PROYECTO : “MEJORAMIENTO Y AMPLIACIÓN DEL MERCADO DE ABASTOS DEL CASERÍO LAGUNAS, DISTRITO DE MÓRROPE - LAMBAYEQUE -
LAMBAYEQUE”
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE MORROPE
UBICACION : MORROPE - LAMBAYEQUE - LAMBAYEQUE
FECHA : NOVIEMBRE 2018
MERCADO
ZAPATAS
Z - 01 6.00 1.00 1.00 1.30 7.80
Z -02 1.00 2.00 2.00 1.30 5.20
CIMIENTO CORRIDO
interiores (area seca) 2.00 9.60 0.50 0.85 8.16
interiores (area mojada) 1.00 21.35 0.50 0.85 9.07
almacen 1.00 6.05 0.50 0.50 1.51
servicios higienicos 1.00 5.25 0.50 0.50 1.31
TANQUE CISTERNA
EXCAVACIÓN DE CISTERNA 1.00 2.30 1.80 1.50 6.21
CIMIENTO CORRIDO
interiores (area seca) 2.00 9.60 0.50 0.35 3.36
interiores (area mojada) 1.00 21.35 0.50 0.35 3.74
AREA CAD
MERCADO 1.00 264.06 264.06
AREA CAD
MERCADO 1.00 264.06 264.06
MERCADO
ZAPATAS
Z - 01 6.00 1.00 1.00 - 6.00
Z -02 1.00 2.00 2.00 - 4.00
MERCADO
CIMIENTO CORRIDO
interiores (area seca) 2.00 9.60 0.50 0.40 3.84
interiores (area mojada) 1.00 21.35 0.50 0.40 4.27
almacen 1.00 6.05 0.50 0.60 1.82
servicios higienicos 1.00 5.25 0.50 0.60 1.58
MERCADO
SOBRECIMIENTO
interiores (area seca) 1.00 15.40 0.15 1.00 2.31
interiores (area mojada) 1.00 17.20 0.15 1.00 2.58
almacen 1.00 6.05 0.15 0.40 0.36
servicios higienicos 1.00 5.25 0.15 0.40 0.32
MERCADO
SOBRECIMIENTO
interiores (area seca) 2.00 15.40 1.00 30.80
interiores (area mojada) 2.00 17.20 1.00 34.40
Partida: 01.04.05 FALSO PISO DE E=4'' CON MEZCLA 1:10 (C:H) Unidad M2
Gráfico Descripción Cantidad Largo Ancho Alto Metrado Parcial
AREA CAD
INTERIOR 1.00 264.06 264.06
Partida: 01.04.06 VEREDAS DE CONCR. F'C =175 KG/CM2 FROTACHADO Y BRUÑADO Unidad M2
Gráfico Descripción Cantidad Largo Ancho Alto Metrado Parcial
AREA CAD
VEREDA DE CIRCULACION 1.00 16.15 16.15
MERCADO
ZAPATAS
Z - 01 6.00 1.00 1.00 0.50 3.00
Z -02 1.00 2.00 2.00 0.50 2.00
MERCADO
ZAPATAS
Z - 01 6.00 4.00 - 0.50 12.00
Z - 02 1.00 8.00 - 0.50 4.00
MERCADO
ZAPATAS
Z - 01 36.00 0.90 5/8" 1.58 51.19
36.00 0.90 5/8" 1.58 51.19
Z - 02 11.00 1.90 5/8" 1.58 33.02
11.00 1.90 5/8" 1.58 33.02
MERCADO
COLUMNAS
1ER NIVEL area cad
C1 6.00 4.90 0.06 1.84
C3 1.00 3.65 0.25 0.91
C2 16.00 1.20 0.06 1.20
MERCADO
PLACAS
1ER NIVEL
PL1 19.00 0.60 0.15 1.75 2.99
C4 8.00 0.20 0.15 4.05 0.97
PLANILLA DE METRADOS - ESTRUCTURAS
PROYECTO : “MEJORAMIENTO Y AMPLIACIÓN DEL MERCADO DE ABASTOS DEL CASERÍO LAGUNAS, DISTRITO DE MÓRROPE - LAMBAYEQUE -
LAMBAYEQUE”
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE MORROPE
UBICACION : MORROPE - LAMBAYEQUE - LAMBAYEQUE
FECHA : NOVIEMBRE 2018
MERCADO PERIMETRO
COLUMNAS
1ER NIVEL
C1 6.00 4.90 1.00 29.40
C3 1.00 3.65 2.00 7.30
C2 16.00 1.20 1.00 19.20
PL1 19.00 1.75 1.50 49.88
C4 8.00 4.05 0.70 22.68
MERCADO
COLUMNAS
C1 24.00 6.80 5/8" 1.58 257.86
Estribos 264.00 1.00 3/8" 0.56 147.84
C3 8.00 5.75 5/8" 1.58 72.68
