METRADOS

PROYECTO : S.E. CAHUACHI


SECTOR : OBRAS PROVISIONALES
REALIZADA POR : J A CONSTRUCIONES Y SERVICIOS SAC
PLANOS DE REFERENCIA:

VOLÚMEN / AREA
N° DE GUIA HORA DE HORA DE
ITEM DESCRIPCION UND FECHA DE PRECIINTO SALIDA LLEGADA HORA DE VACIADO # L B H
REMISION DE PLANTA A OBRA PARCIAL
Rep (m) (m) (m)

Concreto f'c= 280 kg/cm2 48.00


SSP, TC-1 EJE 6 EJE F-I , SRC PEDESTAL EJE 6 EJE I-L , SSP PEDESTAL EJE 7 EJE F-I , VC DE E. CONTROL 11/10/2022 010-2868 15:56 16:00 8.00
SSP, TC-1 EJE 6 EJE F-I , SRC PEDESTAL EJE 6 EJE I-L , SSP PEDESTAL EJE 7 EJE F-I , VC DE E. CONTROL 11/10/2022 010-2869 17:50 18:00 8.00
SOBRECIMIENTO DE CERRAMIENTO , ZAPATA EJE 3J , PEDESTAL EJE 3H , 3D PATIO 60 KV , IN-1 ZAPATA EJE 7 EJE F-I PATIO 220 KV , V.C. EJE 3 EJE A-E E.C. 11/15/2022 010-2885 16:30 16:40 8.00
SOBRECIMIENTO DE CERRAMIENTO , ZAPATA EJE 3J , PEDESTAL EJE 3H , 3D PATIO 60 KV , IN-1 ZAPATA EJE 7 EJE F-I PATIO 220 KV , V.C. EJE 3 EJE A-E E.C. 11/15/2022 010-2886 17:10 17:20 8.00

ZAPATA TT-DS EJE 1 , PEDESTAL IN-1 EJE 2 ,ZAPATA C13 EJE D , PEDESTAL C13 EJE 4H , PEDESTAL C13 EJE 4J PATIO 60 KV , ZAPATA AP-1 EJE 8 EJE I-L PATIO 220 KV 11/22/2022 010-2914 15:04 15:10
, SOBRECIMIENTO EJE LM3 -1 Y EJE 3 - 5 CERRAMIENTO 8.00

ZAPATA TT-DS EJE 1 , PEDESTAL IN-1 EJE 2 ,ZAPATA C13 EJE D , PEDESTAL C13 EJE 4H , PEDESTAL C13 EJE 4J PATIO 60 KV , ZAPATA AP-1 EJE 8 EJE I-L PATIO 220 KV 11/22/2022 010-2916 15:30 15:40
, SOBRECIMIENTO EJE LM3 -1 Y EJE 3 - 5 CERRAMIENTO 8.00

Concreto f'c= 175 kg/cm2 114.00


CIMIENTO CERRAMIENTO 11/12/2022 010-2875 10:00 10:10 7.50
CIMIENTO CERRAMIENTO 11/12/2022 010-2876 11:00 11:10 7.50
CIMIENTO CERRAMIENTO Y E.C. EJE 1 -3 11/17/2022 010-2890 11:00 11:10 7.00
CIMIENTO CERRAMIENTO Y E.C. EJE 1 -3 11/17/2022 010-2891 10:30 10:40 7.00
CIMIENTO CERRAMIENTO 11/19/2022 010-2910 8:50 9:00 8.00
CIMIENTO CERRAMIENTO Y E.C. EJE 1 -3 11/19/2022 010-2911 11:35 11:45 6.00
CIMIENTO CERRAMIENTO EJE 6- 8 11/23/2022 010-2920 14:25 14:40 6.00
CIMIENTO CERRAMIENTO EJE 6- 8 11/23/2022 010-2921 14:50 15:00 6.50
CIMIENTO CORRIDO EDIFICIO DE CONTROL 11/25/2022 010-2926 15:17 15:25 8.50
CIMIENTO CORRIDO EDIFICIO DE CONTROL Y CERRAMIENTO 11/25/2022 010-2927 15:43 15:00 8.50
CIMIENTO CORRIDO CERRAMIENTO 11/26/2022 010-2932 9:45 10:00 6.00
CIMIENTO CORRIDO CERRAMIENTO 11/26/2022 010-2933 9:52 10:10 6.00
CIMIENTO CORRIDO CERRAMIENTO 11/29/2022 010-2947 14:47 14:55 7.00
CIMIENTO CORRIDO CERRAMIENTO 11/29/2022 010-2948 16:00 16:10 7.50
CIMIENTO CORRIDO CERRAMIENTO 12/2/2022 01-2962 13:55 14:05 7.50
CIMIENTO CORRIDO CERRAMIENTO 12/2/2022 01-2963 14:05 14:15 7.50

Concreto f'c= 100 kg/cm2 8.00


SOLADO DE TRANSFORMADOR 12/7/2022 01-2991 14:00 14:10 8.00
METRADOS

PROYECTO : S.E. CAHUACHI


SECTOR : OBRAS PROVISIONALES
REALIZADA POR : J A CONSTRUCIONES Y SERVICIOS SAC
PLANOS DE REFERENCIA:

VOLÚMEN / AREA
N° DE GUIA HORA DE HORA DE
ITEM DESCRIPCION UND FECHA DE PRECIINTO SALIDA LLEGADA HORA DE VACIADO
REMISION DE PLANTA A OBRA PARCIAL

CONCRETO SIMPLE
OBRAS PROVISIONALES
Concreto f'c= 100 kg/cm2 m3 28.00
PISO PARA OFICINAS 16-09-22 010-206 029744 8:50 AM 2:07 PM 2:07 PM 4.00
PISO PARA OFICINAS 16-09-22 010-207 029745 2:00 PM 2:59 PM 2:59 PM 4.00
PISO PARA OFICINAS 19-09-22 010-211 029748 1:17 PM 9:35 AM 9:35 AM 4.00
PISO PARA OFICINAS 20-09-22 010-218 029755 1:55 PM 3:47 PM 3:47 PM 5.00

Concreto f'c= 100 kg/cm2


solado 9/30/2022 010-248 29785 11:20 12:55 12:55 7.00
solado 10/4/2022 010-259 29793 13:30 14:40 14:40 4.00

