ENTIDAD: PROYECTO ESPECIAL OLMOS TINAJONES

SUPERVISION: VCHI S.A. INGENIEROS CONSULTORES

AMORTIZACION DEL ADELANTO DE MATERIALES


(POR FORMULA E INDICE UNIFICADO)

Fórmula : Amortización = Material utilizado * P.U. * Ima/Imo


Amortización = Material utilizado * P.U.

Adelanto Otorgado: S/. 150,847.46 Sin IGV Material: Cemento Portland Tipo I

ADELANTO DESCRIPCION DELMATERIAL F.P. N°02 PROVEEDOR


Cemento Tipo I Portland
ADELANTO OTORGADO MATERIAL PRECIO MONTO SALDO POR
Ima Imo AMORTIZACION ADELANTO AMORTIZ.
FECHA MONTO MONTO VAL. N° MES UTILIZADO UNIT. CONTRATADO AMORTIZAR
OTORG. DEFLATADO (*) AMORTIZABLE
DE P.B. (1) (2) (3)=(1)*(2) (4) (5) (6)=(3)*(4)/(5) (7) (8) (9)=(7)-(8)
11/28/2000 150,847.46 150,847.46 02 Dic. 3,096.16 14.83 45,916.02 350.55 350.55 45,916.02 150,847.46 45,916.02 104,931.44
Acumul. 45,916.02 104,931.44
03 Ene. 6,320.94 14.83 93,739.53 350.55 350.55 93,739.53 104,931.44 104,931.44
Acumul. 0.00

NOTA: A solicitud del Contratista se está amortizando el 100% del adelanto de materiales para el cemento.

CALCULO DE MATERIAL UTILIZADO

VALORIZACION Nº01 y Nº02 VALORIZACION Nº03


CEMENTO CEMENTO CEMENTO CEMENTO
PARTIDA DESCRIPCION UNID MET. METRADO
bls. total bls. total
4.1.01 C.C. F'c = 140 Kg/cm2 + 30% P.M. m3 76.60 4.20 321.72 28.26 4.20 118.69
4.1.02 C.S. F'c = 100 Kg/cm2 m 3
51.08 5.50 280.94 0.00 5.50 0.00
4.1.08 C.S. F'c = 175 Kg/cm2, e = 7.5cm. m2 92.72 0.60 55.63 6541.40 0.60 3924.84
4.1.09 C.S. F'c = 175 Kg/cm2, e = 10cm. m2 0.00 0.00 0.00 128.00 0.80 102.40
4.1.12 C.C. F'c = 175 Kg/cm2 + 30% P.M. m3 126.60 5.46 691.24 385.04 5.46 2102.32
4.1.13 C.Ref. F'c = 210 Kg/cm2 m3 194.07 9.00 1746.63 2.53 9.00 22.77
4.4.03 Mampostería de Piedra labrada m3 0.00 0.00 0.00 21.61 2.31 49.92
TOTAL 3096.16 6320.94
ENTIDAD: PROYECTO ESPECIAL OLMOS TINAJONES
SUPERVISION: VCHI S.A. INGENIEROS CONSULTORES

AMORTIZACION DEL ADELANTO DE MATERIALES


(POR FORMULA E INDICE UNIFICADO)

Fórmula : Amortización = Material utilizado * P.U. * Ima/Imo


Amortización = Material utilizado * P.U.

Adelanto Otorgado: S/. 30,008.63 Sin IGV Material: Acero Corrugado

ADELANTO DESCRIPCION DEL MATERIAL F.P. N°01 PROVEEDOR


Acero Corrugado f'y = 4200 Kg/cm2
ADELANTO OTORGADO MATERIAL PRECIO MONTO SALDO POR
AMORTIZACION ADELANTO AMORTIZACION
UNIT.
MONTO MONTO UTILIZADO CONTRATADO Ima Imo AMORTIZAR
VAL. N° MES
FECHA OTORG. DEFLATADO (*) AMORTIZABLE
DE P.B. (1) (2) (3)=(1)*(2) (4) (5) (6)=(3)*(4)/(5) (7) (8) (9)=(7)-(8)
11/8/2000 30,008.63 30,008.63 02 Dic. 9,670.50 1.30 12,571.65 229.97 229.97 12,571.65 30,008.63 12,571.65 17,436.98
Acumul. 17,436.98
03 Ene. 598.50 1.30 778.05 229.97 229.97 778.05 778.05 16,658.93
Acumul. 16,658.93
04 Feb . 17,335.50 1.30 22,536.15 229.97 229.97 16,658.93 16,658.93 0.00
Acumul. 0.00

CALCULO DE MATERIAL UTILIZADO

VALORIZACION Nº01 y Nº02 VALORIZACION Nº03 VALORIZACION Nº04


PARTIDA DESCRIPCION UND MET. FIERRO FIERRO MET. FIERRO FIERRO MET. FIERRO FIERRO
Kg. total Kg. total Kg. total
4.3.01 Acero de refuerzo f'y=4200 Kg/cm2 Tn. 9.21 1050.00 9670.50 0.57 1050.00 598.50 16.51 1050.00 17,335.50

TOTAL 9670.50 598.50 17,335.50


ENTIDAD: PROYECTO ESPECIAL OLMOS-TINAJONES
SUPERVISION: VCHI S.A. INGENIEROS CONSULTORES

DEDUCCION POR REAJUSTE QUE NO CORRESPONDE POR ADELANTO DE MATERIALES


VALORIZACION CONTRACTUAL Nº04
Del 21 de Enero al 15 de Febrero de 2001.

LICITACION PUBLICA : Nº 01-2000-INADE-8200


PROYECTO : REHABILITACION DE LA PRESA TINAJONES Y REHABILITACION Y CONSTRUCCION DEL CANAL MAGDALENA
ENTIDAD : MINISTERIO DE LA PRESIDENCIA - INADE - PROYECTO ESPECIAL OLMOS TINAJONES - DEPOLTI.
UBICACIÓN : CHICLAYO - LAMBAYEQUE
CONTRATISTA : CONSORCIO CEBASA-INGEDISA-PROYEC S.A.
SUPERVISION : VCHI S.A. INGENIEROS CONSULTORES
FECHA : 20-02-2001.

Fórmula : Deducción = A*(Imo/Ima)*((Imr-Ima)/Imo)

Adelanto Otorgado: S/. 150,847.46 Sin IGV Material: Cemento Portland Tipo I
ADELANTO Nº 01 DESCRIPCION DEL MATERIAL : CEMENTO TIPO I PORTLAND F.P. N°02
MES ADELANTO OTORGADO COEF. INCIDENC ADELANTO SALD.ADEL. DEDUCCION DEDUCC. ACUM.
VAL. PERIODO DE MES MONTO MONTO Vº UTILIZ.( A) Imr Ima Imo POR UTILIZ. MENSUAL MENSUAL
Nº REGULARIZ. OTORG. (1) DEFRACTADO (2) (3) (4) (5)=(2)*(3)*(4) (6) (7) (8) (10)=(1)-(5) (11)=(5)*(8)/(7)*(((6)-(7))/(8))
OCT'00 350.55 350.55 350.55 93,208.44 0.00 0.00
1 19-OCT AL 20-NOV 339,089.97 0.299 0.5685 57,639.02
NOV'00 350.55 350.55 350.55 0.00 0.00
NOV'00 350.55 350.55 350.55 #REF! #REF! #REF!
2 21-NOV AL 20-DIC OCT./00 150,847.46 150,847.46 #REF! 0.299 0.5685 #REF!
DIC'00 350.55 350.55 350.55 #REF! #REF!
DIC'00 350.55 350.55 350.55 #REF! #REF! #REF!
3 21-DIC AL 20-ENE #REF! 0.299 0.5685 #REF!
ENE'01 350.55 350.55 350.55 #REF! #REF!
ENE'01 350.55 350.55 350.55 #REF! #REF! #REF!
4 21-ENE AL 20-FEB #REF! 0.299 0.5685 #REF!
FEB'01 350.55 350.55 350.55 #REF! #REF!

Adelanto Otorgado: S/. 30,008.63 Sin IGV Material: Acero Corrugado


ADELANTO Nº 01 DESCRIPCION DEL MATERIAL : ACERO CORRUGADO F.P. N°02
MES ADELANTO OTORGADO COEF. INCIDENC ADELANTO SALD.ADEL. DEDUCCION DEDUCC. ACUM.
VAL. PERIODO DE MES MONTO MONTO Vº UTILIZ.( A) Imr Ima Imo POR UTILIZ. MENSUAL MENSUAL
Nº REGULARIZ. OTORG. (1) DEFRACTADO (2) (3) (4) (5)=(2)*(3)*(4) (6) (7) (8) (10)=(1)-(5) (11)=(5)*(8)/(7)*(((6)-(7))/(8))

1 19-OCT AL 20-NOV NOV'00 339,089.97 0.299 0.0870 8,820.75 232.87 232.87 223.87 20,028.10 0.00 0.00

NOV'00 232.87 232.87 223.87 #REF! #REF!


2 21-NOV AL 20-DIC OCT./00 30,008.63 28,848.85 #REF! 0.299 0.0870 #REF! #REF!
DIC'00 232.28 232.87 223.87 #REF! 0.00
DIC'00 232.28 232.87 223.87 #REF! 0.00
3 21-DIC AL 20-ENE #REF! 0.299 0.0870 #REF! #REF!
ENE'01 Err:509 232.87 223.87 Err:509 Err:509
ENE'01 Err:509 232.87 223.87 Err:509 0.00
4 21-ENE AL 20-FEB #REF! 0.299 0.0870 #REF! #REF!
FEB'01 232.87 223.87 0.00

Err:509
DATOS GENERALES DE OBRA

1 OBRA
MEJORAMIENTO Y AMPLIACION DEL SISTEMA DE AGUA POTABLE ALCANTARILLADO Y
TRATAMIENTO DE AGUAS RESIDUALES DE LA LOCALIDAD DE LA ENCAÑADA - POLLOC,
DISTRITO DE LA ENCAÑADA - CAJAMARCA - CAJAMARCA

2 UBICACIÓN : LA ENCAÑADA - CAJAMARCA


3 PROPIETARIO : MUNICIPALIDAD DISTRITAL DE LA ENCAÑADA
4 FUENTE DE FINANCIAMIENTO :
5 TIPO DE PROCESO SELECCIÓN : LICITACION PUBLICA

6 Nº PROCESO DE SELECCIÓN : LP Nº 08-2014/MDLE/CEPAD

7 SISTEMA DE CONTRATACIÓN : A Suma Alzada

8 VALOR REFERENCIAL : S/. 1,505.79

9 PRESUPUESTO CONTRATADO : S/. 1,505.79

10 FECHA VALOR REFERENCIAL : Junio 2014

11 FACTOR DE RELACIÓN : 1.00000

12 PLAZO DE EJECUCIÓN : 210 DÍAS CALENDARIO

13 NÚMERO DE CONTRATO DE OBRA : LP Nº 08-2014/MDLE/CEPAD

14 CONTRATISTA : CONSORCIO JH

15 RESIDENTE : Ingº ELIZABETH RUIZ BRIONES

16 INSPECTOR/SUPERVISOR : Ingº CRISTOBAL SUAREZ GUERRERO

17 MONTO ADELANTO DIRECTO (inc. IGV) : S/.

18 FECHA ENTREGA ADEL. DIRECTO :

19 MONTO ADELANTO MATERIALES(inc.IGV) : S/.

20 FECHA ENTREGA AD. MATERIALES :

21 FECHA DE ENTREGA DE TERRENO : 9-Oct-14

22 INICIO PLAZO CONTRACTUAL : 10/10/2014

23 TÉRMINO PLAZO CONTRACTUAL : 5/8/2015

24 AMPLIACIÓN DE PLAZO Nº 01 :

25 VALORIZACIÓN NÚMERO : 01

26 MES CORRESPONDE VALORIZACIÓN : Octubre 2014

27 MONTO VALORZ. CONTRACTUAL(inc. IGV) : S/. 0.27

28 AVANCE PROGRAMADO A LA FECHA : 25.00%

29 AVANCE EJECUTADO A LA FECHA : 26.58%

30 AVANCE PROGRAM. ACUMULADO : 25.00%

31 AVANCE EJECUTADO ACUMULADO : 26.58%

32 CARTA FIANZA DE FIEL CUMPLIMIENTO :

33 CARTA FIANZA DE ADELANTO DIRECTO :


Monto ;
Entidad Financiera :
Vigencia hasta :

33 CARTA FIANZA DEL ADELANTO DE MATERIALES :


Monto ;
Entidad Financiera :
Vigencia hasta :
EJECUCIÓN PRESUPUESTAL 2012
E-4 INFORME MENSUAL DE VALORIZACIONES
(PARA CONTRATOS CUYO PRESUPUESTO BASE NO CONTIENE I.G.V.) SUSTENTACIÓN DEL CALENDARIO DE COMPROMISOS
EJECUCIÓN MENSUAL

VOLUMEN : PROGRAMA : CONTRATO N°40-2018/VIVIENDA/VMCS/PNSU, de fecha 27-04-201PPTO. BASE: 2,531,740.96


PLIEGO : PROYECTO : CONTRATISTA : CONSORCIO LA LIBERTAD. TOTAL
OBRA : "MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO EN EL C.P. MARIA DEL SOCORRO" FUENTE FINANCIAMIENTO

A CANCELAR AL PENDIENTE DE
VALORIZACIÓN REAJUSTE DE VALORIZACIONES POR FÓRMULA POLINÓMICA TOTAL CALENDARIO PAGADO
CONTRATISTA PAGO

MESES DEDUCCIÓN DEL REAJUSTE QUE


IGV DEL
PRESUPUESTO ESCALAMIENTO NO CORRESPONDE DEL VALORIZACIÓN AMORTIZACIÓN DEL ADELANTO EFECTIVO EFECTIVO
VALORIZACIÓN VALORIZACIÓN ADELANTOS ADELANTO EFECTIVO = (VN - Fg)
Nº FECHA BASE REINTEGROS ADELANTO BRUTA I.G.V. VN + IGV +ADELANTO
DEL MES NETA SIN IGV + IGV
CONTRATADO REAJUSTADA
MES K MONTO DIRECTO MATERIALES DIRECTO MATERIALES (18%) (18%) S/. S/.

