Metrado Precio (S/.) PRECIO PARCIAL Metrado Precio (S/.) PRECIO PARCIAL
Item Descripción Und.
02 CAPTACION (AGUA POTABLE) 256,627.72 122,981.01
02.01 BOCATOMA 213,219.19 74,429.77
02.01.01 OBRAS PRELIMINARES 9,015.04 1,722.50
02.01.01.01 LIMPIEZA DE TERRENO MANUAL m2 666.30 2.95 1,965.59 127.31 2.95 375.56
02.01.01.02 TRAZO Y REPLANTEO INICIAL m2 666.30 3.91 2,605.23 127.31 3.91 497.78
02.01.01.03 TRAZO Y REPLANTE DURANTE EJECUCION m2 666.30 6.67 4,444.22 127.31 6.67 849.16
02.01.02 MOVIMIENTO DE TIERRAS 57,647.28 21,039.03
02.01.02.01 EXCAVACION MASIVA MANUAL EN TERRENO NORMAL m3 354.66 37.82 13,413.24 313.69 37.82 11,863.76
02.01.02.02 EXCAVACION MANUAL EN ROCA FIJA m3 85.77 354.36 30,393.46 0.00
02.01.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO m3 105.23 21.88 2,302.43 160.11 21.88 3,503.21
02.01.02.04 ELIMINACION DE MATERIAL EXCEDENTE HASTA 30.00 ML (MANUAL) m3 406.13 28.41 11,538.15 199.65 28.41 5,672.06
02.01.03 OBRAS DE CONCRETO SIMPLE 95,598.97 3,771.15
02.01.03.01 SOLADO DE E=4" MEZCLA 1:12 (C:H) m2 72.33 40.55 2,932.98 93.00 40.55 3,771.15
02.01.03.02 FALSAS ZAPATAS 1:10 (C:H) + 30 P.M. (T.M. = 4") m3 5.66 304.15 1,721.49 0.00
EMBOQUILLADO DE PIEDRA CONCRETO F'C=175KG/CM2 + 60% P.G. (8" A 10"),
02.01.03.03 m3 35.56 302.56 10,759.03 0.00
E=0.30m
02.01.03.04 MURO DE CONCRETO CICLOPEO 1:8 (C:H) + 60% P.G. (6" A 10") m3 189.00 307.19 58,058.91 0.00
02.01.03.05 ENCOFRADO Y DESENCOFRADO EN MURO DE CONCRETO CICLOPEO m2 372.00 59.48 22,126.56 0.00
02.01.04 OBRAS DE CONCRETO ARMADO 45,548.10 43,332.02
02.01.04.01 ZAPATAS 7,339.56 12,087.94
02.01.04.01.01 CONCRETO F'C= 210KG/CM2 ZAPATAS m3 11.31 494.53 5,593.13 7.85 494.53 3,882.06
02.01.04.01.02 ENCOFRADO Y DESENCOFRADO EN PERIMETRO DE LA ZAPATA 0.00 66.85 86.60 5,789.21
02.01.04.01.02 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 288.19 6.06 1,746.43 398.79 6.06 2,416.67
02.01.04.02 LOSA 9,827.26 9,470.05
02.01.04.02.01 CONCRETO F'C= 210KG/CM2 EN LOSAS m3 10.95 494.53 5,415.10 10.41 494.53 5,148.06
02.01.04.02.02 ENCOFRADO Y DESENCOFRADO EN LOSA DE FONDO DE BOCATOMA m2 7.09 59.48 421.71 0.00
02.01.04.02.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 658.49 6.06 3,990.45 713.20 6.06 4,321.99
02.01.04.03 BARRAJE DE BOCATOMA 6,592.72 4,102.62
02.01.04.03.01 CONCRETO F'C= 210KG/CM2 EN BARRAJE m3 7.22 527.45 3,808.19 3.32 527.45 1,751.13
02.01.04.03.02 ENCOFRADO Y DESENCOFRADO PARA BARRAJE m2 9.46 106.63 1,008.72 8.03 106.63 856.24
02.01.04.03.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 265.84 6.68 1,775.81 223.84 6.68 1,495.25
02.01.04.04 MUROS REFORZADOS 21,788.56 17,671.41
02.01.04.04.01 CONCRETO F'C= 210KG/CM2 PARA MUROS REFORZADOS m3 12.93 494.53 6,394.27 10.14 494.53 5,014.53
02.01.04.04.02 ENCOFRADO Y DESENCOFRADO PARA MUROS REFORZADOS m2 128.41 74.93 9,621.76 128.42 74.93 9,622.51
02.01.04.04.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 900.55 6.41 5,772.53 473.38 6.41 3,034.37
02.01.05 REVOQUES Y ENLUCIDOS 3,900.32 3,664.79
02.01.05.01 TARRAJEO INTERIOR C/MORTERO 1:5X1.5CM m2 57.52 29.56 1,700.29 65.19 29.56 1,927.02
02.01.05.02 TARRAJEO EXTERIOR C/MORTERO 1:5X1.5CM m2 57.97 30.92 1,792.43 21.00 30.92 649.32
02.01.05.03 TARRAJEO CON IMPERMEABILIZANTE 1:2 e=1.5CM EN INTERIORES m2 6.22 65.53 407.60 16.61 65.53 1,088.45
02.01.06 CARPINTERIA METALICA 689.29 600.00
02.01.06.01 COMPUERTA METALICA INCLUYE ACCESORIOS E INSTALACION und 1.00 2,500.00 2,500.00
