Está en la página 1de 1

GERENCIA DE ESTUDIOS Y FISCALIZACIÓN

UNIDAD DE COSTOS Y PROCESOS PRECONTRACTUALES HOJA


1 DE 1
CRONOGRAMA VALORADO DE INVERSIONES (REFERENCIAL)
REPAVIMENTACIÓN VIAL ASFÁLTICA - PROGRAMA III. PAQUETE 1.
ADMINISTRACIÓN ZONAL EUGENIO ESPEJO.
MONTO CONTRATO: $ 1,296,567.95
CONTRATISTA: COD.OBRA: PLAZO: 180 dias MAYO / 2021
CODIGO RUBROS UNID CANT P.UNIT. P.TOTAL AVANCE; PERIODO; INVERSIONES
30 DIAS 30 DIAS 30 DIAS 30 DIAS 30 DIAS 30 DIAS

TRABAJOS PRELIMINARES
100
LIMPIEZA MANUAL DE CALZADA DE VIA
1 2778 km 13.00 321.92 4,184.96 697.49 697.49 697.49 697.49 697.49 697.49

LIMPIEZA DE SUMIDERO Y TUBERÍA.


2 1063 u 297.00 11.78 3,498.66 1,166.22 1,166.22 1,166.22
90
FRESADO DE CARPETA ASFÁLTICA.
3 4534 m3 5,890.00 7.80 45,942.00 2,418.00 2,418.00 2,418.00 2,418.00 2,418.00 2,418.00 2,418.00 2,418.00 2,418.00 2,418.00 2,418.00 2,418.00 2,418.00 2,418.00 2,418.00 2,418.00 2,418.00 2,418.00 2,418.00

TRANSPORTE MATERIAL DE FRESADO.


4 V210 m3-km 60,696.00 0.36 21,850.56 1,150.03 1,150.03 1,150.03 1,150.03 1,150.03 1,150.03 1,150.03 1,150.03 1,150.03 1,150.03 1,150.03 1,150.03 1,150.03 1,150.03 1,150.03 1,150.03 1,150.03 1,150.03 1,150.03
80
REFACCIÓN DE POZO DE ACCESO O SUMIDERO.
5 V936 u 80.00 65.96 5,276.80 1,319.20 1,319.20 1,319.20 1,319.20

TRANSPORTE MATERIAL DE EXCAVACIÓN Y


6 V922 ESCOMBROS. m3-km 782.00 0.47 367.54 91.89 91.89 91.89 91.89
70

REASFALTADO

SELLADO DE GRIETAS EN CARPETA ASFALTICA


7 1989 M 859.00 1.63 1,400.17 466.72 466.72 466.72
60
BACHEO CON MEZCLA ASFÁLTICA EN CALIENTE CON
8 V135 EQUIPO LIVIANO. m3 62.00 237.28 14,711.36 2,451.89 2,451.89 2,451.89 2,451.89 2,451.89 2,451.89

ASFALTO DILUIDO RC PARA RIEGO ADHERENCIA


9 V909 l 31,400.00 0.60 18,840.00 942.00 942.00 942.00 942.00 942.00 942.00 942.00 942.00 942.00 942.00 942.00 942.00 942.00 942.00 942.00 942.00 942.00 942.00 942.00 942.00

CARPETA ASFALTICA EN CALIENTE e=7.5cm.


10 V919 INC.TRANS. m2 78,495.00 13.16 1,032,994.20 51,649.71 51,649.71 51,649.71 51,649.71 51,649.71 51,649.71 51,649.71 51,649.71 51,649.71 51,649.71 51,649.71 51,649.71 51,649.71 51,649.71 51,649.71 51,649.71 51,649.71 51,649.71 51,649.71 51,649.71
50

SEÑALIZACION

SEÑALIZACIÓN HORIZONTAL CON MATERIAL


11 2908 TERMOPLÁSTICO. m2 3,257.00 34.73 113,115.61 9,426.30 9,426.30 9,426.30 9,426.30 9,426.30 9,426.30 9,426.30 9,426.30 9,426.30 9,426.30 9,426.30 9,426.30
40
PINTURA ACRILICA MICROESFERAS T. CEBRA Y
12 6038 OTROS. m2 1,423.00 8.22 11,697.06 974.76 974.76 974.76 974.76 974.76 974.76 974.76 974.76 974.76 974.76 974.76 974.76

SEPARADOR VIAL - DOBLE LOMO DE POLIURETANO


13 4541 u 49.00 25.34 1,241.66 206.94 206.94 206.94 206.94 206.94 206.94
30
SEPARADOR VIAL DE POLIURETANO h=10cm, b=15cm,
14 2693 L=30cm u 351.00 25.34 8,894.34 1,482.39 1,482.39 1,482.39 1,482.39 1,482.39 1,482.39

RUBROS AMBIENTALES
20

15 V001 CHARLAS DE CONCIENTIZACION u 7.00 444.72 3,113.04 444.72 444.72 444.72 444.72 444.72 444.72 444.72

LETRERO AMBIENTAL DEL PROYECTO (0.60x1.20m),


16 V007 u 7.00 166.50 1,165.50 166.50 166.50 166.50 166.50 166.50 166.50 166.50
h=2m.
10

17 V014 PUBLICACIONES POR LA PRENSA 8.44x12.63cm u 7.00 851.06 5,957.42 851.06 851.06 851.06 851.06 851.06 851.06 851.06

ROTULO LONA 13 ONZAS DESCR. OBRA 2.40x1.20m (2


18 1162 PARANTES). u 7.00 331.01 2,317.07 331.01 331.01 331.01 331.01 331.01 331.01 331.01
0

TOTAL USD 1,296,567.95


INVERSION VAL.
Firmado electrónicamente por:
73,075.79 229,581.63 278,894.23 253,887.82 253,302.36 207,826.11
CESAR ALONSO Periodo % 5.64 17.71 21.51 19.58 19.54 16.03
DEFAZ CEPEDA
INVERSION VAL. 73,075.79 302,657.43 581,551.65 835,439.48 1,088,741.84 1,296,567.95
UNIDAD DE COSTOS Y PROCESOS PRECONTRACTUALES Acumulado % 5.64 23.34 44.85 64.43 83.97 100.00