Concreto f'c= 280 kg/cm2 661.70


zapata 10/10/2022 010-275 30309 15:10 16:04 16:04
zapata 10/10/2022 010-274 30308 13:30 15:00 15:00 7.00
zapata 10/10/2022 010-273 30307 11:25 12:28 12:28 7.00
zapata 10/10/2022 010-272 30306 10:10 11:17 11:17 7.00
zapata 10/11/2022 010-277 30311 13:30 14:30 14:30 7.35
zapata 10/11/2022 010-278 30312 14:00 14:54 14.54 7.35
Zapata Y Pedestal 10/14/2022 010-285 30318 9:00 10:55 10:55 8.50
Pedestal y Zapata de Edificio de Control 10/17/2022 010-294 30326 13:15 14:00 14:30 6.00
Pedestal y Zapata de Edificio de Control 10/18/2022 010-299 30331 14:30 15:27 15:35 6.00
Pedestal y Zapata de Edificio de Control 10/19/2022 010-303 30334 13:25 14:20 14:35 5.00
Seccionador semipantografo eje 9 10/21/2022 010-309 30338 6:55 8:07 8:10 8.00
Seccionador semipantografo eje 10 10/21/2022 010-307 30336 14:10 15:23 15:31 8.00
TC-1 ZAPATA EJE10 , TO ZAPATA EJE 10 Y PEDESTAL SSP EJE 9 10/22/2022 010-311 30340 10:20 11:10 11:15 5.50
TC-1 ZAPATA EJE 10 , TO ZAPATA EJE 10 Y PEDESTAL SSP EJE 9 10/22/2022 010-312 30341 10:40 11:38 11:45 5.50
TC-1 ZAPATA EJE 10 , TO ZAPATA EJE 10 ,AP-1 , PEDESTAL SSP EJE 9 10/25/2022 010-316 30343 6:20 7:26 7:40 5.50
TC-1 ZAPATA EJE 10 , TO ZAPATA EJE 10 ,AP-1 , PEDESTAL SSP EJE 9 10/25/2022 010-317 30344 6:20 7:26 7:40 5.50
PEDESTAL TRANSFORMADOR DE CORRIENTE EJE 10 10/27/2022 010-327 30352 9:40 10:40 10:50 8.00
INTERRUPTOR EJE 9 10/27/2022 010-328 30353 9:55 10:45 11:00 8.00
PEDESTAL TO EJE 10 10/28/2022 010-330 30355 8:10 8:57 9:10 8.50
ZAPATA SRC EJE 9 10/29/2022 010-332 30857 6:30 7:53 8:15 4.50
ZAPATA SRC EJE 9 10/29/2022 010-333 30858 7:00 7:57 8:30 4.50
IN-1 PEDESTAL EJE 9 , SRCCPT ZAPATA EJE 10 A EJE F- I 11/2/2022 010-339 30364 15:50 16:40 16:50 9.00
SRCCPT ZAPATA EJE 10 11/3/2022 010-342 30366 14:15 15:22 15:40 9.00
ZAPATA C2 EJE 7, PEDESTAL AP-1 EJE 10 , PEDESTAL DS-1 EJE 10 11/3/2022 010-343 30367 14:50 15:50 16:05 8.00
DS-1 PEDESTAL EJE 10 , SRC PEDESTAL EJE 9 , C1 Y C 2 DEL EJE 7 11/4/2022 010-347 30372 15:55 16:42 16:55 9.00
DS-1 PEDESTAL EJE 10 , SRC PEDESTAL EJE 9 , C1 Y C 2 DEL EJE 7 11/4/2022 010-348 30373 16:25 17:12 17:25 8.00
TO PEDESTAL EJE 10,C1 ZAPATA EJE 6F Y 6I 11/7/2022 010-353 30378 10:15 11:05 11:15 9.00
TO PEDESTAL EJE 10,C1 ZAPATA EJE 6F Y 6I 11/7/2022 010-354 30379 10:30 12:00 12:10 8.00
TO PEDESTAL EJE 10,C1 ZAPATA EJE 6F Y 6I 11/7/2022 010-355 30380 14:35 15:40 15:55 9.00
TO PEDESTAL EJE 10,C1 ZAPATA EJE 6F Y 6I 11/7/2022 010-356 30381 15:10 16:10 16:24 8.00
C1 ZAPATA EJE 6- EJE L , AP-1 ZAPATA EJE 8 EJE F-I 11/8/2022 010-357 30382 9:35 10:35 10:48:00 6.50
AP-1 ZAPATA EJE 8 EJE I-L, SRC PEDESTAL EJE 7, C1 PEDESTAL 6F Y 6I 11/8/2022 010-358 30383 14:40 15:40 15:50 7.00
AP-1 ZAPATA EJE 8 EJE I-L, SRC PEDESTAL EJE 7, C1 PEDESTAL 6F Y 6I 11/8/2022 010-359 30384 15:10 16:00 16:10 6.00
C1 PEDESTALEJE 6L , SRC ZAPATA EJE 6, SSP ZAPATA EJE7, AP-1 PEDESTAL EJE 8 11/9/2022 010-362 30387 14:30 15:20 15:40 7.00
C1 PEDESTALEJE 6L , SRC ZAPATA EJE 6, SSP ZAPATA EJE7, AP-1 PEDESTAL EJE 8 11/9/2022 010-363 30388 14:50 15:35 15:50 7.00
ZAPATA C12A,C12A,C14,C,14 EJE 1 PATIO 60 KV , ZAPATA EJE7 AP-1 EJE I-L PATIO 220 KV 11/11/2022 010-367 30392 13:25 14:18 14:33 7.00
ZAPATA C12A,C12A,C14,C,14 EJE 1 PATIO 60 KV , ZAPATA EJE7 AP-1 EJE I-L 220 KV 11/11/2022 010-368 30393 13:50 15:00 15:10 7.00
METRADOS

PROYECTO : S.E. CAHUACHI


SECTOR : OBRAS PROVISIONALES
REALIZADA POR : J A CONSTRUCIONES Y SERVICIOS SAC
PLANOS DE REFERENCIA:

VOLÚMEN / AREA
N° DE GUIA HORA DE HORA DE
ITEM DESCRIPCION UND FECHA DE PRECIINTO SALIDA LLEGADA HORA DE VACIADO
REMISION DE PLANTA A OBRA PARCIAL

ZAPATA TC-1 EJE 6 , PEDESTAL TC-1 EJE 6 , PEDESTAL SSP EJE 6 Y E.C. VIGA DE CIMENTACION EJE E -EJE 1-3,ZAPATA EJE 3D E.C. 11/12/2022 010-369 30394 8:40 9:58 10:10 9.00
PEDESTAL EJE 1 C12A,C14 , C14 PATIO 60 KV 11/12/2022 010-370 30395 9:15 10:30 10:36:00 8.00
11/14/2022
PEDESTAL TC-1 EJE 6 EJE I-L , PEDESTAL AP-1 EJE 7 EJE I-L PATIO 220KV , PEDESTAL 1D C12A, ZAPATA C11,C12,C12 EJE 3 PATIO 60 KV 010-371 30395 13:30 14:40 14:50 6.50
11/14/2022
PEDESTAL TC-1 EJE 6 EJE I-L , PEDESTAL AP-1 EJE 7 EJE I-L PATIO 220KV , PEDESTAL 1D C12A, ZAPATA C11,C12,C12 EJE 3 PATIO 60 KV 010-372 30396 13:50 14:50 15:00 6.00
ZAPATA EJE 5 E PATIO 60 KV , ZAPATA SRCCPT EJE 6 F PATIO 220KV 11/16/2022 010-373 30398 11:50 13:00 13:10 6.00
ZAPATA SRCCPT EJE 6 , ZATA PA IN-1 EJE7 I-L , PEDESTAL IN-1 EJE 7 F-I PATIO 220KV 11/16/2022 010-374 30399 14:30 15:30 15:40 8.00
SOBRECIMIENTO DE CERRAMIENTO 11/16/2022 010-375 30400 15:05 15:50 16:00 7.00

PEDESTAL SRCCPT EJE 6 EJE F-I , PEDESTAL IN-1 EJE 7 EJE I-L , ZAPATA AP-1 EJE 8 PATIO 220KV , PEDESTAL C1A EJE 5 EJE E 11/17/2022 010-376 30401 13:25 14:30 14:40
,
ZAPATA C11A EJE 2 EJE H , ZAPATA C11 EJE 2 EJE J PATIO 60 KV , SOBRE CIMIENTO EJE H-G Y EJE B-C CERRAMIENTO 8.00

PEDESTAL SRCCPT EJE 6 EJE F-I , PEDESTAL IN-1 EJE 7 EJE I-L , ZAPATA AP-1 EJE 8 PATIO 220KV , PEDESTAL C1A EJE 5 EJE E 11/17/2022 010-377 30402 13:55 14:50 14:55
,
ZAPATA C11A EJE 2 EJE H , ZAPATA C11 EJE 2 EJE J PATIO 60 KV , SOBRE CIMIENTO EJE H-G Y EJE B-C CERRAMIENTO 7.50

ZAPATA TT-2 EJE F EJE 8-9 , ZAPATA Y PEDESTAL AP-1 EJE 8 PATIO 220 KV , PEDESTAL C11A EJE 2 EJE H , 11/18/2022 010-378 30403 14:05 15:20 15:30
PEDESTAL C11 EJE 2 EJE J , ZAPATA C13 EJE 4 EJE J PATIO 60 KV ,SOBRECIMIENTO EJE N EJE D-E 8.50

ZAPATA TT-2 EJE F EJE 8-9 , ZAPATA Y PEDESTAL AP-1 EJE 8 PATIO 220 KV , PEDESTAL C11A EJE 2 EJE H , 11/18/2022 010-379 30404 14:40 15:50 16:00
PEDESTAL C11 EJE 2 EJE J , ZAPATA C13 EJE 4 EJE J PATIO 60 KV ,SOBRECIMIENTO EJE N EJE D-E 8.00

