Z1
NUMERO DE VARILLAS (9 m) 0.00
PESO DE VARILLA (Kg/m) 2.240
PESO (Kg) 0.00
TOTAL 10.14
Z2
NUMERO DE VARILLAS (9 m) 0.00
PESO DE VARILLA (Kg/m) 2.240
PESO (Kg) 0.00
TOTAL 44.83
Z3
NUMERO DE VARILLAS (9 m) 0.00
PESO DE VARILLA (Kg/m) 2.240
PESO (Kg) 0.00
TOTAL 18.62
V1
VIGA
INTERMEDIO 3.15
COLUMNA
C1
NUMERO DE VARILLAS (9 m) 0.00 0.00 2.30 2.90
PESO DE VARILLA (Kg/m) 2.240 1.552 0.994 0.559
PESO (Kg) 0.00 0.00 20.58 14.40
TOTAL 34.98 Kg
INTERMEDIO 3.15
COLUMNA
C2
NUMERO DE VARILLAS (9 m) 0.00 0.00 2.30 4.20
PESO DE VARILLA (Kg/m) 2.240 1.552 0.994 0.559
PESO (Kg) 0.00 0.00 20.58 20.66
TOTAL 41.24 Kg
FECHA: 05/08/2022
MONTO TOTAL: S/ 59,906.57
LONGITUDES (m)
5/8" 1/2" 3/8"
5.10
5.10
0.00 10.20 0.00
0.00 1.13 0.00
1.552 0.994 0.559
0.00 10.14 0.00
10.14 Kg
LONGITUDES (m)
5/8" 1/2" 3/8"
22.55
22.55
0.00 45.10 0.00
0.00 5.01 0.00
1.552 0.994 0.559
0.00 44.83 0.00
44.83 Kg
LONGITUDES (m)
5/8" 1/2" 3/8"
6.00
6.00
12.00 0.00 0.00
1.33 0.00 0.00
1.552 0.994 0.559
18.62 0.00 0.00
18.62 Kg
N° DE ESTRIBOS
LUZ LIBRE 3.75
DIST. @ CANT. DIST
0.05 4 0.20
0.10 10 1.00
0.15 10 1.50
0.20 5 1.05
TOTAL 29
N° DE ESTRIBOS
ALTURA DE PISO 2.8
DIST. @ CANT. DIST
0.05 4 0.20
0.10 20 2.00
0.15 0 0.00
0.20 2 0.60
TOTAL 26
N° DE ESTRIBOS
ALTURA DE PISO 2.8
DIST. @ CANT. DIST
0.05 4 0.20
0.10 20 2.00
0.15 0 0.00
0.20 2 0.60
TOTAL 26
PRESUPUESTO DE OBRA
PROYECTO : "CREACIÓN DE VIVIENDAS UNIFAMILIARES"
CLIENTE : SR. RICHARD TAIPE PALOMINO
RESIDENTE : ING. RAUL CASTILLON GALVEZ CIP. 124567 FECHA:
SUPERVISOR : ARG. DANIEL DE LA CRUZ SUAREZ CIP. 184745 MONTO TOTAL:
ESPECIALIDA: ESTRUCTURA
TOTAL
S/ 2,500.00
S/ 1,750.00
S/ 2,000.00
S/ 993.52
S/ 245.29
S/ 204.00
S/ 2,241.40
S/ 8,118.45
S/ 3,607.20
S/ 3,000.00
S/ 6,558.74
S/ 3,412.80
S/ 742.98
S/ 3,481.68
S/ 2,995.20
S/ 1,172.70
S/ 43,023.96
S/ 4,302.40
S/ 3,441.92
S/ 50,768.28
S/ 9,138.29
S/ 59,906.57
CRONOGRAMA VALORIZADO DE OBRA
PROYECTO : "CREACIÓN DE VIVIENDAS UNIFAMILIARES"
CLIENTE : SR. RICHARD TAIPE PALOMINO
RESIDENTE : ING. RAUL CASTILLON GALVEZ CIP. 124567 FECHA: 05/08/2022
SUPERVISOR : ARG. DANIEL DE LA CRUZ SUAREZ CIP. 184745 MONTO TOTAL: S/ 59,906.57
ESPECIALIDA : ESTRUCTURA
ITEM PARTIDAS UND. METRADO P.U. TOTAL Aug-22 Sep-22 Oct-22 Nov-22 Dec-22 Jan-23 Feb-23 Mar-23
01 ESTRUCTURAS
01.01. TRABAJOS PRELIMINARES
01.01.01. LIMPIEZA DE TERRENO MANUAL M2 500.00 S/ 5.00 S/ 2,500.00
01.01.02. TRAZO Y REPLANTEO INICIAL M2 500.00 S/ 3.50 S/ 1,750.00
