.16 2 20.2 1809 473 303
240 37 2.87 18.51 2.2 22.9 2368 528 352
300 37 3.22 20.73 2.4 25.5 2963 633 391
(*) TEMPERATURA AMBIENTE 30°C.
NO MAS DE TRES CONDUCTORES POR DUCTO.
FUENTE: INDECO
FREETOX NHX-80
Conductor de cobre electrolítico recocido, sólido o cableado. Aislamiento de compuesto termoplástico no halogenado HFFR.
Tensión de servicio: 450/750 V Temperatura de operación: 80ºC
TABLA DE DATOS TECNICOS NH-80
AIRE DUCTO
mm² mm mm mm mm Kg/Km A A
1.5 7 0.52 1.5 0.7 2.9 20 18 14
2.5 7 0.66 1.92 0.8 3.5 31 30 24
4 7 0.84 2.44 0.8 4 46 35 31
6 7 1.02 2.98 0.8 4.6 65 50 39
10 7 1.33 3.99 1 6 110 74 51
16 7 1.69 4.67 1 6.7 167 99 68
25 7 2.13 5.88 1.2 8.3 262 132 88
35 7 2.51 6.92 1.2 9.3 356 165 110
50 19 1.77 8.15 1.4 11 480 204 138
70 19 2.13 9.78 1.4 12.6 678 253 165
95 19 2.51 11.55 1.6 14.8 942 303 198
120 37 2.02 13 1.6 16.2 1174 352 231
150 37 2.24 14.41 1.8 18 1443 413 264
185 37 2.51 16.16 2 20.2 1809 473 303
240 37 2.87 18.51 2.2 22.9 2368 528 352
300 37 3.22 20.73 2.4 25.5 2963 633 391
(*) TEMPERATURA AMBIENTE 30°C.
NO MAS DE TRES CONDUCTORES POR DUCTO.
PROYECTO: HOTEL HAMPTON
ΔV = K.I.L/1000
ΔV: CAIDA DE TENSION (V)
K: FACTOR DE CAIDA DE TENSION SELECCIÓN DEL INTERRUPTOR ( IEC 60364 )
K= v3(r.cosφ+x.senφTRIFASICO Icarga ≤ In ≤ In (cable)
K= 2(r.cosφ+x.senφ) MONOFASICO
L= LONGITUD (m)
N2XOH
TABLEROS M.D.(W) U (V) cosφ n(%) FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) r(ohm/km)
TG-CAMP 950000 440 0.85 1.00 3 1466.53 1833.16 3x 1800 8 240 4488 12 0.084
TG-CAMP1 750000 440 0.85 1.00 3 1157.79 1447.23 3x 1600 4 240 2244 12 0.084
TG-CAMP2 200000 440 0.85 1.00 3 308.74 385.93 3x 400 14 240 7854 0.084
TG-CAMP3 440 0.80 1.00 3 0.00 0.00 3x 1 10 95 72 1.995
TG-CAMP4 440 0.80 1.00 3 0.00 0.00 3x 3 120 1140 6 0.167
NYY
TABLEROS Pot. Instalada (W) F.D (%) M.D.(W) U (V) cosφ n(%) FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) r(ohm/km)
TG-CAMP1 0 380
TG-1 169,630.00 136,662.50 440 0.85 1.00 3 210.97 263.71 3x 300 1 185 483 132 0.109
TG-2 165,320.00 131,120.50 440 0.85 1.00 3 202.41 253.02 3x 300 1 185 483 142 0.109
TG-3 165,840.00 132,412.00 400 0.85 1.00 3 224.85 281.06 3x 300 5 240 2805 250 0.084
TG-1 169,630.00 136,662.50 440
C1 Comedor 01 11,150.00 0.75 8,362.50 440 0.85 1.00 3 12.91 16.14 3x 20 1 10 95 30 1.995
C2 Cocina 01 20,000.00 0.80 16,000.00 440 0.85 1.00 3 24.70 30.87 3x 32 1 16 127 75 1.247
C3 Caldera 3,920.00 0.80 3,136.00 440 0.85 1.00 3 4.84 6.05 3x 10 1 10 95 60 1.995
Congelados,
C4 Refrigerados 5,030.00 0.80 4,024.00 440 0.85 1.00 3 6.21 7.76 3x 10 1 10 95 80 1.995
C5 Mano de Obra 54,300.00 0.80 43,440.00 440 0.85 1.00 3 67.06 83.82 3x 100 1 150 428 100 0.134
C6 Ilum. Exterior 5,200.00 1.00 5,200.00 440 0.85 1.00 3 8.03 10.03 3x 10 1 10 95 12 1.995
C6a Ilum. Exterior 1,200.00 1.00 1,200.00 440 0.85 1.00 3 1.85 2.32 3x 1 10 95 33 1.995
C6a1 Ilum. Exterior 400.00 1.00 400.00 220 0.85 1.00 1 2.14 2.67 3x 1 10 95 47 1.995
C6b Ilum. Exterior 1,200.00 1.00 1,200.00 440 0.85 1.00 3 1.85 2.32 3x 1 10 95 44 1.995