INTERRUPTOR EJE 2 , ZAPATA C13 EJE 4 EJE H PATIO 60 KV , PEDESTAL AP-1 EJE 8 EJE I -L , ZAPATA TT-2 EJE F EJE 8-7
11/19/2022 010-380 30405 9:00 10:45 11:00
PATIO 220 KV ,
SOBRECIMIENTO ARMADO EJE A-B CERRAMIENTO 8.00

INTERRUPTOR EJE 2 , ZAPATA C13 EJE 4 EJE H PATIO 60 KV , PEDESTAL AP-1 EJE 8 EJE I -L , ZAPATA TT-2 EJE F EJE 8-7 11/19/2022 010-381 30406 9:20 10:50 11:05
PATIO 220 KV ,
SOBRECIMIENTO ARMADO EJE A-B CERRAMIENTO 7.00
INTERRUPTOR EJE 2 EJE D , PEDESTAL C12 EJE 3 EJE E , C12 EJE 3 EJE G PATIO 60 KV , PEDESTAL TT-2 EJE F EJE 7-9 , 11/21/2022 010-383 30408 14:10 15:20 15:30
PEDESTAL AP-1 EJE 8 EJE F-I PATIO 220 KV , SOBRECIMIENTO EJE LM3 - A , EJE 1- EJE 2 CERRAMIENTO 8.00
INTERRUPTOR EJE 2 EJE D , PEDESTAL C12 EJE 3 EJE E , C12 EJE 3 EJE G PATIO 60 KV , PEDESTAL TT-2 EJE F EJE 7-9 , 11/21/2022 010-384 30409 14:20 15:27 15:40
PEDESTAL AP-1 EJE 8 EJE F-I PATIO 220 KV , SOBRECIMIENTO EJE LM3 - A , EJE 1- EJE 2 CERRAMIENTO 8.00

PEDESTAL TT-DS EJE 1 , PEDESTAL IN-1 EJE 2H , ZAPATA SAC EJE 3 , ZAPATA IN-1 EJE 3H,PEDESTAL C13 EJE 4 J,ZAPATA C13 11/24/2022 010-393 30418 13:05 14:20 14:30
EJE 4D PATIO 60 KV , PEDESTAL AP -1 EJE 8 EJE I-L , ZAPATA AP-1 EJE 8 EJE F-I PATIO 220 KV , SOBRECIMIENTO DEL
CERRAMIENTO 7.50
PEDESTAL TT-DS EJE 1 , PEDESTAL IN-1 EJE 2H , ZAPATA SAC EJE 3 , ZAPATA IN-1 EJE 3H,PEDESTAL C13 EJE 4 J,ZAPATA C13
EJE 4D PATIO 60 KV , PEDESTAL AP -1 EJE 8 EJE I-L , ZAPATA AP-1 EJE 8 EJE F-I PATIO 220 KV , SOBRECIMIENTO DEL 11/24/2022 010-394 30419 16:20 17:15 17:25
CERRAMIENTO 7.50
PEDESTAL TT-DS EJE 1 , PEDESTAL IN-1 EJE 2H , ZAPATA SAC EJE 3 , ZAPATA IN-1 EJE 3H,PEDESTAL C13 EJE 4 J,ZAPATA C13
EJE 4D PATIO 60 KV , PEDESTAL AP -1 EJE 8 EJE I-L , ZAPATA AP-1 EJE 8 EJE F-I PATIO 220 KV , SOBRECIMIENTO DEL 11/24/2022 010-395 30420 16:45 17:40 17:50
CERRAMIENTO 7.00
PEDESTAL C13 EJE 4D PATIO 60KV , SOBRECIMIENTO DE CERRAMIENTO , LOSA INFERIOR DE TANQUE 11/25/2022 010-397 30422 13:40 15:23 15:30
COLECTOR DE ACIETE 8.50
PEDESTAL C13 EJE 4D PATIO 60 KV , SOBRECIMIENTO DE CERRAMIENTO , LOSA INFERIOR DE TANQUE 11/25/2022 010-398 30423 14:00 15:32 15:40
COLECTOR DE ACIETE 8.50
11/26/2022 010-399 30424 9:00 10:10 12:00
ZAPATA SAC EJE 2 EJE H- J , PEDESTAL Y ZAPATA SAC EJE 3 PATIO 60 KV , PEDESTAL AP-1 EJE 8 EJE F-I PATIO 220 KV 9.00
SOBRECIMIENTO DE CERRAMIENTO , PEDESTAL SAC EJE 3 , PEDESTAL IN-1 EJE 3J , PEDESTAL SAC EJE 2J , ZAPATA SACCPT 11/28/2022 010-401 30426 10:40 11:35 11:45
EJE 1 PATIO 60KV 6.00
SOBRECIMIENTO DE CERRAMIENTO , PEDESTAL SAC EJE 3 , PEDESTAL IN-1 EJE 3J , PEDESTAL SAC EJE 2J , ZAPATA SACCPT 11/28/2022 010-402 30427 15:05 15:58 16:10
EJE 1 PATIO 60KV 5.50
11/29/2022 010-403 30428 11:50 13:18 13:25
SOBRECIMIENTO CERRAMIENTO , PEDESTAL SACCPT EJE 1 ZAPATA SAC EJE 3 PATIO 60 KV 7.50
11/29/2022 010-404 30429 15:30 16:10 16:20
EDIFICIO DE CONTROL PLACAS PL1 EJE 1 A Y EJE 1 E , COLUMNAS EJE 1B , 1C , 1D 7.00
METRADOS

PROYECTO : S.E. CAHUACHI


SECTOR : OBRAS PROVISIONALES
REALIZADA POR : J A CONSTRUCIONES Y SERVICIOS SAC
PLANOS DE REFERENCIA:

VOLÚMEN / AREA
N° DE GUIA HORA DE HORA DE
ITEM DESCRIPCION UND FECHA DE PRECIINTO SALIDA LLEGADA HORA DE VACIADO
REMISION DE PLANTA A OBRA PARCIAL