ADELANTOS:
A.D. 0.00 0.00 0.00 0.00 0.00 0.00
A.M. 0.00 0.00 0.00 0.00 0.00 0.00
VALORIZACIONES:
May-18 01 May-18 2,531,740.96 28,268.33 May-18 413.43 0.00 0.00 0.00 28,681.76 0.00 0.00 28,681.76 5,162.72 33,844.48 33,844.48 33,844.48 0.00
206,714.87 Jun-12 1.002 413.43 0.00
0.00 Jun-12 1.014 0.00 0.00
0.00 Jun-12 1.003 0.00 0.00
0.00 Jun-12 0.995 0.00 0.00
Jun-18 02 Jun-18 2,531,740.96 191,981.30 Jun-18 25.96 -1,012.90 0.00 0.00 190,994.36 0.00 0.00 190,994.36 34,378.98 225,373.34 225,373.34 225,373.34 0.00
119,799.10 Jul-12 0.997 -347.42 -1,012.90
0.00 Jul-12 1.012 0.00 0.00
0.00 Jul-12 1.001 0.00 0.00
6,742.82 Jul-12 0.989 -72.15 0.00
Jul-18 03 Jul-18 2,531,740.96 0.00 Jul-18 49.98 -286.44 0.00 0.00 -236.46 0.00 0.00 -236.46 -42.56 -279.02 -279.02 -279.02 0.00
79,556.47 Aug-12 0.995 -373.92 -215.64
36,260.71 Aug-12 1.013 453.26 0.00
5,991.80 Aug-12 0.995 -29.36 0.00
0.00 Aug-12 0.979 0.00 -70.80
Aug-18 04 Aug-18 2,531,740.96 0.00 Aug-18 130.53 237.16 0.00 0.00 367.69 0.00 0.00 367.69 66.18 433.87 433.87 433.87 0.00
92,685.63 Sep-12 0.994 -528.31 -79.55
39,494.21 Sep-12 1.019 766.19 250.20
0.00 Sep-12 1.006 0.00 66.51
3,861.44 Sep-12 0.972 -107.35 0.00
Sep-18 05 Sep-18 2,531,740.96 0.00 Sep-18 Err:509 2,918.36 0.00 0.00 Err:509 0.00 0.00 Err:509 Err:509 Err:509 Err:509 Err:509
Err:509 Oct-12 0.995 Err:509 83.42
11,029.12 Oct-12 1.091 1,001.44 2,819.88
Err:509 Oct-12 1.005 Err:509 0.00
Err:509 Oct-12 0.976 Err:509 15.06
Oct-18 06 Oct-18 2,531,740.96 Oct-18
Dec-18 07 Dec-18 2,531,740.96 Dec-18

TOTAL 2,531,740.96 220,249.63 439.39 -1,012.90 0.00 0.00 Err:509 0.00 0.00 Err:509 Err:509 0.00 0.00 Err:509 Err:509 259,372.67 Err:509

SALDO POR VALOR.

PRESUPUESTO

BASE CONTRATO 2,311,491.33 416,068.44 2,727,559.77


SALDO POR

AMORTIZAR 0.00 0.00 0.00


SALDO POR

AMORTIZAR 0.00 0.00 0.00


SALDO MCO.

PPTAL 2011

PLAZO DE EJECUCIÓN : : 180 DÍAS CALENDARIO FECHA DE INICIO DE OBRA : 10/10/2014 FECHA DE TÉRMINO DE OBRA: 5/8/2015

ELABORADO POR : REVISADO POR : APROBADO POR :


INSPECTOR Ingº ROBERTO OSCCO ROJAS JEFE DE PROYECTO : DIRECTOR DE ADMINISTRACIÓN :
CONTRATO N°40-2018/VIVIENDA/VMCS/PNSU, de fecha 27-04-2018
OBRA : "MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO EN EL C.P. MARIA DEL
SOCORRO"

PROPIETARIO PROGRAMA NACIONAL DE SANEAMIENTO URBANO


UBICACIÓN LA LIBERTAD - TRUJILLO - HUANCHACO
CONTRATISTA CONSORCIO LA LIBERTAD.
RESIDENTE Ingº CRISTOBAL A, SUAREZ GUERRERO
SUPERVISOR Ingº ROBERTO OSCCO ROJAS

RESUMEN GENERAL DE LA VALORIZACIÓN Nº 02 - SISTEMA DE ALCANTARILLADO SANITARIO


(Del 01 de Junio al 30 de Junio del 2018)

ÍTEM CONCEPTO PARCIAL TOTAL

1.0.0 Valorización Contractual


1.0.1 Valorización Contractual Err:509

1.1.0 Reajustes y reintegros


1.1.1 Reajuste reconocido Err:509
1.1.2 Reintegro reconocido 2,918.36

TOTAL MONTO BRUTO (A) Err:509

2.0.0 DESCUENTOS

2.1.0 Amortización del Adelanto Directo


2.1.1 Amortización del Adelanto Directo 0.00

2.2.0 Amortización Adelanto de Materiales


2.2.1 Amortización del Adelanto de Materiales 0.00

2.3.0 Deducción que no corresponde Adelanto Directo


2.3.1 Deducción que no corresponde Adelanto Directo 0.00

2.4.0 Deducción que no corresponde Adelanto Materiales


2.4.1 Deducción que no corresponde Adelanto Materiales 0.00

TOTAL DESCUENTOS (B) 0.00

TOTAL NETO ( A-B) Err:509

I.G.V. 18.00% Err:509

TOTAL A CANCELAR AL CONTRATISTA Err:509

SON: DOSCIENTOS VEINTICINCO MIL NOVENTA Y SEIS CON 36/100 NUEVOS SOLES
CONTRATO N°40-2018/VIVIENDA/VMCS/PNSU, de fecha 27-04-2018
OBRA : "MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO EN EL C.P. MARIA DEL SOCORRO"
PROPIETARIO PROGRAMA NACIONAL DE SANEAMIENTO URBANO
UBICACIÓN LA LIBERTAD - TRUJILLO - HUANCHACO
CONTRATISTA CONSORCIO LA LIBERTAD.
RESIDENTE Ingº CRISTOBAL A, SUAREZ GUERRERO
SUPERVISOR Ingº ROBERTO OSCCO ROJAS

VALOR REFERENCIAL : S/. 7,403,281.18 Inc/IGV


MONTO DE OFERTA : S/. 2,987,454.33 Inc/IGV
MONTO DE OFERTA : S/. 2,531,740.96 sin/IGV

CONTROL GENERAL DE VALORIZACIONES

VALORIZACIÓN MONTO AMORT. ADELANTOS DEDUCCIONES VALORIZ. IGV NETO A


PERIODO VALORIZADO REAJUSTES REINTEGROS
Nº BRUTO DIRECTO MATERIALES DIRECTO MATERIALES NETA 18.00% PAGAR

Del 09 al 31 de Octubre del 2014 01 451,676.93 0.00 0.00 0.00 0.00 0.00 0.00 451,676.93 81,301.85 532,978.78
Del 01 al 30 de Noviembre del 2014 02
Del 01 al 31 de Diciembre del 2014 03
Del 01 al 31 de Enero del 2015 04
Del 01 al 28 de Febrero del 2015 05
Del 01 al 31 de Marzo del 2015 06
Del 01 al 30 de Abril del 2015 07
Del 01 al 08 de Mayo del 2015 08
TOTAL 451,676.93 0.00 0.00 0.00 0.00 0.00 0.00 451,676.93 81,301.85 532,978.78
ADJUDICACIÓN N°40-2018/VIVIENDA/VMCS/PNSU, de fecha 27-04-2018
PROYECTO : "MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO EN EL C.P. MARIA DEL SOCORRO"
ENTIDAD PROGRAMA NACIONAL DE SANEAMIENTO URBANO
UBICACIÓN LA LIBERTAD - TRUJILLO - HUANCHACO
CONTRATISTA CONSORCIO LA LIBERTAD.
INSPECTOR Ingº CRISTOBAL A, SUAREZ GUERRERO

DEDUCCIÓN DEL REAJUSTE QUE NO CORRESPONDE POR ADELANTO DE MATERIALES


VALORIZACIÓN Nº 02 - SISTEMA DE ALCANTARILLADO SANITARIO

NO SE SOLICITO ADELANTO DE MATERIALES

FÓRMULA DEDUCCIÓN QUE NO CORRESPONDE : ÍNDICE :


D = Deducción del adelanto por cada elemento
Imo = Índice del elemento a la fecha base
D = Valoriz. x Coef.Incid. x (Imr - Ima) / Imo Ima = Índice del elemento a la fecha del adelanto
Imr = Índice del elemento a la fecha del reajuste

MATERIAL IU ADELANTO Nº FECHA PAGO ADELANTO


(sin IGV)

TOTAL S/. 0.00

MONTO ADELANTO MONTO ADELANTO SALDO DEDUCCIÓN DEDUCCIÓN D.R.Q.N.C.


VALORIZACIÓN DEL MONOMIO ÍNDICES
DESCRIPCIÓN BRUTO ÍNDICE UTILIZADO MÁXIMO POR POR "D" MES DEL
MATERIAL VALORIZADO UNIFICADO COEF.INCID % Imo Ima Imr UTILIZABLE UTILIZAR UTILIZAR ANTERIOR MES
Nº MES
(1) (2) (2*) (1)(2)(2*)=3 (4) (5) (6) ADEL.x(4)/(5) (8) (8) - (3) (3)X((6-5)/(4))

01 May-18 28,268.33
02 Jun-18 191,981.30
03 Jul-18 0.00
06 Oct-18 0.00

TOTAL 0.00 0.00 0.00


ADJUDICACIÓN N°40-2018/VIVIENDA/VMCS/PNSU, de fecha 27-04-2018
PROYECTO : "MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO EN EL C.P. MARIA DEL SOCORRO"
ENTIDAD PROGRAMA NACIONAL DE SANEAMIENTO URBANO
UBICACIÓN LA LIBERTAD - TRUJILLO - HUANCHACO
CONTRATISTA CONSORCIO LA LIBERTAD.
INSPECTOR Ingº CRISTOBAL A, SUAREZ GUERRERO

DEDUCCIÓN DEL REAJUSTE QUE NO CORRESPONDE POR ADELANTO DIRECTO


VALORIZACIÓN Nº 02 - SISTEMA DE ALCANTARILLADO SANITARIO

NO SE SOLICITO ADELANTO DIRECTO

FÓRMULA DEDUCCIÓN QUE NO CORRESPONDE :

V = Monto de la Valorización Mensual


K = K real del Mes de pago de la Valorización
D = (V x A)/C x (K/Ka-1) Ka = K del Mes de Pago del Adelanto
A = Monto del Adelanto Directo (Sin/IGV) S/. 0.00
C = Monto Contratado (Sin/IGV). S/. 2,531,740.96

VALORIZACIÓN MONTO COEFICIENTE DEDUCCIÓN D.R.Q.N.C.