C6b1 Ilum. Exterior 800.00 1.00 800.00 440 0.85 1.00 3 1.23 1.54 3x 1 10 95 33 1.995
C6b2 Ilum. Exterior 800.00 1.00 400.00 440 0.85 1.00 3 0.62 0.77 3x 1 10 95 119 1.995
C6c Ilum. Exterior 1,200.00 1.00 1,200.00 400 0.85 1.00 3 2.04 2.55 3x 1 10 95 29 1.995
C6d Ilum. Exterior 1,200.00 1.00 1,200.00 440 0.85 1.00 3 1.85 2.32 3x 1 10 95 62 1.995
C6e Ilum. Exterior 800.00 1.00 800.00 440 0.85 1.00 3 1.23 1.54 3x 1 10 95 27 1.995
C6f Ilum. Exterior 800.00 1.00 800.00 440 0.85 1.00 3 1.23 1.54 3x 1 10 95 27 1.995
C7 Oficina 01-a 67,670.00 0.82 55,330.00 440 0.85 1.00 3 85.41 106.77 3x 125 1 240 561 65 0.084
SSHH - Vestidores
C8 Cocina 1 1,020.00 0.75 765.00 440 0.85 1.00 3 1.18 1.48 3x 10 1 10 95 60 1.995
C9 SSHH - Cocina 540.00 0.75 405.00 440 0.85 1.00 3 0.63 0.78 3x 10 1 10 95 95 1.995
TG-2 165,320.00 131,120.50 440
C1 PTAR 24,690.00 0.75 18,517.50 440 0.85 1.00 3 28.59 35.73 3x 40 1 25 163 110 0.798
C2 Oficina 01-B 67,670.00 0.82 55,330.00 440 0.85 1.00 3 85.41 106.77 3x 125 1 240 561 105 0.084
C3 Secos 2,010.00 0.80 1,608.00 440 0.85 1.00 3 2.48 3.10 3x 10 1 10 95 90 1.995
C4 Staff 02-a 11,000.00 0.75 8,250.00 440 0.85 1.00 3 12.74 15.92 3x 16 1 10 95 86 1.995
C5 Staff 02-b 11,000.00 0.75 8,250.00 440 0.85 1.00 3 12.74 15.92 3x 16 1 10 95 120 1.995
PROYECTO: HOTEL HAMPTON
ΔV = K.I.L/1000
ΔV: CAIDA DE TENSION (V)
K: FACTOR DE CAIDA DE TENSION SELECCIÓN DEL INTERRUPTOR ( IEC 60364 )
K= v3(r.cosφ+x.senφTRIFASICO Icarga ≤ In ≤ In (cable)
K= 2(r.cosφ+x.senφ) MONOFASICO
L= LONGITUD (m)
C6 Staff-01 11,000.00 0.75 8,250.00 440 0.85 1.00 3 12.74 15.92 3x 16 1 10 95 65 1.995
C7 Ilum. Exterior 3,000.00 1.00 3,000.00 440 0.85 1.00 3 4.63 5.79 3x 10 1 10 95 42 1.995
C8 Comedor 02 34,050.00 0.80 27,240.00 440 0.85 1.00 3 42.05 52.56 3x 63 1 50 230 65 0.399
C9 SSHH - Comedor 01 900.00 0.75 675.00 440 0.85 1.00 3 1.04 1.30 3x 10 1 10 95 120 1.995
TG-2 165,840.00 132,412.00 440
C1 Est. Maq. Pesada 6,600.00 0.75 4,950.00 440 0.80 1.00 3 8.12 10.15 3x 16 1 10 95 200 1.995
C2 Cisterna 50,000.00 0.80 40,000.00 440 0.80 1.00 3 65.61 82.01 3x 100 1 150 428 110 0.134
C3 Losa Deportiva 01 1,600.00 0.80 1,280.00 440 0.80 1.00 3 2.10 2.62 3x 10 1 10 95 65 1.995
C4 Losa Deportiva 02 1,600.00 0.80 1,280.00 440 0.80 1.00 3 2.10 2.62 3x 10 1 10 95 95 1.995
C5 Sala Recreacional 25,000.00 0.75 18,750.00 440 0.80 1.00 3 30.75 38.44 3x 40 1 25 163 85 0.798
Almacen R.Peligrosos,
C6 R No Peligrosos 15,360.00 0.80 12,288.00 440 0.80 1.00 3 20.15 25.19 3x 30 1 150 428 436 0.134
C7 Almacen General 28,800.00 0.80 23,040.00 440 0.80 1.00 3 37.79 47.24 3x 50 1 120 382 295 0.167
C8 Control de Ingreso 1,030.00 0.80 824.00 440 0.80 1.00 3 1.35 1.69 3x 10 1 10 95 290 1.995
C9 Ilum. Exterior 3,300.00 1.00 3,300.00 440 0.80 1.00 3 5.41 6.77 3x 10 1 10 95 42 1.995
C10 Posta Medica 3,300.00 1.00 3,300.00 440 0.80 1.00 3 5.41 6.77 3x 10 1 10 95 65 1.995
C11 Grifo 12,250.00 0.80 9,800.00 440 0.80 1.00 3 16.07 20.09 3x 225 1 16 127 150 1.247