11/30/2022 010-405 30430 13:55 15:15 15:25


SOBRECIMIENTO CERRAMIENTO , ZAPATA TT-3 EJE D , PEDESTAL SAC EJE 3 PATIO 60 KV 9.00
12/1/2022 010-406 30431 13:40 14:50 15:00
EDIFICIO DE CONTROL PLACAS Y COLUMNAS , PEDESTAL TT-3 EJE D PATIO 60 KV , SOBRECIMIENTO DE CERRAMIENTO 9.00
12/3/2022 010-411 30436 8:15 9:18 9:25
MURO DE TANQUE SEPADADOR DE ACEITE 9.00
12/3/2022 010-412 30437 8:40 9:34 9:45
MURO DE TANQUE SEPADADOR DE ACEITE 8.00
12/5/2022 010-414 30439 14:20 15:15 15:25
SOBRECIMIENTO CERRAMIENTO , LOSA DE FONDO DE CT-1 (CAJA DE TIRO) 0.80X0.80X0.70 4.50
12/6/2022 010-417 30440 14:10 15:00 15:10
SOBRECIMIENTO CERRAMIENTO , LOSA DE FONDO DE CT-1 (CAJA DE TIRO) 0.80X0.80X0.70 4.50
12/7/2022 010-420 30444 14:40 15:40 15:50
SOBRECIMIENTO CERRAMIENTO , LOSA DE FONDO DE CT-1 (CAJA DE TIRO) 0.80X0.80X0.70 , ZAPATA C1A EJE 5J 8.00
12/8/2022 010-423 30447 12:25 13:30 13:40
SOBRECIMIENTO DE CERRAMIENTO , PEDESTAL C1A EJE 5-J PATIO 60 KV , 6.00
12/8/2022 010-424 30448 12:45 14:00 14:10
VIGA EJE 1 - EJE A-E , VIGA EJE 3- EJE A-E , VIGA EJE A - EJE1-3 , VIGA EJE E - EJE 1-3 6.00
12/14/2022 010-426 30450 13:40 14:40 14:50
Tanque separador de aceite LOSA SUPERIOR 9.00
12/14/2022 010-427 30451 14:10 15:15 15:25
SOBRECIMIENTO DE CERRAMIENTO 8.00
12/16/2022 010-429 30453 7:10 8:00 8:10
PLATEA DE CIMENTACION DE Autotransformador 9.00
12/16/2022 010-430 30454 7:20 8:20 8:30
PLATEA DE CIMENTACION DE Autotransformador 7.00
12/16/2022 010-432 30455 7:40 8:40 8:50
PLATEA DE CIMENTACION DE Autotransformador 7.00
12/16/2022 010-433 30456 9:15 9:45 9:55
PLATEA DE CIMENTACION DE Autotransformador 9.00
12/16/2022 010-434 30457 9:30 10:04 10:14
PLATEA DE CIMENTACION DE Autotransformador 7.00
12/16/2022 010-435 30458 10:05 10:42 10:55
PLATEA DE CIMENTACION DE Autotransformador 7.00
12/16/2022 010-436 30459 10:50 11:23 11:33
PLATEA DE CIMENTACION DE Autotransformador 9.00
12/16/2022 010-437 30460 11:10 11:36 11:46
PLATEA DE CIMENTACION DE Autotransformador , CERRAMIENTO SOBRECIMIENTO 7.00
12/17/2022 010-438 30461 8:10 8:50 9:00
PEDESTAL DE Autotransformador 9.00
12/17/2022 010-439 30462 8:35 9:40 9:50
PEDESTAL DE Autotransformador 8.00
12/17/2022 010-440 30463 10:45 11:23 11:33
PEDESTAL DE Autotransformador , MURO DE FONDO DE CT-1 (CAJA DE TIRO) 0.80X0.80X0.70 9.00
12/21/2022 010-443 30466 12:10 13:30 13:40
MURO LATERAL DE AUTOTRANSFORMADOR , SOBRECIMIENTO CERRAMIENTO , VIGA V-D1 DE EDIFICIO DE CONTROL 9.00

AÑO 2023

MURO LATERAL DE AUTOTRANSFORMADOR ,VIGA DE CIMENTACION DE CASETA AUXILIAR ,LOSA DE CANALETA Y MURO DE 1/9/2023 010-447 30467 13:30 14:45 14:55
CAJA DE TIRO 9.00
1/11/2023 010-448 30468 13:02 14:02 14:12
CAJA DE TIRO , CANALETA EN E.C. . LOSA DE CANALETA 8.00
1/12/2023 010-449 30469 13:02 14:35 14:40
CAJA DE TIRO, CANALETA , CANALETA EN E.C. . MURO CORTAFUEGO 7.00
1/16/2023 010-451 30471 12:00 13:25 13:35
CAJA DE TIRO, CANALETA ,PLACAS EN CASETA AUXILIAR 7.00
1/17/2023 010-452 30472 13:30 14:40 14:50
CAJA DE TIRO, CANALETA ,PLACAS EN CASETA AUXILIAR 8.00
METRADOS

PROYECTO : S.E. CAHUACHI


SECTOR : OBRAS PROVISIONALES
REALIZADA POR : J A CONSTRUCIONES Y SERVICIOS SAC
PLANOS DE REFERENCIA:

VOLÚMEN / AREA
N° DE GUIA HORA DE HORA DE
ITEM DESCRIPCION UND FECHA DE PRECIINTO SALIDA LLEGADA HORA DE VACIADO
REMISION DE PLANTA A OBRA PARCIAL
METRADOS

PROYECTO : S.E. CAHUACHI


SECTOR : OBRAS PROVISIONALES
REALIZADA POR : J A CONSTRUCIONES Y SERVICIOS SAC
PLANOS DE REFERENCIA:

VOLÚMEN / AREA
N° DE GUIA HORA DE HORA DE
ITEM DESCRIPCION UND FECHA DE PRECIINTO SALIDA LLEGADA HORA DE VACIADO
REMISION DE PLANTA A OBRA PARCIAL

Concreto f'c= 175 kg/cm2 61.50


CIMIENTO CERRAMIENTO 11/10/2022 010-365 30390 13:40 14:50 15:10 7.00
CIMIENTO CERRAMIENTO 11/10/2022 010-366 30391 14:05 15:00 15:20 6.00
CIMIENTO CERRAMIENTO 12/5/2022 010-413 30438 9:53 10:55 11:05 7.00
CIMIENTO CERRAMIENTO 12/6/2022 010-416 30441 9:50 10:55 11:05 7.00
CIMIENTO CERRAMIENTO 12/7/2022 010-421 30445 15:15 16:15 16:25 7.50
CIMIENTO CERRAMIENTO 12/13/2022 010-425 30449 10:25 11:10 11:20 9.00
CIMIENTO CERRAMIENTO 12/20/2022 010-441 30464 12:00 13:40 13:50 7.00
SOLADO DE CANALETA TIPO I 12/20/2022 010-442 30465 15:10 15:48 16:00 5.00

2023
CIMIENTO CERRAMIENTO 1/18/2023

Concreto f'c= 175 kg/cm2


mortero para fondo de transformador 1/13/2023 010-450 30470 8:00 8:40 8:50 6.00
METRADOS

PROYECTO :
SECTOR :
REALIZADA POR :
PLANOS DE REFERENCIA: Código Rev Fecha

VOLÚMEN / AREA ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO fy=4200 kg/cm2

Ø
ITEM DESCRIPCION UND # de Ø Longitud TOTALES
# L B H # L B AREA # Ver PESO
PARCIAL Por Elemento
Rep (m) (m) (m) Rep (m) (m) (m2) Rep CUADRO N° (KG)
Elemento (ml)
1

02 CONCRETO SIMPLE
PISO PARA OFICINAS
Concreto f'c= 100 kg/cm2 m3 12.00
16-09-22 4.000
16-09-23 4.000
19-09-22 4.000
METRADOS

PROYECTO :
SECTOR : RESERVORIO ELEVADO PROYECTADO - REP 02
REALIZADA POR : LUIS MARTÍNEZ
PLANOS DE REFERENCIA: Código Rev Fecha

VOLÚMEN / AREA ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO fy=4200 kg/cm2

Ø
ITEM DESCRIPCION UND # de Ø Longitud TOTALES
# L B H # L B AREA # Ver PESO
PARCIAL Por Elemento
Rep (m) (m) (m) Rep (m) (m) (m2) Rep CUADRO N° (KG)
Elemento (ml)
1

01 MOVIMIENTO DE TIERRAS

Excavación Masiva m3 1301.54


r1=9.38 1.00 321.988 4.042 1.000 1,301.535
r2=11.31
h=3.86

Excavación para cimentación m3 0.00

Refine y nivelación de terreno normal m2 276.41


r=9.38 1.00 276.411 1.000 1.000 276.411

Relleno con material propio m3 382.73


r1=9.38 1.00 316.446 3.246 1.000 1,027.282
r2=11.23
h=3.7
Zapata -1.00 263.953 2.304 1.000 -608.105
Viga de cimentación
r1=4.45
r2=5.30 -1.00 8.288 4.398 1.000 -36.450

Eliminación de material excedente m3 1232.72


1.00 1301.535 1.300 1,691.996
1.00 0.000 1.300
-1.00 382.727 1.200 -459.272
METRADOS

PROYECTO :
SECTOR : RESERVORIO ELEVADO PROYECTADO - REP 02
REALIZADA POR : LUIS MARTÍNEZ
PLANOS DE REFERENCIA: Código Rev Fecha

VOLÚMEN / AREA ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO fy=4200 kg/cm2

Ø
ITEM DESCRIPCION UND # de Ø Longitud TOTALES
# L B H # L B AREA # Ver PESO
PARCIAL Por Elemento
Rep (m) (m) (m) Rep (m) (m) (m2) Rep CUADRO N° (KG)
Elemento (ml)
1

02 CONCRETO SIMPLE
SOLADOS
Concreto f'c= 100 kg/cm2 m3 27.64
Cimentacion
r= 9.38m 1.00 276.411 0.100 1.000 27.641
e=0.10m