02.01.06.01 COMPUERTA METALICA INC. ACCESORIOS E INST. und 2.00 300.00 600.00
02.01.06.02 ESCALERA METALICA TIPO GATO CON F°G° 1" und 1.00 198.93 198.93 0.00
02.01.06.03 BARANDA METALICA DE F°G° EN COMPUERTA glb 1.00 490.36 490.36 0.00
02.01.07 PINTURAS 820.19 300.28
02.01.07.01 PINTURA EN MUROS EXTERIORES m2 57.52 14.05 808.16 21.00 14.05 295.05
02.01.07.02 PINTURA ANTICORROSIVA m2 1.15 10.46 12.03 0.50 10.46 5.23
02.02 DESARENADOR 26,542.81 18,962.20
02.02.01 OBRAS PRELIMINARES 449.19 405.90
02.02.01.01 LIMPIEZA DE TERRENO MANUAL m2 33.20 2.95 97.94 30.00 2.95 88.50
02.02.01.02 TRAZO Y REPLANTEO INICIAL m2 33.20 3.91 129.81 30.00 3.91 117.30
02.02.01.03 TRAZO Y REPLANTE DURANTE EJECUCION m2 33.20 6.67 221.44 30.00 6.67 200.10
02.02.02 MOVIMIENTO DE TIERRAS 2,622.80 1,388.48
02.02.02.01 EXCAVACION MASIVA MANUAL EN TERRENO NORMAL m3 37.52 37.82 1,419.01 19.16 37.82 724.63
02.02.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO m3 10.52 21.88 230.18 2.93 21.88 64.11
02.02.02.03 ELIMINACION DE MATERIAL EXCEDENTE HASTA 30.00 ML (MANUAL) m3 34.27 28.41 973.61 21.11 28.41 599.74
02.02.03 OBRAS DE CONCRETO SIMPLE 1,138.18 836.55
02.02.03.01 SOLADO DE E=4" MEZCLA 1:12 (C:H) m2 27.70 40.55 1,123.24 20.63 40.55 836.55
02.02.03.02 DADOS DE CONCRETO EN APOYO DE VALVULAS m3 0.01 303.94 3.04 0.00
02.02.03.03 ENCOFRADO Y DESENCOFRADO DE DADO m2 0.20 59.48 11.90 0.00
02.02.04 OBRAS DE CONCRETO ARMADO 14,919.48 11,766.91
02.02.04.01 LOSAS 3,057.11 1,626.04
CUADRO COMPARATIVO DE ADICIONAL DE OBRA N° 01 Y DEDUCTIVO VINCULANTE N° 01
Metrado Precio (S/.) PRECIO PARCIAL Metrado Precio (S/.) PRECIO PARCIAL
Item Descripción Und.
02.02.04.01.01 CONCRETO F'C= 210KG/CM2 EN LOSAS m3 4.05 494.53 2,002.85 2.27 494.53 1,122.58
02.02.04.01.02 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 173.97 6.06 1,054.26 83.08 6.06 503.46
02.02.04.02 MUROS REFORZADOS 11,862.37 10,140.87
02.02.04.02.01 CONCRETO F'C= 210KG/CM2 PARA MUROS REFORZADOS m3 6.73 494.53 3,328.19 6.00 494.53 2,967.18
02.02.04.02.02 ENCOFRADO Y DESENCOFRADO PARA MUROS REFORZADOS m2 89.98 74.93 6,742.20 74.31 74.93 5,568.05
02.02.04.02.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 279.56 6.41 1,791.98 250.49 6.41 1,605.64
02.02.05 REVOQUES Y ENLUCIDOS 4,879.56 2,935.18
02.02.05.01 TARRAJEO EXTERIOR C/MORTERO 1:5X1.5CM m2 22.98 30.92 710.54 3.50 30.92 108.22
02.02.05.02 TARRAJEO CON IMPERMEABILIZANTE 1:2 e=1.5CM EN INTERIORES m2 63.62 65.53 4,169.02 43.14 65.53 2,826.96
02.02.06 CARPINTERIA METALICA 1,500.00 1,400.00
02.02.06.01 COMPUERTA METALICA INCLUYE ACCESORIOS E INST. - DESARENADOR und 1.00 1,500.00 1,500.00 0.00
02.02.06.02 COMPUERTA METALICA INC. ACCESORIOS E INST. EN DESARENADOR und 0.00 4.00 350.00 1,400.00
02.02.07 PINTURAS 322.87 49.18
02.02.07.01 PINTURA EN MUROS EXTERIORES m2 22.98 14.05 322.87 3.50 14.05 49.18
02.02.09 ACCESORIOS 710.73 180.00
02.02.09.02 CANASTILLA DE BRONCE DE DN=110MM und 0.00 1.00 180.00 180.00
02.02.09.02 CANASTILLA DE BRONCE DE DN 50MM und 1.00 54.22 54.22 0.00
02.02.09.03 VALVULA DE BRONCE TIPO COMPUERTA DN=110MM und 1.00 557.14 557.14 0.00
02.02.09.04 VALVULA DE BRONCE TIPO COMPUERTA DN=50MM und 1.00 99.37 99.37 0.00
02.03 CERCO PERIMETRICO 16,865.72 29,589.04
02.03.02 MOVIMIENTO DE TIERRA 847.43 1,877.22
02.03.02.01 EXCAVACION MASIVA MANUAL EN TERRENO NORMAL m3 5.50 37.82 208.01 12.48 37.82 471.99