C12 Mano de Obra 01 17,000.00 0.80 13,600.00 440 0.80 1.00 3 22.31 27.88 3x 30 1 16 127 42 1.247
LSOH-90
TABLEROS Pot. Instalada (W) F.D (%) M.D.(W) U (V) cosφ n(%) FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) r(ohm/km)
TG-CAMP2 13600 380
TG-1 0.00 0.00 440 0.85 1.00 3 0.00 0.00 3x 40 1 10 95 39 1.995
TG-2 0.00 0.00 440 0.85 1.00 3 0.00 0.00 3x 40 1 10 95 42 1.995
TG-3 0.00 0.00 400 0.85 1.00 3 0.00 0.00 3x 40 1 10 95 39 1.995
TG-1 0.00 0.00 440
C1 OFICINAS 1 0.75 0.00 440 0.85 1.00 3 0.00 0.00 3x 20 1 10 95 39 1.995
C2 OFICINAS 2 0.80 0.00 440 0.85 1.00 3 0.00 0.00 3x 32 1 10 95 42 1.995
C3 ALMACEN 0.80 0.00 440 0.85 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995
REIDUOS PELIGROSOS
C4 RESIDUOS NO PELIGROSOS 0.80 0.00 440 0.85 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995
C5 COMEDORES 0.80 0.00 440 0.85 1.00 3 0.00 0.00 3x 100 1 10 95 42 1.995
C6 ILUMINACION EXTERIOR 1.00 0.00 440 0.85 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995
C7 Oficina 01-a 0.00 440 0.85 1.00 3 0.00 0.00 3x 125 1 10 95 42 1.995
SSHH - Vestidores
C8 Cocina 1 0.75 0.00 440 0.85 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995
C9 SSHH - Cocina 0.75 0.00 440 0.85 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995
TG-2 0.00 0.00 440
C1 0.00 440 0.85 1.00 3 0.00 0.00 3x 40 1 10 95 39 1.995
C2 0.00 440 0.85 1.00 3 0.00 0.00 3x 125 1 10 95 42 1.995
C3 0.00 440 0.85 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995
C4 0.00 440 0.85 1.00 3 0.00 0.00 3x 16 1 10 95 42 1.995
PROYECTO: HOTEL HAMPTON
ΔV = K.I.L/1000
ΔV: CAIDA DE TENSION (V)
K: FACTOR DE CAIDA DE TENSION SELECCIÓN DEL INTERRUPTOR ( IEC 60364 )
K= v3(r.cosφ+x.senφTRIFASICO Icarga ≤ In ≤ In (cable)
K= 2(r.cosφ+x.senφ) MONOFASICO
L= LONGITUD (m)
C5 0.00 440 0.85 1.00 3 0.00 0.00 3x 16 1 10 95 42 1.995
C6 0.00 440 0.85 1.00 3 0.00 0.00 3x 16 1 10 95 42 1.995
C7 0.00 440 0.85 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995
C8 0.00 440 0.85 1.00 3 0.00 0.00 3x 63 1 10 95 42 1.995
C9 0.00 440 0.85 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995
TG-2 0.00 0.00 440
C1 0.75 0.00 440 0.80 1.00 3 0.00 0.00 3x 16 1 10 95 39 1.995
C2 0.80 0.00 440 0.80 1.00 3 0.00 0.00 3x 100 1 10 95 42 1.995
C3 0.80 0.00 440 0.80 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995
C4 0.80 0.00 440 0.80 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995
C5 0.75 0.00 440 0.80 1.00 3 0.00 0.00 3x 40 1 10 95 42 1.995
C6 0.80 0.00 440 0.80 1.00 3 0.00 0.00 3x 30 1 10 95 42 1.995
C7 0.80 0.00 440 0.80 1.00 3 0.00 0.00 3x 50 1 10 95 42 1.995
C8 0.80 0.00 440 0.80 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995
C9 1.00 0.00 440 0.80 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995
C10 1.00 0.00 440 0.80 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995
C11 0.80 0.00 440 0.80 1.00 3 0.00 0.00 3x 225 1 10 95 42 1.995
C12 0.80 0.00 440 0.80 1.00 3 0.00 0.00 3x 30 1 10 95 42 1.995
O: HOTEL HAMPTON
ΔV = K.I.L/1000
ΔV: CAIDA DE TENSION (V)