03 CONCRETO ARMADO
ZAPATAS
Concreto f'c=245 kg/cm2 m3 608.10
Zapatas
r=9.38 1.00 276.411 2.200 1.000 608.105 1 58.9362782 2.200 129.660
h=2.2

Encofrado y Desencofrado m2 129.66

Acero de refuerzo kg 0.00

ANILLO "F"
Concreto f'c=245 kg/cm2 m3 35.27
rinterior = 4.48m
rexterior = 5.30m
h= 1.4 1.00 88.247 1.400 1.000 123.546 1 33.3008821 1.400 46.621
-1.00 63.053 1.400 1.000 -88.274 1 28.1486702 1.400 39.408
Acero de refuerzo anillos
recubrimiento= .075
rinterior = +4.48+0.075 1.00 5 17.00 31.420 828.983
rexterior = +5.3-0.075 1.00 5 17.00 35.630 940.053
r=4.48+.075 1.00 6 1.00 32.220 72.011
r=4.48+.215 1.00 6 1.00 33.100 73.978
r=4.48+.355 1.00 6 1.00 33.979 75.944
r=4.48+.495 1.00 6 1.00 34.859 77.910
r=4.48+.635 1.00 6 1.00 35.236 78.752
r=5.3-.075 1.00 6 1.00 37.330 83.432
r=4.48+.355 1.00 5 9.00 33.179 463.447
METRADOS

PROYECTO :
SECTOR : RESERVORIO ELEVADO PROYECTADO - REP 02
REALIZADA POR : LUIS MARTÍNEZ
PLANOS DE REFERENCIA: Código Rev Fecha

VOLÚMEN / AREA ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO fy=4200 kg/cm2

Ø
ITEM DESCRIPCION UND # de Ø Longitud TOTALES
# L B H # L B AREA # Ver PESO
PARCIAL Por Elemento
Rep (m) (m) (m) Rep (m) (m) (m2) Rep CUADRO N° (KG)
Elemento (ml)
1

r=4.48+.495 1.00 5 9.00 34.059 475.734

Acero de refuerzo transversal (vertical)


recubrimiento= .075
rinterior = +4.48+0.075 1.00 6 143.00 4.450 1,422.242
rexterior = +5.30-0.075 1.00 6 164.00 4.450 1,631.103
Separación = 0.20m

Encofrado y Desencofrado m2 86.03

Acero de refuerzo kg 6223.59

MURO CILINDRICO DE SUSTENTACION (FUSTE)


Concreto f'c=245 kg/cm2 m3 110.73
rexterior = 5.00 1.00 78.540 14.460 1.000 1,135.686 1 31.4159265 14.460 454.274
rinterior = 4.75 -1.00 70.882 14.460 1.000 -1,024.956 1 29.8451302 14.460 431.561

Acero de refuerzo vertical


recubrimiento = 0.035m
rinterior = 4.75+.035 1.00 5 50.00 9.000 698.400
1.00 5 50.00 9.000 698.400
Espaciamiento = 0.60m 1.00 5 50.00 6.100 473.360
1.00 5 50.00 9.000 698.400
1.00 5 50.00 3.350 259.960
1.00 5 50.00 9.000 698.400
Espaciamiento = 0.75m 1.00 5 40.00 2.800 173.824
1.00 5 40.00 5.800 360.064
1.00 5 40.00 8.550 530.784

rexterior = 5.00-.035
Espaciamiento = 0.60m 1.00 5 52.00 9.000 726.336
1.00 5 52.00 9.000 726.336
1.00 5 52.00 6.100 492.294
1.00 5 52.00 9.000 726.336
1.00 5 52.00 3.350 270.358
1.00 5 52.00 9.000 726.336
Espaciamiento = 0.75m 1.00 5 42.00 2.800 182.515
1.00 5 42.00 5.800 378.067
1.00 5 42.00 8.550 557.323
Acero de refuerzo anillos
14.46
Espaciamiento = 0.25m
METRADOS

PROYECTO :
SECTOR : RESERVORIO ELEVADO PROYECTADO - REP 02
REALIZADA POR : LUIS MARTÍNEZ
PLANOS DE REFERENCIA: Código Rev Fecha

VOLÚMEN / AREA ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO fy=4200 kg/cm2

Ø
ITEM DESCRIPCION UND # de Ø Longitud TOTALES
# L B H # L B AREA # Ver PESO
PARCIAL Por Elemento
Rep (m) (m) (m) Rep (m) (m) (m2) Rep CUADRO N° (KG)
Elemento (ml)
1

Recubrimiento = 0.075m
rinterior = 4.75+.035 1.00 4 58.00 32.465 1,871.675
rexterior = 5.00-.035 1.00 4 58.00 33.596 1,936.877

Encofrado y Desencofrado m2 885.84

Acero de refuerzo kg 13186.05

VIGA ANILLO "C"


Concreto f'c=280 kg/cm2 m3 13.28
rinterior = +4.75-0.13 1.00 82.677 0.850 1.000 70.275 1.00 32.233 0.770 24.819 1.00 3 152.00 2.700 229.824
rexterior = +5.0+0.13 -1.00 67.055 0.850 1.000 -56.997 1.00 29.028 0.770 22.352 1.00 3 152.00 1.700 144.704
altura = 0.85m 1.00 6 4.00 32.942 294.506
1.00 6 4.00 35.519 317.536

Encofrado y Desencofrado m2 47.17

Acero de refuerzo kg 986.57

MUROS DE CUBA
Concreto f'c=280 kg/cm2 m3 43.02
rinterior = 6.50m 1.00 143.139 3.660 1.000 523.888 1.00 42.412 3.660 155.226
rexterior = 6.75m -1.00 132.732 3.660 1.000 -485.800 1.00 40.8407045 3.660 149.477
Altura = 3.66m

recubrimiento cara humeda =0.05m


recubrimiento cara seca =0.04m

Acero de refuerzo en anillo interior 1.00 5 13.00 44.655 900.957


1.00 5 14.00 44.655 970.261
Acero de refuerzo en anillo exterior 1.00 5 13.00 46.360 935.363
1.00 5 14.00 46.360 1,007.314
Acero de refuerzo vertical interior 1.00 4 165.00 4.835 792.988
1.00 4 165.00 2.375 389.524
Acero de refuerzo vertical enterior 1.00 4 169.00 4.735 795.414

rinterior = 0.85m 1.00 3.464 4.130 1.000 14.305 1.00 6.59734457 4.130 27.247
rexterior = 1.05m -1.00 2.270 4.130 1.000 -9.374 1.00 5.34070751 4.130 22.057
Altura = 4.13m
METRADOS

PROYECTO :
SECTOR : RESERVORIO ELEVADO PROYECTADO - REP 02
REALIZADA POR : LUIS MARTÍNEZ
PLANOS DE REFERENCIA: Código Rev Fecha

VOLÚMEN / AREA ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO fy=4200 kg/cm2

Ø
ITEM DESCRIPCION UND # de Ø Longitud TOTALES
# L B H # L B AREA # Ver PESO
PARCIAL Por Elemento
Rep (m) (m) (m) Rep (m) (m) (m2) Rep CUADRO N° (KG)
Elemento (ml)
1

Acero de refuerzo en anillo interior 1.00 4 21.00 6.412 133.843

Acero de refuerzo vertical interior 1.00 4 23.00 4.920 112.481

Encofrado y Desencofrado m2 354.01

Acero de refuerzo kg 6038.14

ANILLO "A"
Concreto f'c=280 kg/cm2 m3 5.87

rinterior= 6.5m 1.00 147.411 0.400 1.000 58.965 1.00 43.0398194 0.4 17.216
rexterior= 6.85m -1.00 132.732 0.400 1.000 -53.093 1.00 40.8407045 0.2 8.168
altura= 0.40m 1.00 4.27256601 1 4.273

recubrimiento = 0.04m
Acero de refuerzo en anillo interior
1.00 6 3.00 45.592 305.695
1.00 6 3.00 48.188 323.104
1.00 3 163.00 1.480 135.094