02.03.02.02 ELIMINACION DE MATERIAL EXCEDENTE HASTA 30.00 ML (MANUAL) m3 6.88 28.41 195.46 16.22 28.41 460.81
02.03.02.03 PERFILADO DE LAS ZANJAS m2 44.00 10.09 443.96 93.60 10.09 944.42
02.03.03 CONCRETO SIMPLE 3,255.01 11,014.91
02.03.03.01 CONCRETO EN CIMIENTOS CORRIDOS F'C=175 KG/CM2 m3 5.50 422.86 2,325.73 12.48 422.86 5,277.29
02.03.03.02 SOBRECIMIENTO CONCRETO 1:8 + 25% P.M. m3 0.00 5.85 417.59 2,442.90
02.03.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 22.00 42.24 929.28 78.00 42.24 3,294.72
02.03.04 CARPINTERIA METALICA 11,102.86 14,616.42
MALLA METALICA CON BORDE DE PERFIL L INC. COLOCADO SEGÚN DISEÑO
02.03.04.01 ml 59.25 187.39 11,102.86 78.00 187.39 14,616.42
H= 2.55m
02.03.05 PINTURA ANTICORROSIVA 1,660.42 2,080.49
02.03.05.01 PINTURA ANTICORROSIVA EN CERCO PERIMETRICO m2 158.74 10.46 1,660.42 198.90 10.46 2,080.49
03 LINEA DE CONDUCCION 556,055.84 745,040.68
03.01 OBRAS PRELIMINARES 56,065.34 58,295.88
03.01.01 LIMPIEZA DE TERRENO MANUAL m 7,505.40 1.89 14,185.21 7,804.00 1.89 14,749.56
03.01.02 TRAZO, NIVEL Y REPLANTEO INICIAL m 7,505.40 1.97 14,785.64 7,804.00 1.97 15,373.88
03.01.03 TRAZO DURANTE LA EJECUCION DE LA OBRA m 7,505.40 3.61 27,094.49 7,804.00 3.61 28,172.44
03.02 MOVIMIENTO DE TIERRAS 176,508.33 115,186.14
03.02.01 EXCAVACION DE ZANJA 0.60x0.80m TERRENO MANUAL m3 2,165.94 37.82 81,915.85 1,602.84 37.82 60,619.41
03.02.02 EXCAVACION DE ZANJA EN TERRENO ROCOSO m3 44.48 354.36 15,761.93 0.00
03.02.03 REFINE Y NIVELACION DE ZANJAS m2 7,219.80 3.02 21,803.80 5,158.40 3.02 15,578.37
03.02.04 CAMA DE APOYO CON MATERIAL CON MATERIAL ZARANDEADO m3 386.78 37.83 14,631.89 193.44 37.83 7,317.84
03.02.05 RELLENO Y COMPACTADO CON MATERIAL PROPIO m3 1,701.81 21.88 37,235.60 1,354.08 21.88 29,627.27
03.02.06 ELIMINACION DE MATERIAL EXCEDENTE HASTA 30.00 ML (MANUAL) m3 181.60 28.41 5,159.26 71.92 28.41 2,043.25
03.03 OBRAS DE CONCRETO SIMPLE 15,996.21 64,007.74
03.03.01 DADOS DE CONCRETO F'C=175 KG/CM2 m3 14.39 415.26 5,975.59 55.32 415.26 22,972.18
03.03.02 ENCOFRADO Y DESENCOFRADO DE DADOS m2 153.08 65.46 10,020.62 626.88 65.46 41,035.56
03.04 CARPINTERIA METALICA 20,018.85 88,135.65
03.04.01 ABRAZADERA DE PLATINA DE ANCHO 2" Y ESPESOR=1/8" TIPO 1 und 307.00 21.75 6,677.25 1,223.00 21.75 26,600.25
03.04.02 ABRAZADERA DE PLATINA DE ANCHO 2" Y ESPESOR=1/8" TIPO 2 und 50.00 19.75 987.50 390.00 19.75 7,702.50
03.04.03 PERNOS GALVANIZADO DE Ø1/2"x3" und 1,021.00 12.10 12,354.10 4,449.00 12.10 53,832.90
03.05 PINTURA EN DADOS 143.09 624.36
03.05.01 PINTURA ANTICORROSIVA m2 13.68 10.46 143.09 59.69 10.46 624.36
03.06 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS PVC 182,156.06 189,403.08
03.06.01 SUMINISTRO E INSTALACION DE TUBERIA HDPE 20BAR D=110mm (4") m 7,505.40 24.27 182,156.06 7,804.00 24.27 189,403.08
03.07 PRUEBAS DE CALIDAD 11,258.10 11,706.00
03.07.01 PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA D=110mm (4") m 7,505.40 1.50 11,258.10 7,804.00 1.50 11,706.00
03.08 UNION POR TERMOFUCION PARA TUBERIAS HDPE 19,760.00 40,560.00
03.08.01 UNION POR TERMOFUCION PARA D=110mm pto 76.00 260.00 19,760.00 156.00 260.00 40,560.00
03.09 VALVULA DE AIRE TIPO 1 (01 UND) 5,977.87 38,641.96
CUADRO COMPARATIVO DE ADICIONAL DE OBRA N° 01 Y DEDUCTIVO VINCULANTE N° 01
Metrado Precio (S/.) PRECIO PARCIAL Metrado Precio (S/.) PRECIO PARCIAL
Item Descripción Und.