4.00 5.75 3/4" 2.26 51.98
Estribos 340.00 2.10 3/8" 0.56 399.84
C2 96.00 1.50 1/2" 1.02 146.88
Estribos 192.00 1.00 3/8" 0.56 107.52
COLUMNETAS
PL1 - AV 76.00 2.25 3/8" 0.56 95.76
PL1 - AH 114.00 0.65 3/8" 0.56 41.50
C4 4.00 5.00 1/2" 1.02 20.40
Estribos 352.00 0.60 3/8" 0.56 118.27
MERCADO
VIGAS
FRENTE 1.00 16.15 0.25 0.20 0.81
POSTERIOR 1.00 16.15 0.25 0.20 0.81
LATERAL 2.00 16.96 0.25 0.20 1.70
ALMACEN 1.00 7.10 0.25 0.20 0.36
SS.HH 1.00 6.10 0.25 0.20 0.31
MERCADO
VIGAS Perimetro
FRENTE 1.00 16.15 0.90 14.54
POSTERIOR 1.00 16.15 0.90 14.54
LATERAL 2.00 16.96 0.90 30.53
ALMACEN 1.00 7.10 0.90 6.39
SS.HH 1.00 6.10 0.90 5.49
MERCADO
VIGAS
FRENTE 4.00 16.35 1/2" 1.02 66.71
Estribos 100.00 0.90 3/8" 0.56 50.40
POSTERIOR 4.00 16.35 1/2" 1.02 66.71
Estribos 100.00 0.90 3/8" 0.56 50.40
LATERAL 8.00 17.16 1/2" 1.02 140.03
Estribos 120.00 0.90 3/8" 0.56 60.48
ALMACEN 4.00 7.50 1/2" 1.02 30.60
Estribos 32.00 0.90 3/8" 0.56 16.13
SS.HH 4.00 6.50 1/2" 1.02 26.52
PLANILLA DE METRADOS - ESTRUCTURAS
PROYECTO : “MEJORAMIENTO Y AMPLIACIÓN DEL MERCADO DE ABASTOS DEL CASERÍO LAGUNAS, DISTRITO DE MÓRROPE - LAMBAYEQUE -
LAMBAYEQUE”
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE MORROPE
UBICACION : MORROPE - LAMBAYEQUE - LAMBAYEQUE
FECHA : NOVIEMBRE 2018
TANQUE ELEVADO
DESCANSO 1.00 1.50 1.50 0.150 0.34
MESA DE VENTAS
AREA SECA 1.00 11.05 0.60 0.100 0.66
AREA MOJADA 1 2.00 11.05 0.60 0.100 1.33
AREA MOJADA 2 1.00 10.10 0.100 1.01
TANQUE ELEVADO
DESCANSO 1.00 1.50 1.50 2.25
1.00 6.00 0.15 0.90
MESA DE VENTAS
AREA SECA 1.00 11.05 0.60 6.63
1.00 22.40 0.10 2.24
AREA MOJADA 1 2.00 11.05 0.60 13.26
2.00 22.40 0.10 4.48
AREA MOJADA 2 1.00 10.10 10.10
1.00 10.60 0.10 1.06
TANQUE ELEVADO
DESCANSO 16.00 1.60 1/2" 1.02 26.11
16.00 1.60 1/2" 1.02 26.11
MESA DE VENTAS
AREA SECA 3.00 11.20 3/8" 0.56 18.82
38.00 0.60 3/8" 0.56 12.77
AREA MOJADA 1 6.00 11.20 3/8" 0.56 37.63
76.00 0.60 3/8" 0.56 25.54
AREA MOJADA 2 3.00 11.10 3/8" 0.56 18.65
40.00 0.60 3/8" 0.56 13.44
FONDO
12.00 2.00 1/2" 1.02 24.5
12.00 2.00 1/2" 1.02 24.5
MUROS
8.00 1.90 1/2" 1.02 15.5
VERTICAL
8.00 1.50 1/2" 1.02 12.2
HORIZONTAL 12.00 1.50 1/2" 1.02 18.4
12.00 1.50 1/2" 1.02 18.4
MUROS
8.00 1.50 1/2" 1.02 12.2
VERTICAL
8.00 1.90 1/2" 1.02 15.5
HORIZONTAL 12.00 1.90 1/2" 1.02 23.3
12.00 1.90 1/2" 1.02 23.3
TECHO
12.00 2.00 3/8" 0.56 13.4
12.00 2.00 3/8" 0.56 13.4
MERCADO
Modulos de ventas
interiores (area seca) 1.00 2.40 - 1.20 2.88
interiores (area mojada) 1.00 3.00 - 1.20 3.60
en porton existente 1.00 2.14 - 3.05 6.53
En ventanas existentes 3.00 1.50 - 0.85 3.83
2.00 1.50 - 0.75 2.25
Para perimetro (aumento de altura) 2.00 14.90 - 1.00 29.80
2.00 15.71 - 1.00 31.42
MERCADO
Deposito 1.00 5.22 - 4.05 21.14
Ss.hh 1.00 4.64 - 4.05 18.79
MERCADO
TECHO 4.00 17.26 - - 69.04
6.00 5.95 - - 35.70
MERCADO
TECHO 4.00 17.26 - - 69.04