Análisis:ELECTRO-01 Unidad:PZA

SUMINISTRO Y COLOCACIÓN DE ELECTRONIVELES PARA LLENADO INDEPENDIENTE DE TINACOS


INCLUYE:EMPOTRADO EN MURO EXISTENTE CONEXIONES ,MATERIAL Y MANO DE OBRA.

MATERIALES
ELECTRONIVEL PZA $1,350.00 1.000000 $1,350.00 5.90%
CABLE USO RUDO 3X12 ML $59.45 15.000000 $891.75 3.90%
TUBO PVC CONDUIT T.P. 19 MM. ML $35.29 34.000000 $1,199.86 5.24%
TAQUETE EXPANSOR TIPO Z 3/8 PZA $25.46 50.000000 $1,273.00 5.56%
COPLE D/COBRE 1" PZA $17.60 10.000000 $176.00 0.77%
CODO D/PVC CONDUIT 1" PZA $10.02 6.000000 $60.12 0.26%
CABLE THW # 12 ML $35.34 100.000000 $3,534.00 15.45%
CABLE THW # 12 ML $35.34 100.000000 $3,534.00 15.45%
CABLE THW # 12 ML $35.34 100.000000 $3,534.00 15.45%
CAJA Y TAPA 19 MM. PZA $35.29 5.000000 $176.45 0.77%
CONDUELE 3/4" PZA $66.49 1.000000 $66.49 0.29%
CUERPOS DE ANDAMIOS JGO $500.00 3.000000 $1,500.00 6.56%
ABRAZADERA UNICANAL 1" PZA $34.32 60.000000 $2,059.20 9.00%
PERFIL UNICANAL SOLIDO 4X2CMS PZA $425.32 3.000000 $1,275.96 5.58%
BARRA ROSCADA SERIE 10 DE 3/8 X3.05 PZA $125.30 3.000000 $375.90 1.64%
CINTA AISLANTE PLASTICA SCOTCH 33 PZA $100.87 3.000000 $302.61 1.32%
DE .018X20MTS.MCA.3M
CONECTOR USO RUDO 13MM PZA $15.27 4.000000 $61.08 0.27%
TUBO TERMOC.P/AISL.1.20MTS CAL.8-3AWG 20- PZA $456.84 1.000000 $456.84 2.00%
56MM
Subtotal: MATERIALES $21,827.26 95.41%
MANO DE OBRA
CUADRILLA No 06 ( 1 OF. ELECTRICISTA + 1 JOR $1,050.00 1.000000 $1,050.00 4.59%
AYUDANTE GENERAL )
Subtotal: MANO DE OBRA $1,050.00
Costo directo $22,877.26 100.00%
INDIRECTOS 10% $2,287.73
SUBTOTAL $25,164.99
FINANCIAMIENTO 0% $0.00
SUBTOTAL $25,164.99
UTILIDAD 10% $2,516.50
PRECIO UNITARIO $27,681.48
(* VEINTISIETE MIL SEISCIENTOS OCHENTA Y UN PESOS 48/100 M.N. *)
Análisis: LLEN-CIS Unidad: PZA

SUMINISTRO, COLOCACION Y CONEXION DE LLENADO GENERAL PARA CISTERNAS, INCLUYE: HERRAMIENTA,


MATERIAL, Y MANO DE OBRA.

MATERIALES
TUBO P.V.C HID 3" RD-26 ML $346.40 15.000000 $5,196.00 38.29%
CODO 90° DE PVC 3" PZA $650.23 4.000000 $2,600.92 19.16%
COPLE DE REPARACION 3" PZA $524.15 1.000000 $524.15 3.86%
TEE PVC HID 3" PZA $620.12 3.000000 $1,860.36 13.71%
ABRAZADERA UNICANAL 1" PZA $34.32 15.000000 $514.80 3.79%
CUERPOS DE ANDAMIOS JGO $500.00 3.000000 $1,500.00 11.05%
PERFIL UNICANAL SOLIDO 4X2CMS PZA $425.32 1.000000 $425.32 3.13%
BARRA ROSCADA SERIE 10 DE 3/8 X3.05 PZA $125.30 1.000000 $125.30 0.92%
Subtotal: MATERIALES $12,621.55 93.00%
MANO DE OBRA
CUADRILLA No 07 ( 1 OF. PLOMERO + 1 JOR $950.00 1.000000 $950.00 7.00%
AYUDANTE GENERAL )
Subtotal: MANO DE OBRA $950.00
Costo directo $13,571.55 100.00%
INDIRECTOS 10% $1,357.16
SUBTOTAL $14,928.71
FINANCIAMIENTO 0% $0.00
SUBTOTAL $14,928.71
UTILIDAD 10% $1,492.87
PRECIO UNITARIO $16,421.58
(*DIECISEIS MIL CUATROCIENTOS VEINTIUN PESOS 58/100 M.N. *)
Análisis: LLEN-CIS/INT Unidad: PZA

SUMINISTRO, COLOCACION Y CONEXION DE LLENADO INTERIOR PARA CISTERNAS, INCLUYE: HERRAMIENTA,


MATERIAL, Y MANO DE OBRA.

MATERIALES
TUBO P.V.C HID 3" RD-26 CON COPLES ML $346.40 6.000000 $2,078.40 40.13%
CODO DE PVC 3" PZA $650.23 1.000000 $650.23 12.56%
CUERPOS DE ANDAMIOS JGO $500.00 3.000000 $1,500.00 28.97%

Subtotal: MATERIALES $4,228.63 81.66%


MANO DE OBRA
CUADRILLA No 07 ( 1 OF. PLOMERO + 1 JOR $950.00 1.000000 $950.00 18.34%
AYUDANTE GENERAL )
Subtotal: MANO DE OBRA $950.00
Costo directo $5,178.63 100.00%
INDIRECTOS 10% $517.86
SUBTOTAL $5,696.49
FINANCIAMIENTO 0% $0.00
SUBTOTAL $5,696.49
UTILIDAD 10% $569.65
PRECIO UNITARIO $6,266.14
(* SEIS MIL DOSCIENTOS SESENTA Y SEIS PESOS 14/100 M.N. *)