01.02. MOVIMIENTO DE TIERRAS S/ -
01.02.01. EXCAVACIÓN C/ MAQUINARIA DE H=1.00m P/ SEMI M3 500.00 S/ 4.00 S/ 2,000.00
01.02.02. EXCAVACIÓN DE ZANJAS PARA ZAPATAS M3 14.24 S/ 69.77 S/ 993.52
01.02.03. EXCAVACIÓN DE ZANJAS PARA CIMIENTOS M3 2.88 S/ 85.17 S/ 245.29
01.02.04. EXCAVACIÓN DE ZANJAS PARA TUBERIA DE DESAGÜE M3 3.40 S/ 60.00 S/ 204.00
01.02.05. NIVELACIÓN Y PERFILADO DE ZANJAS M2 320.20 S/ 7.00 S/ 2,241.40
01.02.06. RELLENO Y NIVELACIÓN DE ZANJAS M3 180.45 S/ 44.99 S/ 8,118.45
01.02.07. ELIMINACIÓN DE MATERIAL EXCEDENTE M3 240.48 S/ 15.00 S/ 3,607.20
01.03. CONCRETO ARMADO
01.03.01. ACERO PARA ZAPATAS KG 200.00 S/ 15.00 S/ 3,000.00
01.03.02. CONCRETO PARA ZAPATAS M3 15.80 S/ 415.11 S/ 6,558.74
01.03.03. ENCOFRADO DE COLUMNAS M2 47.40 S/ 72.00 S/ 3,412.80
01.03.04. ACERO PARA COLUMNAS KG 139.92 S/ 5.31 S/ 742.98
01.03.05. CONCRETO PARA COLUMNAS M3 8.00 S/ 435.21 S/ 3,481.68
01.03.06. ENCOFRADO DE VIGAS M2 38.40 S/ 78.00 S/ 2,995.20
01.03.07. ACERO PARA VIGAS KG 234.54 S/ 5.00 S/ 1,172.70
COSTO DIRECTO S/ 43,023.96
GASTOS GENERALES (10%) S/ 4,302.40
UTILIDAD (8%) S/ 3,441.92
SUB TOTAL S/ 50,768.28
IGV (18%) S/ 9,138.29
PRESUPUESTO DE OBRA S/ 59,906.57
PRESUPUESTO DE OBRA
PROYECTO "CREACIÓN DE VIVIENDAS UNIFAMILIARES"
CLIENTE SR. RICHARD TAIPE PALOMINO
RESIDENTE ING. RAUL CASTILLON GALVEZ CIP. 124567 FE
SUPERVISOR ARG. DANIEL DE LA CRUZ SUAREZ CIP. 184745 MONTO T
ESPECIALIDAD ESTRUCTURA
ITEM Nombre de tarea UND METRADO P.U. TOTAL SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8 SEMANA 9
1 OBRAS PROVISIONALES, TRABAJOS PRELIMINARES, SEGURIDAD Y
SALUD S/ 16,098.62
S/ 6,556.14 S/ 1,108.52 S/ 959.59 S/ 959.59 S/ 959.59 S/ 959.59 S/ 959.59 S/ 959.59 S/ 959.59
1.01 PLAN PARA LA VIGILANCIA, PREVENCIÓN Y CONTROL DE COVID-19 S/ 4,301.00
S/ 1,027.88 S/ 339.80 S/ 339.80 S/ 339.80 S/ 339.80 S/ 339.80 S/ 339.80 S/ 339.80 S/ 339.80
01.01.01 LIMPIEZA Y DESINFECCIÓN DEL CENTRO DE TRABAJO S/ 423.00 S/ 423.00
01.01.02 EVALUACIÓN DE LAS CONDICIONES DE SALUD DEL TRABAJADOR
PREVIO AL INICIO A OBRA S/ 480.00
S/ 480.00
01.01.03 LAVADO Y DESINFECCION DE MANOS S/ 1,028.00 S/ 27.54 S/ 102.80 S/ 102.80 S/ 102.80 S/ 102.80 S/ 102.80 S/ 102.80 S/ 102.80 S/ 102.80
SENSIBILIZACION DE LA PREVENCION DEL CONTAGIO EN EL
01.01.04 CENTRO DE TRABAJO S/ 2,370.00
S/ 97.34 S/ 237.00 S/ 237.00 S/ 237.00 S/ 237.00 S/ 237.00 S/ 237.00 S/ 237.00 S/ 237.00
