Está en la página 1de 13

¤ Item Descripción Und. Metrado Precio (S/.) Parcial (S/.

)
0 01 PAVIMENTO RÍGIDO, CUNETAS, SARDINEL Y VEREDAS 852,103.83
0 01.01 OBRAS PROVISIONALES 58,792.71
0 01.01.01 ALQUILER DE OFICINA Y ALMACEN mes 6.00 1,000.00 6,000.00
0 01.01.02 CARTEL DE IDENTIFICACION DE LA OBRA DE 4.80x3.6 und 1.00 1,053.99 1,053.99
0 01.01.03 DEMOLICIÓN DE ESTRUCTURAS EXISTENTES GLB 1.00 8,738.78 8,738.78
0 01.01.04 SEÑALIZACION DE DESVIOS DE VIAS GLB 1.00 874.14 874.14
0 01.01.05 SEÑALIZACION EN OBRA DURANTE LA EJECUCION m 770.00 8.64 6,652.80
0 01.01.06 SEGURIDAD EN OBRA 35,473.00
0 01.01.06.01 EQUIPOS DE PROTECCIÓN INDIVIDUAL (PERSON GLB 1.00 23,980.00 23,980.00
0 01.01.06.02 EQUIPOS DE PROTECCIÓN INDIVIDUAL (PERSON GLB 1.00 5,298.00 5,298.00
0 01.01.06.03 SEGURIDAD EN OBRA GLB 1.00 6,195.00 6,195.00
0 01.02 TRABAJOS PRELIMINARES 25,712.87
0 01.02.01 LIMPIEZA DE TERRENO MANUAL m2 5,430.15 1.55 8,416.73
0 01.02.02 TRAZO Y NIVELACION Y REPLANTEO DE VIAS m2 5,430.15 1.08 5,864.56
0 01.02.03 TRAZO, NIVELACIÓN Y REPLANTEO DURANTE EL PR m2 5,430.15 1.18 6,407.58
0 01.02.04 REUBICACION DE POSTES DE LUZ, TELEFONIA, INTE GLB 1.00 5,024.00 5,024.00
0 01.03 EXPLANACIONES 51,756.69
0 01.03.01 CORTE DE MATERIAL SUELTO A NIVEL DE LA SUB R m3 548.62 58.76 32,236.91
0 01.03.02 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIP m3 658.34 29.65 19,519.78
0 01.04 PAVIMENTO RIGIDO 398,617.59
0 01.04.01 SUB RASANTE 72,261.83
0 01.04.01.01 PERFILADO, NIVELACIÓN Y COMPACTADO DE LA m2 3,004.65 7.82 23,496.36
0 01.04.01.02 MEJORAMIENTO DE LA SUB RASANTE E=0.20 m2 3,004.65 16.23 48,765.47
0 01.04.02 SUB BASE GRANULAR 48,014.31
0 01.04.02.01 SUB BASE GRANULAR E=0.20m - EXTENDIDO R m2 3,004.65 15.98 48,014.31
0 01.04.03 PAVIMENTO RIGIDO 278,341.45
0 01.04.03.01 ENCOFRADO Y DESENCOFRADO DE LOSAS m2 249.76 40.95 10,227.67
0 01.04.03.02 CONCRETO F'C=210 KG/CM2 PARA LOSAS m3 512.10 428.63 219,501.42
0 01.04.03.03 JUNTAS LONGITUDINALES AMARRADAS m 344.00 12.03 4,138.32
0 01.04.03.04 JUNTAS TRANSVERSALES O DOWELS m 903.00 21.55 19,459.65
0 01.04.03.05 CURADO DE LOSAS DE PAVIMENTO m2 2,560.50 6.79 17,385.80
0 01.04.03.06 JUNTAS ASFALTICAS E=1" m 1,236.40 6.17 7,628.59
0 01.05 OBRAS DE ARTE Y DRENAJE 282,597.56
0 01.05.01 BADEN (02 UNIDADES) 2,659.48
0 01.05.01.01 ENCOFRADO Y DESENCOFRADO EN BADEN m2 7.13 40.86 291.33
0 01.05.01.02 CONCRETO F'C=210 KG/CM2 EN BADEN m3 4.13 428.63 1,770.24
0 01.05.01.03 JUNTAS ASFALTICAS E=1" m 25.45 6.17 157.03
0 01.05.01.04 ACABADO CON CEMENTO PULIDO m2 20.65 21.35 440.88
0 01.05.02 CUNETAS LATERALES 51,064.22
0 01.05.02.01 ENCOFRADO Y DESENCOFRADO PARA CUNETA m2 268.00 40.86 10,950.48
0 01.05.02.02 CONCRETO F'C=210KG/CM2 EN CUNETA m3 73.51 428.63 31,508.59
0 01.05.02.03 JUNTAS ASFALTICAS E=1" m 122.88 6.17 758.17
0 01.05.02.04 ACABADO CON CEMENTO PULIDO m2 367.54 21.35 7,846.98
0 01.05.03 SARDINEL 57,030.75
0 01.05.03.01 ENCOFRADO Y DESENCOFRADO EN SARDINEL m2 536.05 40.86 21,903.00
0 01.05.03.02 CONCRETO F'C=210 KG/CM2 EN SARDINEL m3 51.69 428.63 22,155.88
0 01.05.03.03 JUNTAS ASFALTICAS E=1" m 115.20 6.17 710.78
0 01.05.03.04 ACABADO CON CEMENTO PULIDO m2 574.29 21.35 12,261.09
0 01.05.04 VEREDAS PEATONALES DE CONCRETO 122,468.68
0 01.05.04.01 CORTE SUPERFICIAL MANUAL HASTA 0.20 M m3 244.72 26.60 6,509.55
0 01.05.04.02 REFINE Y NIVELACION m2 1,223.60 2.91 3,560.68
0 01.05.04.03 RELLENO Y COMPACTADO EN BASE DE VEREDA m2 1,223.60 9.96 12,187.06
0 01.05.04.04 ENCOFRADO Y DESENCOFRADO NORMAL DE VE m2 227.20 40.86 9,283.39
0 01.05.04.05 CONCRETO F'C=175KG/CM2 EN VEREDAS m3 183.54 371.90 68,258.53
0 01.05.04.06 ACABADO FROTACHADO EN VEREDAS m2 1,233.60 16.27 20,070.67
0 01.05.04.07 JUNTAS ASFALTICAS E=1" m 421.20 6.17 2,598.80
01.05.05 RAMPAS PARA ACCESO VEHICULAR 12,527.64
01.05.05.01 RELLENO Y COMPACTADO EN BASE DE VEREDA m2 90.00 9.96 896.40
01.05.05.02 ENCOFRADO Y DESENCOFRADO NORMAL EN RA m2 60.00 40.86 2,451.60
01.05.05.03 CONCRETO F'C=210 KG/CM2 EN RAMPA m3 18.00 428.63 7,715.34
01.05.05.04 ACABADO FROTACHADO EN RAMPA m2 90.00 16.27 1,464.30
01.05.06 RAMPAS PEATONALES 882.37
01.05.06.01 RELLENO Y COMPACTADO EN BASE DE VEREDA m2 9.36 9.96 93.23
01.05.06.02 ENCOFRADO Y DESENCOFRADO NORMAL EN RA m2 0.90 40.86 36.77
01.05.06.03 CONCRETO F'C=210 KG/CM2 EN RAMPA m3 1.40 428.63 600.08
01.05.06.04 ACABADO FROTACHADO EN RAMPA m2 9.36 16.27 152.29
01.05.07 MARTILLOS 17,144.10
