Cimbra en Vigas (Viga V-1)
CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE
No. ELEMENTO
P.T. CONTACTO P.T./M2 DESPERDICIO P.T./M2 USO P.T./M2/USO
1 Duela (1''x4''x 5.60m x2)/3.6576 12.25 1/0.7285 16.81 1.2 20.18 5 4.04
2 Yugo (2''x4''x0.35m x 24)/3.6576 18.37 1/0.7285 25.22 1.2 30.26 5 6.05
3 Base (2''x4''x 5.60m x 1)/3.6576 12.25 1/0.7285 16.81 1.2 20.18 7 2.88
4 Madrina (4''x4''x 1m x 6)/3.6576 26.25 1/0.7285 36.03 1.2 43.23 10 4.32
5 Patas gallo (1''x4''x 0.40m x 6)/3.6576 2.62 1/0.7285 3.60 1.2 4.32 8 0.54
6 Pie derecho (4''x4''x 2.75m x 6)/3.6576 72.18 1/0.7285 99.08 1.2 118.89 10 11.89
7 Contraviento (1''x4'' x 5.6m x(2))/3.6576 12.25 1/0.7285 16.81 1.2 20.18 5 4.04
8 Arrastre (4''x4''x 1m x6)/3.6576 26.25 1/0.7285 36.03 1.2 43.23 10 4.32
9 Cuñas (2''x4''x1'x6)/3.6576 4.00 1/0.7285 5.49 1.2 6.59 5 1.32
10 Cachetes (1''x4''x1' x12)/3.6576 4.00 1/0.7285 5.49 1.2 6.59 5 1.32

Total 7.27
INSTITUTO TECNOLOGICO DE CIUDAD VICTORIA
COSTOS Y PRESUPUESTOS
Ing. Lancelot Anael Ruidias Ardito
Castillos (K-3)
CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE
No. ELEMENTO
P.T. CONTACTO P.T./M2 DESPERDICIO P.T./M2 USO P.T./M2/USO
1 Duela (1''x4''x 2.70m x4)/3.6576 11.81 1/0.75 15.75 1.2 18.90 5 3.78
2 Yugo (1 1/2''x3''x0.8167m x5 )/3.6576 5.02 1/0.75 6.70 1.2 8.04 5 1.61
3 Pie derecho (2''x4''x 2.26m x 2)/3.6576 9.89 1/0.75 13.18 1.2 15.82 10 1.58
4 Estacas (2''x4''x1'x2)/3.6576 1.33 1/0.75 1.78 1.2 2.13 8 0.27
5 Arrastre (2''x4''x0.98m x2)/3.6576 4.29 1/0.75 5.72 1.2 6.86 10 0.69

Total 2.93
INSTITUTO TECNOLOGICO DE CIUDAD VICTORIA
COSTOS Y PRESUPUESTOS
Ing. Lancelot Anael Ruidias Ardito
Columna (C-1)
CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE
No. ELEMENTO
P.T. CONTACTO P.T./M2 DESPERDICIO P.T./M2 USO P.T./M2/USO
1 Duela en contacto (1''x4''x 2.70m x12)/3.6576 11.81 1/1.2 9.84 1.2 11.81 5 2.36
2 Yugo (2''x4''x 2.6m x6 )/3.6576 34.12 1/1.2 28.43 1.2 34.12 5 6.82
3 Pie derecho (4''x4''x 2.43m x 4)/3.6576 42.52 1/1.2 35.43 1.2 42.52 10 4.25
4 Plomos (1''x4''x1.5m x 2)/3.6576 3.28 1/1.2 2.73 1.2 3.28 8 0.41
5 Estacas (2''x4''x0.40m x4)/3.6576 3.50 1/1.2 2.92 1.2 3.50 10 0.35