K: FACTOR DE CAIDA DE TENSION SELECCIÓN DEL INTERRUPTOR ( IEC 60364 )
K= v3(r.cosφ+x.senφTRIFASICO Icarga ≤ In ≤ In (cable)
K= 2(r.cosφ+x.senφ) MONOFASICO
L= LONGITUD (m)
N2XOH
M.D.(W) U (V) cosφ n(%) FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) r(ohm/km) x(ohm/km) K ΔV(V) ΔV(%)
950000 440 0.85 1.00 3 1466.53 1833.16 3x 1800 8 240 4488 12 0.084 0.137 0.249 0.68 0.16%
750000 440 0.85 1.00 3 1157.79 1447.23 3x 1600 4 240 2244 12 0.084 0.137 0.249 1.08 0.25%
200000 440 0.85 1.00 3 308.74 385.93 3x 400 14 240 7854 0.084 0.137 0.249 0.00 0.00%
440 0.80 1.00 3 0.00 0.00 3x 1 10 95 72 1.995 0.166 2.937 0.00 0.00%
440 0.80 1.00 3 0.00 0.00 3x 3 120 1140 6 0.167 0.140 0.377 0.00 0.00%
NYY
Pot. Instalada (W) F.D (%) M.D.(W) U (V) cosφ n(%) FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) r(ohm/km) x(ohm/km) K ΔV(V) ΔV(%)
0 380 0.00 0.00%
169,630.00 136,662.50 440 0.85 1.00 3 210.97 263.71 3x 300 1 185 483 132 0.109 0.139 0.287 10.00 2.27%
165,320.00 131,120.50 440 0.85 1.00 3 202.41 253.02 3x 300 1 185 483 142 0.109 0.139 0.287 10.32 2.35%
165,840.00 132,412.00 400 0.85 1.00 3 224.85 281.06 3x 300 5 240 2805 250 0.084 0.137 0.249 3.49 0.87%
169,630.00 136,662.50 440 0.00 0.00%
Comedor 01 11,150.00 0.75 8,362.50 440 0.85 1.00 3 12.91 16.14 3x 20 1 10 95 30 1.995 0.166 3.089 1.50 0.34%
Cocina 01 20,000.00 0.80 16,000.00 440 0.85 1.00 3 24.70 30.87 3x 32 1 16 127 75 1.247 0.152 1.975 4.57 1.04%
Caldera 3,920.00 0.80 3,136.00 440 0.85 1.00 3 4.84 6.05 3x 10 1 10 95 60 1.995 0.166 3.089 1.12 0.25%
Congelados,
Refrigerados 5,030.00 0.80 4,024.00 440 0.85 1.00 3 6.21 7.76 3x 10 1 10 95 80 1.995 0.166 3.089 1.92 0.44%
Mano de Obra 54,300.00 0.80 43,440.00 440 0.85 1.00 3 67.06 83.82 3x 100 1 150 428 100 0.134 0.141 0.326 2.73 0.62%
Ilum. Exterior 5,200.00 1.00 5,200.00 440 0.85 1.00 3 8.03 10.03 3x 10 1 10 95 12 1.995 0.166 3.089 0.37 0.08%
Ilum. Exterior 1,200.00 1.00 1,200.00 440 0.85 1.00 3 1.85 2.32 3x 1 10 95 33 1.995 0.166 3.089 0.24 0.05%
Ilum. Exterior 400.00 1.00 400.00 220 0.85 1.00 1 2.14 2.67 3x 1 10 95 47 1.995 0.166 3.566 0.45 0.20%
Ilum. Exterior 1,200.00 1.00 1,200.00 440 0.85 1.00 3 1.85 2.32 3x 1 10 95 44 1.995 0.166 3.089 0.31 0.07%
Ilum. Exterior 800.00 1.00 800.00 440 0.85 1.00 3 1.23 1.54 3x 1 10 95 33 1.995 0.166 3.089 0.16 0.04%
Ilum. Exterior 800.00 1.00 400.00 440 0.85 1.00 3 0.62 0.77 3x 1 10 95 119 1.995 0.166 3.089 0.28 0.06%
Ilum. Exterior 1,200.00 1.00 1,200.00 400 0.85 1.00 3 2.04 2.55 3x 1 10 95 29 1.995 0.166 3.089 0.23 0.06%
Ilum. Exterior 1,200.00 1.00 1,200.00 440 0.85 1.00 3 1.85 2.32 3x 1 10 95 62 1.995 0.166 3.089 0.44 0.10%
Ilum. Exterior 800.00 1.00 800.00 440 0.85 1.00 3 1.23 1.54 3x 1 10 95 27 1.995 0.166 3.089 0.13 0.03%
Ilum. Exterior 800.00 1.00 800.00 440 0.85 1.00 3 1.23 1.54 3x 1 10 95 27 1.995 0.166 3.089 0.13 0.03%
Oficina 01-a 67,670.00 0.82 55,330.00 440 0.85 1.00 3 85.41 106.77 3x 125 1 240 561 65 0.084 0.137 0.249 1.73 0.39%
SHH - Vestidores