01.05.07.01 RELLENO Y COMPACTADO EN BASE DE VEREDA m2 144.45 9.96 1,438.72
01.05.07.02 ENCOFRADO Y DESENCOFRADO NORMAL EN MA m2 23.79 40.86 972.06
01.05.07.03 CONCRETO F'C=210KG/CM2 EN MARTILLO m3 28.89 428.63 12,383.12
01.05.07.04 ACABADO FROTACHADO EN MARTILLO m2 144.45 16.27 2,350.20
0 01.05.08 MUROS DE CONTENCIÓN DE CONCRETO ARMADO 18,820.32
0 01.05.08.01 MOVIMIENTO DE TIERRAS 1,736.86
0 01.05.08.01.01 EXCAVACION DE ZANJA PARA ZAPATAS HAS m3 39.38 17.58 692.30
0 01.05.08.01.02 RELLENO Y COMPACTADO CON MATERIAL PRO m3 22.00 19.38 426.36
0 01.05.08.01.03 ELIMINACION DE MATERIAL EXCEDENTE CON m3 20.85 29.65 618.20
0 01.05.08.02 OBRAS DE CONCRETO SIMPLE 2,186.63
0 01.05.08.02.01 SOLADO DE CONCRETO F'C=210 KG/CM2 PAR m2 37.50 58.31 2,186.63
0 01.05.08.03 OBRAS DE CONCRETO ARMADO 14,896.83
0 01.05.08.03.01 CONCRETO F'C=210 KG/CM2 EN ZAPATA DE MU m3 7.50 421.20 3,159.00
0 01.05.08.03.02 ACERO FY=4200 KG/CM2 kg 352.18 8.39 2,954.79
0 01.05.08.03.03 ENCOFRADO Y DESENCOFRADO EN MURO DE m2 100.00 40.81 4,081.00
0 01.05.08.03.04 CONCRETO F'C=210 KG/CM2 EN MURO DE CON m3 10.00 449.75 4,497.50
0 01.05.08.03.05 JUNTAS ASFALTICAS E=1" m 33.15 6.17 204.54
0 01.06 OTROS 34,626.41
0 01.06.01 SEÑALIZACIONES HORIZONTALES 34,626.41
0 01.06.01.01 PINTURA LINEAL EN SARDINEL m 1,531.45 16.53 25,314.87
0 01.06.01.02 PINTURA LINEA DISCONTINUA EJE DE VIA m 385.00 17.22 6,629.70
0 01.06.01.03 PINTURA ZONAL (CRUCE PEATONAL) m2 24.00 29.20 700.80
0 01.06.01.04 PINTURA DE SIMBOLOS (FLECHAS Y OTROS) m2 6.20 29.20 181.04
0 01.06.01.05 SEÑALIZACIONES VERTICALES INFORMATIVAS GLB 1.00 1,800.00 1,800.00
0 02 SISTEMA SANITARIO 391,362.75
0 02.01 REPOSICIÓN DEL SISTEMA DE DESAGUE 317,152.52
0 02.01.01 RED EMISORA 253,905.93
0 02.01.01.01 TRABAJOS PRELIMINARES 1,959.40
0 02.01.01.01.01 TRAZO DE NIVELES Y REPLANTEO INICIAL DE m 404.00 2.04 824.16
0 02.01.01.01.02 TRAZO DE NIVELES Y REPLANTEO DE ZANJAS m 404.00 2.81 1,135.24
0 02.01.01.02 MOVIMIENTO DE TIERRAS 74,643.85
0 02.01.01.02.01 EXCAVACION DE ZANJAS C/RETROEXCAVADO m 404.00 34.82 14,067.28
0 02.01.01.02.02 ENTIBADO Y DESENTIBADO DE ZANJAS H>3.00mm 404.00 30.58 12,354.32
0 02.01.01.02.03 REFINE Y NIVELACION DE ZANJAS, TUB. PA m 404.00 11.62 4,694.48
0 02.01.01.02.04 PREPARACION DE CAMA DE APOYO C/ MATERI m 404.00 10.39 4,197.56
0 02.01.01.02.05 RELLENO DE PROTECCIÓN - PRIMER RELL m 404.00 40.01 16,164.04
0 02.01.01.02.06 RELLENO Y COMPACTACIÓN EN CAPAS 0.4 m 404.00 7.53 3,042.12
0 02.01.01.02.07 ELIMINACION DE MATERIAL EXCEDENTE CON m3 678.72 29.65 20,124.05
0 02.01.01.03 SUMINISTRO E INSTALACION DE TUBERÍAS P/DESAGUE 177,302.68
0 02.01.01.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC m 404.00 407.27 164,537.08
0 02.01.01.03.02 PRUEBA HIDRAULICA EN TUB. PVC P/DESAGUE m 404.00 7.98 3,223.92
0 02.01.01.03.03 DADOS DE CONCRETO P/ANCLAJE TUBO ENT und 24.00 397.57 9,541.68
0 02.01.02 CONSTRUCCION DE BUZONES 63,246.59
0 02.01.02.01 MOVIMIENTO DE TIERRAS 13,452.23
0 02.01.02.01.01 EXCAVACION MANUAL PARA BUZÓN Ø 1.50 ( m3 140.58 47.46 6,671.93
0 02.01.02.01.02 ACARREO INTERNO DE MATERIAL EXCEDENTE m3 140.58 12.65 1,778.34
0 02.01.02.01.03 ELIMINACION DE MATERIAL EXCEDENTE CON m3 168.70 29.65 5,001.96
0 02.01.02.02 CONSTRUCCION DE BUZONES 49,794.36
0 02.01.02.02.01 CONSTRUCCIÓN DE BUZONES Ø 1.50 (DE 4.00M und 11.00 4,526.76 49,794.36
0 02.02 REPOSICIÓN Y RECONEXIÓN DEL SISTEMA DE AGUA POTABLE 74,210.23
0 02.02.01 REPOSICIÓN DE TUBERIAS DEL SISTEMA DE AGUA POTABLE 74,210.23
0 02.02.01.01 EXCAVACION DE ZANJAS C/RETROEXCAVADORA m 395.00 9.12 3,602.40
0 02.02.01.02 REFINE Y NIVELACION DE ZANJA P/TUBERIA m 395.00 10.68 4,218.60
0 02.02.01.03 PREPARACION DE CAMA DE APOYO C/ MATERIA m 395.00 7.65 3,021.75
0 02.02.01.04 RELLENO DE PROTECCIÓN - PRIMER RELLEN m 395.00 16.12 6,367.40
0 02.02.01.05 RELLENO Y COMPACTACIÓN EN CAPAS 0.30M m 395.00 5.02 1,982.90
0 02.02.01.06 ELIMINACION DE MATERIAL EXCEDENTE CON E m3 395.00 29.65 11,711.75
0 02.02.01.07 SUMINISTRO E INSTALACION DE TUBERIA PVC- m 395.00 70.03 27,661.85
0 02.02.01.08 PRUEBA HIDRAULICA + DESINFECCIÓN DE TUB. m 395.00 13.73 5,423.35
0 02.02.01.09 INSTALACION DE ACCESORIOS GLB 1.00 3,349.97 3,349.97
0 02.02.01.10 INSTALACION DE GRIFOS CONTRA INCENDIOS GLB 1.00 5,570.29 5,570.29
0 02.02.01.11 INSTALACION DE EMPALMES RED EXISTENTE - R GLB 1.00 1,299.97 1,299.97
0 03 DRENAJE PLUVIAL 617,674.06
0 03.01 RED COLECTORA 484,207.33
0 03.01.01 TRABAJOS PRELIMINARES 2,022.45
