DEPTO: PROYECTOS
ESCALERA
Importe:
Volumen: $ 9,250.33
SUBTOTAL: BASICOS $9,250.33 52.26%
Costo Directo: $14,606.33 82.52%
INDIRECTO TOTAL 8.0000% $1,168.51 6.60%
D) SUBTOTAL (CD+B+C) $15,774.84 89.13%
E) FINANCIAMIENTO 2.0000% $315.50 1.78%
F) SUBTOTAL D+E $16,090.34 90.91%
G) UTILIDAD 10.0000% $1,609.03 9.09%
H) SUBTOTAL (F+G) $17,699.37 100.00%
0% $0.00
DEPTO: PROYECTOS
CISTERNA
Importe:
Volumen: $ 10,180.00
SUBTOTAL: BASICOS $10,180.00 59.17%
Costo Directo: $14,197.00 82.52%
INDIRECTO TOTAL 8.0000% $1,135.76 6.60%
D) SUBTOTAL (CD+B+C) $15,332.76 89.13%
E) FINANCIAMIENTO 2.0000% $306.66 1.78%
F) SUBTOTAL D+E $15,639.42 90.91%
G) UTILIDAD 10.0000% $1,563.94 9.09%
H) SUBTOTAL (F+G) $17,203.36 100.00%
0% $0.00
DEPTO: PROYECTOS
TINACO
Importe:
Volumen: $ 2,079.00
SUBTOTAL: BASICOS $2,079.00 62.42%
Costo Directo: $2,748.50 82.52%
INDIRECTO TOTAL 8.0000% $219.88 6.60%
D) SUBTOTAL (CD+B+C) $2,968.38 89.13%
E) FINANCIAMIENTO 2.0000% $59.37 1.78%
F) SUBTOTAL D+E $3,027.75 90.91%
G) UTILIDAD 10.0000% $302.77 9.09%
H) SUBTOTAL (F+G) $3,330.52 100.00%
0% $0.00
DEPTO: PROYECTOS
REGADERA
Importe:
Volumen: $ 930.00
SUBTOTAL: BASICOS $930.00 70.77%
Costo Directo: $1,084.50 82.52%
INDIRECTO TOTAL 8.0000% $86.76 6.60%
D) SUBTOTAL (CD+B+C) $1,171.26 89.13%
E) FINANCIAMIENTO 2.0000% $23.43 1.78%
F) SUBTOTAL D+E $1,194.69 90.91%
G) UTILIDAD 10.0000% $119.47 9.09%
H) SUBTOTAL (F+G) $1,314.15 100.00%
0% $0.00
DEPTO: PROYECTOS
W.C
Importe:
Volumen: $ 1,435.00
SUBTOTAL: BASICOS $1,435.00 69.97%
Costo Directo: $1,692.50 82.52%
INDIRECTO TOTAL 8.0000% $135.40 6.60%
D) SUBTOTAL (CD+B+C) $1,827.90 89.13%
E) FINANCIAMIENTO 2.0000% $36.56 1.78%
F) SUBTOTAL D+E $1,864.46 90.91%
G) UTILIDAD 10.0000% $186.45 9.09%
H) SUBTOTAL (F+G) $2,050.90 100.00%
0% $0.00
DEPTO: PROYECTOS
LAVABO
Importe:
Volumen: $ 1,380.00
SUBTOTAL: BASICOS $1,380.00 69.55%
Costo Directo: $1,637.50 82.52%
INDIRECTO TOTAL 8.0000% $131.00 6.60%
D) SUBTOTAL (CD+B+C) $1,768.50 89.13%
E) FINANCIAMIENTO 2.0000% $35.37 1.78%
F) SUBTOTAL D+E $1,803.87 90.91%
G) UTILIDAD 10.0000% $180.39 9.09%
H) SUBTOTAL (F+G) $1,984.26 100.00%
0% $0.00
DEPTO: PROYECTOS
TARJA
Importe:
Volumen: $ 1,370.00
SUBTOTAL: BASICOS $1,370.00 69.47%
Costo Directo: $1,627.50 82.52%
INDIRECTO TOTAL 8.0000% $130.20 6.60%
D) SUBTOTAL (CD+B+C) $1,757.70 89.13%
E) FINANCIAMIENTO 2.0000% $35.15 1.78%
F) SUBTOTAL D+E $1,792.85 90.91%
G) UTILIDAD 10.0000% $179.29 9.09%
H) SUBTOTAL (F+G) $1,972.14 100.00%
0% $0.00
DEPTO: PROYECTOS
AZULEJO
Importe:
Volumen: $ 228.33
SUBTOTAL: BASICOS $228.33 55.64%
Costo Directo: $338.69 82.52%
INDIRECTO TOTAL 8.0000% $27.10 6.60%
D) SUBTOTAL (CD+B+C) $365.79 89.13%
E) FINANCIAMIENTO 2.0000% $7.32 1.78%
F) SUBTOTAL D+E $373.10 90.91%
G) UTILIDAD 10.0000% $37.31 9.09%
H) SUBTOTAL (F+G) $410.41 100.00%
0% $0.00