Cocina 1 1,020.00 0.75 765.00 440 0.85 1.00 3 1.18 1.48 3x 10 1 10 95 60 1.995 0.166 3.089 0.27 0.06%
SSHH - Cocina 540.00 0.75 405.00 440 0.85 1.00 3 0.63 0.78 3x 10 1 10 95 95 1.995 0.166 3.089 0.23 0.05%
165,320.00 131,120.50 440 0.37 0.08%
PTAR 24,690.00 0.75 18,517.50 440 0.85 1.00 3 28.59 35.73 3x 40 1 25 163 110 0.798 0.152 1.314 5.16 1.17%
Oficina 01-B 67,670.00 0.82 55,330.00 440 0.85 1.00 3 85.41 106.77 3x 125 1 240 561 105 0.084 0.137 0.249 2.79 0.63%
Secos 2,010.00 0.80 1,608.00 440 0.85 1.00 3 2.48 3.10 3x 10 1 10 95 90 1.995 0.166 3.089 0.86 0.20%
Staff 02-a 11,000.00 0.75 8,250.00 440 0.85 1.00 3 12.74 15.92 3x 16 1 10 95 86 1.995 0.166 3.089 4.23 0.96%
Staff 02-b 11,000.00 0.75 8,250.00 440 0.85 1.00 3 12.74 15.92 3x 16 1 10 95 120 1.995 0.166 3.089 5.90 1.34%
O: HOTEL HAMPTON
ΔV = K.I.L/1000
ΔV: CAIDA DE TENSION (V)
K: FACTOR DE CAIDA DE TENSION SELECCIÓN DEL INTERRUPTOR ( IEC 60364 )
K= v3(r.cosφ+x.senφTRIFASICO Icarga ≤ In ≤ In (cable)
K= 2(r.cosφ+x.senφ) MONOFASICO
L= LONGITUD (m)
Staff-01 11,000.00 0.75 8,250.00 440 0.85 1.00 3 12.74 15.92 3x 16 1 10 95 65 1.995 0.166 3.089 3.20 0.73%
Ilum. Exterior 3,000.00 1.00 3,000.00 440 0.85 1.00 3 4.63 5.79 3x 10 1 10 95 42 1.995 0.166 3.089 0.75 0.17%
Comedor 02 34,050.00 0.80 27,240.00 440 0.85 1.00 3 42.05 52.56 3x 63 1 50 230 65 0.399 0.146 0.721 2.46 0.56%
HH - Comedor 01 900.00 0.75 675.00 440 0.85 1.00 3 1.04 1.30 3x 10 1 10 95 120 1.995 0.166 3.089 0.48 0.11%
165,840.00 132,412.00 440 3.20 0.73%
st. Maq. Pesada 6,600.00 0.75 4,950.00 440 0.80 1.00 3 8.12 10.15 3x 16 1 10 95 200 1.995 0.166 2.937 5.96 1.35%
Cisterna 50,000.00 0.80 40,000.00 440 0.80 1.00 3 65.61 82.01 3x 100 1 150 428 110 0.134 0.141 0.332 3.00 0.68%
osa Deportiva 01 1,600.00 0.80 1,280.00 440 0.80 1.00 3 2.10 2.62 3x 10 1 10 95 65 1.995 0.166 2.937 0.50 0.11%
osa Deportiva 02 1,600.00 0.80 1,280.00 440 0.80 1.00 3 2.10 2.62 3x 10 1 10 95 95 1.995 0.166 2.937 0.73 0.17%
ala Recreacional 25,000.00 0.75 18,750.00 440 0.80 1.00 3 30.75 38.44 3x 40 1 25 163 85 0.798 0.152 1.264 4.13 0.94%
macen R.Peligrosos,
R No Peligrosos 15,360.00 0.80 12,288.00 440 0.80 1.00 3 20.15 25.19 3x 30 1 150 428 436 0.134 0.141 0.332 3.65 0.83%
Almacen General 28,800.00 0.80 23,040.00 440 0.80 1.00 3 37.79 47.24 3x 50 1 120 382 295 0.167 0.140 0.377 5.25 1.19%
ontrol de Ingreso 1,030.00 0.80 824.00 440 0.80 1.00 3 1.35 1.69 3x 10 1 10 95 290 1.995 0.166 2.937 1.44 0.33%
Ilum. Exterior 3,300.00 1.00 3,300.00 440 0.80 1.00 3 5.41 6.77 3x 10 1 10 95 42 1.995 0.166 2.937 0.83 0.19%
Posta Medica 3,300.00 1.00 3,300.00 440 0.80 1.00 3 5.41 6.77 3x 10 1 10 95 65 1.995 0.166 2.937 1.29 0.29%
Grifo 12,250.00 0.80 9,800.00 440 0.80 1.00 3 16.07 20.09 3x 225 1 16 127 150 1.247 0.152 1.886 5.68 1.29%
Mano de Obra 01 17,000.00 0.80 13,600.00 440 0.80 1.00 3 22.31 27.88 3x 30 1 16 127 42 1.247 0.152 1.886 2.21 0.50%
LSOH-90
Pot. Instalada (W) F.D (%) M.D.(W) U (V) cosφ n(%) FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) r(ohm/km) x(ohm/km) K ΔV(V) ΔV(%)