0 03.01.01.01 TRAZO DE NIVELES Y REPLANTEO INICIAL DE OB m 417.00 2.04 850.68
0 03.01.01.02 TRAZO DE NIVELES Y REPLANTEO DE ZANJAS m 417.00 2.81 1,171.77
0 03.01.02 MOVIMIENTO DE TIERRAS 92,050.05
0 03.01.02.01 EXCAVACION DE ZANJAS C/RETROEXCAVADORA m 417.00 35.16 14,661.72
0 03.01.02.02 ENTIBADO Y DESENTIBADO DE ZANJAS H>3.00mtsm 417.00 30.58 12,751.86
0 03.01.02.03 REFINE Y NIVELACION DE ZANJAS, TUB. PARA m 417.00 11.62 4,845.54
0 03.01.02.04 PREPARACION DE CAMA DE APOYO C/ MATERIAL m 417.00 10.39 4,332.63
0 03.01.02.05 RELLENO DE PROTECCIÓN - PRIMER RELLEN m 417.00 56.01 23,356.17
0 03.01.02.06 RELLENO Y COMPACTACIÓN EN CAPAS 0.40M m 417.00 7.53 3,140.01
0 03.01.02.07 ELIMINACION DE MATERIAL EXCEDENTE CON E m3 976.80 29.65 28,962.12
0 03.01.03 SUMINISTRO E INSTALACION DE TUBERÍAS P/DESAGUE 390,134.83
0 03.01.03.01 SUMINISTRO E INSTALACION DE TUBERIA PVC U m 417.00 903.76 376,867.92
0 03.01.03.02 PRUEBA HIDRAULICA EN TUB. PVC P/DESAGUE m 417.00 7.98 3,327.66
0 03.01.03.03 DADOS DE CONCRETO P/ANCLAJE TUBO ENTRA und 25.00 397.57 9,939.25
0 03.02 CONSTRUCCION DE BUZONES 61,850.75
0 03.02.01 MOVIMIENTO DE TIERRAS 3,002.87
0 03.02.01.01 EXCAVACION MANUAL PARA BUZÓN Ø 1.50 (DE m3 31.38 47.46 1,489.29
0 03.02.01.02 ACARREO INTERNO DE MATERIAL EXCEDENTE m3 31.38 12.65 396.96
0 03.02.01.03 ELIMINACION DE MATERIAL EXCEDENTE CON E m3 37.66 29.65 1,116.62
0 03.02.02 CONSTRUCCION DE BUZONES 58,847.88
0 03.02.02.01 CONSTRUCCIÓN DE BUZONES Ø 1.50 (DE 4.00M A und 13.00 4,526.76 58,847.88
0 03.03 SUMIDERO MIXTO 44,542.10
0 03.03.01 MOVIMIENTO DE TIERRAS 3,795.30
0 03.03.01.01 EXCAVACIÓN MANUAL DE ZANJAS PARA EST m3 47.52 31.64 1,503.53
0 03.03.01.02 ACARREO INTERNO DE MATERIAL EXCEDENTE m3 47.52 12.65 601.13
0 03.03.01.03 ELIMINACION DE MATERIAL EXCEDENTE CON E m3 57.02 29.65 1,690.64
0 03.03.02 OBRAS DE CONCRETO SIMPLE 1,004.30
0 03.03.02.01 SOLADO DE CONCRETO F'c=100 kg/cm2 m2 36.60 27.44 1,004.30
0 03.03.03 OBRAS DE CONCRETO ARMADO 26,627.55
0 03.03.03.01 CONCRETO F'C=210KG/CM2 EN SUMIDERO m3 25.54 426.91 10,903.28
0 03.03.03.02 ENCOFRADO Y DESENCOFRADO NORMAL m2 152.10 35.33 5,373.69
0 03.03.03.03 ACERO FY=4200 KG/CM2 kg 1,233.68 8.39 10,350.58
0 03.03.04 TARRAJEO Y ACABADOS 3,674.55
0 03.03.04.01 TARRAJEO CON IMPERMEABILIZANTE - ACABADO m2 131.00 28.05 3,674.55
0 03.03.05 INSTALACIONES METALICAS 9,440.40
0 03.03.05.01 VENTANA SUMIDERO 0.90x0.25M und 20.00 211.01 4,220.20
0 03.03.05.02 SUMIDERO DE REJILLA 1.00x0.50M und 20.00 261.01 5,220.20
0 03.04 INSTALACIÓN DE SUMIDEROS A RED MATRIZ 27,073.88
0 03.04.01 MOVIMIENTO DE TIERRAS 5,820.23
0 03.04.01.01 EXCAVACION DE ZANJAS C/RETROEXCAVADORA m 66.50 15.71 1,044.72
0 03.04.01.02 REFINE Y NIVELACION DE ZANJAS, TUB. PARA m 66.50 11.62 772.73
0 03.04.01.03 PREPARACION DE CAMA DE APOYO C/ MATERIA m 66.50 7.65 508.73
0 03.04.01.04 RELLENO DE PROTECCIÓN - PRIMER RELLEN m 66.50 16.12 1,071.98
0 03.04.01.05 RELLENO Y COMPACTACIÓN EN CAPAS 0.40M m 66.50 7.53 500.75
0 03.04.01.06 ELIMINACION DE MATERIAL EXCEDENTE CON E m3 64.80 29.65 1,921.32
0 03.04.02 SUMINISTRO E INSTALACION DE TUBERÍAS P/DESAGUE PLUVIAL 10,552.05
0 03.04.02.01 SUMINISTRO E INSTALACION DE TUBERIA PVC-U m 66.50 66.90 4,448.85
0 03.04.02.02 DADOS DE CONCRETO P/ANCLAJE TUBO ENTRADA
und 40.00 152.58 6,103.20
0 03.04.03 CONEXIONES DE DESAGUE PLUVIAL A LA RED MATRIZ 10,701.60
0 03.04.03.01 CONEXIÓN A LA RED MATRIZ und 20.00 535.08 10,701.60
0 04 MITIGACION AMBIENTAL 15,444.29
0 04.01 LIMPIEZA FINAL DE OBRA m2 5,430.15 1.27 6,896.29
0 04.02 RIEGO PERMANENTE DE ZONA DE TRABAJO PARA MIT m 385.00 7.80 3,003.00
0 04.03 AREAS VERDES GLB 1.00 5,545.00 5,545.00
05 PREVENCION ANTE EL COVID-19 23,100.00
05.01 IMPLEMENTACION PARA PRECENCION DEL COVID-19 mes 6.00 3,850.00 23,100.00
CRONOGRAMA VALORIZADO DE OBRA
OBRA : "MEJORAMIENTO DE LOS SERVICIOS DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA AV. MARISCAL CACERES TRAMO CARRETERA CENTRAL - FERROCARRIL DEL DISTRITO DE CONCEPCION - PROVINCIA DE CONCEPCION - DEPARTAMENTO DE JUNIN" - CUI:N° 2540918
ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CONCEPCIÓN FECHA DE INICIO DE OBRA : 17 DE MARZO DEL 2022 DISTRITO : CONCEPCIÓN
CONSULTOR : PLAZO DE EJECUCION DE OBRA : 180 DIAS CALENDARIOS PROVINCIA : CONCEPCIÓN
SUSPENSIÓN DE OBRA Nº 01 : DEL 19 DE JULIO AL 31 JULIO (13 DIAS)
FECHA DE CULMINACION DE OBRA : 25 DE SETIEMBRE DEL 2022 DEPARTAMENTO : JUNÍN