1.02 PROCEDIMIENTO OBLIGATORIO PARA INICIO DE LOS TRABAJOS S/ 6,375.00
S/ 254.57 S/ 619.79 S/ 619.79 S/ 619.79 S/ 619.79 S/ 619.79 S/ 619.79 S/ 619.79 S/ 619.79
01.02.01 PROCESO PARA INICIO DEL TRABAJO S/ 6,375.00 S/ 254.57 S/ 619.79 S/ 619.79 S/ 619.79 S/ 619.79 S/ 619.79 S/ 619.79 S/ 619.79 S/ 619.79
1.03 TRABAJOS PRELIMINARES S/ 503.44 S/ 503.44
01.03.01 CARTEL DE OBRA de 4.00 X 2.50 S/ 503.44 S/ 503.44
1.04 TRAZO, NIVELES Y REPLANTEO PRELIMINAR S/ 1,191.38 S/ 1,042.46 S/ 148.92
01.04.01 LIMPIEZA, TRAZOS, NIVELES (REPLANTEO PRELIMINAR) S/ 1,191.38 S/ 1,042.46 S/ 148.92
1.05 SEGURIDAD Y SALUD S/ 3,727.80 S/ 3,727.80
01.05.01 EQUIPO DE SEGURIDAD INDIVIDUAL S/ 2,244.00 S/ 2,244.00
01.05.02 EQUIPO DE SEGURIDAD COLECTIVA S/ 377.20 S/ 377.20
01.05.03 SEÑALIZACIÓN TEMPORAL DE SEGURIDAD S/ 106.60 S/ 106.60
01.05.04 CAPACITACION EN SALUD Y SEGURIDAD S/ 1,000.00 S/ 1,000.00
2 MOVIMIENTO DE TIERRAS S/ 12,459.29 S/ 12,459.29
2.01 EXCAVACIONES S/ 12,459.29 S/ 12,459.29
02.01.01 CORTE Y EXPLANACIÓN DE TERRENO NORMAL MANUAL (APORTE) S/ 9,390.16
S/ 9,390.16
02.01.02 EXCAVACION DE ZANJAS HASTA H=1.00m S/ 3,069.13 S/ 3,069.13
3 OBRAS DE CONCRETO SIMPLE S/ 25,627.23 S/ 4,006.81 S/ 13,349.30 S/ 8,271.12
3.01 CIMIENTO S/ 12,141.72 S/ 4,006.81 S/ 8,134.91
03.01.01 SOLADO 1:10, E=10cm S/ 770.29 S/ 224.67 S/ 545.62
CIMIENTO CORRIDO DE CONCRETO CICLOPEO MEZCLA CEMENTO
03.01.02 HORMIGON 1:10 + 30% P.G. S/ 7,215.96
S/ 7,215.96
03.01.03 SUMINISTRO DE PIEDRA MEDIANA (APORTE) S/ 2,828.07 S/ 2,828.07
03.01.04 NIVELACIÓN, RELLENO Y APISONADO DE CAMA DE PIEDRA
MEDIANA (APORTE) S/ 1,327.40
S/ 954.07 S/ 373.33
3.02 SOBRECIMIENTO S/ 13,485.51 S/ 5,214.39 S/ 8,271.12
03.02.01 SOBRECIMIENTOS MEZCLA CEMENTO-HORMIGON 1:8 + 30% PM S/ 6,230.71
S/ 6,230.71
03.02.02 ENCOFRADO Y DESENCOFRADO DE SOBRECIMIENTO h=0.35m S/ 7,254.80 S/ 5,214.39 S/ 2,040.41
4 CONCRETO ARMADO S/ 64,643.94 S/ 18,210.79 S/ 20,647.05 S/ 25,384.55 S/ 401.55
4.01 COLUMNAS S/ 36,410.04 S/ 18,210.79 S/ 18,199.25
04.01.01 CONCRETO COLUMNAS f'c=175 kg/cm2 S/ 12,524.37 S/ 12,524.37
04.01.02 ENCOFRADO Y DESENCOFRADO DE COLUMNAS S/ 7,245.91 S/ 2,264.35 S/ 4,981.56
04.01.03 ACERO CORRUGADO FY=4,200 kg/cm2 GRADO 60 COLUMNAS S/ 16,639.76
S/ 15,946.44 S/ 693.32
PRESUPUESTO DE OBRA
PROYECTO "CREACIÓN DE VIVIENDAS UNIFAMILIARES"
CLIENTE SR. RICHARD TAIPE PALOMINO
RESIDENTE ING. RAUL CASTILLON GALVEZ CIP. 124567 FE