DEDUCC. MES
(VxA)/C
ANTERIOR
Nº MES VALORIZADO Ka K ADEL. DIRECTO DEL MES

01 May-18 28,268.33 1.0020 0.9971 0.00 0.00 0.00 0.00


02 Jun-18 191,981.30
03 Jul-18 0.00
04 Aug-18 0.00
05 Sep-18 0.00
06 Oct-18 0.00
07 Dec-18
TOTAL 0.00 0.00 0.00 0.00
CONTRATO N°40-2018/VIVIENDA/VMCS/PNSU, de fecha 27-04-2018
OBRA : "MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO EN EL C.P. MARIA DEL SOCORRO"
PROPIETARIO PROGRAMA NACIONAL DE SANEAMIENTO URBANO
UBICACIÓN LA LIBERTAD - TRUJILLO - HUANCHACO
CONTRATISTA CONSORCIO LA LIBERTAD.
RESIDENTE Ingº CRISTOBAL A, SUAREZ GUERRERO
SUPERVISOR Ingº ROBERTO OSCCO ROJAS

CONTROL DE AMORTIZACIÓN DEL ADELANTO DE MATERIALES


(Del 01 de Junio al 30 de Junio del 2018)

DATOS GENERALES AMORTIZACIÓN DEL ADELANTO EN EFECTIVO DEL ADELANTO


MONTO CONTRATADO (Inc/IGV) S/. 2,987,454.33 VALORIZACIÓN AMORTIZACIÓN CARTA FIANZA MONTO (S/.) VIGENCIA
MONTO CONTRATADO (Sin/IGV) S/. 2,531,740.96 N° MES F.P. Nº 01 (%) F.P. Nº 01 ACUMUL. SALDO

ADELANTO SOLICITADO (Inc/IGV) S/. 0.00 01 May-18 28,268.33 0.00000% 0.00 0.00 0.00
ADELANTO SOLICITADO (Sin/IGV) S/. 0.00 02 F4
03 Jul-18
04 Aug-18
ENTREGA DEL ADELANTO S/. (Sin / IGV) 05 Sep-18
FECHA PAGO PARCIAL ACUMULADO SALDO 06 Oct-18
0.00 0.00 0.00 07 Dec-18
OBSERVACIONES :

LOS MONTOS EN EL CUADRO DE AMORTIZACIÓN


NO INCLUYEN EL IGV

NO SE SOLICITO ADELANTO DE MATERIALES


CONTRATO N°40-2018/VIVIENDA/VMCS/PNSU, de fecha 27-04-2018
OBRA : "MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO EN EL C.P. MARIA DEL SOCORRO"
PROPIETARIO PROGRAMA NACIONAL DE SANEAMIENTO URBANO
UBICACIÓN LA LIBERTAD - TRUJILLO - HUANCHACO
CONTRATISTA CONSORCIO LA LIBERTAD.
RESIDENTE Ingº CRISTOBAL A, SUAREZ GUERRERO
SUPERVISOR Ingº ROBERTO OSCCO ROJAS

CONTROL DE AMORTIZACIÓN DEL ADELANTO DIRECTO


(Del 01 de Junio al 30 de Junio del 2018)

DATOS GENERALES AMORTIZACIÓN DEL ADELANTO EN EFECTIVO DEL ADELANTO


MONTO CONTRATADO (Inc/IGV) S/. 2,987,454.33 VALORIZACIÓN AMORTIZACIÓN CARTA FIANZA MONTO (S/.) VIGENCIA
MONTO CONTRATADO (Sin/IGV) S/. 2,531,740.96 N° MES F.P. Nº 01 (%) F.P. Nº 01 ACUMUL. SALDO

ADELANTO SOLICITADO (Inc/IGV) S/. 0.00


ADELANTO SOLICITADO (Sin/IGV) S/. 0.00 01 May-18
02 F4
03 Jul-18
ENTREGA DEL ADELANTO S/. (Sin / IGV) 04 Aug-18
FECHA PAGO PARCIAL ACUMULADO SALDO 05 Sep-18
0.00 0.00 0.00 06 Oct-18
07 Dec-18 OBSERVACIONES :
Carta Fianza emitida por la:

LOS MONTOS EN EL CUADRO DE AMORTIZACIÓN


NO INCLUYEN EL IGV

NO SE SOLICITO ADELANTO DIRECTO


CONTRATO N°40-2018/VIVIENDA/VMCS/PNSU, de fecha 27-04-2018

: "MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO EN EL C.P. MARIA DEL SOCORRO"
OBRA
PROPIETARIO PROGRAMA NACIONAL DE SANEAMIENTO URBANO
UBICACIÓN LA LIBERTAD - TRUJILLO - HUANCHACO
CONTRATISTA CONSORCIO LA LIBERTAD.
RESIDENTE Ingº CRISTOBAL A, SUAREZ GUERRERO
SUPERVISOR Ingº ROBERTO OSCCO ROJAS

CÁLCULO DE REINTEGROS DE VALORIZACIONES


AL MES DE SETIEMBRE DEL 2012

FÓRMULA DEL REAJUSTE :

V = Monto de la Valorización Mensual


R = V x (K-1)
K = Factor de reajuste real del Mes de pago de la Valorización

VALORIZACIÓN MONTO REAJUSTE REAL REAJUSTE REINTEGRO DE


"K" REAL
VALORIZADO DEL MES ANTERIOR REAJUSTE
Nº MES

01 May-18 206,714.87 (599.47) 413.43 (1,012.90)


F1 206,714.87 0.9971 (599.47) 413.43 (1,012.90)
F2 0.00 1.0115 0.00 0.00 0.00
F3 0.00 1.0012 0.00 0.00 0.00
F4 0.00 0.9893 0.00 0.00 0.00
02 Jun-18 126,541.92 (706.01) (419.57) (286.44)
F1 119,799.10 0.9953 (563.06) (347.42) (215.64)
F2 0.00 1.0125 0.00 0.00 0.00
F3 0.00 0.9951 0.00 0.00 0.00
F4 6,742.82 0.9788 (142.95) (72.15) (70.80)
03 Jul-18 0.00 287.14 49.98 237.16
F1 79,556.47 0.9943 (453.47) (373.92) (79.55)
F2 36,260.71 1.0194 703.46 453.26 250.20
F3 5,991.80 1.0062 37.15 (29.36) 66.51
F4 0.00 0.9722 0.00 0.00 0.00
04 Aug-18 0.00 3,048.89 130.53 2,918.36
F1 92,685.63 0.9952 (444.89) (528.31) 83.42
F2 39,494.21 1.0908 3,586.07 766.19 2,819.88
F3 0.00 1.0049 0.00 0.00 0.00
F4 3,861.44 0.9761 (92.29) (107.35) 15.06
05 Sep-18 0.00
F1 Err:509
F2 11,029.12
F3 Err:509
F4 Err:509
06 Oct-18 0.00 0.0000 0.00 0.00 0.00
07 Dec-18 0.00 0.0000 0.00 0.00 0.00

TOTAL DE REINTEGROS DE REAJUSTE DEL MES S/. 1,856.18


CONTRATO N°40-2018/VIVIENDA/VMCS/PNSU, de fecha 27-04-2018
OBRA : "MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO EN EL C.P. MARIA DEL SOCORRO"
PROPIETARIO PROGRAMA NACIONAL DE SANEAMIENTO URBANO
UBICACIÓN LA LIBERTAD - TRUJILLO - HUANCHACO
CONTRATISTA CONSORCIO LA LIBERTAD.
RESIDENTE Ingº CRISTOBAL A, SUAREZ GUERRERO
SUPERVISOR Ingº ROBERTO OSCCO ROJAS

MONTO CONTRATADO : S/. 2,987,454.33 Inc/IGV


COSTO DIRECTO : S/. 2,531,740.96 Sin/IGV

VALORIZACIÓN Nº 02 - SISTEMA DE ALCANTARILLADO SANITARIO


CÁLCULO DE REAJUSTES
(Del 01 de Junio al 30 de Junio del 2018)
VAL. PROGRAMADO EJECUTADO REAJUSTES
RECONOCIDO
MES Nº % % K-1 PROGRAMADO EJECUTADO
MES ACUMUL, MES ACUMUL.
ACUMUL. ACUMUL. MES ACUMUL. MES ACUMUL. MES ACUMUL.

15,400.96 15,400.96 0.61% 206,714.87 206,714.87 8.16% 69.52 69.52 413.43 413.43 413.43 413.43
F1 11,376.99 11,376.99 206,714.87 206,714.87 0.0020 22.75 22.75 413.43 413.43
May-18 01 F2 3,429.49 3,429.49 0.00 0.00 0.0140 48.01 48.01 0.00 0.00
F3 217.10 217.10 0.00 0.00 0.0030 0.65 0.65 0.00 0.00
F4 377.38 377.38 0.00 0.00 (0.0050) (1.89) (1.89) 0.00 0.00
Jun-18 02 149,830.37 165,231.33 6.53% 126,541.92 333,256.78 13.16% 25.96 95.48 (419.57) (6.14) 25.96 439.39
F1 110,682.58 122,059.57 119,799.10 326,513.96 (0.0029) (320.98) (298.23) (347.42) 66.01
F2 33,364.31 36,793.80 0.00 0.00 0.0115 383.69 431.70 0.00 0.00
F3 2,112.13 2,329.23 0.00 0.00 0.0012 2.53 3.18 0.00 0.00
F4 3,671.35 4,048.73 6,742.82 6,742.82 (0.0107) (39.28) (41.17) (72.15) (72.15)
Jul-18 03 235,019.28 400,250.61 15.81% 121,808.98 455,065.76 17.97% (300.12) (204.64) 49.98 43.84 49.98 489.37
F1 173,613.27 295,672.84 79,556.47 406,070.43 (0.0047) (815.98) (1,114.21) (373.92) (307.91)
F2 52,334.22 89,128.02 36,260.71 36,260.71 0.0125 654.18 1,085.88 453.26 453.26
F3 3,313.02 5,642.25 5,991.80 5,991.80 (0.0049) (16.23) (13.05) (29.36) (29.36)
F4 5,758.77 9,807.50 0.00 6,742.82 (0.0212) (122.09) (163.26) 0.00 (72.15)
Aug-18 04 473,575.95 873,826.56 34.51% 162,696.02 186,652.23 7.37% (90.40) (295.04) 130.53 174.37 130.53 619.90
F1 137,836.59 433,509.43 92,685.63 498,756.06 (0.0057) (785.67) (1,899.88) (528.31) (836.22)
F2 41,549.65 130,677.67 39,494.21 75,754.92 0.0194 806.06 1,891.94 766.19 1,219.45
F3 2,630.30 8,272.55 0.00 5,991.80 0.0062 16.31 3.26 0.00 (29.36)
F4 4,572.05 14,379.55 3,861.44 10,604.26 (0.0278) (127.10) (290.36) (107.35) (179.50)
Sep-18 05 241,465.29 1,115,291.85 44.05% 162,696.02 186,652.23 7.37% (77.25) (372.29) Err:509 Err:509 Err:509 Err:509
F1 117,789.27 551,298.70 Err:509 Err:509 (0.0057) (671.40) (2,571.28) Err:509 Err:509
F2 35,506.56 166,184.23 11,029.12 86,784.04 0.0194 688.83 2,580.77 213.96 1,433.41
F3 2,247.74 10,520.29 Err:509 Err:509 0.0062 13.94 17.20 Err:509 Err:509
F4 3,907.08 18,286.63 Err:509 Err:509 (0.0278) (108.62) (398.98) Err:509 Err:509
Oct-18 06 435,837.21 1,551,129.06 61.27%
Dec-18 07 0.00 1,551,129.06 61.27%

1,551,129.06 780,457.80 Err:509

RESUMEN :
MES QUE
REAJUSTE RECONOCIDO EN PARCIAL ACUMULADO
CORRESPONDE

Valorización Nº 01 May-18 413.43 413.43


Valorización Nº 02 Jun-18 25.96 439.39
Valorización Nº 03 Jul-18 49.98 489.37
Valorización Nº 04 Aug-18 130.53 619.90
Valorización Nº 05 Sep-18 Err:509 Err:509
Valorización Nº 06 Oct-18
Valorización Nº 07 Dec-18

REAJUSTE TOTAL RECONOCIDO Err:509


CONTRATO N°40-2018/VIVIENDA/VMCS/PNSU, de fecha 27-04-2018 MODALIDAD DE EJECUCIÓN : A PRECIOS UNITARIOS
OBRA : "MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO EN EL C.P. MARIA DEL SOCORRO" PLAZO DE EJECUCIÓN : 180 DÍAS CALENDARIO
PROPIETARIO PROGRAMA NACIONAL DE SANEAMIENTO URBANO VALOR REFERENCIAL : S/. 7,403,281.18 Inc/IGV.
UBICACIÓN LA LIBERTAD - TRUJILLO - HUANCHACO MONTO OFERTADO : S/. 7,287,403.73 Inc/IGV.
CONTRATISTA CONSORCIO LA LIBERTAD. FECHA BASE : Abril 2017
RESIDENTE Ingº CRISTOBAL A, SUAREZ GUERRERO FACTOR DE RELACIÓN :
SUPERVISOR Ingº ROBERTO OSCCO ROJAS

CÁLCULO DEL FACTOR DE REAJUSTE " K "


FÓRMULA POLINÓMICA Nº 01

K = 0.187*(Jr / Jo) + 0.147*(Ar / Ao) + 0.205*(AGr / AGo) + 0.150*(Cr / Co) + 0.083*(Mr / Mo) + 0.098*(MQr / MQo) + 0.130*(Ir / Io)