MARZO ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE


PARTIDA DESCRIPCION PARCIAL S/.
17/03/2022 - 31/03/2022 01/04/2022 - 15/04/2022 16/04/2022 - 30/04/2022 01/05/2022 - 15/05/2022 16/05/2022 - 31/05/2022 01/06/2022 - 15/06/2022 16/06/2022 - 30/06/2022 01/07/2022 - 18/07/2022 19/07/2022 - 31/07/2022 01/08/2022 - 15/08/2022 16/08/2022 - 27/08/2022 01/09/2022 - 15/09/2022

SUSPENSIÓN DE PLAZO DE FIN DE OBRA PLAZO CONTRACTUAL CON SUSPECION DE PLAZO - 180 DI
EJECUCION CALENDARIO (26/09/2022)

PAVIMENTO RÍGIDO, CUNETAS, SARDINEL Y VEREDAS S/.852,103.83 AMPLIACION DE PLAZO Nº 01 DE 65 DIAS CALENDARIOS

01.01 OBRAS PROVISIONALES S/.58,792.71 9,792.77

01.02 TRABAJOS PRELIMINARES S/.25,712.87 14,281.29

01.03 EXPLANACIONES S/.51,756.69 51,756.69

01.04 PAVIMENTO RIGIDO S/.398,617.59 23,496.36

01.04.01 SUB RASANTE

01.04.02 SUB BASE GRANULAR

01.04.03 PAVIMENTO RIGIDO

01.05 OBRAS DE ARTE Y DRENAJE S/.282,597.56 #REF!

01.05.01 BADEN (02 UNIDADES)

01.05.02 CUNETAS LATERALES

01.05.03 SARDINEL

01.05.04 VEREDAS PEATONALES DE CONCRETO

01.05.05 RAMPAS PARA ACCESO VEHICULAR

01.05.06 RAMPAS PEATONALES

01.05.07 MARTILLOS

01.05.08 MUROS DE CONTENCIÓN DE CONCRETO ARMADO

01.06 OTROS S/.34,626.41 #REF!

01.06.01 SEÑALIZACIONES HORIZONTALES

SISTEMA SANITARIO S/.391,362.75


02.01 REPOSICIÓN DEL SISTEMA DE DESAGUE S/.317,152.52 15,202.52

02.01.01 RED EMISORA

02.01.02 CONSTRUCCION DE BUZONES

02.02 REPOSICIÓN Y RECONEXIÓN DEL SISTEMA DE AGUA POTABLE S/.74,210.23 #REF!

02.02.01 REPOSICIÓN DE TUBERIAS DEL SISTEMA DE AGUA POTABLE

DRENAJE PLUVIAL S/.617,674.06


03.01 RED COLECTORA S/.484,207.33 1,171.77

03.02 CONSTRUCCION DE BUZONES S/.61,850.75 #REF!

03.03 SUMIDERO MIXTO S/.44,542.10 2,694.94

03.04 INSTALACIÓN DE SUMIDEROS A RED MATRIZ S/.27,073.88 12,974.12

MITIGACION AMBIENTAL S/.15,444.29


PREVENCION ANTE EL COVID-19 S/.23,100.00
VALORIZADO DE OBRA
PARTAMENTO DE JUNIN" - CUI:N° 2540918

SETIEMBRE OCTUBRE NOVIEMBRE


16/09/2022 - 30/09/2022 01/10/2022 - 15/10/2022 16/10/2022 - 31/10/2022 01/11/2022 - 15/11/2022 16/11/2022 - 30/11/2022

FIN DE OBRA PLAZO CONTRACTUAL CON SUSPECION DE PLAZO - 180 DIAS


CALENDARIO (26/09/2022)

AMPLIACION DE PLAZO Nº 01 DE 65 DIAS CALENDARIOS


CALENDARIO DE ADQUISICIÓN DE MATERIALES
OBRA : "MEJORAMIENTO DE LOS SERVICIOS DE TRANSITABILIDAD PEATONAL Y VEHICULAR DE LA AV. MARISCAL CACERES TRAMO CARRETERA CENTRAL - FERROCARRIL DEL DISTRITO DE CONCEPCION - PROVINCIA DE CONCEPCION - DEPARTAMENTO DE JUNIN" - CUI:N° 2540918

ENTIDAD : MUNICIPALIDAD PROVINCIAL DE CONCEPCIÓN FECHA DE INICIO DE OBRA : 17 DE MARZO DEL 2022 DISTRITO : CONCEPCIÓN
CONSULTOR : PLAZO DE EJECUCION : 180 DIAS CALENDARIOS PROVINCIA : CONCEPCIÓN
FECHA DE CULMINACON DE OBRA : 25 DE SETIEMBRE DEL 2022 DEPARTAMENTO : JUNÍN

PRECIO PRECIO TOTAL


CODIGO DESCRIPCION UNID CANTIDAD MARZO ABRIL MAYO JUNIO JULIO AGOSTO
UNITARIO S/. S/.