13600 380 2.21 0.58%
0.00 0.00 440 0.85 1.00 3 0.00 0.00 3x 40 1 10 95 39 1.995 0.166 3.089 0.00 0.00%
0.00 0.00 440 0.85 1.00 3 0.00 0.00 3x 40 1 10 95 42 1.995 0.166 3.089 0.00 0.00%
0.00 0.00 400 0.85 1.00 3 0.00 0.00 3x 40 1 10 95 39 1.995 0.166 3.089 0.00 0.00%
0.00 0.00 440 2.21 0.50%
OFICINAS 1 0.75 0.00 440 0.85 1.00 3 0.00 0.00 3x 20 1 10 95 39 1.995 0.166 3.089 0.00 0.00%
OFICINAS 2 0.80 0.00 440 0.85 1.00 3 0.00 0.00 3x 32 1 10 95 42 1.995 0.166 3.089 0.00 0.00%
ALMACEN 0.80 0.00 440 0.85 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995 0.166 3.089 0.00 0.00%
DUOS PELIGROSOS
UOS NO PELIGROSOS 0.80 0.00 440 0.85 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995 0.166 3.089 0.00 0.00%
COMEDORES 0.80 0.00 440 0.85 1.00 3 0.00 0.00 3x 100 1 10 95 42 1.995 0.166 3.089 0.00 0.00%
MINACION EXTERIOR 1.00 0.00 440 0.85 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995 0.166 3.089 0.00 0.00%
Oficina 01-a 0.00 440 0.85 1.00 3 0.00 0.00 3x 125 1 10 95 42 1.995 0.166 3.089 0.00 0.00%
SHH - Vestidores
Cocina 1 0.75 0.00 440 0.85 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995 0.166 3.089 0.00 0.00%
SSHH - Cocina 0.75 0.00 440 0.85 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995 0.166 3.089 0.00 0.00%
0.00 0.00 440 0.00 0.00%
0.00 440 0.85 1.00 3 0.00 0.00 3x 40 1 10 95 39 1.995 0.166 3.089 0.00 0.00%
0.00 440 0.85 1.00 3 0.00 0.00 3x 125 1 10 95 42 1.995 0.166 3.089 0.00 0.00%
0.00 440 0.85 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995 0.166 3.089 0.00 0.00%
0.00 440 0.85 1.00 3 0.00 0.00 3x 16 1 10 95 42 1.995 0.166 3.089 0.00 0.00%
O: HOTEL HAMPTON
ΔV = K.I.L/1000
ΔV: CAIDA DE TENSION (V)
K: FACTOR DE CAIDA DE TENSION SELECCIÓN DEL INTERRUPTOR ( IEC 60364 )
K= v3(r.cosφ+x.senφTRIFASICO Icarga ≤ In ≤ In (cable)
K= 2(r.cosφ+x.senφ) MONOFASICO
L= LONGITUD (m)
0.00 440 0.85 1.00 3 0.00 0.00 3x 16 1 10 95 42 1.995 0.166 3.089 0.00 0.00%
0.00 440 0.85 1.00 3 0.00 0.00 3x 16 1 10 95 42 1.995 0.166 3.089 0.00 0.00%
0.00 440 0.85 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995 0.166 3.089 0.00 0.00%
0.00 440 0.85 1.00 3 0.00 0.00 3x 63 1 10 95 42 1.995 0.166 3.089 0.00 0.00%
0.00 440 0.85 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995 0.166 3.089 0.00 0.00%
0.00 0.00 440 0.00 0.00%
0.75 0.00 440 0.80 1.00 3 0.00 0.00 3x 16 1 10 95 39 1.995 0.166 2.937 0.00 0.00%
0.80 0.00 440 0.80 1.00 3 0.00 0.00 3x 100 1 10 95 42 1.995 0.166 2.937 0.00 0.00%
0.80 0.00 440 0.80 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995 0.166 2.937 0.00 0.00%
0.80 0.00 440 0.80 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995 0.166 2.937 0.00 0.00%
0.75 0.00 440 0.80 1.00 3 0.00 0.00 3x 40 1 10 95 42 1.995 0.166 2.937 0.00 0.00%
0.80 0.00 440 0.80 1.00 3 0.00 0.00 3x 30 1 10 95 42 1.995 0.166 2.937 0.00 0.00%
0.80 0.00 440 0.80 1.00 3 0.00 0.00 3x 50 1 10 95 42 1.995 0.166 2.937 0.00 0.00%