ÍNDICE
Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12
ÍNDICE DESCRIPCIÓN SÍMBOLO COEFIC. INCIDENCIA BASE
(Dic. 2011) ÍNDICE COEF. ÍNDICE COEF. ÍNDICE COEF. ÍNDICE COEF. ÍNDICE COEF. ÍNDICE COEF.
47 MANO DE OBRA INC. LEYES SOCIALES J 0.187 100.00% 448.29 448.25 0.187 448.25 0.187 448.25 0.187 470.75 0.196 470.79 0.196 0.000
03 ACERO DE CONSTRUCCION CORRUGADO A 0.147 100.00% 527.51 498.41 0.139 486.71 0.136 471.48 0.131 431.43 0.120 429.12 0.120 0.000
05 AGREGADO GRUESO AG 0.205 100.00% 423.49 433.49 0.210 430.70 0.208 432.27 0.209 427.04 0.207 428.01 0.207 0.000
21 CEMENTO PORTLAND TIPO I C 0.150 100.00% 415.90 418.26 0.151 419.05 0.151 422.97 0.153 432.21 0.156 438.98 0.158 0.000
43 MADERA NACIONAL PARA ENCOF. Y CARPINT. M 0.083 100.00% 599.67 613.84 0.085 613.50 0.085 617.61 0.085 615.62 0.085 602.54 0.083 0.000
48 MAQUINARIA Y EQUIPO NACIONAL MQ 0.098 100.00% 328.94 329.22 0.098 328.79 0.098 327.55 0.098 325.98 0.097 325.11 0.097 0.000
39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR I 0.130 100.00% 371.47 377.30 0.132 377.16 0.132 377.50 0.132 379.42 0.133 381.48 0.134 0.000

1.000 Ka May-12 = 1.002 K jun-12 = 0.997 K jul-12 = 0.995 K ago-12 = 0.994 K sep-12 = 0.9952 K oct-12 = 0.0000
CÁLCULO DEL FACTOR DE REAJUSTE " K "
FÓRMULA POLINÓMICA Nº 02

K = 0.227*(Jr / Jo) + 0.095*(Ar / Ao) + 0.078*(AFr / AFo) + 0.095*(Cr / Co) + 0.114*(Pr / Po) + 0.075*(PLr / PLo) + 0.186*(Mr / Mo) + 0.130*(Ir / Io)

ÍNDICE
Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12
BASE
ÍNDICE DESCRIPCIÓN SÍMBOLO COEFIC. INCIDENCIA
(Dic. 2011) ÍNDICE COEF. ÍNDICE COEF. ÍNDICE COEF. ÍNDICE COEF. ÍNDICE COEF. ÍNDICE COEF.

47 J 0.227 100.00% 448.29 448.25 0.227 448.25 0.227 448.25 0.227 470.75 0.238 470.79 0.238 0.000
MANO DE OBRA INC. LEYES SOCIALES

02 A 0.095 100.00% 532.38 505.67 0.090 490.10 0.087 476.32 0.085 437.12 0.078 434.54 0.078 0.000
ACERO DE CONSTRUCCION LISO

04 AF 0.078 100.00% 464.72 478.93 0.080 479.55 0.080 486.25 0.082 487.20 0.082 489.19 0.082 0.000
AGREGADO FINO

21 C 0.095 100.00% 415.90 418.26 0.096 419.05 0.096 422.97 0.097 432.21 0.099 438.98 0.100 0.000
CEMENTO PORTLAND TIPO I

54 P 0.114 100.00% 348.58 363.01 0.119 363.28 0.119 363.28 0.119 363.77 0.119 363.77 0.119 0.000
PINTURA LATEX

59 PL 0.075 100.00% 188.17 200.22 0.080 200.22 0.080 200.22 0.080 200.22 0.080 384.13 0.153 0.000
PLANCHA DE ASBESTO-CEMENTO

43 M 0.186 100.00% 599.67 613.84 0.190 613.50 0.190 617.61 0.192 615.62 0.191 602.54 0.187 0.000
MADERA NACIONAL PARA ENCOF. Y CARPINT.

39 I 0.130 100.00% 371.47 377.30 0.132 377.16 0.132 377.50 0.132 379.42 0.133 381.48 0.134 0.000
INDICE GENERAL DE PRECIOS AL CONSUMIDOR

1.000 Ka May-12 = 1.014 K jun-12 = 1.012 K jul-12 = 1.013 K ago-12 = 1.0194 K sep-12 = 1.0908 K oct-12 = 0.0000
CÁLCULO DEL FACTOR DE REAJUSTE " K "
FÓRMULA POLINÓMICA Nº 03

K = 0.239*(Jr / Jo) + 0.179*(Ar / Ao) + 0.321*(ARr / ARo) + 0.131*(Tr / To) + 0.130*(Ir / Io)

ÍNDICE
Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12
BASE
ÍNDICE DESCRIPCIÓN SÍMBOLO COEFIC. INCIDENCIA
(Dic. 2011) ÍNDICE COEF. ÍNDICE COEF. ÍNDICE COEF. ÍNDICE COEF. ÍNDICE COEF. ÍNDICE COEF.

47 J 0.239 100.00% 448.29 448.25 0.239 448.25 0.239 448.25 0.239 470.75 0.251 470.79 0.251 0.000
MANO DE OBRA INC. LEYES SOCIALES

07 A 0.179 100.00% 592.91 598.55 0.181 587.50 0.177 577.93 0.174 578.53 0.175 576.16 0.174 0.000
ALAMBRE Y CABLE TIPO TW Y THW

12 AR 0.321 100.00% 295.64 295.17 0.320 295.34 0.321 292.27 0.317 290.65 0.316 289.45 0.314 0.000
ARTEFACTO DE ALUMBRADO INTERIOR

74 T 0.131 100.00% 347.42 346.99 0.131 350.65 0.132 350.65 0.132 350.65 0.132 350.65 0.132 0.000
TUBERIA DE PVC PARA ELECTRICIDAD (SAP)

39 I 0.130 100.00% 371.47 377.30 0.132 377.16 0.132 377.50 0.132 379.42 0.133 381.48 0.134 0.000
INDICE GENERAL DE PRECIOS AL CONSUMIDOR

1.000 Ka May-12 = 1.003 K jun-12 = 1.001 K jul-12 = 0.995 K ago-12 = 1.0062 K sep-12 = 1.0049 K oct-12 = 0.0000

CÁLCULO DEL FACTOR DE REAJUSTE " K "


FÓRMULA POLINÓMICA Nº 04

K = 0.185*(Jr / Jo) + 0.071*(Ar / Ao) + 0.090*(AGr / AGo) + 0.074*(Cr / Co) + 0.094*(ASr / ASo) + 0.156*(Tr / To) + 0.200*(Pr / Po) + 0.130*(Ir / Io)

ÍNDICE
Jun-12 Jul-12 Aug-12 Sep-12 Oct-12 Nov-12
BASE
ÍNDICE DESCRIPCIÓN SÍMBOLO COEFIC. INCIDENCIA
(Dic. 2011) ÍNDICE COEF. ÍNDICE COEF. ÍNDICE COEF. ÍNDICE COEF. ÍNDICE COEF. ÍNDICE COEF.

47 J 0.185 100.00% 448.29 448.25 0.185 448.25 0.185 448.25 0.185 470.75 0.194 470.79 0.194 0.000
MANO DE OBRA INC. LEYES SOCIALES

03 A 0.071 100.00% 527.51 498.41 0.067 486.71 0.066 471.48 0.063 431.43 0.058 429.12 0.058 0.000
ACERO DE CONSTRUCCION CORRUGADO

05 AG 0.090 100.00% 423.49 433.49 0.092 430.70 0.092 432.27 0.092 427.04 0.091 428.01 0.091 0.000
AGREGADO GRUESO

21 C 0.074 100.00% 415.90 418.26 0.074 419.05 0.075 422.97 0.075 432.21 0.077 438.98 0.078 0.000
CEMENTO PORTLAND TIPO I

10 AS 0.094 100.00% 337.44 345.54 0.096 345.12 0.096 345.63 0.096 345.45 0.096 353.71 0.099 0.000
APARATO SANITARIO CON GRIFERIA
72 TUBERIA DE PVC PARA AGUA T 0.156 100.00% 347.42 346.99 0.156 350.65 0.157 348.79 0.157 346.50 0.156 347.79 0.156 0.000
51 PERFIL DE ACERO LIVIANO P 0.200 100.00% 337.24 324.79 0.193 315.55 0.187 300.46 0.178 282.68 0.168 281.21 0.167 0.000
39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR I 0.130 100.00% 371.47 377.30 0.132 377.16 0.132 377.50 0.132 379.42 0.133 381.48 0.134 0.000

1.000 Ka May-12 = 0.995 K jun-12 = 0.989 K jul-12 = 0.979 K ago-12 = 0.9722 K sep-12 = 0.9761 K oct-12 = 0.0000
CONTRATO N°40-2018/VIVIENDA/VMCS/PNSU, de fecha 27-04-2018
OBRA : "MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO EN EL C.P. MARIA DEL SOCORRO"
PROPIETARIO PROGRAMA NACIONAL DE SANEAMIENTO URBANO
UBICACIÓN LA LIBERTAD - TRUJILLO - HUANCHACO
CONTRATISTA CONSORCIO LA LIBERTAD.
RESIDENTE Ingº CRISTOBAL A, SUAREZ GUERRERO
SUPERVISOR Ingº ROBERTO OSCCO ROJAS

VALORIZACIÓN Nº 02 - SISTEMA DE ALCANTARILLADO SANITARIO

3,500,000 GRÁFICO DEL AVANCE FINANCIERO PROGRAMADO VS. AVANCE FINANCIERO EJE-
CUTADO
2,987,454.37 2,987,454.37
3,000,000

2,429,597.97
2,500,000
AVANCE MENSUAL ACUMULADO (S/.)

1,993,760.76
2,000,000
1,752,295.47

1,500,000

1,278,719.52
1,000,000 Column D
684,086.83
Column J

500,000
28,268.33
19,625.50
0 220,249.63
14-May-18 31-May-18 30-Jun-18 31-Jul-18 31-Aug-18 30-Sep-18 31-Oct-18 30-Nov-18 09-Dec-18

PLAZO DE EJECUCIÓN (Meses)

MONTOS VALORIZADOS PROGRAMADOS MONTOS VALORIZADOS EJECUTADOS


MONTOS (SIN/ IGV) PORCENTAJES MONTOS (Inc/ IGV) PORCENTAJES
MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES PARCIAL ACUMUL. PARCIAL ACUMUL.
S/. S/. % % S/. S/. % %
14-May-18 0.00 0.00 0.00% 0.00% 14-May-18 0.00 0.00 0.00% 0.00%
31-May-18 19,625.50 19,625.50 0.66% 0.66% 31-May-18 28,268.33 28,268.33 0.95% 0.95%
30-Jun-18 664,461.33 684,086.83 22.24% 22.90% 30-Jun-18 191,981.30 220,249.63 6.43% 7.37%
31-Jul-18 594,632.69 1,278,719.52 19.90% 42.80% 31-Jul-18 0.00 0.00 0.00% 0.00%
31-Aug-18 473,575.95 1,752,295.47 15.85% 58.66% 31-Aug-18 0.00 0.00 0.00% 0.00%
30-Sep-18 241,465.29 1,993,760.76 8.08% 66.74% 30-Sep-18 0.00 0.00 0.00% 0.00%
31-Oct-18 435,837.21 2,429,597.97 14.59% 81.33% 31-Oct-18 0.00 0.00 0.00% 0.00%
30-Nov-18 557,856.40 2,987,454.37 18.67% 100.00% 30-Nov-18 0.00 0.00 0.00% 0.00%
9-Dec-18 0.00 2,987,454.37 0.00% 100.00% 9-Dec-18 0.00 0.00 0.00% 0.00%

TOTAL 2,987,454.37 100.00% TOTAL 220,249.63 7.37%


CONTRATO N°40-2018/VIVIENDA/VMCS/PNSU, de fecha 27-04-2018
OBRA : "MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO EN EL C.P. MARIA DEL SOCORRO"
PROPIETARIO PROGRAMA NACIONAL DE SANEAMIENTO URBANO
UBICACIÓN LA LIBERTAD - TRUJILLO - HUANCHACO
CONTRATISTA CONSORCIO LA LIBERTAD.
RESIDENTE Ingº CRISTOBAL A, SUAREZ GUERRERO
SUPERVISOR Ingº ROBERTO OSCCO ROJAS

VALORIZACIÓN Nº 02 - SISTEMA DE ALCANTARILLADO SANITARIO

GRÁFICO DEL AVANCE FÍSICO PROGRAMADO VS. AVANCE FÍSICO EJECUTADO 100.00%
100%
100.00%
90%

80%
81.33%
AVANCE MENSUAL ACUMULADO (%)

70%

60% 66.74%
58.66%
50%

40% 42.80%

30%
22.90%
20%
Column F Column L
10%
0.95% 7.37%
0%
14-May-18 31-May-18 30-Jun-18 31-Jul-18 31-Aug-18 30-Sep-18 31-Oct-18 30-Nov-18 09-Dec-18
0.66%

PLAZO DE EJECUCIÓN (Meses)