MANO DE OBRA 307,576.33


0147010002 OPERARIO hh 5,340.02 14.12 75,401.12 12,566.85 12,566.85 12,566.85 12,566.85 12,566.85 12,566.85
0147010003 OFICIAL hh 3,541.46 12.71 45,012.00 7,502.00 7,502.00 7,502.00 7,502.00 7,502.00 7,502.00
0147010004 PEON hh 16,563.12 11.30 187,163.21 31,193.87 31,193.87 31,193.87 31,193.87 31,193.87 31,193.87

MATERIALES 1,459,901.10
0201000012 INSUMOS CONTRA EL COVID-19 gln 6.00 3,850.00 23,100.00 3,850.00 3,850.00 3,850.00 3,850.00 3,850.00 3,850.00
0202000007 ALAMBRE NEGRO RECOCIDO # 16 kg 477.77 6.50 3,105.52 1,242.21 931.66 931.66
0202000008 ALAMBRE NEGRO RECOCIDO # 8 kg 324.99 6.50 2,112.42 844.97 633.73 633.73
0202010005 CLAVOS PARA MADERA C/C 3" kg 491.19 6.50 3,192.72 319.27 957.82 957.82 957.82
0202020003 CLAVOS Fo No C/C 2 1/2" kg 10.90 6.50 70.85 70.85
0202110008 FIERRO LISO DE 5/8" kg 1,354.50 7.50 10,158.75 4,063.50 3,047.63 3,047.63
0202130032 POLO MANGA LARGA und 100.00 12.00 1,200.00 600.00 600.00
0202580003 CONO SE SEGURIDAD und 40.00 40.00 1,600.00 1,600.00
0202970002 ACERO DE REFUERZO FY=4200 GRADO 60 kg 6,108.01 7.00 42,756.09 17,102.44 12,826.83 12,826.83
0204010009 ARENA FINA (PUESTA EN OBRA) m3 41.21 90.00 3,709.01 1,483.60 1,112.70 1,112.70
0204010012 AREAS VERDES GLB 1.00 5,545.00 5,545.00 5,545.00
0205010034 ARENA GRUESA (PUESTO EN OBRA) m3 565.10 70.00 39,556.94 15,822.78 11,867.08 11,867.08
0205010035 ARENA GRUESA (PARA RELLENO DE PROTECCION) m3 1,148.82 40.00 45,952.60 4,595.26 20,678.67 20,678.67
0205030080 PIEDRA CHANCADA 3/4" - 1/2" (PUESTO EN OBRA) m3 606.60 80.00 48,528.24 19,411.30 14,558.47 14,558.47
0205300087 MATERIAL AFIRMADO (PUESTO EN OBRA) m3 1,596.31 40.00 63,852.40 31,926.20 31,926.20
0206510098 CINTA DE SEGURIDAD m 6,808.50 0.25 1,702.13 1,702.13
0206510099 MALLA DE SEGURIDAD und 40.00 45.50 1,820.00 1,820.00
0210140080 CACHACO DE CONCRETO und 154.00 40.00 6,160.00 3,080.00 3,080.00
0213000006 ASFALTO RC-250 gln 488.57 20.00 9,771.40 3,908.56 3,908.56 1,954.28
0221000000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 10,511.27 26.00 273,292.95 81,987.89 81,987.89 81,987.89 27,329.30
0229030002 YESO EN BOLSAS DE 25 KG. BOL 117.22 35.00 4,102.82 820.56 820.56 820.56 820.56 820.56
0229220001 CORDEL kg 54.30 8.00 434.42 434.42
0230110014 IMPERMEABILIZANTE kg 39.69 5.30 210.37 210.37
0230860080 CURADOR PARA CONCRETO lt 2,944.58 4.50 13,250.59 5,962.77 5,962.77 1,325.06
0231800003 YEE PVC DE 200mm und 20.00 60.00 1,200.00 240.00 960.00
0231800005 CODO PVC DE 200mm X 45º und 20.00 40.00 800.00 800.00
0231800006 CODO PVC DE 200mm X 90º und 20.00 50.00 1,000.00 1,000.00
0238000004 HORMIGON (PUESTO EN OBRA) m3 54.57 55.00 3,001.25 1,050.44 1,050.44 900.38
0239010101 ALQUILER PARA OFICINA Y ALMACEN DE OBRA GLB 6.00 1,000.00 6,000.00 1,000.00 1,000.00 1,000.00 1,000.00 1,000.00 1,000.00
0239020079 HIPOCLORITO DE CALCIO 70% kg 3.95 30.00 118.50 118.50
0239020100 EMPALMES und 2.00 300.00 600.00 600.00
0239050000 AGUA m3 708.79 2.00 1,417.57 283.51 283.51 283.51 283.51 283.51
0239900007 GRIFO CONTRA INCENDIO SEGUN ESPECIFIC. und 3.00 1,750.00 5,250.00 5,250.00
0239900103 CARTEL DE OBRA (4.80X3.60M) SEGUN DISEÑO und 1.00 250.00 250.00 250.00
0239900106 CARTEL DE SEÑALIZACIONES
CABALLETES DE MADERA INFORMATIVAS SEGUN DISEÑO INC. INSTALAC pza 4.00 450.00 1,800.00 1,800.00
0243010099 und 10.00 55.00 550.00 550.00
CABALLETE DE MADERA
PRECIO PRECIO TOTAL
CODIGO DESCRIPCION UNID CANTIDAD MARZO ABRIL MAYO JUNIO JULIO AGOSTO
UNITARIO S/. S/.