Encofrado y Desencofrado m2 29.66

Acero de refuerzo kg 763.89

ANILLO "B"
Concreto f'c=280 kg/cm2 m3 13.37

rinterior= 6.50m 1.00 153.938 0.588 1.000 90.439


rintermedio = 6.75m -1.00 143.139 0.588 1.000 -84.094
rexterior= 7.00m 1.00 143.139 0.675 1.000 96.619 1.00 40.8407045 0.375 15.315
h1= +.5+.0875 -1.00 132.732 0.675 1.000 -89.594 1.00 43.9822972 0.675 29.688
h2= +.5+.175 1.00 10.7992247 1 10.799
recubrimiento cara humeda =0.05m
recubrimiento cara seca =0.04m
Acero de refuerzo en anillo 1.00 6 4.00 44.655 399.214
1.00 5 2.00 46.643 144.780
1.00 6 4.00 47.931 428.503
1.00 3 204.00 1.980 226.195
METRADOS

PROYECTO :
SECTOR : RESERVORIO ELEVADO PROYECTADO - REP 02
REALIZADA POR : LUIS MARTÍNEZ
PLANOS DE REFERENCIA: Código Rev Fecha

VOLÚMEN / AREA ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO fy=4200 kg/cm2

Ø
ITEM DESCRIPCION UND # de Ø Longitud TOTALES
# L B H # L B AREA # Ver PESO
PARCIAL Por Elemento
Rep (m) (m) (m) Rep (m) (m) (m2) Rep CUADRO N° (KG)
Elemento (ml)
1

Encofrado y Desencofrado m2 55.80

Acero de refuerzo kg 1198.69

ANILLO "D"
Concreto f'c=280 kg/cm2 m3 1.45

rinterior= 0.85m 1.00 4.909 0.500 1.000 2.454 1.00 5.34070751 0.5 2.670
rexterior= 1.25m -1.00 2.011 0.500 1.000 -1.005 1.00 7.85398163 0.14 1.100
altura= 0.50m 1.00 2.63893783 1 2.639

recubrimiento cara humeda =0.05m


recubrimiento cara seca =0.04m
Acero de refuerzo en anillo 1.00 6 2.00 6.492 29.019
1.00 6 2.00 7.466 33.373
1.00 6 2.00 8.440 37.726
1.00 3 26.00 1.780 25.917

Encofrado y Desencofrado m2 6.41

Acero de refuerzo kg 126.03

FONDO ESFERICO DE CUBA


Concreto f'c=280 kg/cm2 m3 24.63
rinterior = 7.07m -1.00 2.284 19.733 1.000 -45.080 1.00 65.483 1 65.483
hinterior = 1.477m
a radio base= 4.32m

rexterior = 7.42m 1.00 3.495 20.433 1.000 71.423 1.00 85.179 1 85.179
hexterior = 1.827m
a radio base= 4.876m

rcentral = 1.25 -1.00 4.909 0.350 1.000 -1.718 -2.00 4.90873852 1 -9.817
hcentral= 0.35

Encofrado y Desencofrado m2 140.85

Acero de refuerzo kg 0.00


METRADOS

PROYECTO :
SECTOR : RESERVORIO ELEVADO PROYECTADO - REP 02
REALIZADA POR : LUIS MARTÍNEZ
PLANOS DE REFERENCIA: Código Rev Fecha

VOLÚMEN / AREA ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO fy=4200 kg/cm2

Ø
ITEM DESCRIPCION UND # de Ø Longitud TOTALES
# L B H # L B AREA # Ver PESO
PARCIAL Por Elemento
Rep (m) (m) (m) Rep (m) (m) (m2) Rep CUADRO N° (KG)
Elemento (ml)
1

FONDO TRONCO CONICO DE CUBA


Concreto f'c=280 kg/cm2 m3 27.98

rinferior= 4.876m -1.00 2.024 97.719 1.000 -197.807 1.00 90.240364 1 90.240
rsuperior = 6.50m
altura = 1.933m 1.00 2.024 111.541 1.000 225.785 1.00 96.4515283 1 96.452
generatriz = 2.525

rinferior= 5.267m
rsuperior = 6.892m
altura = 1.933m
generatriz = 2.525
METRADOS

PROYECTO :
SECTOR : RESERVORIO ELEVADO PROYECTADO - REP 03
REALIZADA POR : LUIS MARTÍNEZ
PLANOS DE REFERENCIA: Código Rev Fecha

VOLÚMEN / AREA ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO fy=4200 kg/cm2

Ø
ITEM DESCRIPCION UND # de Ø Longitud TOTALES
# L B H # L B AREA # Ver PESO
PARCIAL Por Elemento
Rep (m) (m) (m) Rep (m) (m) (m2) Rep CUADRO N° (KG)
Elemento (ml)
1

01 MOVIMIENTO DE TIERRAS

Excavación Masiva m3 1300.84


r1=9.5 1.00 326.898 3.979 1.000 1,300.840
r2=11.35
h=3.8

Excavación para cimentación m3 0.00

Refine y nivelación de terreno normal m2 283.53


r=9.5 1.00 283.529 1.000 1.000 283.529

Relleno con material propio m3 519.24


r1=9.5 1.00 311.973 3.875 1.000 1,208.778
r2=11.35
h=3.7
Zapata -1.00 270.750 2.409 1.000 -652.116
Viga de cimentación
r1=5.43
r2=4.58 -1.00 8.509 4.398 1.000 -37.422

Eliminación de material excedente m3 1068.00


1.00 1300.840 1.300 1,691.092
1.00 0.000 1.300
-1.00 519.240 1.200 -623.088

02 CONCRETO SIMPLE
SOLADOS
Concreto f'c= 100 kg/cm2 m3 28.35
Cimentacion
METRADOS

PROYECTO :
SECTOR : RESERVORIO ELEVADO PROYECTADO - REP 03
REALIZADA POR : LUIS MARTÍNEZ
PLANOS DE REFERENCIA: Código Rev Fecha

VOLÚMEN / AREA ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO fy=4200 kg/cm2

Ø
ITEM DESCRIPCION UND # de Ø Longitud TOTALES
# L B H # L B AREA # Ver PESO
PARCIAL Por Elemento
Rep (m) (m) (m) Rep (m) (m) (m2) Rep CUADRO N° (KG)
Elemento (ml)
1

r= 9.5m 1.00 283.529 0.100 1.000 28.353


e=0.10m

03 CONCRETO ARMADO
ZAPATAS
Concreto f'c=245 kg/cm2 m3 623.76
Zapatas
r=9.5 1.00 283.529 2.200 1.000 623.763 1 59.69026041821 2.200 131.319
h=2.2

Encofrado y Desencofrado m2 131.32

Acero de refuerzo kg 0.00

ANILLO "F"
Concreto f'c=245 kg/cm2 m3 37.42
rinterior = 4.58m
rexterior = 5.43m
h= 1.4 1.00 92.630 1.400 1.000 129.681 1 34.11769621799 1.400 47.765
-1.00 65.899 1.400 1.000 -92.259 1 28.77698870688 1.400 40.288
Acero de refuerzo anillos
recubrimiento= .075
rinterior = +4.58+0.075 1.00 5 17.00 32.048 845.560
rexterior = +5.43-0.075 1.00 5 17.00 37.146 980.072
r=4.58+.075 1.00 6 1.00 32.848 73.416
r=4.58+.215 1.00 6 1.00 33.728 75.382
r=4.58+.355 1.00 6 1.00 34.608 77.348
r=4.58+.495 1.00 6 1.00 35.487 79.314
r=4.58+.635 1.00 6 1.00 37.267 83.291
r=5.43-.075 1.00 6 1.00 38.146 85.257
r=4.58+.355 1.00 5 9.00 33.808 472.223
r=4.58+.495 1.00 5 9.00 34.687 484.510

Acero de refuerzo transversal (vertical)


recubrimiento= .075
rinterior = +4.58+0.075 1.00 6 146.00 4.450 1,452.080
rexterior = +5.43-0.075 1.00 6 168.00 4.450 1,670.886
Separación = 0.20m
METRADOS