MONTOS VALORIZADOS PROGRAMADOS MONTOS VALORIZADOS EJECUTADOS


MONTOS (Inc/ IGV) PORCENTAJES MONTOS (Inc/ IGV) PORCENTAJES
MES PARCIAL ACUMUL. PARCIAL ACUMUL. MES PARCIAL ACUMUL. PARCIAL ACUMUL.
S/. S/. % % S/. S/. % %
14-May-18 0.00 0.00 0.00% 0.00% 14-May-18 0.00 0.00 0.00% 0.00%
31-May-18 19,625.50 19,625.50 0.66% 0.66% 31-May-18 28,268.33 28,268.33 0.95% 0.95%
30-Jun-18 664,461.33 684,086.83 22.24% 22.90% 30-Jun-18 191,981.30 220,249.63 6.43% 7.37%
31-Jul-18 594,632.69 1,278,719.52 19.90% 42.80% 31-Jul-18 0.00 0.00 0.00% 0.00%
31-Aug-18 473,575.95 1,752,295.47 15.85% 58.66% 31-Aug-18 0.00 0.00 0.00% 0.00%
30-Sep-18 241,465.29 1,993,760.76 8.08% 66.74% 30-Sep-18 0.00 0.00 0.00% 0.00%
31-Oct-18 435,837.21 2,429,597.97 14.59% 81.33% 31-Oct-18 0.00 0.00 0.00% 0.00%
30-Nov-18 557,856.40 2,987,454.37 18.67% 100.00% 30-Nov-18 0.00 0.00 0.00% 0.00%
9-Dec-18 0.00 2,987,454.37 0.00% 100.00% 9-Dec-18 0.00 0.00 0.00% 0.00%
TOTAL 2,987,454.37 100.00% TOTAL 220,249.63 7.37%
CONTRATO N°40-2018/VIVIENDA/VMCS/PNSU, de fecha 27-04-2018

OBRA : "MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO EN EL C.P. MARIA DEL SOCORRO"
PROPIETARIO PROGRAMA NACIONAL DE SANEAMIENTO URBANO
UBICACIÓN LA LIBERTAD - TRUJILLO - HUANCHACO
CONTRATISTA CONSORCIO LA LIBERTAD.
RESIDENTE Ingº CRISTOBAL A, SUAREZ GUERRERO
SUPERVISOR Ingº ROBERTO OSCCO ROJAS

MONTO DEL CONTRATO : S/. 2,987,454.33 Inc/IGV


MONTO DEL CONTRATO : S/. 2,531,740.96 Sin/IGV

VALORIZACIÓN Nº 02 - SISTEMA DE ALCANTARILLADO SANITARIO


CONTROL DE VALORIZACIONES EJECUTADAS VS. PROGRAMADAS

PROGRAMADO EJECUTADO
%
MES VALORIZACIÓN Nº AVANCE PORCENTAJE AVANCE PORCENTAJE
AVANCE MENSUAL AVANCE ACUMULADO EJEC./ PROG.
ACUMULADO ACUMULADO MENSUAL ACUMULADO

14-May-18
31-May-18 01 19,625.50 19,625.50 0.66% 28,268.33 28,268.33 0.95% 144.04%
30-Jun-18 02 664,461.33 684,086.83 22.90% 191,981.30 220,249.63 7.37% 32.20%
31-Jul-18 03 594,632.69 1,278,719.52 42.80% 0.00 0.00 0.00% 0.00%
31-Aug-18 04 473,575.95 1,752,295.47 58.66% 0.00 0.00 0.00% 0.00%
30-Sep-18 05 241,465.29 1,993,760.76 66.74% 0.00 0.00 0.00% 0.00%
31-Oct-18 06 435,837.21 2,429,597.97 81.33% 0.00 0.00 0.00% 0.00%
30-Nov-18 07 557,856.40 2,987,454.37 100.00% 0.00 0.00 0.00% 0.00%
9-Dec-18 08 0.00 2,987,454.37 100.00% 0.00 0.00 0.00% 0.00%

TOTAL 2,987,454.37 220,249.63


CONTRATO N°40-2018/VIVIENDA/VMCS/PNSU, de fecha 27-04-2018 MODALIDAD DE EJECUCIÓN : A PRECIOS UNITARIOS
OBRA : "MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO EN EL C.P. MARIA DEL SOCORRO" PLAZO DE EJECUCIÓN : 180 DÍAS CALENDARIO
PROPIETARIO PROGRAMA NACIONAL DE SANEAMIENTO URBANO VALOR REFERENCIAL : S/. 7,403,281.18 Inc/IGV.
UBICACIÓN LA LIBERTAD - TRUJILLO - HUANCHACO MONTO OFERTADO : S/. 7,287,403.73 Inc/IGV.
CONTRATISTA CONSORCIO LA LIBERTAD. FECHA BASE : Abril 2017
RESIDENTE Ingº CRISTOBAL A, SUAREZ GUERRERO FACTOR DE RELACIÓN : 0.9843
SUPERVISOR Ingº ROBERTO OSCCO ROJAS

VALORIZACIÓN Nº 02 - SISTEMA DE ALCANTARILLADO SANITARIO


(Del 01 de Junio al 30 de Junio del 2018)

PRESUPUESTO BASE AVANCE


SALDOS
PARTIDA DESCRIPCIÓN UNID METRADO P.U. PARCIAL ANTERIOR ACTUAL ACUMULADO
(S/.) (S/.) METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL % METRADO PARCIAL %
02 SISTEMA DE ALCANTARILLADO SANITARIO 2,236,520.28
02.01 LINEAS DE ALCANTARILLADO SANITARIO 2,236,520.28
02.01.01 TRABAJOS PRELIMINARES GENERALES 15,707.65
02.01.01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO, MATERIALES Y EQUIPAMIENTO HIDRAULICO A OBRA LINEALES vje 3.00 4,634.2400 13,902.72 1.50 6,951.36 - - 1.50 6,951.36 50.0% 1.50 6,951.36 50%
02.01.01.02 CARTEL DE IDENTIFICACION DE LA OBRA DE 5.40 X 3.60 m u 1.00 1,804.9300 1,804.93 1.00 1,804.93 - - 1.00 1,804.93 100.0% 0.00 0.00 0%
02.01.02 RED COLECTORA 1,687,269.03
02.01.02.01 TRABAJOS PRELIMINARES 130,896.68
02.01.02.01.01 LIMPIEZA DE TERRENO m 6,265.88 1.2300 7,707.03 - - 744.52 915.76 744.52 915.76 11.9% 5,521.36 6,791.27 88%
02.01.02.01.02 RIEGO DE ZONA DE TRABAJO PARA MITIGAR LA CONTAMINACION - POLVO (CON AUTORIZACION DE USO DE GRIFO) m 6,265.88 1.5600 9,774.77 - - 744.52 1,161.45 744.52 1,161.45 11.9% 5,521.36 8,613.32 88%
02.01.02.01.03 TRAZO Y REPLANTEO INICIAL m 6,265.88 1.9800 12,406.44 6,265.88 12,406.44 - - 6,265.88 12,406.44 100.0% 0.00 0.00 0%
02.01.02.01.04 TRAZO Y REPLANTEO FINAL DE OBRA m 6,265.88 1.8000 11,278.58 - - 655.00 1,179.00 655.00 1,179.00 10.5% 5,610.88 10,099.58 90%
02.01.02.01.05 NIVELACION Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m 6,265.88 1.8900 11,842.51 - - 744.52 1,407.14 744.52 1,407.14 11.9% 5,521.36 10,435.37 88%
02.01.02.01.06 DESVIO DE RED DE AGUAS RESIDUALES CON MOTOBOMBA u 657.00 118.5500 77,887.35 - - 32.00 3,793.60 32.00 3,793.60 4.9% 625.00 74,093.75 95%
02.01.02.02 SEÑALIZACION DE TRANSITO 22,175.14
02.01.02.02.01 PARANTE PARA CINTA PLASTICA SEÑAL u 300.00 24.1800 7,254.00 - - 50.00 1,209.00 50.00 1,209.00 16.7% 250.00 6,045.00 83%
02.01.02.02.02 CINTA PLASTICA SEÑALIZADORA P/LIMITE DE SEGURIDAD DE OBRA m 6,265.88 1.0100 6,328.54 - - 744.52 751.97 744.52 751.97 11.9% 5,521.36 5,576.57 88%
02.01.02.02.03 TRANQUERAS DE MADERA 1.20X1.10 m PARA DESVIO TRANSITO VEHICULAR u 15.00 274.8300 4,122.45 - - 5.00 1,374.15 5.00 1,374.15 33.3% 10.00 2,748.30 67%
02.01.02.02.04 SEÑALIZACION NOCTURNA d 150.00 13.0400 1,956.00 - - 20.00 260.80 20.00 260.80 13.3% 130.00 1,695.20 87%
02.01.02.02.05 PUENTE DE MADERA PASE PEATONAL u 25.00 63.6700 1,591.75 - - 2.00 127.34 2.00 127.34 8.0% 23.00 1,464.41 92%
02.01.02.02.06 PUENTE DE MADERA PASE VEHICULAR u 10.00 32.2400 322.40 - - 2.00 64.48 2.00 64.48 20.0% 8.00 257.92 80%
02.01.02.02.07 CONO FIBRA DE VIDRIO FOSFORESCENTE PARA SEÑALIZACION u 20.00 30.0000 600.00 - - 5.00 150.00 5.00 150.00 25.0% 15.00 450.00 75%
02.01.02.03 MOVIMIENTO DE TIERRAS 610,029.10
02.01.02.03.01 ROTURA Y REPOSICION DE PAVIMENTO RIGIDO F'c=210kg/cm2 m2 835.00 137.4500 114,770.75 - - - - - - 0.0% 835.00 114,770.75 100%
02.01.02.03.02 ROTURA DE PAVIMENTO FLEXIBLE m2 5,209.14 21.7900 113,507.16 - - 446.71 9,733.81 446.71 9,733.81 8.6% 4,762.43 103,773.35 91%
02.01.02.03.03 EXCAV.C/EQ.P.ALCAN.T.NORMAL A= 0.60M H=1.21M - H=1.50M m 4,976.34 12.2600 61,009.93 - - 744.52 9,127.82 744.52 9,127.82 15.0% 4,231.82 51,882.11 85%
02.01.02.03.04 EXCAV.C/EQ.P.ALCAN.T.NORMAL A= 0.80M H=1.51M - H=2.00M m 1,236.29 14.6200 18,074.56 - - - - - - 0.0% 1,236.29 18,074.56 100%
02.01.02.03.05 EXCAV.C/EQ.P.ALCAN.T.NORMAL A= 0.80M H=2.01M - H=2.50M m 53.25 17.1200 911.64 - - - - - - 0.0% 53.25 911.64 100%
02.01.02.03.06 EXCAVACION PARA BUZONES C/EQUIPO, T.NORMAL m3 352.07 46.2700 16,290.28 - - 48.25 2,232.53 48.25 2,232.53 13.7% 303.82 14,057.75 86%
02.01.02.03.07 ENTIBADO Y DESENTIBADO DE ZANJA m2 2,248.19 55.7800 125,404.04 - - - - - - 0.0% 2,248.19 125,404.04 100%
02.01.02.03.08 BOMBEO DE AGUA EN TERRENO SATURADO CON EMPLEO DE MOTOBOMBA DN 80 h 240.00 34.7100 8,330.40 - - 24.00 833.04 24.00 833.04 10.0% 216.00 7,497.36 90%
02.01.02.03.09 REFINE Y NIVELACION FONDO DE ZANJA TN A= 0.60M m 4,976.34 1.9200 9,554.57 - - 744.52 1,429.48 744.52 1,429.48 15.0% 4,231.82 8,125.09 85%
02.01.02.03.10 REFINE Y NIVELACION FONDO DE ZANJA TN A= 0.80M m 1,289.54 2.1800 2,811.20 - - - - - - 0.0% 1,289.54 2,811.20 100%
02.01.02.03.11 CAMA DE ARENA MANUAL E=0.10M A= 0.60M m 4,976.34 3.8000 18,910.09 - - 744.52 2,829.18 744.52 2,829.18 15.0% 4,231.82 16,080.92 85%
02.01.02.03.12 CAMA DE ARENA MANUAL E=0.10M A= 0.80M m 1,289.54 4.6600 6,009.26 - - - - - - 0.0% 1,289.54 6,009.26 100%
02.01.02.03.13 RELLENO ZANJA MAT.PROPIO.COMPACT.C/EQUIPO A=0.60M H=1.20M - H=1.50M m 4,976.34 14.4100 71,709.06 - - 744.52 10,728.53 744.52 10,728.53 15.0% 4,231.82 60,980.53 85%
02.01.02.03.14 RELLENO ZANJA MAT.PROPIO.COMPACT.C/EQUIPO A=0.80M H=1.51M - H=2.00M m 1,236.29 16.8900 20,880.94 - - - - - - 0.0% 1,236.29 20,880.94 100%
02.01.02.03.15 RELLENO ZANJA MAT.PROPIO.COMPACT.C/EQUIPO A=0.80M H=2.01M - H=2.50M m 53.25 18.8100 1,001.63 - - - - - - 0.0% 53.25 1,001.63 100%
02.01.02.03.16 ACARREO DE MATERIAL EXCEDENTE-C/EQUIPO m3 1,171.55 5.8600 6,865.28 - - 268.03 1,570.66 268.03 1,570.66 22.9% 903.52 5,294.63 77%
02.01.02.03.17 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA 5 km m3 1,171.55 11.9400 13,988.31 - - 268.03 3,200.28 268.03 3,200.28 22.9% 903.52 10,788.03 77%
02.01.02.04 PAVIMENTACION 364,352.07 - - - - - -
02.01.02.04.01 PAVIMENTO FLEXIBLE 273,909.94 - - - - - -
02.01.02.04.01.01 PERFILADO Y COMPACTACION DE SUBRASANTE m2 3,906.86 5.9000 23,050.47 - - - - - - 0.0% 3,906.86 23,050.47 100%
02.01.02.04.01.02 SUB - BASE DE 0.15 m CON HORMIGON m2 3,906.86 5.3200 20,784.50 - - - - - - 0.0% 3,906.86 20,784.50 100%
02.01.02.04.01.03 BASE CON AFIRMADO E=0.20M m2 3,906.86 17.1100 66,846.37 - - - - - - 0.0% 3,906.86 66,846.37 100%
02.01.02.04.01.04 IMPRIMACION ASFALTICA m2 3,906.86 5.4900 21,448.66 - - - - - - 0.0% 3,906.86 21,448.66 100%
02.01.02.04.01.05 CARPETA ASFALTICA EN FRIO DE 2" EN PARCHE m2 3,906.86 27.1200 105,954.04 - - - - - - 0.0% 3,906.86 105,954.04 100%
02.01.02.04.01.06 BARRIDO Y LIMPIEZA PARA SELLADO m2 3,906.86 1.3400 5,235.19 - - - - - - 0.0% 3,906.86 5,235.19 100%
02.01.02.04.01.07 SELLADO ASFALTICO m2 3,906.86 6.9300 27,074.54 - - - - - - 0.0% 3,906.86 27,074.54 100%
02.01.02.04.01.08 BARRIDO DE ARENA SOBRANTE m2 3,906.86 0.9000 3,516.17 - - - - - - 0.0% 3,906.86 3,516.17 100%
02.01.02.04.02 PAVIMENTO RIGIDO 85,963.40
02.01.02.04.02.01 BASE GRANULAR e = 0.20 m, EXTENDIDO, BATIDO, RIEGO Y COMPACTACION m2 626.25 10.2100 6,394.01 - - - - - - 0.0% 626.25 6,394.01 100%
02.01.02.04.02.02 CONCRETO EN PAVIMENTO RIGIDO fc= 210 KGCM2, FROTACHADO e=0,20m m3 125.25 359.5800 45,037.40 - - - - - - 0.0% 125.25 45,037.40 100%
02.01.02.04.02.03 ACERO DE TRANSFERENCIA DE CARGA LONGITUDINAL Y TRANSVERSAL (TIPO DOWELLS) kg 1,409.06 4.3200 6,087.14 - - - - - - 0.0% 1,409.06 6,087.14 100%
02.01.02.04.02.04 ENCOFRADO Y DESENCOFRADO EN PAVIMENTO RIGIDO m2 334.30 24.6400 8,237.15 - - - - - - 0.0% 334.30 8,237.15 100%
02.01.02.04.02.05 JUNTA DE CONTRACCION ASERRADA RELLENO CON POLIURETANO E=8MM m 835.00 15.4800 12,925.80 - - - - - - 0.0% 835.00 12,925.80 100%
02.01.02.04.02.06 JUNTAS DE DILATACION ASFALTICAS E=1" m 1,395.00 5.2200 7,281.90 - - - - - - 0.0% 1,395.00 7,281.90 100%