SUPERVISOR ARG. DANIEL DE LA CRUZ SUAREZ CIP. 184745 MONTO T
ESPECIALIDAD ESTRUCTURA
ITEM Nombre de tarea UND METRADO P.U. TOTAL SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8 SEMANA 9
4.02 VIGAS S/ 28,233.90 S/ 2,447.80 S/ 25,384.55 S/ 401.55
04.02.01 CONCRETO VIGAS f'c=175 kg/cm2 S/ 9,637.15 S/ 9,235.60 S/ 401.55
04.02.02 ENCOFRADO Y DESENCOFRADO EN VIGAS S/ 10,204.28 S/ 10,204.28
04.02.03 ACERO CORRUGADO FY=4,200 kg/cm2 GRADO 60 PARA VIGAS S/ 8,392.47
S/ 2,447.80 S/ 5,944.67
5 TIJERALES Y RETICULADOS S/ 43,967.45 S/ 43,872.89
5.01 TIJERAL TIPO A DE ACERO LAC 0.80x0.40x1.80 M S/ 21,175.56 S/ 21,175.56
5.02 CORREAS DE TUBO DE ACERO LAC 40X60x1.5mm S/ 18,785.99 S/ 18,785.99
5.03 FRISO DE MADERA DE 1 1/2" X 2 1/2" S/ 1,513.04 S/ 1,418.48
5.04 TIJERAL DE MADERA DE 2"X4" S/ 1,327.36 S/ 1,327.36
PRESUPUESTO DE OBRA
PROYECTO "CREACIÓN DE VIVIENDAS UNIFAMILIARES"
CLIENTE SR. RICHARD TAIPE PALOMINO
RESIDENTE ING. RAUL CASTILLON GALVEZ CIP. 124567 FE
SUPERVISOR ARG. DANIEL DE LA CRUZ SUAREZ CIP. 184745 MONTO T
ESPECIALIDAD ESTRUCTURA
ITEM Nombre de tarea UND METRADO P.U. TOTAL SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8 SEMANA 9
5.05 CORREAS DE MADERA 2"X2" S/ 836.24 S/ 836.24
5.06 FRISO DE MADERA DE 1 1/2" X 2 1/2" S/ 329.26 S/ 329.26
6 COBERTURAS S/ 40,069.30
6.01 COBERTURA DE PLANCHA ONDULADA GALVANIZADA S/ 34,434.68
CUMBRERA CALAMINA GALVANIZADA 0.30 mm, 11 CANALES INC.
6.02 PINTADO S/ 2,842.86
ITEM Nombre de tarea UND METRADO P.U. TOTAL SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8 SEMANA 9
14.02 PUERTA INTERIOR CONTRAPLACADA DE MADERA + TRIPLEY 4 MM
DE 0.90x2.10M / INCL. TRANSPORTE E INSTALACION S/ 9,513.20
S/ 2,972.88
14.03 PUERTA INTERIOR CONTRAPLACADA DE MADERA + TRIPLEY 3 MM
DE 0.80x2.10M / INCL. TRANSPORTE E INSTALACION S/ 15,088.28
15 VENTANAS S/ 19,358.66 S/ 19,358.66
15.01 VENTANA DE ALUMINIO DE 0.78 X 1.065 M INC/VIDRIO, CON
CONTRAVENTANA DE MADERA S/ 19,358.66
S/ 19,358.66
16 INSTALACIONES ELECTRICAS S/ 9,656.40 S/ 2,586.54 S/ 7,069.86
16.01 INSTALACION ELECTRICA EN MODULO S/ 9,656.40 S/ 2,586.54 S/ 7,069.86
17 EVACUACIÓN AGUAS PLUVIALES S/ 14,163.72
17.01 SISTEMA DE EVACUACIÓN DE AGUAS PLUVIALES S/ 13,631.20
17.02 ENCOFRADO Y DESENCOFRADO DE DADOS DE CONCRETO S/ 315.84
17.03 CONCRETO SIMPLE f'c=100 kg/cm2 PARA DADOS DE PROTECCIÓN S/ 216.68
PRESUPUESTO DE OBRA
PROYECTO "CREACIÓN DE VIVIENDAS UNIFAMILIARES"