Total 5.26
INSTITUTO TECNOLOGICO DE CIUDAD VICTORIA
COSTOS Y PRESUPUESTOS
Ing. Lancelot Anael Ruidias Ardito
Contratabe (Dado)
CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE
No. ELEMENTO
P.T. CONTACTO P.T./M2 DESPERDICIO P.T./M2 USO P.T./M2/USO
1 Duela en contacto (1''x4''x 0.40m x27)/3.6576 11.81 1/0.80 14.76 1.2 17.72 5 3.54
2 Yugo (2''x4''x 1.55m x4 )/3.6576 13.56 1/0.80 16.95 1.2 20.34 5 4.07
3 Separadores (2''x4''x 0.48m x 2)/3.6576 2.10 1/0.80 2.62 1.2 3.15 10 0.31
4 Madrinas (2''x4''x0.4m x 4)/3.6576 3.50 1/0.80 4.37 1.2 5.25 8 0.66
5 Pie derecho (4''x4''x0.5m x8)/3.6576 17.50 1/0.80 21.87 1.2 26.25 10 2.62
6 Arrastres (1''x4''x1.485m x 4)/3.6576 6.50 1/0.80 8.12 1.2 9.74 8 1.22

Total 10.02
INSTITUTO TECNOLOGICO DE CIUDAD VICTORIA
COSTOS Y PRESUPUESTOS
Ing. Lancelot Anael Ruidias Ardito
Zapata Corrida (ZC-1)
CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE
No. ELEMENTO
P.T. CONTACTO P.T./M2 DESPERDICIO P.T./M2 USO P.T./M2/USO
1 Duela (1''x4''x26.15m x2)/3.6576 57.20 1/0.30 190.65 1.2 228.78 5 45.76
2 Yugo (2''x4''x0.35m x104)/3.6576 79.62 1/0.30 265.38 1.2 318.46 5 63.69
3 Clavo de madera de 2 1/2'' 40 PZA/M2

Total 3.74
COSTOS Y PRESUPUESTOS
Ing. Lancelot Anael Ruidias Ardito
Zapata Corrida (ZC-2)
CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE
No. ELEMENTO
P.T. CONTACTO P.T./M2 DESPERDICIO P.T./M2 USO P.T./M2/USO
1 Duela (1''x4''x 90.98m x1)/3.6576 99.50 1/0.30 331.66 1.2 397.99 5 79.60
2 Yugo (2''x4''x0.35m x364)/3.6576 278.65 1/0.30 928.84 1.2 1114.61 5 222.92
3 Clavo de madera de 2 1/2'' 40 PZA/M2

Total 6.74
INSTITUTO TECNOLOGICO DE CIUDAD VICTORIA
COSTOS Y PRESUPUESTOS
Ing. Lancelot Anael Ruidias Ardito
Zapata Corrida (ZC-3)
CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE
No. ELEMENTO
P.T. CONTACTO P.T./M2 DESPERDICIO P.T./M2 USO P.T./M2/USO
1 Duela (1''x4''x 47.45m x2)/3.6576 103.78 1/0.30 345.95 1.2 415.14 5 83.03
2 Yugo (2''x4''x0.35m x190)/3.6576 145.45 1/0.30 484.84 1.2 581.80 5 116.36
3 Clavo de madera de 2 1/2'' 40 PZA/M2

Total 4.26
INSTITUTO TECNOLOGICO DE CIUDAD VICTORIA
COSTOS Y PRESUPUESTOS
Ing. Lancelot Anael Ruidias Ardito
Cimbra en Trabes (Trabe T-1)
CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE
No. ELEMENTO
P.T. CONTACTO P.T./M2 DESPERDICIO P.T./M2 USO P.T./M2/USO
1 Duela (1''x4''x 5.20m x2)/3.6576 11.37 1/1.20 9.48 1.2 11.37 5 2.27
2 Yugo (2''x4''x0.35m x20)/3.6576 15.31 1/1.20 12.76 1.2 15.31 5 3.06
3 Base (2''x4''x 5.20m x1)/3.6576 11.37 1/1.20 9.48 1.2 11.37 7 1.62
4 Madrina (4''x4''x 1m x6)/3.6576 26.25 1/1.20 21.87 1.2 26.25 10 2.62
5 Patas gallo (1''x4''x 0.40m x6)/3.6576 2.62 1/1.20 2.19 1.2 2.62 8 0.33
6 Pie derecho (4''x4''x 2.75m x6)/3.6576 72.18 1/1.20 60.15 1.2 72.18 10 7.22
7 Contraviento (1''x4'' x 4m x(2))/3.6576 8.75 1/1.20 7.29 1.2 8.75 5 1.75
8 Arrastre (4''x4''x 1m x6)/3.6576 26.25 1/1.20 21.87 1.2 26.25 10 2.62
9 Cuñas (2''x4''x1' x6)/3.6576 4.00 1/1.20 3.33 1.2 4.00 5 0.80
10 Cachetes (1''x4''x1' x12)/3.6576 4.00 1/1.20 3.33 1.2 4.00 5 0.80