20 de 27
CONTRATO N°40-2018/VIVIENDA/VMCS/PNSU, de fecha 27-04-2018 MODALIDAD DE EJECUCIÓN : A PRECIOS UNITARIOS
OBRA : "MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO EN EL C.P. MARIA DEL SOCORRO" PLAZO DE EJECUCIÓN : 180 DÍAS CALENDARIO
PROPIETARIO PROGRAMA NACIONAL DE SANEAMIENTO URBANO VALOR REFERENCIAL : S/. 7,403,281.18 Inc/IGV.
UBICACIÓN LA LIBERTAD - TRUJILLO - HUANCHACO MONTO OFERTADO : S/. 7,287,403.73 Inc/IGV.
CONTRATISTA CONSORCIO LA LIBERTAD. FECHA BASE : Abril 2017
RESIDENTE Ingº CRISTOBAL A, SUAREZ GUERRERO FACTOR DE RELACIÓN : 0.9843
SUPERVISOR Ingº ROBERTO OSCCO ROJAS

VALORIZACIÓN Nº 02 - SISTEMA DE ALCANTARILLADO SANITARIO


(Del 01 de Junio al 30 de Junio del 2018)

PRESUPUESTO BASE AVANCE


SALDOS
PARTIDA DESCRIPCIÓN UNID METRADO P.U. PARCIAL ANTERIOR ACTUAL ACUMULADO
(S/.) (S/.) METRADO PARCIAL METRADO PARCIAL METRADO PARCIAL % METRADO PARCIAL %
02.01.02.04.03 PAVIMENTO ADOQUINADO 4,478.73 - - - - - -
02.01.02.04.03.01 DESMONTAJE Y REPOSICION DE ADOQUINES m2 166.31 26.9300 4,478.73 - - - - - - 0.0% 166.31 4,478.73 100%
02.01.02.05 SUMINISTRO E INSTALACION TUBERIAS DE DESAGUE NTP ISO 21138 248,755.44 - - - - - -
02.01.02.05.01 SUMINISTRO DE TUBERÍA PVC-U NTP ISO 4435 DN 200 SN4 INC. ANILLO m 6,265.88 35.2900 221,122.91 - - 744.52 26,274.11 744.52 26,274.11 11.9% 5,521.36 194,848.79 88%
02.01.02.05.02 PRUEBA HIDR. NIVELACION, ALINEAMIENTO Y DEFLEXION. TUBERIA DN 200 MM m 6,265.88 4.4100 27,632.53 - - 744.52 3,283.33 744.52 3,283.33 11.9% 5,521.36 24,349.20 88%
02.01.02.06 BUZONES /CAJAS DE INSPECCION (RED ALCANTARILLADO DOMESTICO) 277,420.35
02.01.02.06.01 BUZON Di=1.20M DESDE 1.20 MPP HASTA 1.50 MPP (Cemento Tipo-V) u 75.00 2,265.2300 169,892.25 - - 16.00 36,243.68 16.00 36,243.68 21.3% 59.00 133,648.57 79%
02.01.02.06.02 BUZON Di=1.20M DESDE 1.51 MPP HASTA 2.00 MPP (Cemento Tipo-V) u 20.00 2,650.5700 53,011.40 - - - - - - 0.0% 20.00 53,011.40 100%
02.01.02.06.03 DEMOLICION DE BUZONES EXISTENTES u 95.00 573.8600 54,516.70 - - 5.00 2,869.30 5.00 2,869.30 5.3% 90.00 51,647.40 95%
02.01.02.07 CONCRETO SIMPLE 10,782.50
02.01.02.07.01 DADOS DE CONCRETO PARA TUBERIA PVC-U DN 200 u 190.00 56.7500 10,782.50 - - 35.00 1,986.25 35.00 1,986.25 18.4% 155.00 8,796.25 82%
02.01.02.08 VARIOS 22,857.75
02.01.02.08.01 PRUEBA COMPACTACION SUELOS (PROCTOR MODIFICADO) u 150.00 72.5300 10,879.50 - - 5.00 362.65 5.00 362.65 3.3% 145.00 10,516.85 97%
02.01.02.08.02 PRUEBA COMPACTACION SUELOS (DENSIDAD DE CAMPO) u 150.00 61.7000 9,255.00 - - 5.00 308.50 5.00 308.50 3.3% 145.00 8,946.50 97%
02.01.02.08.03 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) u 75.00 36.3100 2,723.25 - - 5.00 181.55 5.00 181.55 6.7% 70.00 2,541.70 93%
02.01.03 CONEXIONES DOMICILIARIAS ALCANTARILLADO 533,543.60
02.01.03.01 CONEXIONES DOM. ALCANTARILLADO TUB PVC ISO 21138 DN 160/200MM H=2,00M 388,424.92
02.01.03.01.01 RIEGO DE ZONA DE TRABAJO PARA MITIGAR LA CONTAMINACION - POLVO (CON AUTORIZACION DE USO DE GRIFO) m 3,942.00 1.5600 6,149.52 - - 160.00 249.60 160.00 249.60 4.1% 3,782.00 5,899.92 96%
02.01.03.01.02 LIMPIEZA DURANTE LA EJECUCIÓN DE OBRA m 3,942.00 0.9200 3,626.64 - - 160.00 147.20 160.00 147.20 4.1% 3,782.00 3,479.44 96%
02.01.03.01.03 TRAZO NIVELACION Y REPLANTEO CONEXION DOMIC. ALCANTARILLADO m 3,942.00 1.3000 5,124.60 - - 160.00 208.00 160.00 208.00 4.1% 3,782.00 4,916.60 96%
02.01.03.01.04 EXCAVACION DE ZANJA MANUAL EN T.NORMAL SECCION 0.60 m. DE ANCHO Y H=1,20 m P/CONEX. DOMICIL. m 3,942.00 16.3000 64,254.60 - - 160.00 2,608.00 160.00 2,608.00 4.1% 3,782.00 61,646.60 96%
02.01.03.01.05 REFINE, NIVELACION Y CONFORMACION DE FONDO DE ZANJA T. NORMAL P/CONEX. DOMICIL. 0.6m m 3,942.00 2.0400 8,041.68 - - 160.00 326.40 160.00 326.40 4.1% 3,782.00 7,715.28 96%
02.01.03.01.06 CAMA DE ARENA MANUAL E=0.10M A= 0.60M m 3,942.00 2.2300 8,790.66 - - 160.00 356.80 160.00 356.80 4.1% 3,782.00 8,433.86 96%
02.01.03.01.07 RELLENO Y COMPACTACION DE ZANJA CON MATERIAL PROPIO P/CONEX. DOMICIL, HASTA 1,20m m 3,942.00 9.8300 38,749.86 - - 160.00 1,572.80 160.00 1,572.80 4.1% 3,782.00 37,177.06 96%
02.01.03.01.08 ACARREO DE MATERIAL EXCENTE-MANUAL DH = 30M (DISTANIA PROMEDIO m 103.04 8.1500 839.78 - - 28.80 234.72 28.80 234.72 28.0% 74.24 605.06 72%
02.01.03.01.09 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA 5 km m3 103.04 11.9400 1,230.30 - - 28.80 343.87 28.80 343.87 28.0% 74.24 886.43 72%
02.01.03.01.10 CONEXIÓN DOMICIL. ALCANTARILLADO TUBO PVC DN 160/200 MM T.N. L= 6,00M u 657.00 344.6600 226,441.62 - - 32.00 11,029.12 32.00 11,029.12 4.9% 625.00 215,412.50 95%
02.01.03.01.11 PRUEBA Z ZANJA TAPADA Y DESINFECCION DE TUBERIA P/DESAGUE PVC UF DN160 SN4 m 3,942.00 4.9600 19,552.32 - - 160.00 793.60 160.00 793.60 4.1% 3,782.00 18,758.72 96%
02.01.03.01.12 PRUEBA COMPACTACION SUELOS (DENSIDAD DE CAMPO) u 10.00 61.7000 617.00 - - 1.00 61.70 1.00 61.70 10.0% 9.00 555.30 90%
02.01.03.01.13 LIMPIEZA FINAL DE OBRA m 3,942.00 1.2700 5,006.34 - - 160.00 203.20 160.00 203.20 4.1% 3,782.00 4,803.14 96%
02.01.03.02 PAVIMENTACION EN CONEXIONES DOMICILIARIAS 145,118.68
02.01.03.02.01 PAVIMENTO FLEXIBLE 116,312.49
02.01.03.02.01.01 PERFILADO Y COMPACTACION DE SUBRASANTE m2 1,659.00 5.9000 9,788.10 - - - - - - 0.0% 1,659.00 9,788.10 100%
02.01.03.02.01.02 SUB - BASE DE 0.15 m CON HORMIGON m2 1,659.00 5.3200 8,825.88 - - - - - - 0.0% 1,659.00 8,825.88 100%
02.01.03.02.01.03 BASE CON AFIRMADO E=0.20M m2 1,659.00 17.1100 28,385.49 - - - - - - 0.0% 1,659.00 28,385.49 100%
02.01.03.02.01.04 IMPRIMACION ASFALTICA m2 1,659.00 5.4900 9,107.91 - - - - - - 0.0% 1,659.00 9,107.91 100%
02.01.03.02.01.05 CARPETA ASFALTICA EN FRIO DE 2" EN PARCHE m2 1,659.00 27.1200 44,992.08 - - - - - - 0.0% 1,659.00 44,992.08 100%
02.01.03.02.01.06 BARRIDO Y LIMPIEZA PARA SELLADO m2 1,659.00 1.3400 2,223.06 - - - - - - 0.0% 1,659.00 2,223.06 100%
02.01.03.02.01.07 SELLADO ASFALTICO m2 1,659.00 6.9300 11,496.87 - - - - - - 0.0% 1,659.00 11,496.87 100%
02.01.03.02.01.08 BARRIDO DE ARENA SOBRANTE m2 1,659.00 0.9000 1,493.10 - - - - - - 0.0% 1,659.00 1,493.10 100%
02.01.03.02.02 PAVIMENTO RIGIDO 27,594.34
02.01.03.02.02.01 BASE GRANULAR e = 0.20 m, EXTENDIDO, BATIDO, RIEGO Y m2 336.00 10.2100 3,430.56 - - - - - - 0.0% 336.00 3,430.56 100%
02.01.03.02.02.02 CONCRETO EN PAVIMENTO RIGIDO fc=210 kg/cm2, FROTACHADO e=0,20 m3 67.20 359.5800 24,163.78 - - - - - - 0.0% 67.20 24,163.78 100%
02.01.03.02.03 PAVIMENTO ADOQUINADO 1,211.85
02.01.03.02.03.01 DESMONTAJE Y REPOSICION DE ADOQUINES m3 45.00 26.9300 1,211.85 - - - - - - 0.0% 45.00 1,211.85 100%