03.09.01 OBRAS PRELIMINARES 51.42 257.21
03.09.01.01 LIMPIEZA DE TERRENO MANUAL m2 3.80 2.95 11.21 19.01 2.95 56.08
03.09.01.02 TRAZO Y REPLANTEO INICIAL m2 3.80 3.91 14.86 19.01 3.91 74.33
03.09.01.03 TRAZO Y REPLANTE DURANTE EJECUCION m2 3.80 6.67 25.35 19.01 6.67 126.80
03.09.02 MOVIMIENTO DE TIERRAS 621.05 12,336.41
03.09.02.01 EXCAVACION MANUAL EN ROCA FIJA m3 1.90 284.18 539.94 38.01 284.18 10,801.68
03.09.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO m3 0.50 21.88 10.94 6.00 21.88 131.28
03.09.02.03 ELIMINACION DE MATERIAL EXCEDENTE HASTA 30.00 ML (MANUAL) m3 2.47 28.41 70.17 49.40 28.41 1,403.45
03.09.03 OBRAS DE CONCRETO SIMPLE 50.56 260.93
03.09.03.01 SOLADO DE E=4" MEZCLA 1:12 (C:H) m2 0.31 40.55 12.57 1.53 40.55 62.04
03.09.03.02 DADOS DE CONCRETO F'C=175 KG/CM2 m3 0.03 415.26 12.46 0.17 415.26 70.59
03.09.03.03 ENCOFRADO Y DESENCOFRADO DE DADOS m2 0.39 65.46 25.53 1.96 65.46 128.30
03.09.04 OBRAS DE CONCRETO ARMADO 3,862.90 18,829.17
03.09.04.01 CONCRETO F'C=210 KG/CM2 m3 2.87 529.45 1,519.52 14.37 529.45 7,608.20
03.09.04.02 ENCOFRADO Y DESENCOFRADO m2 25.43 79.93 2,032.62 127.13 79.93 10,161.50
03.09.04.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 51.28 6.06 310.76 174.83 6.06 1,059.47
03.09.05 CARPINTERIA METALICA 270.00 1,350.00
03.09.05.01 TAPA METALICA PARA INSPECCION D= 0.60M und 1.00 150.00 150.00 5.00 150.00 750.00
03.09.05.02 ESCALERA METALICA TIPO GATO EN BUZON und 1.00 120.00 120.00 5.00 120.00 600.00
03.09.06 PINTURAS 173.93 869.29
03.09.06.01 PINTURA EN MUROS EXTERIORES m2 11.94 14.05 167.76 59.69 14.05 838.64
03.09.06.02 PINTURA ANTICORROSIVA m2 0.59 10.46 6.17 2.93 10.46 30.65
03.09.07 SUMINISTRO E INSTALACION DE TUBERIAS 70.58 352.91
03.09.07.01 INSTALACION DE TUBERIA PARA VENTILACION EN BUZON DN = 1 1/2" m 0.30 16.84 5.05 1.50 16.84 25.26
03.09.07.02 SUMINISTRO E INSTALACION DE TUBERIA HDPE 20BAR D=110mm (4") m 2.70 24.27 65.53 13.50 24.27 327.65
03.09.08 SUMINISTRO E INSTALACION DE ACCESORIOS 735.73 3,678.65
03.09.08.01 SUMINISTRO Y COLOCACION DE VALVULAS D=110 mm und 1.00 735.73 735.73 5.00 735.73 3,678.65
03.09.09 SUMINISTRO Y COLOCACION DE GRAVA PARA SUMIDERO 6.70 32.39
03.09.09.01 SUMINISTRO Y COLOCADO DE GRAVA EN SUMIDERO 3/4" m3 0.06 111.70 6.70 0.29 111.70 32.39
03.09.10 VARIOS 135.00 675.00
03.09.10.01 PRUEBA DE CALIDAD DE CONCRETO (COMPRESION) und 3.00 45.00 135.00 15.00 45.00 675.00
03.10 VALVULA DE AIRE TIPO 2 (04 UND) 25,411.04 64,835.09
03.10.01 OBRAS PRELIMINARES 205.79 462.86
03.10.01.01 LIMPIEZA DE TERRENO MANUAL m2 15.21 2.95 44.87 34.21 2.95 100.92
03.10.01.02 TRAZO Y REPLANTEO INICIAL m2 15.21 3.91 59.47 34.21 3.91 133.76
03.10.01.03 TRAZO Y REPLANTE DURANTE EJECUCION m2 15.21 6.67 101.45 34.21 6.67 228.18
03.10.02 MOVIMIENTO DE TIERRAS 2,495.02 13,553.37
03.10.02.01 EXCAVACION MANUAL EN ROCA FIJA m3 7.60 284.18 2,159.77 37.63 284.18 10,693.69
03.10.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO m3 2.00 21.88 43.76 10.80 21.88 236.30
03.10.02.03 ELIMINACION DE MATERIAL EXCEDENTE HASTA 30.00 ML (MANUAL) m3 10.26 28.41 291.49 92.34 28.41 2,623.38
03.10.03 OBRAS DE CONCRETO SIMPLE 178.97 402.19
03.10.03.01 SOLADO DE E=4" MEZCLA 1:12 (C:H) m2 1.22 40.55 49.47 2.75 40.55 111.51
03.10.03.02 DADOS DE CONCRETO F'C=175 KG/CM2 m3 0.17 415.26 70.59 0.38 415.26 157.80