Total 4.44
INSTITUTO TECNOLOGICO DE CIUDAD VICTORIA
COSTOS Y PRESUPUESTOS
Ing. Lancelot Anael Ruidias Ardito
Castillos (K1)
CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE
No. ELEMENTO
P.T. CONTACTO P.T./M2 DESPERDICIO P.T./M2 USO P.T./M2/USO
1 Duela (1''x4''x 2.70m x2)/3.6576 5.91 1/0.30 19.69 1.2 23.62 5 4.72
2 Yugo (1 1/2''x3''x0.35m x5)/3.6576 2.15 1/0.30 7.18 1.2 8.61 5 1.72
3 Pie derecho (2''x4''x2.26m x2)/3.6576 9.89 1/0.30 32.95 1.2 39.55 10 3.95
4 Estacas (2''x4''x1' x2)/3.6576 1.33 1/0.30 4.44 1.2 5.33 7 0.76
5 Arrastre (2''x4''x0.98m x2)/3.6576 4.29 1/0.30 14.29 1.2 17.15 10 1.71

Total 4.77
INSTITUTO TECNOLOGICO DE CIUDAD VICTORIA
COSTOS Y PRESUPUESTOS
Ing. Lancelot Anael Ruidias Ardito
Firme
CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE
No. ELEMENTO
P.T. CONTACTO P.T./M2 DESPERDICIO P.T./M2 USO P.T./M2/USO
1 Duela (1''x4''x 1m x4)/3.6576 4.37 1/0.10 43.74 1.2 52.49 5 10.50
2 Yugo (1 1/2''x3''x3m x1)/3.6576 3.69 1/0.10 36.91 1.2 44.29 5 8.86

Total 0.16
INSTITUTO TECNOLOGICO DE CIUDAD VICTORIA
COSTOS Y PRESUPUESTOS
Ing. Lancelot Anael Ruidias Ardito
Zapata Aislada (ZA-1)
CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE
No. ELEMENTO
P.T. CONTACTO P.T./M2 DESPERDICIO P.T./M2 USO P.T./M2/USO
1 Duela (1''x4''x1.20m x4)/3.6576 5.25 1/0.6 8.75 1.2 10.50 5 2.10
2 Yugo (2''x4''x0.35m x8)/3.6576 6.12 1/0.6 10.21 1.2 12.25 5 2.45
3 Clavo de madera de 2 1/2'' 40 PZA/M2

Total 4.55
INSTITUTO TECNOLOGICO DE CIUDAD VICTORIA
COSTOS Y PRESUPUESTOS
Ing. Lancelot Anael Ruidias Ardito
Escalera
CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE
No. ELEMENTO
P.T. CONTACTO P.T./M2 DESPERDICIO P.T./M2 USO P.T./M2/USO
1 Duela (1''x4''x5.4m x14)/3.6576 82.68 1/1.74 47.52 1.2 57.02 5 11.40
2 Duela (1''x4''x1.23m x30)/3.6577 40.35 1/1.74 23.19 1.2 27.83 6 4.64
3 Separadores (2''x4''x0.40m x24)/3.6576 21.00 1/1.74 12.07 1.2 14.48 8 1.81
4 Pie Derecho (4''x4''x 2.7m x4)/3.6577 47.24 1/1.74 27.15 1.2 32.58 10 3.26
5 Contraventeo (1''x4''x0.675m x6)/3.6576 4.43 1/1.74 2.55 1.2 3.05 3 1.02