DEPTO: PROYECTOS
LOSA RETICULAR
Importe: $ -
Volumen: $ 446.00
SUBTOTAL: BASICOS $446.00 40.26%
Costo Directo: $914.18 82.52%
INDIRECTO TOTAL 8.0000% $73.13 6.60%
D) SUBTOTAL (CD+B+C) $987.32 89.13%
E) FINANCIAMIENTO 2.0000% $19.75 1.78%
F) SUBTOTAL D+E $1,007.06 90.91%
G) UTILIDAD 10.0000% $100.71 9.09%
H) SUBTOTAL (F+G) $1,107.77 100.00%
0% $0.00
DEPTO: PROYECTOS
TIERRA NEGRA
Importe: $ -
Volumen: $ 183.33
SUBTOTAL: BASICOS $183.33 61.72%
Costo Directo: $245.13 82.52%
INDIRECTO TOTAL 8.0000% $19.61 6.60%
D) SUBTOTAL (CD+B+C) $264.74 89.13%
E) FINANCIAMIENTO 2.0000% $5.29 1.78%
F) SUBTOTAL D+E $270.04 90.91%
G) UTILIDAD 10.0000% $27.00 9.09%
H) SUBTOTAL (F+G) $297.04 100.00%
0% $0.00
DEPTO: PROYECTOS
PISO ESTACIONAMIENTO
Importe: $ -
Volumen: $ 150.00
SUBTOTAL: BASICOS $150.00 58.45%
Costo Directo: $211.80 82.52%
INDIRECTO TOTAL 8.0000% $16.94 6.60%
D) SUBTOTAL (CD+B+C) $228.74 89.13%
E) FINANCIAMIENTO 2.0000% $4.57 1.78%
F) SUBTOTAL D+E $233.32 90.91%
G) UTILIDAD 10.0000% $23.33 9.09%
H) SUBTOTAL (F+G) $256.65 100.00%
0% $0.00
DEPTO: PROYECTOS
Importe: $ -
Volumen: $ 150.00
SUBTOTAL: BASICOS $150.00 58.45%
Costo Directo: $211.80 82.52%
INDIRECTO TOTAL 8.0000% $16.94 6.60%
D) SUBTOTAL (CD+B+C) $228.74 89.13%
E) FINANCIAMIENTO 2.0000% $4.57 1.78%
F) SUBTOTAL D+E $233.32 90.91%
G) UTILIDAD 10.0000% $23.33 9.09%
H) SUBTOTAL (F+G) $256.65 100.00%
0% $0.00
DEPTO: PROYECTOS
PLANTILLA DE 5 CM
Importe: $ -
Volumen: $ 75.00
SUBTOTAL: BASICOS $75.00 55.22%
Costo Directo: $112.08 82.52%
INDIRECTO TOTAL 8.0000% $8.97 6.60%
D) SUBTOTAL (CD+B+C) $121.05 89.13%
E) FINANCIAMIENTO 2.0000% $2.42 1.78%
F) SUBTOTAL D+E $123.47 90.91%
G) UTILIDAD 10.0000% $12.35 9.09%
H) SUBTOTAL (F+G) $135.81 100.00%
0% $0.00
DEPTO: PROYECTOS
CADENA O CASTILLO
DEPTO: PROYECTOS
ZAPATA CORRIDA
DEPTO: PROYECTOS
PISO ESTACIONAMIENTO
Importe: $ -
Volumen: $ 225.00
SUBTOTAL: BASICOS $225.00 58.45%
Costo Directo: $317.70 82.52%
INDIRECTO TOTAL 8.0000% $25.42 6.60%
D) SUBTOTAL (CD+B+C) $343.12 89.13%
E) FINANCIAMIENTO 2.0000% $6.86 1.78%
F) SUBTOTAL D+E $349.98 90.91%
G) UTILIDAD 10.0000% $35.00 9.09%
H) SUBTOTAL (F+G) $384.98 100.00%
0% $0.00
DEPTO: PROYECTOS
PISO DE LOSETA
Importe:
Volumen: $ 258.33
SUBTOTAL: BASICOS $258.33 57.82%
Costo Directo: $368.69 82.52%
INDIRECTO TOTAL 8.0000% $29.50 6.60%
D) SUBTOTAL (CD+B+C) $398.19 89.13%
E) FINANCIAMIENTO 2.0000% $7.96 1.78%
F) SUBTOTAL D+E $406.15 90.91%
G) UTILIDAD 10.0000% $40.61 9.09%
H) SUBTOTAL (F+G) $446.76 100.00%
0% $0.00
DEPTO: PROYECTOS
MURO DE TABIQUE
DEPTO: PROYECTOS
APLANADO
DEPTO: PROYECTOS
FIRME DE 10 CM
DEPTO: PROYECTOS
EXCAVACION EN TERRENO TIPO B A UNA PROFUNDIDAD DE 0.00 A 3.00 M, INCUYE: TRAZO, NIVELACION, AFINE, HERRAMIENTA,MANO DE OBRA Y
ACARREO DE MATERIAL PRODUCTO DE LA EXCAVACION A LUGAR INDICADO POR LA PLANTA