03.10.03.03 ENCOFRADO Y DESENCOFRADO DE DADOS m2 0.90 65.46 58.91 2.03 65.46 132.88
03.10.04 OBRAS DE CONCRETO ARMADO 15,120.71 33,741.59
03.10.04.01 CONCRETO F'C=210 KG/CM2 m3 11.37 529.45 6,019.85 25.58 529.45 13,543.33
03.10.04.02 ENCOFRADO Y DESENCOFRADO m2 101.71 79.93 8,129.68 228.84 79.93 18,291.18
03.10.04.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 160.26 6.06 971.18 314.70 6.06 1,907.08
03.10.05 CARPINTERIA METALICA 1,080.00 2,430.00
03.10.05.01 TAPA METALICA PARA INSPECCION D= 0.60M und 4.00 150.00 600.00 9.00 150.00 1,350.00
03.10.05.02 ESCALERA METALICA TIPO GATO EN BUZON und 4.00 120.00 480.00 9.00 120.00 1,080.00
03.10.06 PINTURAS 695.47 1,564.76
03.10.06.01 PINTURA EN MUROS EXTERIORES m2 47.75 14.05 670.89 107.44 14.05 1,509.53
03.10.06.02 PINTURA ANTICORROSIVA m2 2.35 10.46 24.58 5.28 10.46 55.23
03.10.07 SUMINISTRO E INSTALACION DE TUBERIAS 463.55 1,042.98
03.10.07.01 INSTALACION DE TUBERIA PARA VENTILACION EN BUZON DN = 1 1/2" m 1.20 16.84 20.21 2.70 16.84 45.47
03.10.07.02 SUMINISTRO E INSTALACION DE TUBERIA HDPE 20BAR D=110mm (4") m 10.80 24.27 262.12 24.30 24.27 589.76
03.10.07.03 SUMINISTRO E INSTALACION DE TUBERIA HDPE 20BAR D=50mm (1.5") m 10.80 16.78 181.22 24.30 16.78 407.75
03.10.08 SUMINISTRO E INSTALACION DE ACCESORIOS 4,605.84 10,363.14
03.10.08.01 SUMINISTRO Y COLOCACION DE VALVULAS D=110 mm und 4.00 735.73 2,942.92 9.00 735.73 6,621.57
03.10.08.02 SUMINISTRO Y COLOCACION DE VALVULAS D=50 mm und 4.00 415.73 1,662.92 9.00 415.73 3,741.57
03.10.09 SUMINISTRO Y COLOCACION DE GRAVA PARA SUMIDERO 25.69 59.20
CUADRO COMPARATIVO DE ADICIONAL DE OBRA N° 01 Y DEDUCTIVO VINCULANTE N° 01
Metrado Precio (S/.) PRECIO PARCIAL Metrado Precio (S/.) PRECIO PARCIAL
Item Descripción Und.
03.10.09.01 SUMINISTRO Y COLOCADO DE GRAVA EN SUMIDERO 3/4" m3 0.23 111.70 25.69 0.53 111.70 59.20
03.10.10 VARIOS 540.00 1,215.00
03.10.10.01 PRUEBA DE CALIDAD DE CONCRETO (COMPRESION) und 12.00 45.00 540.00 27.00 45.00 1,215.00
03.11 VALVULA DE PURGA TIPO 1 (02 UND) 12,616.81 32,634.87
03.11.01 OBRAS PRELIMINARES 102.83 205.79
03.11.01.01 LIMPIEZA DE TERRENO MANUAL m2 7.60 2.95 22.42 15.21 2.95 44.87
03.11.01.02 TRAZO Y REPLANTEO INICIAL m2 7.60 3.91 29.72 15.21 3.91 59.47
03.11.01.03 TRAZO Y REPLANTE DURANTE EJECUCION m2 7.60 6.67 50.69 15.21 6.67 101.45
03.11.02 MOVIMIENTO DE TIERRAS 1,242.11 9,869.69
03.11.02.01 EXCAVACION MANUAL EN ROCA FIJA m3 3.80 284.18 1,079.88 30.41 284.18 8,641.91
03.11.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO m3 1.00 21.88 21.88 4.80 21.88 105.02
03.11.02.03 ELIMINACION DE MATERIAL EXCEDENTE HASTA 30.00 ML (MANUAL) m3 4.94 28.41 140.35 39.52 28.41 1,122.76
03.11.03 OBRAS DE CONCRETO SIMPLE 393.69 902.21
03.11.03.01 SOLADO DE E=4" MEZCLA 1:12 (C:H) m2 0.61 40.55 24.74 1.22 40.55 49.47
03.11.03.02 DADOS DE CONCRETO F'C=175 KG/CM2 m3 0.28 415.26 116.27 0.66 415.26 274.07
03.11.03.03 ENCOFRADO Y DESENCOFRADO DE DADOS m2 3.86 65.46 252.68 8.84 65.46 578.67
03.11.04 OBRAS DE CONCRETO ARMADO 7,582.01 15,065.97
03.11.04.01 CONCRETO F'C=210 KG/CM2 m3 5.75 529.45 3,044.34 11.50 529.45 6,088.68
03.11.04.02 ENCOFRADO Y DESENCOFRADO m2 50.85 79.93 4,064.44 101.71 79.93 8,129.68
03.11.04.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 78.09 6.06 473.23 139.87 6.06 847.61
03.11.05 CARPINTERIA METALICA 540.00 1,080.00