COSTO DIRECTO DEL VALOR REFERENCIAL S/. 2,236,520.28 S/. 21,162.73 S/. 143,724.40 S/. 164,887.13 S/. 2,071,633.16
GASTOS GENERALES FIJOS (0.2364533 %) 0.24% 5,288.33 S/. 50.04 S/. 339.84 S/. 389.88 S/. 4,898.44
GASTOS GENERALES VARIABLES (9.76354673 %) 9.76% 218,363.70 S/. 2,066.23 S/. 14,032.60 S/. 16,098.83 S/. 202,264.87
UTILIDAD (3.2 %) 3.20% 71,568.65 S/. 677.21 S/. 4,599.18 S/. 5,276.39 S/. 66,292.26
SUB - TOTAL 2,531,740.96 S/. 23,956.21 S/. 162,696.02 S/. 186,652.23 0.00 S/. 2,345,088.73
I.G.V. (18 % ) 18.00% S/. 455,713.37 S/. 4,312.12 S/. 29,285.28 S/. 33,597.40 0.00 S/. 422,115.97
TOTAL S/. 2,987,454.33 S/. 28,268.33 S/. 191,981.30 S/. 220,249.63 S/. 2,767,204.70
PORCENTAJE 0.95% 6.43% 7.37% 92.63%

21 de 27
CONTRATO N°40-2018/VIVIENDA/VMCS/PNSU, de fecha 27-04-2018

OBRA : "MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO EN EL C.P. MARIA DEL SOCORRO"

Subpresupuesto 01 SISTEMA DE ALCANTARILLADO SANITARIO


PROPIETARIO PROGRAMA NACIONAL DE SANEAMIENTO URBANO
UBICACIÓN LA LIBERTAD - TRUJILLO - HUANCHACO
CONTRATISTA CONSORCIO LA LIBERTAD.
RESIDENTE Ingº CRISTOBAL A, SUAREZ GUERRERO
SUPERVISOR Ingº ROBERTO OSCCO ROJAS

VALORIZACIÓN Nº 02 - SISTEMA DE ALCANTARILLADO SANITARIO


CONTROL DE METRADOS EJECUTADOS
(Del 01 de Junio al 30 de Junio del 2018)

METRADO METRADOS EJECUTADOS % SALDO


PARTIDA UND
BASE ANTERIOR MAYO ACTUAL ACUMULADO AVANCE METRADO
02 SISTEMA DE ALCANTARILLADO SANITARIO
02.01 LINEAS DE ALCANTARILLADO SANITARIO
02.01.01 TRABAJOS PRELIMINARES GENERALES
02.01.01.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPO, MATERIALES Y EQUIPAMIENTO HIDRAULICO A OBRA LINEALES vje 3.00 1.50 1.50 0.00 1.50 50.00% 1.50
02.01.01.02 CARTEL DE IDENTIFICACION DE LA OBRA DE 5.40 X 3.60 m u 1.00 1.00 1.00 0.00 1.00 100.00% 0.00
02.01.02 RED COLECTORA
02.01.02.01 TRABAJOS PRELIMINARES
02.01.02.01.01 LIMPIEZA DE TERRENO m 6,265.88 0.00 0.00 744.52 744.52 11.88% 5,521.36
02.01.02.01.02 RIEGO DE ZONA DE TRABAJO PARA MITIGAR LA CONTAMINACION - POLVO (CON AUTORIZACION DE USO DE GRIFO) m 6,265.88 0.00 0.00 744.52 744.52 11.88% 5,521.36
02.01.02.01.03 TRAZO Y REPLANTEO INICIAL m 6,265.88 6,265.88 6,265.88 0.00 6,265.88 100.00% 0.00
02.01.02.01.04 TRAZO Y REPLANTEO FINAL DE OBRA m 6,265.88 0.00 0.00 655.00 655.00 10.45% 5,610.88
02.01.02.01.05 NIVELACION Y REPLANTEO DURANTE EL PROCESO CONSTRUCTIVO m 6,265.88 0.00 0.00 744.52 744.52 11.88% 5,521.36
02.01.02.01.06 DESVIO DE RED DE AGUAS RESIDUALES CON MOTOBOMBA u 657.00 0.00 0.00 32.00 32.00 4.87% 625.00
02.01.02.02 SEÑALIZACION DE TRANSITO
02.01.02.02.01 PARANTE PARA CINTA PLASTICA SEÑAL u 300.00 0.00 0.00 50.00 50.00 16.67% 250.00
02.01.02.02.02 CINTA PLASTICA SEÑALIZADORA P/LIMITE DE SEGURIDAD DE OBRA m 6,265.88 0.00 0.00 744.52 744.52 11.88% 5,521.36
02.01.02.02.03 TRANQUERAS DE MADERA 1.20X1.10 m PARA DESVIO TRANSITO VEHICULAR u 15.00 0.00 0.00 5.00 5.00 33.33% 10.00
02.01.02.02.04 SEÑALIZACION NOCTURNA d 150.00 0.00 0.00 20.00 20.00 13.33% 130.00
02.01.02.02.05 PUENTE DE MADERA PASE PEATONAL u 25.00 0.00 0.00 2.00 2.00 8.00% 23.00
02.01.02.02.06 PUENTE DE MADERA PASE VEHICULAR u 10.00 0.00 0.00 2.00 2.00 20.00% 8.00
02.01.02.02.07 CONO FIBRA DE VIDRIO FOSFORESCENTE PARA SEÑALIZACION u 20.00 0.00 0.00 5.00 5.00 25.00% 15.00
02.01.02.03 MOVIMIENTO DE TIERRAS
02.01.02.03.01 ROTURA Y REPOSICION DE PAVIMENTO RIGIDO F'c=210kg/cm2 m2 835.00 0.00 0.00 0.00 0.00 0.00% 835.00
02.01.02.03.02 ROTURA DE PAVIMENTO FLEXIBLE m2 5,209.14 0.00 0.00 446.71 446.71 8.58% 4,762.43
02.01.02.03.03 EXCAV.C/EQ.P.ALCAN.T.NORMAL A= 0.60M H=1.21M - H=1.50M m 4,976.34 0.00 0.00 744.52 744.52 14.96% 4,231.82
02.01.02.03.04 EXCAV.C/EQ.P.ALCAN.T.NORMAL A= 0.80M H=1.51M - H=2.00M m 1,236.29 0.00 0.00 0.00 0.00 0.00% 1,236.29
02.01.02.03.05 EXCAV.C/EQ.P.ALCAN.T.NORMAL A= 0.80M H=2.01M - H=2.50M m 53.25 0.00 0.00 0.00 0.00 0.00% 53.25
02.01.02.03.06 EXCAVACION PARA BUZONES C/EQUIPO, T.NORMAL m3 352.07 0.00 0.00 48.25 48.25 13.70% 303.82
02.01.02.03.07 ENTIBADO Y DESENTIBADO DE ZANJA m2 2,248.19 0.00 0.00 0.00 0.00 0.00% 2,248.19
02.01.02.03.08 BOMBEO DE AGUA EN TERRENO SATURADO CON EMPLEO DE MOTOBOMBA DN 80 h 240.00 0.00 0.00 24.00 24.00 10.00% 216.00
02.01.02.03.09 REFINE Y NIVELACION FONDO DE ZANJA TN A= 0.60M m 4,976.34 0.00 0.00 744.52 744.52 14.96% 4,231.82
02.01.02.03.10 REFINE Y NIVELACION FONDO DE ZANJA TN A= 0.80M m 1,289.54 0.00 0.00 0.00 0.00 0.00% 1,289.54
02.01.02.03.11 CAMA DE ARENA MANUAL E=0.10M A= 0.60M m 4,976.34 0.00 0.00 744.52 744.52 14.96% 4,231.82
02.01.02.03.12 CAMA DE ARENA MANUAL E=0.10M A= 0.80M m 1,289.54 0.00 0.00 0.00 0.00 0.00% 1,289.54
02.01.02.03.13 RELLENO ZANJA MAT.PROPIO.COMPACT.C/EQUIPO A=0.60M H=1.20M - H=1.50M m 4,976.34 0.00 0.00 744.52 744.52 14.96% 4,231.82
02.01.02.03.14 RELLENO ZANJA MAT.PROPIO.COMPACT.C/EQUIPO A=0.80M H=1.51M - H=2.00M m 1,236.29 0.00 0.00 0.00 0.00 0.00% 1,236.29
02.01.02.03.15 RELLENO ZANJA MAT.PROPIO.COMPACT.C/EQUIPO A=0.80M H=2.01M - H=2.50M m 53.25 0.00 0.00 0.00 0.00 0.00% 53.25
02.01.02.03.16 ACARREO DE MATERIAL EXCEDENTE-C/EQUIPO m3 1,171.55 0.00 0.00 268.03 268.03 22.88% 903.52
02.01.02.03.17 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA 5 km m3 1,171.55 0.00 0.00 268.03 268.03 22.88% 903.52
02.01.02.04 PAVIMENTACION
02.01.02.04.01 PAVIMENTO FLEXIBLE
02.01.02.04.01.01 PERFILADO Y COMPACTACION DE SUBRASANTE m2 3,906.86 0.00 0.00 0.00 0.00 0.00% 3,906.86
02.01.02.04.01.02 SUB - BASE DE 0.15 m CON HORMIGON m2 3,906.86 0.00 0.00 0.00 0.00 0.00% 3,906.86
02.01.02.04.01.03 BASE CON AFIRMADO E=0.20M m2 3,906.86 0.00 0.00 0.00 0.00 0.00% 3,906.86
02.01.02.04.01.04 IMPRIMACION ASFALTICA m2 3,906.86 0.00 0.00 0.00 0.00 0.00% 3,906.86
02.01.02.04.01.05 CARPETA ASFALTICA EN FRIO DE 2" EN PARCHE m2 3,906.86 0.00 0.00 0.00 0.00 0.00% 3,906.86
02.01.02.04.01.06 BARRIDO Y LIMPIEZA PARA SELLADO m2 3,906.86 0.00 0.00 0.00 0.00 0.00% 3,906.86
02.01.02.04.01.07 SELLADO ASFALTICO m2 3,906.86 0.00 0.00 0.00 0.00 0.00% 3,906.86
02.01.02.04.01.08 BARRIDO DE ARENA SOBRANTE m2 3,906.86 0.00 0.00 0.00 0.00 0.00% 3,906.86
02.01.02.04.02 PAVIMENTO RIGIDO
02.01.02.04.02.01 BASE GRANULAR e = 0.20 m, EXTENDIDO, BATIDO, RIEGO Y COMPACTACION m2 626.25 0.00 0.00 0.00 0.00 0.00% 626.25
02.01.02.04.02.02 CONCRETO EN PAVIMENTO RIGIDO fc= 210 KGCM2, FROTACHADO e=0,20m m3 125.25 0.00 0.00 0.00 0.00 0.00% 125.25
02.01.02.04.02.03 ACERO DE TRANSFERENCIA DE CARGA LONGITUDINAL Y TRANSVERSAL (TIPO DOWELLS) kg 1,409.06 0.00 0.00 0.00 0.00 0.00% 1,409.06
02.01.02.04.02.04 ENCOFRADO Y DESENCOFRADO EN PAVIMENTO RIGIDO m2 334.30 0.00 0.00 0.00 0.00 0.00% 334.30
02.01.02.04.02.05 JUNTA DE CONTRACCION ASERRADA RELLENO CON POLIURETANO E=8MM m 835.00 0.00 0.00 0.00 0.00 0.00% 835.00
02.01.02.04.02.06 JUNTAS DE DILATACION ASFALTICAS E=1" m 1,395.00 0.00 0.00 0.00 0.00 0.00% 1,395.00
02.01.02.04.03 PAVIMENTO ADOQUINADO
02.01.02.04.03.01 DESMONTAJE Y REPOSICION DE ADOQUINES m2 166.31 0.00 0.00 0.00 0.00 0.00% 166.31
02.01.02.05 SUMINISTRO E INSTALACION TUBERIAS DE DESAGUE NTP ISO 21138
02.01.02.05.01 SUMINISTRO DE TUBERÍA PVC-U NTP ISO 4435 DN 200 SN4 INC. ANILLO m 6,265.88 0.00 0.00 744.52 744.52 11.88% 5,521.36
02.01.02.05.02 PRUEBA HIDR. NIVELACION, ALINEAMIENTO Y DEFLEXION. TUBERIA DN 200 MM m 6,265.88 0.00 0.00 744.52 744.52 11.88% 5,521.36
02.01.02.06 BUZONES /CAJAS DE INSPECCION (RED ALCANTARILLADO DOMESTICO)
02.01.02.06.01 BUZON Di=1.20M DESDE 1.20 MPP HASTA 1.50 MPP (Cemento Tipo-V) u 75.00 0.00 0.00 16.00 16.00 21.33% 59.00
02.01.02.06.02 BUZON Di=1.20M DESDE 1.51 MPP HASTA 2.00 MPP (Cemento Tipo-V) u 20.00 0.00 0.00 0.00 0.00 0.00% 20.00
02.01.02.06.03 DEMOLICION DE BUZONES EXISTENTES u 95.00 0.00 0.00 5.00 5.00 5.26% 90.00
02.01.02.07 CONCRETO SIMPLE
02.01.02.07.01 DADOS DE CONCRETO PARA TUBERIA PVC-U DN 200 u 190.00 0.00 0.00 35.00 35.00 18.42% 155.00
02.01.02.08 VARIOS
02.01.02.08.01 PRUEBA COMPACTACION SUELOS (PROCTOR MODIFICADO) u 150.00 0.00 0.00 5.00 5.00 3.33% 145.00
02.01.02.08.02 PRUEBA COMPACTACION SUELOS (DENSIDAD DE CAMPO) u 150.00 0.00 0.00 5.00 5.00 3.33% 145.00
02.01.02.08.03 PRUEBA DE CALIDAD DEL CONCRETO (PRUEBA A LA COMPRESION) u 75.00 0.00 0.00 5.00 5.00 6.67% 70.00
02.01.03 CONEXIONES DOMICILIARIAS ALCANTARILLADO
02.01.03.01 CONEXIONES DOM. ALCANTARILLADO TUB PVC ISO 21138 DN 160/200MM H=2,00M
02.01.03.01.01 RIEGO DE ZONA DE TRABAJO PARA MITIGAR LA CONTAMINACION - POLVO (CON AUTORIZACION DE USO DE GRIFO) m 3,942.00 0.00 0.00 160.00 160.00 4.06% 3,782.00
02.01.03.01.02 LIMPIEZA DURANTE LA EJECUCIÓN DE OBRA m 3,942.00 0.00 0.00 160.00 160.00 4.06% 3,782.00
02.01.03.01.03 TRAZO NIVELACION Y REPLANTEO CONEXION DOMIC. ALCANTARILLADO m 3,942.00 0.00 0.00 160.00 160.00 4.06% 3,782.00
02.01.03.01.04 EXCAVACION DE ZANJA MANUAL EN T.NORMAL SECCION 0.60 m. DE ANCHO Y H=1,20 m P/CONEX. DOMICIL. m 3,942.00 0.00 0.00 160.00 160.00 4.06% 3,782.00
02.01.03.01.05 REFINE, NIVELACION Y CONFORMACION DE FONDO DE ZANJA T. NORMAL P/CONEX. DOMICIL. 0.6m m 3,942.00 0.00 0.00 160.00 160.00 4.06% 3,782.00
02.01.03.01.06 CAMA DE ARENA MANUAL E=0.10M A= 0.60M m 3,942.00 0.00 0.00 160.00 160.00 4.06% 3,782.00
02.01.03.01.07 RELLENO Y COMPACTACION DE ZANJA CON MATERIAL PROPIO P/CONEX. DOMICIL, HASTA 1,20m m 3,942.00 0.00 0.00 160.00 160.00 4.06% 3,782.00
02.01.03.01.08 ACARREO DE MATERIAL EXCENTE-MANUAL DH = 30M (DISTANIA PROMEDIO m3 103.04 0.00 0.00 28.80 28.80 27.95% 74.24
02.01.03.01.09 ELIMINACION DE MATERIAL EXCEDENTE CON EQUIPO HASTA 5 km m3 103.04 0.00 0.00 28.80 28.80 27.95% 74.24
02.01.03.01.10 CONEXIÓN DOMICIL. ALCANTARILLADO TUBO PVC DN 160/200 MM T.N. L= 6,00M u 657.00 0.00 0.00 32.00 32.00 4.87% 625.00
02.01.03.01.11 PRUEBA Z ZANJA TAPADA Y DESINFECCION DE TUBERIA P/DESAGUE PVC UF DN160 SN4 m 3,942.00 0.00 0.00 160.00 160.00 4.06% 3,782.00
02.01.03.01.12 PRUEBA COMPACTACION SUELOS (DENSIDAD DE CAMPO) u 10.00 0.00 0.00 1.00 1.00 10.00% 9.00
02.01.03.01.13 LIMPIEZA FINAL DE OBRA m 3,942.00 0.00 0.00 160.00 160.00 4.06% 3,782.00
02.01.03.02 PAVIMENTACION EN CONEXIONES DOMICILIARIAS
02.01.03.02.01 PAVIMENTO FLEXIBLE
02.01.03.02.01.01 PERFILADO Y COMPACTACION DE SUBRASANTE m2 1,659.00 0.00 0.00 0.00 0.00 0.00% 1,659.00
02.01.03.02.01.02 SUB - BASE DE 0.15 m CON HORMIGON m2 1,659.00 0.00 0.00 0.00 0.00 0.00% 1,659.00
VALORIZACIÓN Nº 02 - SISTEMA DE ALCANTARILLADO SANITARIO
CONTROL DE METRADOS EJECUTADOS
(Del 01 de Junio al 30 de Junio del 2018)