Total 19.08

INSTITUTO TECNOLOGICO DE CIUDAD VICTORIA


COSTOS Y PRESUPUESTOS
Ing. Lancelot Anael Ruidias Ardito
Losa
CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE
No. ELEMENTO
P.T. CONTACTO P.T./M2 DESPERDICIO P.T./M2 USO P.T./M2/USO
1 Duela (1"x4"x4mx40)/3.6576 174.98 0.0625 10.94 1.2 13.12 5 2.62
2 Madrina (4"x4"x4mx5)/3.6576 87.49 0.0625 5.47 1.2 6.56 10 0.66
3 Pie Derecho (4"x4"x2.45mx25)/3.6576 267.94 0.0625 16.75 1.2 20.10 10 2.01
4 Contravientos (1"x4"x4mx16)/3.6576 43.74 0.0625 2.73 1.2 3.28 5 0.66
5 Cachetes (1"x4"x1'x100)/3.6576 33.33 0.0625 2.08 1.2 2.50 5 0.50
6 Cuña (2"x4"x1´x50)/3.6576 33.33 0.0625 2.08 1.2 2.50 5 0.50
7 Arrastre (4"x4"x1mx25)/3.6576 109.36 0.0625 6.84 1.2 8.20 10 0.82
8 Chaflan (1"x4x1mx16)/3.6576 17.50 0.0625 1.09 1.2 1.31 5 0.26

Total 8.03

INSTITUTO TECNOLOGICO DE CIUDAD VICTORIA


COSTOS Y PRESUPUESTOS
Ing. Lancelot Anael Ruidias Ardito
Dala
CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE FACTOR DE CANTIDAD DE
No. ELEMENTO
P.T. CONTACTO P.T./M2 DESPERDICIO P.T./M2 USO P.T./M2/USO
1 Duela (1"x4"x20mx2)/3.6576 43.74 0.05 2.19 1.20 2.62 5.00 0.52
2 Yugo (2''x4''x0.35m x82)/3.6576 62.77 0.05 3.14 1.20 3.77 5.00 0.75
3 Separadores (2''x4''x0.25m x41)/3.6576 11.21 0.05 0.56 1.20 0.67 5.00 0.13
Total 1.41
Planta Alta
Vacio
No. Elemento Cantidad F. Contacto Cantidad PT/M2
Factor de desperdicio
Cantidad PT/M2Factor de uso
1 Duela 1"*4"*(40 Pza)*4m
174.98 0.06 10.94 1.20 13.12 5.00
2 Madrina 4"*4"*(5 Pza)*4m
87.49 0.06 5.47 1.20 6.56 10.00
3 Pie Derecho 4"*4"*(25
267.94
Pza)*2.45m 0.06 16.75 1.20 20.10 10.00
4 Contravientos 1"*4"*(10
43.74Pza)*4 0.06 2.73 1.20 3.28 5.00
5 Cachetes 1"*4"*(100 33.33
Pza)*.3048m 0.06 2.08 1.20 2.50 5.00
6 Cuña 2"*4"*(50 Pza)*.3048m
33.33 0.06 2.08 1.20 2.50 5.00
7 Arrastre 4"*4"*(25 Pza)*1m
109.36 0.06 6.84 1.20 8.20 10.00
8 Chaflan 1"*4*(16 Pza)*1m
17.50 0.06 1.09 1.20 1.31 5.00
Suma

Materiales
Clave Descripcion Unidad Cantidad P.U. Importe
Madera PT 8.03 11 88.33
Diesel LT 0.5 16.95 8.475
Clavo 2 1/2 KG 0.1384615 25.79 3.5709231
Clavo 3 1/2 KG 0.1904762 29.9 5.6952381
SUB TOTAL (1) IMPORTE POR MATERIALES SUMA $ 106.07116

Materiales
Clave Descripcion Unidad Cantidad P.U. Importe
Duela (1''x4''x 4m xPT
40)/3.6576 2.62 11.00 28.87
Madrina 4"*4"*(5 Pza)*4m
PT 0.66 11.00 7.22
Pie Derecho 4"*4"*(25
PT Pza)*2.45m 2.01 11.00 22.10
Contravientos 1"*4"*(10
PT Pza)*4 0.66 11.00 7.22
Cachetes 1"*4"*(100
PTPza)*.3048m 0.50 11.00 5.50
Cuña 2"*4"*(50 Pza)*.3048m
PT 0.50 11.00 5.50
Arrastre 4"*4"*(25PT
Pza)*1m 0.82 11.00 9.02
Chaflan 1"*4*(16 Pza)*1m
PT 0.26 11.00 2.89
Diesel LT 0.50 16.94 8.47
Clavo 2 1/2 KG 0.14 25.79 3.57
Clavo 3 1/2 KG 0.19 29.90 5.70
SUB TOTAL (1) IMPORTE POR MATERIALES SUMA $ 106.06