0.80 0.00 440 0.80 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995 0.166 2.937 0.00 0.00%
1.00 0.00 440 0.80 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995 0.166 2.937 0.00 0.00%
1.00 0.00 440 0.80 1.00 3 0.00 0.00 3x 10 1 10 95 42 1.995 0.166 2.937 0.00 0.00%
0.80 0.00 440 0.80 1.00 3 0.00 0.00 3x 225 1 10 95 42 1.995 0.166 2.937 0.00 0.00%
0.80 0.00 440 0.80 1.00 3 0.00 0.00 3x 30 1 10 95 42 1.995 0.166 2.937 0.00 0.00%
N2XOH OK
TABLEROS U (V) cosφ FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) ∑ΔV(%)
TG-CAMP2 380 0.85 3 977.30 1221.62 3x 1250 2 240 1050 15 0.60%
OK N2XOH
TABLEROS U (V) cosφ FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) ∑ΔV(%)
TG-CAMP2
CAMP2-1 Tablero General 1 (TG-1) 380 0.85 3 236.93 296.16 3x 400 1 240 525 5 0.10%
CAMP2-2 Tablero General 2 (TG-2) 380 0.85 3 243.07 303.83 3x 400 2 150 820 84 1.09%
CAMP2-3 Tablero General 3 (TG-3) 380 0.85 3 497.30 621.62 3x 630 2 240 1050 72 1.46%
OK N2XOH
TABLEROS U (V) cosφ FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) ∑ΔV(%)
TG-1 0.10%
TG1-1 T-EA.S 380 0.85 3 272.68 340.85 3x 400 1 150 410 40 1.27%
TG1-2 Ilum. Exterior 380 0.85 3 6.43 8.04 3x 16 1 6 68 236 2.62%
TG1-3 Ilum. Exterior 380 0.85 3 5.72 7.15 3x 16 1 6 68 210 2.09%
TG1-4 Oficina de seguridad (TD-OSEG) 220 0.85 1 33.90 42.38 3x 50 1 6 68 30 3.46%
N2XOH
Edificios de alojamiento
TABLEROS U (V) cosφ FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) ∑ΔV(%)
STAFF
T-EA.S 1.27%
CEA- S-1 Alojamiento Staff 1_TD-AS1 380 0.85 3 7.02 8.78 3x 16 1 4 55 40 0.69%
CEA- S-2 Alojamiento Staff 1_TD-AS2 380 0.85 3 7.02 8.78 3x 16 1 4 55 38 1.92%
CEA- S-3 Alojamiento Staff 1_TD-AS3 380 0.85 3 7.02 8.78 3x 16 1 4 55 32 1.82%
CEA- S-4 Alojamiento Staff 1_TD-AS4 380 0.85 3 7.02 8.78 3x 16 1 4 55 30 1.79%
CEA- S-5 Alojamiento Staff 1_TD-AS5 380 0.85 3 7.02 8.78 3x 16 1 4 55 24 1.68%
CEA- S-6 Alojamiento Staff 1_TD-AS6 380 0.85 3 7.02 8.78 3x 16 1 4 55 22 1.65%
CEA- S-7 Alojamiento Staff 1_TD-AS7 380 0.85 3 7.02 8.78 3x 16 1 4 55 16 1.54%
CEA- S-8 Alojamiento Staff 1_TD-AS8 380 0.85 3 7.02 8.78 3x 16 1 4 55 14 1.51%
CEA- S-9 Alojamiento Staff 1_TD-AS9 380 0.85 3 7.02 8.78 3x 16 1 4 55 15 1.53%
CEA- S-10 Alojamiento Staff 1_TD-AS10 380 0.85 3 7.02 8.78 3x 16 1 4 55 22 1.65%
CEA- S-11 Alojamiento Staff 1_TD-AS11 380 0.85 3 7.02 8.78 3x 16 1 4 55 58 2.27%
CEA- S-12 Alojamiento Staff 1_TD-AS12 380 0.85 3 7.02 8.78 3x 16 1 4 55 52 2.17%
CEA- S-13 Alojamiento Staff 1_TD-AS13 380 0.85 3 7.02 8.78 3x 16 1 4 55 48 2.10%
CEA- S-14 Alojamiento Staff 1_TD-AS14 380 0.85 3 7.02 8.78 3x 16 1 4 55 46 2.06%
CEA- S-15 Alojamiento Staff 1_TD-AS15 380 0.85 3 7.02 8.78 3x 16 1 4 55 40 1.96%
CEA- S-16 Alojamiento Staff 1_TD-AS16 380 0.85 3 7.02 8.78 3x 16 1 4 55 38 1.92%
CEA- S-17 Alojamiento Staff 1_TD-AS17 380 0.85 3 7.02 8.78 3x 16 1 4 55 32 1.82%
CEA- S-18 Alojamiento Staff 1_TD-AS18 380 0.85 3 7.02 8.78 3x 16 1 4 55 30 1.79%
CEA- S-19 Alojamiento Staff 1_TD-AS19 380 0.85 3 7.02 8.78 3x 16 1 4 55 24 1.68%