03.11.05.01 TAPA METALICA PARA INSPECCION D= 0.60M und 2.00 150.00 300.00 4.00 150.00 600.00
03.11.05.02 ESCALERA METALICA TIPO GATO EN BUZON und 2.00 120.00 240.00 4.00 120.00 480.00
03.11.06 PINTURAS 347.75 695.47
03.11.06.01 PINTURA EN MUROS EXTERIORES m2 23.88 14.05 335.51 47.75 14.05 670.89
03.11.06.02 PINTURA ANTICORROSIVA m2 1.17 10.46 12.24 2.35 10.46 24.58
03.11.07 SUMINISTRO E INSTALACION DE TUBERIAS 141.16 282.33
03.11.07.01 INSTALACION DE TUBERIA PARA VENTILACION PVC DN 1 1/2" m 0.60 16.84 10.10 1.20 16.84 20.21
03.11.07.02 SUMINISTRO E INSTALACION DE TUBERIA HDPE DN 110 mm m 5.40 24.27 131.06 10.80 24.27 262.12
03.11.08 SUMINISTRO E INSTALACION DE ACCESORIOS 1,983.86 3,967.72
03.11.08.01 SUMINISTRO Y COLOCACION DE VALVULAS (PURGA) D=110 mm und 2.00 991.93 1,983.86 4.00 991.93 3,967.72
03.11.09 SUMINISTRO Y COLOCACION DE GRAVA PARA SUMIDERO 13.40 25.69
03.11.09.01 SUMINISTRO Y COLOCADO DE GRAVA EN SUMIDERO 3/4" m3 0.12 111.70 13.40 0.23 111.70 25.69
03.11.10 VARIOS 270.00 540.00
03.11.10.01 PRUEBA DE CALIDAD DE CONCRETO (COMPRESION) und 6.00 45.00 270.00 12.00 45.00 540.00
03.11 VALVULA DE PURGA TIPO 2 (04 UND) 27,926.02 41,009.91
03.11.01 OBRAS PRELIMINARES 205.79 257.21
03.11.01.01 LIMPIEZA DE TERRENO MANUAL m2 15.21 2.95 44.87 19.01 2.95 56.08
03.11.01.02 TRAZO Y REPLANTEO INICIAL m2 15.21 3.91 59.47 19.01 3.91 74.33
03.11.01.03 TRAZO Y REPLANTE DURANTE EJECUCION m2 15.21 6.67 101.45 19.01 6.67 126.80
03.11.02 MOVIMIENTO DE TIERRAS 2,694.84 9,733.61
03.11.02.01 EXCAVACION MANUAL EN ROCA FIJA m3 7.91 284.18 2,247.86 28.89 284.18 8,209.96
03.11.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO m3 7.60 21.88 166.29 19.01 21.88 415.94
03.11.02.03 ELIMINACION DE MATERIAL EXCEDENTE HASTA 30.00 ML (MANUAL) m3 9.88 28.41 280.69 38.99 28.41 1,107.71
03.11.03 OBRAS DE CONCRETO SIMPLE 347.41 439.50
03.11.03.01 SOLADO DE E=4" MEZCLA 1:12 (C:H) m2 1.22 40.55 49.47 1.53 40.55 62.04
03.11.03.02 DADOS DE CONCRETO F'C=175 KG/CM2 m3 0.47 415.26 195.17 0.60 415.26 249.16
03.11.03.03 ENCOFRADO Y DESENCOFRADO DE DADOS m2 1.57 65.46 102.77 1.96 65.46 128.30
03.11.04 OBRAS DE CONCRETO ARMADO 15,277.83 18,829.17
03.11.04.01 CONCRETO F'C=210 KG/CM2 m3 11.50 529.45 6,088.68 14.37 529.45 7,608.20
03.11.04.02 ENCOFRADO Y DESENCOFRADO m2 101.71 79.93 8,129.68 127.13 79.93 10,161.50
03.11.04.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 174.83 6.06 1,059.47 174.83 6.06 1,059.47
03.11.05 CARPINTERIA METALICA 1,080.00 1,350.00
03.11.05.01 TAPA METALICA PARA INSPECCION D= 0.60M und 4.00 150.00 600.00 5.00 150.00 750.00
03.11.05.02 ESCALERA METALICA TIPO GATO EN BUZON und 4.00 120.00 480.00 5.00 120.00 600.00
03.11.06 PINTURAS 695.47 869.29
03.11.06.01 PINTURA EN MUROS EXTERIORES m2 47.75 14.05 670.89 59.69 14.05 838.64
03.11.06.02 PINTURA ANTICORROSIVA m2 2.35 10.46 24.58 2.93 10.46 30.65
03.11.07 SUMINISTRO E INSTALACION DE TUBERIAS 463.55 579.44
03.11.07.01 INSTALACION DE TUBERIA PARA VENTILACION PVC DN 1 1/2" m 1.20 16.84 20.21 1.50 16.84 25.26
03.11.07.02 SUMINISTRO E INSTALACION DE TUBERIA HDPE DN 110 mm m 10.80 24.27 262.12 13.50 24.27 327.65
03.12.07.03 SUMINISTRO E INSTALACION DE TUBERIA HDPE D=50mm m 10.80 16.78 181.22 13.50 16.78 226.53
CUADRO COMPARATIVO DE ADICIONAL DE OBRA N° 01 Y DEDUCTIVO VINCULANTE N° 01
Metrado Precio (S/.) PRECIO PARCIAL Metrado Precio (S/.) PRECIO PARCIAL
Item Descripción Und.