Dala De Desplante

No. Elemento Cantidad F. Contacto Cantidad PT/M2


Factor de desperdicio
Cantidad PT/M2Factor de usoCantidad
1 Forro 1"*4"*(2 Pza)*20 m 43.74 0.05 2.19 1.20 2.62 5.00 0.52
2 Retenes Yugo 2"*4"*(82 Pza)*.3048 m 54.67 0.05 2.73 1.20 3.28 5.00 0.66
3 Horqueta Separadaores 1"*4"*(41 Pza)*.20 m 8.97 0.05 0.45 1.20 0.54 5.00 0.11
Suma 1.29

Materiales
Clave Descripcion Unidad Cantidad P.U. Importe
Madera PT 1.29 11 14.174005
Diesel LT 0.5 16.95 8.475
Clavo 2 1/2 KG 0.0923077 25.79 2.3806154

OTAL (1) IMPORTE POR MATERIALES SUMA $ 25.029621

Materiales
Clave Descripcion Unidad Cantidad P.U. Importe
Duela (1''x4''x 4m x 40)/3.6576 PT 0.52 11.00 5.77
Retenes Yugo 2"*4"*(82 Pza)*.3048 m PT 0.66 11.00 7.22
Horqueta Separadaores 1"*4"*(41 Pza)*.20 m PT 0.11 11.00 1.18
Diesel LT 0.50 16.94 8.47
Clavo 2 1/2 KG 0.09 25.79 2.38

SUMA $ 25.02

OTAL (1) IMPORTE POR MATERIALES


Materiales
Clave Descripcion Unidad Cantidad P.U. Importe
Madera PT 7.27 11 79.981028
Diesel LT 0.5 16.95 8.475
Clavo 2 1/2 KG 0.1384615 25.79 3.5709231
Clavo 3 1/2 KG 0.1904762 29.9 5.6952381

SUB TOTAL (1) IMPORTE POR MATERIALES SUMA $ 97.72219


Materiales
Clave Descripcion Unidad Cantidad P.U. Importe
Madera PT 2.93 11 32.273136
Diesel LT 0.5 16.95 8.475
Clavo 2 1/2 KG 0.1384615 25.79 3.5709231
Clavo 3 1/2 KG 0.1904762 29.9 5.6952381

SUB TOTAL (1) IMPORTE POR MATERIALES SUMA $ 50.014297


Materiales
Clave Descripcion Unidad Cantidad P.U. Importe
Madera PT 5.26 11 57.845258
Diesel LT 0.5 16.95 8.475
Clavo 2 1/2 KG 0.1384615 25.79 3.5709231
Clavo 3 1/2 KG 0.1904762 29.9 5.6952381

SUB TOTAL (1) IMPORTE POR MATERIALES SUMA $ 75.586419


Materiales
Clave Descripcion Unidad Cantidad P.U. Importe
Madera PT 10.02 11 110.22498
Diesel LT 0.5 16.95 8.475
Clavo 2 1/2 KG 0.1384615 25.79 3.5709231
Clavo 3 1/2 KG 0.1904762 29.9 5.6952381

SUB TOTAL (1) IMPORTE POR MATERIALES SUMA $ 127.96614


Materiales
Clave Descripcion Unidad Cantidad P.U. Importe
Madera PT 3.74 11 41.16024
Diesel LT 0.5 16.95 8.475
Clavo 2 1/2 KG 0.1384615 25.79 3.5709231
Clavo 3 1/2 KG 0.1904762 29.9 5.6952381

SUB TOTAL (1) IMPORTE POR MATERIALES SUMA $ $ 58.90


Materiales
Clave Descripcion Unidad Cantidad P.U. Importe
Madera PT 6.74 11 74.180039
Diesel LT 0.5 16.95 8.475
Clavo 2 1/2 KG 0.1384615 25.79 3.5709231
Clavo 3 1/2 KG 0.1904762 29.9 5.6952381