CLIENTE SR. RICHARD TAIPE PALOMINO
RESIDENTE ING. RAUL CASTILLON GALVEZ CIP. 124567 FE
SUPERVISOR ARG. DANIEL DE LA CRUZ SUAREZ CIP. 184745 MONTO T
ESPECIALIDAD ESTRUCTURA
ITEM Nombre de tarea UND METRADO P.U. TOTAL SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8 SEMANA 9
18 MITIGACIÓN DEL IMPACTO AMBIENTAL Y LIMPIEZA S/ 2,735.60 S/ 151.43 S/ 273.56 S/ 273.56 S/ 273.56 S/ 273.56 S/ 273.56 S/ 273.56 S/ 273.56 S/ 273.56
18.01 MITIGACION DEL IMPACTO AMBIENTAL (APORTE) S/ 2,735.60 S/ 151.43 S/ 273.56 S/ 273.56 S/ 273.56 S/ 273.56 S/ 273.56 S/ 273.56 S/ 273.56 S/ 273.56
19 ACARREOS S/ 5,471.40
19.01 ACARREO MATERIAL EXCED, EXCAV. DRENAJES Y LIMPIEZA FINAL
OBRA (APORTE) S/ 5,471.40
20 FLETES Y TRANSPORTE S/ 56,722.67 S/ 6,585.75 S/ 37,171.26 S/ 12,965.66
20.01 FLETE Y TRANSPORTE DE MATERIALES S/ 14,967.39 S/ 6,585.75 S/ 8,381.64
20.01.01 FLETE TERRESTRE TRANSP. MATERIALES DEL PROVEEDOR AL
ALMACEN (INCL. CARGA-DESCARGA) S/ 4,768.56
S/ 4,768.56
20.01.02 FLETE TERRESTRE TRANSP. MATERIALES DE ALMACEN A PUNTA DE
CARRETERA (INCL. CARGA-DESCARGA) S/ 4,153.57
S/ 1,817.19 S/ 2,336.38
FLETE RURAL DE MATERIALES PUNTA DE CARRETERA A VIVIENDA
20.01.03 (APORTE) S/ 3,703.34
S/ 3,703.34
ACOMPAÑAMIENTO, CARGA Y DESCARGA TRANSP. DE MATERIALES
20.01.04 PUNTA DE CARRETERA A VIVIENDA (APORTE) S/ 2,341.92
S/ 2,341.92
20.02 FLETE Y TRANSPORTE DE PIEDRA Y AGREGADOS S/ 41,755.28 S/ 28,789.62 S/ 12,965.66
20.02.01 FLETE TERRESTRE TRANSP. AGREGADOS DEL PROVEEDOR A PUNTA
DE CARRETERA (INCL. CARGA-DESCARGA) S/ 27,906.76
S/ 27,906.76
20.02.02 FLETE TERRESTRE TRANSP. PIEDRA DE CANTER A PUNTA DE
CARRETERA (INCL. CARGA-DESCARGA) S/ 941.72
S/ 882.86 S/ 58.86
20.02.03 FLETE TERRESTRE TRANSP. DE AGREGADO Y PIEDRA DE PUNTA DE
CARRETERA A VIVIENDA (APORTE) S/ 6,171.82
S/ 6,171.82
AVANCE FINANCIERO SEMANAL 2.55% 10.54% 5.28% 5.25% 9.27% 13.11% 6.82% 10.92% 16.85%
AVANCE FINANCIERO SEMANAL ACUMU 2.55% 13.08% 18.36% 23.61% 32.88% 46.00% 52.82% 63.73% 80.58%
UPUESTO DE OBRA
FECHA: 05/08/2022
MONTO TOTAL: S/ 7,215.96
S/ 959.59 S/ 757.24
S/ 339.80 S/ 214.92
S/ 102.80 S/ 75.26
S/ 237.00 S/ 139.66
S/ 619.79 S/ 542.32
S/ 619.79 S/ 542.32
UPUESTO DE OBRA
FECHA: 05/08/2022
MONTO TOTAL: S/ 7,215.96
S/ 94.56
S/ 94.56
UPUESTO DE OBRA
FECHA: 05/08/2022
MONTO TOTAL: S/ 7,215.96
S/ 40,069.30
S/ 34,434.68
S/ 2,842.86
S/ 2,791.76
S/ 11,033.85 S/ 5,728.24
S/ 7,544.72 S/ 5,576.54