0243010100 MADERA TORNILLO DE 2"X2"(CORREAS) pza 4.00 25.00 100.00 100.00


0243010101 MADERA TORNILLO DE 2"X3"(LISTON) pza 5.00 35.00 175.00 175.00
0243010102 MADERA PARA ENCOFRADO/MONTAÑA p2 9,676.21 5.50 53,219.18 13,304.80 13,304.80 13,304.80 13,304.80
0243600031 MADERA ROLLIZO EUCALIPTO O SIMILAR 2" p2 15.00 6.00 90.00 90.00
0243600032 ESTRUCTURA DE MADERA PARA SEÑALIZACIONES und 5.00 30.00 150.00 150.00
0250060025 TAPA C/MARCO FºFº PARA DESAGUE DE 60KG pza 24.00 350.00 8,400.00 8,400.00
0251960002 VENTANA SUMIDERO 0.90x0.25M SEGÚN DISEÑO und 20.00 150.00 3,000.00 3,000.00
0251960003 SUMIDERO DE REJILLA 1.00x0.50M SEGÚN DISEÑO und 20.00 200.00 4,000.00 4,000.00
0252040051 CLAVOS C/C DE 3" kg 0.80 6.50 5.20 5.20
0253030027 THINER gln 192.40 25.00 4,810.01 962.00 3,848.01
0254110096 PINTURA ESMALTE gln 21.72 60.00 1,303.24 1,303.24
0254450070 PINTURA DE TRAFICO gln 233.60 80.00 18,688.18 3,737.64 14,950.54
0259010100 TAPONES AUDITIVOS und 90.00 5.00 450.00 225.00 225.00
0259010101 GUANTES DE NYLON Y NITRILO PAR 120.00 7.00 840.00 420.00 420.00
0259010102 LENTES DE PROTECCION und 60.00 7.00 420.00 210.00 210.00
0259010103 CORTAVIENTOS PARA CASCO und 60.00 6.00 360.00 180.00 180.00
0259010104 GUANTES DE JEBE PAR 120.00 15.00 1,800.00 900.00 900.00
0259010105 GUANTES DE CUERO REFORZADO PAR 120.00 12.00 1,440.00 720.00 720.00
0259010106 CASCO DE PROTECCION + BARBIQUEJO und 40.00 18.00 720.00 360.00 360.00
0259010107 CHALECO DE SEGURIDAD und 90.00 25.00 2,250.00 1,125.00 1,125.00
0259010108 BOTAS DE JEBE PAR 100.00 38.00 3,800.00 1,900.00 1,900.00
0259010109 PANTALON DE OBRA und 100.00 25.00 2,500.00 1,250.00 1,250.00
0259010110 CAMISA DE OBRA und 100.00 25.00 2,500.00 1,250.00 1,250.00
0259010111 ZAPATO DE PROTECCION PAR 60.00 70.00 4,200.00 2,100.00 2,100.00
0259010112 CAPOTIN IMPERMEABLE PARA LLUVIA und 60.00 25.00 1,500.00 750.00 750.00
0259010115 ZAPATO DE PROTECCION TECNICO PAR 8.00 250.00 2,000.00 2,000.00
0259010116 CASCO DE PROTECCION + BARBIQUEJO (TECNICO) und 8.00 45.00 360.00 360.00
0259010117 CHALECO DE SEGURIDAD (TECNICO) und 14.00 55.00 770.00 385.00 385.00
0259010119 GUANTES DE SEGURIDAD (TECNICO) PAR 14.00 28.00 392.00 196.00 196.00
0259010120 LENTES DE PROTECCION (TECNICO) und 8.00 12.00 96.00 96.00
0259010121 OREGERAS (TECNICO) und 8.00 20.00 160.00 160.00
0259010122 CAMISA DE OBRA (TECNICO) und 8.00 45.00 360.00 360.00
0259010123 PANTALON (TECNICO) und 8.00 55.00 440.00 440.00
0259010124 PARANTES DE SEGURIDAD und 50.00 25.50 1,275.00 1,275.00
0259010125 ORMA DE BUZON METALICO und 96.00 100.00 9,600.00 4,800.00 4,800.00
0259010126 CASACA IMPERMEABLE und 8.00 90.00 720.00 720.00
0266990001 LUBRICANTE PARA ANILLO DE CAUCHO gln 57.25 50.00 2,862.50 1,145.00 1,145.00 572.50
0272010013 TUBERIA PVC SAP C-10 DE 1" m 948.15 9.00 8,533.35 3,413.34 2,560.01 2,560.01
0272020105 TUBO UPVC U/F DN 200MM S-25 PARA DESAGUE INC. ANILLO m 130.49 60.00 7,829.40 3,131.76 3,131.76 1,565.88
0272020108 TUBO PVC UF DN 400mm S-25 PARA DESAGUE INC. ANILLO m 428.24 380.00 162,731.20 65,092.48 65,092.48 32,546.24
0272020110 TUBO PVC UF DN 630mm S-25 PARA DESAGUE INC. ANILLO m 437.85 840.00 367,794.00 147,117.60 147,117.60 73,558.80
0277030018 VALVULA DE CONTROL und 3.00 350.00 1,050.00 1,050.00
0282010003 REUBICACION DE POSTES ELETCRICOS GLB 1.00 5,024.00 5,024.00 5,024.00
0283770002 DEMOLICION DE ESTRUCTURAS EXISTENTES und 1.00 8,738.78 8,738.78 8,738.78
0290010029 TUBERIA PVC UF C-10 DN 110MM INC. ANILLO DE JEBE m 414.75 55.00 22,811.25 4,562.25 18,249.00
0290010030 CODO PVC UF DN=110MM x 45º und 10.00 100.00 1,000.00 200.00 800.00
0290010031 TEE PVC UF DN=110MM und 4.00 150.00 600.00 600.00
0298010082 PETROLEO DIESSEL D5 gln 6,521.19 17.00 110,860.27 33,258.08 33,258.08 16,629.04 16,629.04 5,543.01 5,543.01
PRECIO PRECIO TOTAL
CODIGO DESCRIPCION UNID CANTIDAD MARZO ABRIL MAYO JUNIO JULIO AGOSTO
UNITARIO S/. S/.