SUB TOTAL (1) IMPORTE POR MATERIALES SUMA $ 91.9212


Materiales
Clave Descripcion Unidad Cantidad P.U. Importe
Madera PT 4.26 11 46.814586
Diesel LT 0.5 16.95 8.475
Clavo 2 1/2 KG 0.1384615 25.79 3.5709231
Clavo 3 1/2 KG 0.1904762 29.9 5.6952381

SUB TOTAL (1) IMPORTE POR MATERIALES SUMA $ $ 64.56


Materiales
Clave Descripcion Unidad Cantidad P.U. Importe
Madera PT 4.44 11 48.879529
Diesel LT 0.5 16.95 8.475
Clavo 2 1/2 KG 0.1384615 25.79 3.5709231
Clavo 3 1/2 KG 0.1904762 29.9 5.6952381

SUB TOTAL (1) IMPORTE POR MATERIALES SUMA $ 66.620691


Materiales
Clave Descripcion Unidad Cantidad P.U. Importe
Madera PT 4.77 11 52.466115
Diesel LT 0.5 16.95 8.475
Clavo 2 1/2 KG 0.1384615 25.79 3.5709231
Clavo 3 1/2 KG 0.1904762 29.9 5.6952381

SUB TOTAL (1) IMPORTE POR MATERIALES SUMA $ 70.207277


Materiales
Clave Descripcion Unidad Cantidad P.U. Importe
Madera PT 0.16 11 1.7600141
Diesel LT 0.5 16.95 8.475
Clavo 2 1/2 KG 0.1384615 25.79 3.5709231
Clavo 3 1/2 KG 0.1904762 29.9 5.6952381

SUB TOTAL (1) IMPORTE POR MATERIALES SUMA $ 19.501175


Materiales
Clave Descripcion Unidad Cantidad P.U. Importe
Madera PT 4.55 11 50.043745
Diesel LT 0.5 16.95 8.475
Clavo 2 1/2 KG 0.1384615 25.79 3.5709231

SUB TOTAL (1) IMPORTE POR MATERIALES SUMA $ $ 62.09


Materiales
Clave Descripcion Unidad Cantidad P.U. Importe
Madera PT 19.08 11 209.84112
Diesel LT 0.5 16.95 8.475
Clavo 2 1/2 KG 0.1384615 25.79 3.5709231
Clavo 3 1/2 KG 0.1904762 29.9 5.6952381

SUB TOTAL (1) IMPORTE POR MATERIALES SUMA $ 227.58228


Materiales
Clave Descripcion Unidad Cantidad P.U. Importe
Madera PT 8.03 11 88.33
Diesel LT 0.8 16.95 13.56
Clavo 2 1/2 KG 0.1384615 25.79 3.5709231
Clavo 3 1/2 KG 0.1904762 29.9 5.6952381

SUB TOTAL (1) IMPORTE POR MATERIALES SUMA $ 111.15616

Materiales
Clave Descripcion Unidad Cantidad P.U. Importe
Madera PT 1.41 11 15.540026
Diesel LT 0.5 16.95 8.475
Clavo 2 1/2 KG 0.1384615 25.79 3.5709231
Clavo 3 1/2 KG 0.1904762 29.9 5.6952381

SUB TOTAL (1) IMPORTE POR MATERIALES SUMA $ 33.281187

Cantidad
2.62
0.66
2.01
0.66
0.50
0.50
0.82
0.26
8.03
cimbra importe

Cimbra en Vigas (Viga V-1) $ 97.72


Castillos (K-3) $ 50.01
Columna (C-1) $ 75.59
Contratabe (Dado) $ 127.97
Zapata Corrida (ZC-1) $ 58.90
Zapata Corrida (ZC-2) $ 91.92
Zapata Corrida (ZC-3) $ 64.56
Cimbra en Trabes (Trabe T-1) $ 66.62
Castillos (K1) $ 70.21
Firme $ 19.50
Zapata Aislada (ZA-1) $ 62.09
Escalera $ 227.58
Losa $ 111.16
Dala $ 33.28
Zapata Aislada (ZA-2) $ 62.09
Dala de Desplante $ 25.02
Castillos (K-2) $ 70.21
Columna (C-2) $ 75.59