PROYECTO :
SECTOR : RESERVORIO ELEVADO PROYECTADO - REP 03
REALIZADA POR : LUIS MARTÍNEZ
PLANOS DE REFERENCIA: Código Rev Fecha

VOLÚMEN / AREA ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO fy=4200 kg/cm2

Ø
ITEM DESCRIPCION UND # de Ø Longitud TOTALES
# L B H # L B AREA # Ver PESO
PARCIAL Por Elemento
Rep (m) (m) (m) Rep (m) (m) (m2) Rep CUADRO N° (KG)
Elemento (ml)
1

Encofrado y Desencofrado m2 88.05

Acero de refuerzo kg 6379.34

MURO CILINDRICO DE SUSTENTACION (FUSTE)


Concreto f'c=245 kg/cm2 m3 161.24
rexterior = 4.875 1.00 82.516 20.530 1.000 1,694.051 1 32.2013246993 20.530 661.093
rinterior = 5.125 -1.00 74.662 20.530 1.000 -1,532.809 1 30.6305283725 20.530 628.845

Acero de refuerzo vertical


recubrimiento = 0.035m
rinterior = 4.875+.035 1.00 5 51.00 9.000 712.368
1.00 5 51.00 9.000 712.368
Espaciamiento = 0.60m 1.00 5 51.00 6.100 482.827
1.00 5 51.00 9.000 712.368
1.00 5 51.00 9.000 712.368
1.00 5 51.00 3.350 265.159
1.00 5 51.00 9.000 712.368
1.00 5 51.00 9.000 712.368
Espaciamiento = 0.75m 1.00 5 41.00 8.850 563.143
1.00 5 41.00 3.600 229.075
1.00 5 41.00 6.350 404.063

rexterior = 5.125-.035
Espaciamiento = 0.60m 1.00 5 53.00 9.000 740.304
1.00 5 53.00 9.000 740.304
1.00 5 53.00 6.100 501.762
1.00 5 53.00 9.000 740.304
1.00 5 53.00 9.000 740.304
1.00 5 53.00 3.350 275.558
1.00 5 53.00 9.000 740.304
1.00 5 53.00 9.000 740.304
Espaciamiento = 0.75m 1.00 5 43.00 8.850 590.614
1.00 5 51.00 3.600 284.947
1.00 5 51.00 6.350 502.615
Acero de refuerzo anillos
h= 20.53m
Espaciamiento = 0.25m
Recubrimiento = 0.075m
rinterior = 4.875+.035 1.00 4 83.00 33.250 2,743.228
rexterior = 5.125-.035 1.00 4 83.00 34.381 2,836.535
METRADOS

PROYECTO :
SECTOR : RESERVORIO ELEVADO PROYECTADO - REP 03
REALIZADA POR : LUIS MARTÍNEZ
PLANOS DE REFERENCIA: Código Rev Fecha

VOLÚMEN / AREA ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO fy=4200 kg/cm2

Ø
ITEM DESCRIPCION UND # de Ø Longitud TOTALES
# L B H # L B AREA # Ver PESO
PARCIAL Por Elemento
Rep (m) (m) (m) Rep (m) (m) (m2) Rep CUADRO N° (KG)
Elemento (ml)
1

Encofrado y Desencofrado m2 1289.94

Acero de refuerzo kg 18395.56

VIGA ANILLO "C"


Concreto f'c=280 kg/cm2 m3 7.54
rinterior = +4.875-0.13 1.00 86.755 0.900 1.000 78.080 1.00 33.018 0.900 29.716 1.00 3 157.00 2.800 246.176
rexterior = +5.125+0.13 -1.00 78.383 0.900 1.000 -70.545 1.00 29.814 0.900 26.832 1.00 3 157.00 1.700 149.464
altura = 0.90m 1.00 6 4.00 33.665 300.965
1.00 6 4.00 37.267 333.165

Encofrado y Desencofrado m2 56.55

Acero de refuerzo kg 1029.77

MUROS DE CUBA
Concreto f'c=280 kg/cm2 m3 56.45
rinterior = 7.00m 1.00 165.130 4.600 1.000 759.598 1.00 45.553 4.600 209.544
rexterior = 7.25m -1.00 153.938 4.600 1.000 -708.115 1.00 43.98229715026 4.600 202.319
Altura = 4.60m

recubrimiento cara humeda =0.05m


recubrimiento cara seca =0.04m

Acero de refuerzo en anillo interior 1.00 5 13.00 48.496 978.465


1.00 5 14.00 48.496 1,053.731
1.00 5 4.00 48.496 301.066

Acero de refuerzo en anillo exterior 1.00 5 13.00 49.502 998.748


1.00 5 14.00 49.502 1,075.574
1.00 5 4.00 49.502 307.307

Acero de refuerzo vertical interior 1.00 4 177.00 6.154 1,082.722


1.00 4 177.00 2.507 441.077
Acero de refuerzo vertical enterior 1.00 4 181.00 5.039 906.587
METRADOS

PROYECTO :
SECTOR : RESERVORIO ELEVADO PROYECTADO - REP 03
REALIZADA POR : LUIS MARTÍNEZ
PLANOS DE REFERENCIA: Código Rev Fecha

VOLÚMEN / AREA ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO fy=4200 kg/cm2

Ø
ITEM DESCRIPCION UND # de Ø Longitud TOTALES
# L B H # L B AREA # Ver PESO
PARCIAL Por Elemento
Rep (m) (m) (m) Rep (m) (m) (m2) Rep CUADRO N° (KG)
Elemento (ml)
1

rinterior = 0.95m 1.00 3.801 5.140 1.000 19.539 1.00 6.911503837898 5.140 35.525
rexterior = 1.10m -1.00 2.835 5.140 1.000 -14.573 1.00 5.969026041821 5.140 30.681
Altura = 5.14m

Acero de refuerzo en anillo interior 1.00 4 26.00 7.040 181.949

Acero de refuerzo vertical interior 1.00 4 32.00 5.940 188.940

Encofrado y Desencofrado m2 478.07

Acero de refuerzo kg 7516.16

ANILLO "A"
Concreto f'c=280 kg/cm2 m3 7.24

rinterior= 7.00m 1.00 172.034 0.400 1.000 68.813 1.00 46.49557127313 0.4 18.598
rexterior= 7.40m -1.00 153.938 0.400 1.000 -61.575 1.00 43.98229715026 0.3 13.195
altura= 0.40m 1.00 4.618141200777 1 4.618
recubrimiento cara humeda =0.05m
recubrimiento cara seca =0.04m
Acero de refuerzo en anillo interior
1.00 6 3.00 49.696 333.215
1.00 6 3.00 51.644 346.275
1.00 3 176.00 1.580 155.725

Encofrado y Desencofrado m2 36.41

Acero de refuerzo kg 835.21

ANILLO "B"
Concreto f'c=280 kg/cm2 m3 14.05

rinterior= 7.00m 1.00 176.715 0.500 1.000 88.357 1.00 47.12388980385 0.675 31.809
rexterior= 7.50m -1.00 153.938 0.500 1.000 -76.969 1.00 43.98229715026 0.35 15.394
altura= 0.50m 1.00 169.140 0.175 1.000 29.599 1.00 13.85442360233 1 13.854
-1.00 153.938 0.175 1.000 -26.939
recubrimiento cara humeda =0.05m
recubrimiento cara seca =0.04m
Acero de refuerzo en anillo 1.00 6 4.00 49.696 444.286
1.00 5 2.00 50.953 158.158
METRADOS

PROYECTO :
SECTOR : RESERVORIO ELEVADO PROYECTADO - REP 03
REALIZADA POR : LUIS MARTÍNEZ
PLANOS DE REFERENCIA: Código Rev Fecha

VOLÚMEN / AREA ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO fy=4200 kg/cm2

Ø
ITEM DESCRIPCION UND # de Ø Longitud TOTALES
# L B H # L B AREA # Ver PESO
PARCIAL Por Elemento
Rep (m) (m) (m) Rep (m) (m) (m2) Rep CUADRO N° (KG)
Elemento (ml)
1