EQUIPOS 132,204.03
0337010001 HERRAMIENTAS MANUALES %MO 14,523.47 2,420.58 2,420.58 2,420.58 2,420.58 2,420.58 2,420.58
0337020047 BALDE P/PRUEBA HIDROSTATICA INC. ACCESORIOS HE 31.60 15.00 474.00 237.00 237.00
0337540017 ESTACION TOTAL (inc. miras y tripode) hm 141.64 20.00 2,832.86 472.14 472.14 472.14 472.14 472.14 472.14
0348010011 MEZCLADORA DE CONCRETO DE 9 -11P3 hm 104.66 25.00 2,616.47 654.12 654.12 654.12 654.12
0348040003 CAMION CISTERNA 4x2 (AGUA) 122 HP 2,000 hm 94.65 100.00 9,464.75 1,892.95 1,892.95 1,892.95 1,892.95 1,892.95
0348040036 VOLQUETE DE 15 M3 hm 101.83 100.00 10,182.77 2,036.55 2,036.55 2,036.55 2,036.55 2,036.55
0348120094 MOTOBOMBA INCL. MANGUERA Y ACCS. hm 225.28 10.00 2,252.81 1,126.41 1,126.41
0348960005 CIZALLA P/FIERRO DE CONSTRUCCION hm 129.42 3.50 452.98 226.49 226.49
0349030001 COMPACTADOR VIBR. TIPO PLANCHA 4 HP hm 307.67 20.00 6,153.37 3,076.69 3,076.69
0349030007 RODILLO LISO VIBR AUTOP 125HP hm 82.33 150.00 12,349.13 6,174.57 6,174.57
0349040091 CARGADOR FRONTAL 950H hm 101.83 150.00 15,274.20 3,054.84 3,054.84 3,054.84 3,054.84 3,054.84
0349040092 EXCAVADORA SOBRE ORUGA 360 hm 21.94 380.00 8,339.02 8,339.02
0349050032 ZARANDA METALICA hm 164.82 2.50 412.05 412.05
0349050033 PISON MANUAL hm 96.46 1.00 96.47 96.47
0349060055 RETROEXCAVADORA 310 SL 286758 hm 158.81 150.00 23,821.78 11,910.89 11,910.89
0349070004 VIBRADOR DE CONCRETO 4 HP 2.40" hm 556.67 5.00 2,783.36 278.34 278.34 1,113.34 1,113.34
0349090003 MOTONIVELADORA DE 130-135 HP hm 82.33 150.00 12,349.13 9,879.30 2,469.83
0349100007 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 hm 460.67 15.00 6,910.04 691.00 691.00 2,764.02 2,764.02
0349880002 NIVEL TOPOGRAFICO hm 76.28 12.00 915.37 183.07 366.15 366.15

COSTO DIRECTO 1,899,681.46 162,517.40 394,900.00 514,371.24 429,646.40 257,654.92 140,591.49


8.55% 20.79% 27.08% 22.62% 13.56% 7.40%
Precios y cantidades de recursos requeridos

Código Recurso Unidad Cantidad Precio S/. Parcial S/.


MANO DE OBRA
0147010002 OPERARIO hh 5,340.0200 14.12 75,401.12
0147010003 OFICIAL hh 3,541.4600 12.71 45,012.00
0147010004 PEON hh 16,563.1200 11.30 187,163.21

307,576.33

MATERIALES
0201000012 INSUMOS CONTRA EL COVID-19 gln 6.0000 3,850.00 23,100.00
0202000007 ALAMBRE NEGRO RECOCIDO # 16 kg 477.7700 6.50 3,105.52
0202000008 ALAMBRE NEGRO RECOCIDO # 8 kg 324.9900 6.50 2,112.42
0202010005 CLAVOS PARA MADERA C/C 3" kg 491.1900 6.50 3,192.72
0202020003 CLAVOS Fo No C/C 2 1/2" kg 10.9000 6.50 70.85
0202110008 FIERRO LISO DE 5/8" kg 1,354.5000 7.50 10,158.75
0202130032 POLO MANGA LARGA und 100.0000 12.00 1,200.00
0202580003 CONO SE SEGURIDAD und 40.0000 40.00 1,600.00
0202970002 ACERO DE REFUERZO FY=4200 GRADO 60 kg 6,108.0100 7.00 42,756.09
0204010009 ARENA FINA (PUESTA EN OBRA) m3 41.2100 90.00 3,709.01
0204010012 AREAS VERDES GLB 1.0000 5,545.00 5,545.00
0205010034 ARENA GRUESA (PUESTO EN OBRA) m3 565.1000 70.00 39,556.94
0205010035 ARENA GRUESA (PARA RELLENO DE m3 1,148.8200 40.00 45,952.60
0205030080 PROTECCION)
PIEDRA CHANCADA 3/4" - 1/2" (PUESTO EN m3 606.6000 80.00 48,528.24
0205300087 OBRA)
MATERIAL AFIRMADO (PUESTO EN OBRA) m3 1,596.3100 40.00 63,852.40
0206510098 CINTA DE SEGURIDAD m 6,808.5000 0.25 1,702.13
0206510099 MALLA DE SEGURIDAD und 40.0000 45.50 1,820.00
0210140080 CACHACO DE CONCRETO und 154.0000 40.00 6,160.00
0213000006 ASFALTO RC-250 gln 488.5700 20.00 9,771.40
0221000000 CEMENTO PORTLAND TIPO I (42.5KG) BOL 10,511.2700 26.00 273,292.95
0229030002 YESO EN BOLSAS DE 25 KG. BOL 117.2200 35.00 4,102.82
0229220001 CORDEL kg 54.3000 8.00 434.42
0230110014 IMPERMEABILIZANTE kg 39.6900 5.30 210.37
0230860080 CURADOR PARA CONCRETO lt 2,944.5800 4.50 13,250.59
0231800003 YEE PVC DE 200mm und 20.0000 60.00 1,200.00
0231800005 CODO PVC DE 200mm X 45º und 20.0000 40.00 800.00
0231800006 CODO PVC DE 200mm X 90º und 20.0000 50.00 1,000.00
0238000004 HORMIGON (PUESTO EN OBRA) m3 54.5700 55.00 3,001.25
0239010101 ALQUILER PARA OFICINA Y ALMACEN DE OBRA GLB 6.0000 1,000.00 6,000.00
0239020079 HIPOCLORITO DE CALCIO 70% kg 3.9500 30.00 118.50
0239020100 EMPALMES und 2.0000 300.00 600.00
0239050000 AGUA m3 708.7900 2.00 1,417.57
0239900007 GRIFO CONTRA INCENDIO SEGUN ESPECIFIC. und 3.0000 1,750.00 5,250.00
0239900103 CARTEL DE OBRA (4.80X3.60M) SEGUN DISEÑO und 1.0000 250.00 250.00
0239900106 CARTEL DE SEÑALIZACIONES INFORMATIVAS pza 4.0000 450.00 1,800.00
0243010099 SEGUN DISEÑO
CABALLETES DEINC. INSTALACION
MADERA und 10.0000 55.00 550.00
0243010100 MADERA TORNILLO DE 2"X2"(CORREAS) pza 4.0000 25.00 100.00
0243010101 CABALLETE DE MADERA
MADERA TORNILLO DE 2"X3"(LISTON) pza 5.0000 35.00 175.00
0243010102 MADERA PARA ENCOFRADO/MONTAÑA p2 9,676.2100 5.50 53,219.18
0243600031 MADERA ROLLIZO EUCALIPTO O SIMILAR 2" p2 15.0000 6.00 90.00
0243600032 ESTRUCTURA DE MADERA PARA und 5.0000 30.00 150.00
0250060025 SEÑALIZACIONES
TAPA C/MARCO FºFº PARA DESAGUE DE 60KG pza 24.0000 350.00 8,400.00
0251960002 VENTANA SUMIDERO 0.90x0.25M SEGÚN DISEÑO und 20.0000 150.00 3,000.00
0251960003 SUMIDERO DE REJILLA 1.00x0.50M SEGÚN und 20.0000 200.00 4,000.00
0252040051 DISEÑO
CLAVOS C/C DE 3" kg 0.8000 6.50 5.20
0253030027 THINER gln 192.4000 25.00 4,810.01
0254110096 PINTURA ESMALTE gln 21.7200 60.00 1,303.24
0254450070 PINTURA DE TRAFICO gln 233.6000 80.00 18,688.18
0259010100 TAPONES AUDITIVOS und 90.0000 5.00 450.00
0259010101 GUANTES DE NYLON Y NITRILO PAR 120.0000 7.00 840.00
0259010102 LENTES DE PROTECCION und 60.0000 7.00 420.00
0259010103 CORTAVIENTOS PARA CASCO und 60.0000 6.00 360.00
0259010104 GUANTES DE JEBE PAR 120.0000 15.00 1,800.00
0259010105 GUANTES DE CUERO REFORZADO PAR 120.0000 12.00 1,440.00
0259010106 CASCO DE PROTECCION + BARBIQUEJO und 40.0000 18.00 720.00
0259010107 CHALECO DE SEGURIDAD und 90.0000 25.00 2,250.00
0259010108 BOTAS DE JEBE PAR 100.0000 38.00 3,800.00
0259010109 PANTALON DE OBRA und 100.0000 25.00 2,500.00
0259010110 CAMISA DE OBRA und 100.0000 25.00 2,500.00
0259010111 ZAPATO DE PROTECCION PAR 60.0000 70.00 4,200.00
0259010112 CAPOTIN IMPERMEABLE PARA LLUVIA und 60.0000 25.00 1,500.00
0259010115 ZAPATO DE PROTECCION TECNICO PAR 8.0000 250.00 2,000.00
0259010116 CASCO DE PROTECCION + BARBIQUEJO und 8.0000 45.00 360.00
0259010117 (TECNICO)
CHALECO DE SEGURIDAD (TECNICO) und 14.0000 55.00 770.00
0259010119 GUANTES DE SEGURIDAD (TECNICO) PAR 14.0000 28.00 392.00
0259010120 LENTES DE PROTECCION (TECNICO) und 8.0000 12.00 96.00
0259010121 OREGERAS (TECNICO) und 8.0000 20.00 160.00
0259010122 CAMISA DE OBRA (TECNICO) und 8.0000 45.00 360.00
0259010123 PANTALON (TECNICO) und 8.0000 55.00 440.00
0259010124 PARANTES DE SEGURIDAD und 50.0000 25.50 1,275.00
0259010125 ORMA DE BUZON METALICO und 96.0000 100.00 9,600.00
0259010126 CASACA IMPERMEABLE und 8.0000 90.00 720.00
0266990001 LUBRICANTE PARA ANILLO DE CAUCHO gln 57.2500 50.00 2,862.50
0272010013 TUBERIA PVC SAP C-10 DE 1" m 948.1500 9.00 8,533.35
0272020105 TUBO UPVC U/F DN 200MM S-25 PARA DESAGUE m 130.4900 60.00 7,829.40
0272020108 INC. ANILLO
TUBO PVC UF DN 400mm S-25 PARA DESAGUE m 428.2400 380.00 162,731.20
0272020110 INC. ANILLO
TUBO PVC UF DN 630mm S-25 PARA DESAGUE m 437.8500 840.00 367,794.00
0277030018 INC. ANILLO
VALVULA DE CONTROL und 3.0000 350.00 1,050.00
0282010003 REUBICACION DE POSTES ELETCRICOS GLB 1.0000 5,024.00 5,024.00
0283770002 DEMOLICION DE ESTRUCTURAS EXISTENTES und 1.0000 8,738.78 8,738.78
0290010029 TUBERIA PVC UF C-10 DN 110MM INC. ANILLO DE m 414.7500 55.00 22,811.25
0290010030 JEBE
CODO PVC UF DN=110MM x 45º und 10.0000 100.00 1,000.00
0290010031 TEE PVC UF DN=110MM und 4.0000 150.00 600.00
0298010082 PETROLEO DIESSEL D5 gln 6,521.1900 17.00 110,860.27