03.11.08 SUMINISTRO E INSTALACION DE ACCESORIOS 6,595.44 8,244.30
03.11.08.01 SUMINISTRO Y COLOCACION DE VALVULAS (PURGA) D=110 mm und 4.00 991.93 3,967.72 5.00 991.93 4,959.65
03.12.08.02 SUMINISTRO Y COLOCACION DE VALVULAS (PURGA) D=50 mm und 4.00 656.93 2,627.72 5.00 656.93 3,284.65
03.11.09 SUMINISTRO Y COLOCACION DE GRAVA PARA SUMIDERO 25.69 32.39
03.11.09.01 SUMINISTRO Y COLOCADO DE GRAVA EN SUMIDERO 3/4" m3 0.23 111.70 25.69 0.29 111.70 32.39
03.11.10 VARIOS 540.00 675.00
03.11.10.01 PRUEBA DE CALIDAD DE CONCRETO (COMPRESION) und 12.00 45.00 540.00 15.00 45.00 675.00
03.15 MEJORAMIENTO EN EL CRUCE DE QUEBRADA 2,218.12 0.00
03.15.01 EXCAVACION DE ZANJA TERRENO MANUAL m3 15.94 53.15 847.21 0.00
03.15.02 REFINE Y NIVELACION DE ZANJAS A MANO m2 37.50 3.02 113.25 0.00
03.15.03 CAMA DE APOYO m3 1.45 156.49 226.91 0.00
03.15.04 RELLENO Y COMPACTACION CON MATERIAL PROPIO ESCOGIDO m3 11.75 71.27 837.42 0.00
03.15.05 ELIMINACION DE MATERIAL EXCEDENTE HASTA 30.00 ML A MANO m3 4.19 46.14 193.33 0.00
04 RESERVORIO CONCRETO ARMADO V=150M3 236,167.70 180,829.57
04.02 MOVIMIENTO DE TIERRAS 147,384.78 112,207.80
04.02.01 EXCAVACION MASIVA MANUAL EN TERRENO NORMAL m3 1,506.51 37.82 56,976.21 1,136.21 37.82 42,971.46
04.02.02 REFINE TALUD EN RESERVORIO m2 356.69 3.78 1,348.29 337.97 3.78 1,277.53
04.02.03 RELLENO Y COMPACTADO CON MATERIAL PROPIO m3 47.44 21.88 1,037.99 10.98 21.88 240.24
04.02.04 ELIMINACION DE MATERIAL EXCEDENTE HASTA 30.00 ML (MANUAL) m3 1,901.54 28.41 54,022.75 1,462.92 28.41 41,561.56
ELIMINACION DE MATERIAL EXCEDENTE HASTA EL DME 3 KM
04.02.05 m3 1,901.54 17.88 33,999.54 1,462.92 17.88 26,157.01
(DME=DEPOSITO DE MATERIAL EXCEDENTE)
04.04 OBRAS DE CONCRETO ARMADO 48,359.99 44,769.86
04.04.01 ZAPATAS 25,575.37 17,065.07
04.04.01.01 CONCRETO F'C= 210KG/CM2 ZAPATAS m3 26.11 494.53 12,912.18 20.59 494.53 10,182.37
04.04.01.02 ENCOFRADO Y DESENCOFRADO EN PERIMETRO DE LA ZAPATA m2 48.36 86.60 4,187.98 21.55 86.60 1,866.23
04.04.01.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 1,398.55 6.06 8,475.21 827.80 6.06 5,016.47
04.04.02 LOSAS 3,577.76 12,180.54
04.04.02.02 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 590.39 6.06 3,577.76 2,009.99 6.06 12,180.54
04.04.04 MUROS REFORZADOS 19,206.86 15,524.25
04.04.05.03 ACERO CORRUGADO FY= 4200 kg/cm2 GRADO 60 kg 2,996.39 6.41 19,206.86 2,421.88 6.41 15,524.25
04.12 CERCO PERIMETRICO 40,422.93 23,851.91
04.12.01 OBRAS PRELIMINARES 7,070.30 2,285.28
04.12.01.01 TRAZO Y REPLANTEO INICIAL m2 668.27 3.91 2,612.94 216.00 3.91 844.56
04.12.01.02 TRAZO Y REPLANTEO DURANTE LA EJECUCION m2 668.27 6.67 4,457.36 216.00 6.67 1,440.72
04.12.02 MOVIMIENTO DE TIERRAS 1,142.87 1,264.70
04.12.02.01 EXCAVACION MASIVA MANUAL EN TERRENO NORMAL m3 7.35 37.82 277.98 7.20 37.82 272.30
04.12.02.02 ELIMINACION DE MATERIAL EXCEDENTE (HASTA 30.00 ML) m3 9.56 28.41 271.60 9.36 28.41 265.92
04.12.02.03 PERFILADO DE LAS ZANJAS m2 58.80 10.09 593.29 72.00 10.09 726.48
04.12.03 CONCRETO SIMPLE 4,349.88 7,458.15
04.12.03.01 CONCRETO EN CIMIENTOS CORRIDOS F'C=175 KG/CM2 m3 7.35 422.86 3,108.02 7.20 422.86 3,044.59
04.12.03.02 SOBRECIMIENTO CONCRETO 1:8 + 25% P.M. m3 0.00 4.50 417.59 1,879.16
04.12.03.03 ENCOFRADO Y DESENCOFRADO m2 29.40 42.24 1,241.86 60.00 42.24 2,534.40
04.12.04 CARPINTERIA METALICA 19,726.55 11,243.40
MALLA METALICA CON BORDE DE PLATINA INC. COLOCADO SEGÚN DISEÑO
04.12.04.01 m 105.27 187.39 19,726.55 60.00 187.39 11,243.40
H= 2.55m
04.12.05 PINTURA 2,807.88 1,600.38
04.12.05.01 PINTURA ANTICORROSIVA m2 268.44 10.46 2,807.88 153.00 10.46 1,600.38
04.05.06 MURO DE CONTENCION 5,325.45 0.00
04.05.06.01 EXCAVACION MASIVA MANUAL EN TERRENO NORMAL m3 12.47 37.82 471.62 0.00
04.05.06.02 MURO DE CONCRETO CICLOPEO 1:8 (C:H) + 60 P.G. (6" A 10") m3 9.14 307.19 2,807.72 0.00
04.05.06.03 ENCOFRADO Y DESENCOFRADO EN MURO DE CONCRETO CICLOPEO m2 34.40 59.48 2,046.11 0.00