CEA- S-20 Alojamiento Staff 1_TD-AS20 380 0.85 3 7.02 8.78 3x 16 1 4 55 22 1.65%
CEA- S-21 Alojamiento Staff 1_TD-AS21 380 0.85 3 7.02 8.78 3x 16 1 4 55 23 1.66%
CEA- S-22 Alojamiento Staff 1_TD-AS22 380 0.85 3 7.02 8.78 3x 16 1 4 55 30 1.79%
CEA- S-23 Alojamiento Staff 1_TD-AS23 380 0.85 3 7.02 8.78 3x 16 1 4 55 65 2.39%
CEA- S-24 Alojamiento Staff 1_TD-AS24 380 0.85 3 7.02 8.78 3x 16 1 4 55 59 2.29%
CEA- S-25 Alojamiento Staff 1_TD-AS25 380 0.85 3 7.02 8.78 3x 16 1 4 55 55 2.22%
CEA- S-26 Alojamiento Staff 1_TD-AS26 380 0.85 3 7.02 8.78 3x 16 1 4 55 52 2.17%
CEA- S-27 Alojamiento Staff 1_TD-AS27 380 0.85 3 7.02 8.78 3x 16 1 4 55 47 2.08%
CEA- S-28 Alojamiento Staff 1_TD-AS28 380 0.85 3 7.02 8.78 3x 16 1 4 55 45 2.05%
CEA- S-29 Alojamiento Staff 1_TD-AS29 380 0.85 3 7.02 8.78 3x 16 1 4 55 39 1.94%
CEA- S-30 Alojamiento Staff 1_TD-AS30 380 0.85 3 7.02 8.78 3x 16 1 4 55 37 1.91%
CEA- S-31 Alojamiento Staff 1_TD-AS31 380 0.85 3 7.02 8.78 3x 16 1 4 55 31 1.80%
CEA- S-32 Alojamiento Staff 1_TD-AS32 380 0.85 3 7.02 8.78 3x 16 1 4 55 29 1.77%
CEA- S-33 Alojamiento Staff 1_TD-AS33 380 0.85 3 7.02 8.78 3x 16 1 4 55 30 1.79%
CEA- S-34 Alojamiento Staff 1_TD-AS34 380 0.85 3 7.02 8.78 3x 16 1 4 55 37 1.91%
CEA- S-35 Edificio Gerente 1 380 0.85 3 12.71 15.89 3x 16 1 4 55 19 1.86%
CEA- S-36 Edificio Gerente2 380 0.85 3 10.56 13.20 3x 16 1 4 55 28 2.00%
CEA- S-37 Edificio Gerente 3 380 0.85 3 10.56 13.20 3x 16 1 4 55 35 2.18%
N2XOH
TABLEROS U (V) cosφ FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) ∑ΔV(%)
TG-2 1.09%
TG2-1 Almacen General TD- ALM 380 0.85 3 34.53 43.17 3x 50 1 10 95 40 2.50%
TG2-2 TD 1A 380 0.85 3 84.80 106.00 3x 125 1 25 160 37 2.45%
TG2-3 TD 1B 380 0.85 3 71.46 89.33 3x 100 1 16 125 27 2.35%
TG2-4 TD 2 380 0.85 3 113.04 141.30 3x 160 1 35 195 42 2.62%
OK N2XOH
TABLEROS U (V) cosφ FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) ∑ΔV(%)
TG-3 1.46%
TG3-1 T-EA.1 380 0.85 3 129.15 161.43 3x 200 1 50 230 5 1.62%
TG3-2 T-EA.2 380 0.85 3 129.15 161.43 3x 200 1 75 275 42 2.45%
TG3-3 Ilum. Exterior 380 0.85 3 5.72 7.15 3x 16 1 6 68 130 2.70%
TG3-4 Ilum. Exterior 380 0.85 3 5.72 7.15 3x 16 1 10 95 230 2.80%
TG3-5 T-EA.3 380 0.85 3 129.15 161.43 3x 200 1 150 410 60 2.30%
TG3-6 T-EA.4 380 0.85 3 139.35 174.18 3x 200 1 150 410 86 2.75%
TG3-7 T-EA.5 380 0.85 3 172.20 215.25 3x 250 1 95 330 76 3.36%
TABLEROS Edificios de alojamiento de Obreros 1 U (V) cosφ FASES I (A) Id (A) ITM TERNAS S(mm²) In (cable) (A) L(m) ∑ΔV(%)
T-EA.1 1.62%
T-EA.-1-1 Edificio de Alojamiento_TD-ALO.1 380 0.85 3 23.92 29.90 3x 32 1 4 55 24 3.03%
T-EA.-1-2 Edificio de Alojamiento_TD-ALO.2 380 0.85 3 23.92 29.90 3x 32 1 4 55 16 2.56%
T-EA.-1-3 Edificio de Alojamiento_TD-ALO.3 380 0.85 3 23.92 29.90 3x 32 1 4 55 16 2.56%
T-EA.-1-4 Edificio de Alojamiento_TD-ALO.4 380 0.85 3 23.92 29.90 3x 32 1 4 55 24 3.03%
T-EA.-1-5 Edificio de Alojamiento_TD-ALO.5 380 0.85 3 23.92 29.90 3x 32 1 6 68 36 3.05%
T-EA.-1-6 Edificio de Alojamiento_TD-ALO.6 380 0.85 3 23.92 29.90 3x 32 1 6 68 45 3.40%