GRUPO 6 :

NICOLAS ASALDE CUADRO DE METRADO ESTRUCTURAS


PIETRO TUANAMA
JULISSA NEIRA
PARTIDAS : ACERO DE REFUERZO

ACERO FY = 4,200 KG/CM2 LONGITUD TOTAL


UBICACI0N UBICACIÓN Nº DE 6mm 1/4" 8mm 3/8" 12mm 1/2" 5/8" 3/4" 1"
DIAM. CANT. LONG.
VECES 0.222 0.250 0.395 0.560 0.888 0.994 1.552 2.235 3.973
ZAPATA 3.10 m x 2.35 m (Z2) Eje 2-B
Acero Horizontal 1.00 3/4 15 3.25 48.18
Acero Vertical 1.00 3/4 19 2.50 46.62

ZAPATA 2.85 m x 2.15m (Z3) EJE 5-B


Acero Horizontal 1.00 3/4 14 3.00 40.94
Acero Vertical 1.00 3/4 14 2.30 31.39

COLUMNA C-1 (0.25x1.0)/Sotano 3 Eje 2-C

Acero Principal 1.00 1 20 4.15 83.00


Estribo 1.00 3/8 23 2.70 61.43
Gancho 1.00 3/8 23 0.28 6.37

COLUMNA C-2 (0.25x1.0)/Sotano 3 Eje 5-F

Acero Principal 1.00 3/8 20 4.15 83.00


Estribo 1.00 1 23 2.70 61.43
Gancho 1.00 1 23 0.30 6.83
TOTAL POR DIAM. EN M. 67.80 167.12 83.00
TOTAL POR DIAM. EN KG. 37.97 373.52 329.76
DESPERDICIO 1.05 1.05 1.05 1.05 1.05 1.05 1.05 1.08 1.08
Total Desperdicio 39.86 403.40 356.14
TOTAL GENERAL EN KG. 799.41

1de2
GRUPO 6 :
NICOLAS ASALDE CUADRO DE METRADO ESTRUCTURAS
PIETRO TUANAMA
JULISSA NEIRA
PARTIDAS : ACERO DE REFUERZO

ACERO FY = 4,200 KG/CM2 LONGITUD TOTAL


UBICACI0N UBICACIÓN Nº DE 6mm 1/4" 8mm 3/8" 12mm 1/2" 5/8" 3/4" 1"
DIAM. CANT. LONG.
VECES 0.222 0.250 0.395 0.560 0.888 0.994 1.552 2.235 3.973

2de2

También podría gustarte