1.00 6 4.00 52.273 467.317


1.00 3 220.00 1.980 243.936

Encofrado y Desencofrado m2 61.06

Acero de refuerzo kg 1313.70

ANILLO "D"
Concreto f'c=280 kg/cm2 m3 1.45

rinterior= 0.95m 1.00 5.726 0.500 1.000 2.863 1.00 8.482300164692 0.14 1.188
rexterior= 1.35m -1.00 2.835 0.500 1.000 -1.418 1.00 5.969026041821 0.5 2.985
altura= 0.50m 1.00 2.890265241303 1 2.890

recubrimiento cara humeda =0.05m


recubrimiento cara seca =0.04m
Acero de refuerzo en anillo 1.00 6 2.00 7.120 31.828
1.00 6 2.00 9.068 40.535
1.00 6 2.00 8.094 36.181
1.00 3 30.00 1.780 29.904

Encofrado y Desencofrado m2 7.06

Acero de refuerzo kg 138.45

FONDO ESFERICO DE CUBA


Concreto f'c=280 kg/cm2 m3 24.38
rinterior = 7.57m -1.00 1.827 21.389 1.000 -39.086 1.00 63.624 1 63.624
hinterior = 1.321m
a radio base= 4.302m

rexterior = 8.02m 1.00 2.924 22.389 1.000 65.466 1.00 84.171 1 84.171
hexterior = 1.671m
a radio base= 4.899m

rcentral = 1.35 -1.00 5.726 0.350 1.000 -2.004 -2.00 5.725552611167 1 -11.451
hcentral= 0.35
METRADOS

PROYECTO :
SECTOR : RESERVORIO ELEVADO PROYECTADO - REP 03
REALIZADA POR : LUIS MARTÍNEZ
PLANOS DE REFERENCIA: Código Rev Fecha

VOLÚMEN / AREA ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO fy=4200 kg/cm2

Ø
ITEM DESCRIPCION UND # de Ø Longitud TOTALES
# L B H # L B AREA # Ver PESO
PARCIAL Por Elemento
Rep (m) (m) (m) Rep (m) (m) (m2) Rep CUADRO N° (KG)
Elemento (ml)
1

Encofrado y Desencofrado m2 136.34

Acero de refuerzo kg 0.00

FONDO TRONCO CONICO DE CUBA


Concreto f'c=280 kg/cm2 m3 38.12

rinferior= 4.899m -1.00 1.917 107.293 1.000 -205.726 1.00 104.1831072154 1 104.183
rsuperior = 7.00m
altura = 1.831m 1.00 1.917 127.172 1.000 243.842 1.00 113.5165967768 1 113.517
generatriz = 2.787

rinferior= 5.432m
rsuperior = 7.533m
altura = 1.831m
generatriz = 2.787

Encofrado y Desencofrado m2 217.70

Acero de refuerzo kg 0.00

CUPULA
Concreto f'c=245 kg/cm2 m3 12.43

rinterior= 14.94m -1.00 3.192 43.074 1.000 -137.509 1.00 163.5152354959 1 163.515
Base = 7.00m
Altura = 1.746

rexterior = 15.01m 1.00 3.435 43.219 1.000 148.436


Base = 7.00m
Altura = 1.811

-1.00 0.503 0.070 1.000 -0.035

1.00 43.982 0.034 1.000 1.495


METRADOS

PROYECTO :
SECTOR : RESERVORIO ELEVADO PROYECTADO - REP 03
REALIZADA POR : LUIS MARTÍNEZ
PLANOS DE REFERENCIA: Código Rev Fecha

VOLÚMEN / AREA ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO fy=4200 kg/cm2

Ø
ITEM DESCRIPCION UND # de Ø Longitud TOTALES
# L B H # L B AREA # Ver PESO
PARCIAL Por Elemento
Rep (m) (m) (m) Rep (m) (m) (m2) Rep CUADRO N° (KG)
Elemento (ml)
1

Anillo "E" 1.00 0.306 0.150 1.000 0.046 1.00 1.570796326795 0.15 0.236
1.00 2.513274122872 0.08 0.201

Encofrado y Desencofrado m2 163.95

Acero de refuerzo kg 0.00

LOSA DE PISO
Concreto f'c=245 kg/cm2 m3 11.20

r= 4.875
espesor = 0.15m 1.00 74.662 0.150 1.000 11.199
recubrimiento = 0.075

Encofrado y Desencofrado m2 0.00

Acero de refuerzo kg 0.00

PUENTE
Concreto f'c=245 kg/cm2 m3 5.58

Vigas 2.00 9.750 0.250 0.800 3.900 2.00 9.750 1.7 33.150 2.00 3 68.00 2.080 158.413
2.00 6 6.00 2.870 76.973
2.00 6 6.00 9.000 241.380
2.00 3 4.00 10.970 49.146

Losa 1.00 9.750 1.150 0.150 1.682 1.00 9.750 1.150 11.213 1.00 3 5.00 11.370 31.836
1.00 3 63.00 2.070 73.030

Encofrado y Desencofrado m2 44.36


METRADOS

PROYECTO :
SECTOR : RESERVORIO ELEVADO PROYECTADO - REP 03
REALIZADA POR : LUIS MARTÍNEZ
PLANOS DE REFERENCIA: Código Rev Fecha

VOLÚMEN / AREA ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO fy=4200 kg/cm2

Ø
ITEM DESCRIPCION UND # de Ø Longitud TOTALES
# L B H # L B AREA # Ver PESO
PARCIAL Por Elemento
Rep (m) (m) (m) Rep (m) (m) (m2) Rep CUADRO N° (KG)
Elemento (ml)
1

Acero de refuerzo kg 630.78

ARTEZA DE REBOSE
Concreto f'c=245 kg/cm2 m3 0.56
Losa de piso 1.00 1.738 1.000 0.150 0.261 1.00 4.406 0.65 2.864 1.00 3 14.00 1.568 12.293
Muros 1.00 0.418 1.000 0.500 0.209 1.00 3.570 0.5 1.785 1.00 3 6.00 0.900 3.024
2.00 0.600 0.150 0.500 0.090 1.00 1.738 1 1.738 1.00 3 3.00 3.020 5.074
1.00 3 4.00 3.205 7.179
1.00 3 8.00 1.302 5.833

Encofrado y Desencofrado m2 6.39

Acero de refuerzo kg 33.40

04 ACABADOS
REVOQUES Y ENLUCIDOS
Tarrajeo con impermeabilizante de fondo de cuba de re m2 188.35
Tronco de cono
rinferior= 4.899m 1.00 8.756 11.899 1.000 104.183
rsuperior = 7.00m
altura = 1.831m
generatriz = 2.787

Casquete esferico
rexterior = 8.02m 1.00 84.171 1.000 1.000 84.171
hexterior = 1.671m
a radio base= 4.899m

Tarrajeo con impermeabilizante de muros de reservorio m2 428.15

rinterior = 7.00m 1.00 43.982 5.136 1.000 225.893


altura = 5.136m

rexterior= 1.10m 1.00 6.912 5.140 1.000 35.525


altura = 5.14

Anillo "D" 1.00 8.482 0.140 1.000 1.188


1.00 9.527 1.000 1.000 9.527
METRADOS

PROYECTO :
SECTOR : RESERVORIO ELEVADO PROYECTADO - REP 03
REALIZADA POR : LUIS MARTÍNEZ
PLANOS DE REFERENCIA: Código Rev Fecha

VOLÚMEN / AREA ENCOFRADO Y DESENCOFRADO ACERO DE REFUERZO fy=4200 kg/cm2

Ø
ITEM DESCRIPCION UND # de Ø Longitud TOTALES
# L B H # L B AREA # Ver PESO
PARCIAL Por Elemento
Rep (m) (m) (m) Rep (m) (m) (m2) Rep CUADRO N° (KG)
Elemento (ml)
1

Artesa de rebose 1.00 4.406 0.650 1.000 2.864


1.00 3.578 0.500 1.000 1.789
1.00 1.738 1.000 1.000 1.738

PISOS
Acabado pulido de piso con mortero 1:2 x 1.5cm de es m2 74.82

r= 4.88m 1.00 74.815 1.000 1.000 74.815