S/ 3,489.13 S/ 151.70
S/ 1,101.64
S/ 1,101.64
S/ 13,770.12 S/ 7,858.48
UPUESTO DE OBRA
FECHA: 05/08/2022
MONTO TOTAL: S/ 7,215.96
S/ 6,540.32
S/ 7,229.80 S/ 7,858.48
S/ 9,797.42 S/ 4,366.30
S/ 9,797.42 S/ 3,833.78
S/ 315.84
S/ 216.68
UPUESTO DE OBRA
FECHA: 05/08/2022
MONTO TOTAL: S/ 7,215.96
S/ 5,129.44 S/ 341.96
18.00%
16.00%
14.00%
12.00%
10.00%
8.00%
6.00%
4.00%
2.00%
0.00%
SEMANA 0 SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8 SEMANA 9 SEMANA 10 SEMANA 11 SEMANA 12
Row 40 Row 42
SEMANAL SEMANA 0 SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8 SEMANA 9 SEMANA 10 SEMANA 11 SEMANA 12
S/ - S/ 18,509.62 S/ 76,609.07 S/ 38,357.99 S/ 38,186.09 S/ 67,411.88 S/ 95,353.10 S/ 49,588.08 S/ 79,371.66 S/ 122,506.92 S/ 107,354.09 S/ 33,364.45 S/ 476.13
PROGRAMADO
0.00% 2.55% 10.54% 5.28% 5.25% 9.27% 13.11% 6.82% 10.92% 16.85% 14.77% 4.59% 0.07%
S/ - S/ 29,017.62 S/ 66,101.07 S/ 27,849.99 S/ 48,694.09 S/ 67,411.88 S/ 110,353.10 S/ 64,588.08 S/ 94,371.66 S/ 137,506.92 S/ 107,354.09
EJECUTADO
0.00% 3.99% 9.09% 3.83% 6.70% 9.27% 15.18% 8.88% 12.98% 18.91% 14.77%
CONSTRUCTORA J y J
CURVA S
PROYECTO : "CREACIÓN DE VIVIENDAS UNIFAMILIARES"
CLIENTE : SR. RICHARD TAIPE PALOMINO
RESIDENTE : ING. RAUL CASTILLON GALVEZ CIP. 124567 FECHA: 05/08/2022
SUPERVISOR : ARG. DANIEL DE LA CRUZ SUAREZ CIP. 184745 MONTO TOTAL: S/ 59,906.57
ESPECIALIDA : ESTRUCTURA
16.00%
100.00%
14.00%
12.00%
80.00%
10.00%
8.00%
60.00%
6.00%
4.00%
40.00%
2.00%
0.00%
SEMANA 0 SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8 SEMANA 9 SEMANA 10 SEMANA 11 SEMANA 12
20.00%
Row 40 Row 42
0.00%
SEMANA 0 SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8 SEMANA 9 SEMANA 10 SEMANA 11 SEMANA 12
Row 81 Row 83
ACUMULADO SEMANA 0 SEMANA 1 SEMANA 2 SEMANA 3 SEMANA 4 SEMANA 5 SEMANA 6 SEMANA 7 SEMANA 8 SEMANA 9 SEMANA 10 SEMANA 11 SEMANA 12
S/ - S/ 18,509.62 S/ 95,118.69 S/ 133,476.68 S/ 171,662.77 S/ 239,074.65 S/ 334,427.75 S/ 384,015.83 S/ 463,387.49 S/ 585,894.41 S/ 693,248.50 S/ 726,612.95 S/ 727,089.08
PROGRAMADO
0.00% 2.55% 13.08% 18.36% 23.61% 32.88% 46.00% 52.82% 63.73% 80.58% 95.35% 99.93% 100.00%
S/ - S/ 29,017.62 S/ 95,118.69 S/ 122,968.68 S/ 171,662.77 S/ 239,074.65 S/ 349,427.75 S/ 414,015.83 S/ 508,387.49 S/ 645,894.41
EJECUTADO
0.00% 3.99% 13.08% 16.91% 23.61% 32.88% 48.06% 56.94% 69.92% 88.83%
A B
105 8.69047619
FINAL 250
ENCONTRAR 250
RESULTADO > 1150
OK