METRADO METRADOS EJECUTADOS % SALDO


PARTIDA UND
BASE ANTERIOR MAYO ACTUAL ACUMULADO AVANCE METRADO
02.01.03.02.01.03 BASE CON AFIRMADO E=0.20M m2 1,659.00 0.00 0.00 0.00 0.00 0.00% 1,659.00
02.01.03.02.01.04 IMPRIMACION ASFALTICA m2 1,659.00 0.00 0.00 0.00 0.00 0.00% 1,659.00
02.01.03.02.01.05 CARPETA ASFALTICA EN FRIO DE 2" EN PARCHE m2 1,659.00 0.00 0.00 0.00 0.00 0.00% 1,659.00
02.01.03.02.01.06 BARRIDO Y LIMPIEZA PARA SELLADO m2 1,659.00 0.00 0.00 0.00 0.00 0.00% 1,659.00
02.01.03.02.01.07 SELLADO ASFALTICO m2 1,659.00 0.00 0.00 0.00 0.00 0.00% 1,659.00
02.01.03.02.01.08 BARRIDO DE ARENA SOBRANTE m2 1,659.00 0.00 0.00 0.00 0.00 0.00% 1,659.00
02.01.03.02.02 PAVIMENTO RIGIDO
02.01.03.02.02.01 BASE GRANULAR e = 0.20 m, EXTENDIDO, BATIDO, RIEGO Y m2 336.00 0.00 0.00 0.00 0.00 0.00% 336.00
02.01.03.02.02.02 CONCRETO EN PAVIMENTO RIGIDO fc=210 kg/cm2, FROTACHADO e=0,20 m3 67.20 0.00 0.00 0.00 0.00 0.00% 67.20
02.01.03.02.03 PAVIMENTO ADOQUINADO
02.01.03.02.03.01 DESMONTAJE Y REPOSICION DE ADOQUINES m3 45.00 0.00 0.00 0.00 0.00 0.00% 45.00
FORMULA POLINOMICA SISTEMA DE AGUA POTABLE

Obra: : "MEJORAMIENTO Y AMPLIACION DEL SERVICIO DE AGUA POTABLE Y ALCANTARILLADO SANITARIO EN EL C.P. MARIA DEL SOCORRO"

Propietario: PROGRAMA NACIONAL DE SANEAMIENTO URBANO


Contratista: CONSORCIO LA LIBERTAD.
Supervisor: Ingº ROBERTO OSCCO ROJAS
Fórmula 01: PRESUPUESTO BASE Monto contratado CON IGV= 7,287,403.73
Lugar: LA LIBERTAD - TRUJILLO - HUANCHACO Area Geográfica: 01 Costo a: FEBRERO 2017 Monto contratado SIN IGV= 6,175,765.87
Adelanto directo con IGV = 0.00
MONOMIO FACTOR INCID. % SIMBOLO INDICE DESCRIPCION Adelanto directo sin IGV = 0
1 0.280 0.280 100.000 J 47 MANO DE OBRA (INCLUIDO LEYES SOCIALES) Contratado Componente sin IGV 2,531,740.96
2 0.126 0.126 100.000 Tp 66 TUBERIA DE PVC PARA LA RED DE AGUA POTABLE Y ALCANTARILLADO Prorrateo del AD = 40.99% 0.00
3 0.094 0.094 100.000 C 21 CEMENTO PORTLAND TIPO I
4 0.055 0.055 100.000 Ag 05 AGREGADO GRUESO
5 0.051 0.051 100.000 Md 43 MADERA NACIONAL PARA ENCOFRADO Y CARPINTERIA
6 0.167 0.167 100.000 M 49 MAQUINARIA Y EQUIPO IMPORTADO
7 0.073 0.073 100.000 D 30 DÓLAR MAS INFLACION DEL MERCADO USA
8 0.154 0.154 100.000 GG 39 INDICE GENERAL DE PRECIOS AL CONSUMIDOR
1.000 1.000

K= 0.280 (Jr/Jo) + 0.126 (Tr/To) + 0.094 (Cr/Co) + 0.055 (Ar/Ao) + 0.051 (Mdr/Mdo) + 0.167 (Mir/Mio) + 0.073 (Dr/Do) + 0.154 (GGr/GGo)

CALCULO DE COEFICIENTES DE REAJUSTE


A.D. v1 (Mayo-2018) v2 (Jun. 2018) v3 (Jul. 2018) v4 (Ago. 2018) v5 (Set. 2018) v6 (Oct. 2018) v7 (Nov. 2018)
Feb-17 Apr-17 Apr-18 May-18 Jul-18 Aug-18 Sep-18 Oct-18 Nov-18
INDICE SIMBOLO FACTOR % INCIDENCIA
Ino Ina FACTOR Inr FACTOR Inr FACTOR Inr FACTOR Inr FACTOR Inr FACTOR Inr FACTOR Inr FACTOR
47 J 0.280 100.000 0.280 563.25 563.25 0.28000 582.52 0.28958 582.52 0.28958 - - - - -
66 Tp 0.126 100.000 0.126 684.04 684.04 0.12600 732.29 0.13489 735.57 0.13549 - - - - -
21 C 0.094 100.000 0.094 459.40 459.40 0.09400 476.04 0.09740 476.04 0.09740 - - - - -
05 Ag 0.055 100.000 0.055 449.52 449.52 0.05500 449.53 0.05500 450.97 0.05518 - - - - -
43 Md 0.051 100.000 0.051 716.35 716.35 0.05100 726.59 0.05173 718.60 0.05116 - - - - -
49 M 0.167 100.000 0.167 292.48 292.48 0.16700 295.18 0.16854 298.68 0.17054 - - - - -
30 D 0.073 100.000 0.073 461.46 461.46 0.07300 471.87 0.07465 478.04 0.07562 - - - - -
39 GG 0.154 100.000 0.154 443.37 443.37 0.15400 446.14 0.15496 445.61 0.15478 - - - - -
1.000 1.000 1.000 1.027 1.030 - - - - -
k base Ka K K K
Valorización programada 16,631.78 563,102.82 0.00 0.00 0.00 0.00 0.00
Valorización programada acumulada 16,631.78 579,734.60 579,734.60 579,734.60 579,734.60 579,734.60 579,734.60
Valorizacion Ejecutada 23,956.21 162,696.02 0.00 0.00 0.00 0.00 0.00
Valorización ejecutada acumulada 23,956.21 186,652.23 186,652.23 186,652.23 186,652.23 186,652.23 186,652.23
Reajuste programado V(K-1) 449.06 16,893.08 - - - - -
Reajuste ejecutado V(K-1) 646.82 4,880.88 - - - - -
Deductivo AD = (AD/MC) V(K/Ka-1) - - . - . - - - -
Reajuste deducido 646.82 4,880.88 - - - - -
Reajuste reconocido 646.82 16,893.08 - - - - -
Feb-17
Aug-17