1,459,901.10
EQUIPOS
0337010001 HERRAMIENTAS MANUALES %MO 14,523.47
0337020047 BALDE P/PRUEBA HIDROSTATICA INC. HE 31.6000 15.00 474.00
0337540017 ACCESORIOS
ESTACION TOTAL (inc. miras y tripode) hm 141.6400 20.00 2,832.86
0348010011 MEZCLADORA DE CONCRETO DE 9 -11P3 hm 104.6600 25.00 2,616.47
0348040003 CAMION CISTERNA 4x2 (AGUA) 122 HP 2,000 hm 94.6500 100.00 9,464.75
0348040036 VOLQUETE DE 15 M3 hm 101.8300 100.00 10,182.77
0348120094 MOTOBOMBA INCL. MANGUERA Y ACCS. hm 225.2800 10.00 2,252.81
0348960005 CIZALLA P/FIERRO DE CONSTRUCCION hm 129.4200 3.50 452.98
0349030001 COMPACTADOR VIBR. TIPO PLANCHA 4 HP hm 307.6700 20.00 6,153.37
0349030007 RODILLO LISO VIBR AUTOP 125HP hm 82.3300 150.00 12,349.13
0349040091 CARGADOR FRONTAL 950H hm 101.8300 150.00 15,274.20
0349040092 EXCAVADORA SOBRE ORUGA 360 hm 21.9400 380.00 8,339.02
0349050032 ZARANDA METALICA hm 164.8200 2.50 412.05
0349050033 PISON MANUAL hm 96.4600 1.00 96.47
0349060055 RETROEXCAVADORA 310 SL 286758 hm 158.8100 150.00 23,821.78
0349070004 VIBRADOR DE CONCRETO 4 HP 2.40" hm 556.6700 5.00 2,783.36
0349090003 MOTONIVELADORA DE 130-135 HP hm 82.3300 150.00 12,349.13
0349100007 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 hm 460.6700 15.00 6,910.04
0349880002 NIVEL TOPOGRAFICO hm 76.2800 12.00 915.37

132,204.03

1,899,681.46
PIEDRA
CONCRETO CEMENTO ARENA CHANCADA 3/4" - AGUA
1/2"
kg/cm2 Bolsas m3 m3 m3
175 8.43 0.54 0.55 0.185
210 9.70 0.50 0.60 0.186

También podría gustarte