ADICIONAL DE OBRA N° 01
ADICIONAL DE OBRA N° 01
02.02.06.01 COMPUERTA METALICA INCLUYE ACCESORIOS E INST. - DESARENADOR und 1.00 1,500.00 1,500.00
ADICIONAL DE OBRA N° 01
ADICIONAL DE OBRA N° 01
ADICIONAL DE OBRA N° 01
DEDUCTIVO VINCULANTE N° 01
DEDUCTIVO VINCULANTE N° 01
02.02.06.02 COMPUERTA METALICA INC. ACCESORIOS E INST. EN DESARENADOR und 4.00 350.00 1,400.00
02.02.07 PINTURAS 49.18
02.02.07.01 PINTURA EN MUROS EXTERIORES m2 3.50 14.05 49.18
02.02.09 ACCESORIOS 180.00
02.02.09.02 CANASTILLA DE BRONCE DE DN=110MM und 1.00 180.00 180.00
02.03 CERCO PERIMETRICO 29,589.04
02.03.02 MOVIMIENTO DE TIERRA 1,877.22
02.03.02.01 EXCAVACION MASIVA MANUAL EN TERRENO NORMAL m3 12.48 37.82 471.99
02.03.02.02 ELIMINACION DE MATERIAL EXCEDENTE HASTA 30.00 ML (MANUAL) m3 16.22 28.41 460.81
02.03.02.03 PERFILADO DE LAS ZANJAS m2 93.60 10.09 944.42
02.03.03 CONCRETO SIMPLE 11,014.91
02.03.03.01 CONCRETO EN CIMIENTOS CORRIDOS F'C=175 KG/CM2 m3 12.48 422.86 5,277.29
02.03.03.02 SOBRECIMIENTO CONCRETO 1:8 + 25% P.M. m3 5.85 417.59 2,442.90
02.03.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 78.00 42.24 3,294.72
02.03.04 CARPINTERIA METALICA 14,616.42
MALLA METALICA CON BORDE DE PERFIL L INC. COLOCADO SEGÚN DISEÑO
02.03.04.01 ml 78.00 187.39 14,616.42
H= 2.55m
02.03.05 PINTURA ANTICORROSIVA 2,080.49
02.03.05.01 PINTURA ANTICORROSIVA EN CERCO PERIMETRICO m2 198.90 10.46 2,080.49
03 LINEA DE CONDUCCION 745,040.68
03.01 OBRAS PRELIMINARES 58,295.88
03.01.01 LIMPIEZA DE TERRENO MANUAL m 7,804.00 1.89 14,749.56
03.01.02 TRAZO, NIVEL Y REPLANTEO INICIAL m 7,804.00 1.97 15,373.88
03.01.03 TRAZO DURANTE LA EJECUCION DE LA OBRA m 7,804.00 3.61 28,172.44
03.02 MOVIMIENTO DE TIERRAS 115,186.14
03.02.01 EXCAVACION DE ZANJA 0.60x0.80m TERRENO MANUAL m3 1,602.84 37.82 60,619.41
03.02.03 REFINE Y NIVELACION DE ZANJAS m2 5,158.40 3.02 15,578.37
03.02.04 CAMA DE APOYO CON MATERIAL CON MATERIAL ZARANDEADO m3 193.44 37.83 7,317.84
03.02.05 RELLENO Y COMPACTADO CON MATERIAL PROPIO m3 1,354.08 21.88 29,627.27
03.02.06 ELIMINACION DE MATERIAL EXCEDENTE HASTA 30.00 ML (MANUAL) m3 71.92 28.41 2,043.25
03.03 OBRAS DE CONCRETO SIMPLE 64,007.74
03.03.01 DADOS DE CONCRETO F'C=175 KG/CM2 m3 55.32 415.26 22,972.18
03.03.02 ENCOFRADO Y DESENCOFRADO DE DADOS m2 626.88 65.46 41,035.56
03.04 CARPINTERIA METALICA 88,135.65
03.04.01 ABRAZADERA DE PLATINA DE ANCHO 2" Y ESPESOR=1/8" TIPO 1 und 1,223.00 21.75 26,600.25
03.04.02 ABRAZADERA DE PLATINA DE ANCHO 2" Y ESPESOR=1/8" TIPO 2 und 390.00 19.75 7,702.50
03.04.03 PERNOS GALVANIZADO DE Ø1/2"x3" und 4,449.00 12.10 53,832.90
03.05 PINTURA EN DADOS 624.36
03.05.01 PINTURA ANTICORROSIVA m2 59.69 10.46 624.36
03.06 SUMINISTRO E INSTALACION DE TUBERIAS Y ACCESORIOS PVC 189,403.08
03.06.01 SUMINISTRO E INSTALACION DE TUBERIA HDPE 20BAR D=110mm (4") m 7,804.00 24.27 189,403.08
03.07 PRUEBAS DE CALIDAD 11,706.00
03.07.01 PRUEBA HIDRAULICA Y DESINFECCION DE TUBERIA D=110mm (4") m 7,804.00 1.50 11,706.00
03.08 UNION POR TERMOFUCION PARA TUBERIAS HDPE 40,560.00
03.08.01 UNION POR TERMOFUCION PARA D=110mm pto 156.00 260.00 40,560.00
03.09 VALVULA DE AIRE TIPO 1 (01 UND) 38,641.96
03.09.01 OBRAS PRELIMINARES 257.21
03.09.01.01 LIMPIEZA DE TERRENO MANUAL m2 19.01 2.95 56.08
03.09.01.02 TRAZO Y REPLANTEO INICIAL m2 19.01 3.91 74.33
03.09.01.03 TRAZO Y REPLANTE DURANTE EJECUCION m2 19.01 6.67 126.80
03.09.02 MOVIMIENTO DE TIERRAS 12,336.41
03.09.02.01 EXCAVACION MANUAL EN ROCA FIJA m3 38.01 284.18 10,801.68
03.09.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO m3 6.00 21.88 131.28
03.09.02.03 ELIMINACION DE MATERIAL EXCEDENTE HASTA 30.00 ML (MANUAL) m3 49.40 28.41 1,403.45
CUADRO COMPARATIVO DE ADICIONAL DE OBRA N° 01 Y DEDUCTIVO VINCULANTE N° 01
DEDUCTIVO VINCULANTE N° 01
DEDUCTIVO VINCULANTE N° 01
DEDUCTIVO VINCULANTE N° 01