ANEXO N° 04

CRONOGRAMA VALORIZADO DE EJECUCION DE OBRA POR PARTIDAS (PROGRAMADO - EJECUTADO)

PROGRAMADO EJECUTADO
ITEM DESCRIPCION COSTO
MES 1 MES 2 MES 3 MES 4 MES 1 MES 2 MES 3 MES 4 SALDO
DIRECTO
OBRAS
1
PROVISIONALES
CAMPAMENTO
1.01 PROVICIONAL DE 9,185.86 --------- --------- --------- --------- 0 2755.76
---------
OBRA
MOVILIZACION Y
1.02 DESMOVILIZACION 65,771.52 2,055.36 4,110.72 4110.72 4110.72 4,110.72 8,221.44 1,603.18 0.00 2,507.54
DE EQUIPOS
1.03 GUARDIANIA 54,000.00 4,500.00 2,250.00 2250 2250 4,500.00 4,500.00 4,500.00 0.00 ---------
CARTEL DE
1.04 2,744.28 --------- --------- --------- --------- 0 ---------
IDENTIFICACION ---------
HABILITACION DE
1.05 169,030.80 14,100.00 16,920.00 16920 27487 28,200.00 14,100.00 14,100.00 4,089.00 74,002.81
VIAS DE ACCESOS
TRABAJOS
2
PRELIMINARES
TRAZO, NIVELES Y
2.01 REPLANTEO (DIQUE 52,744.00 4,560.00 7,600.00 7600 7306.53 10,729.68 3,046.99 3,496.00 456.00 24,406.94
DE ENROCADOS)
LIMPIEZA DEL
2.02 4,459.00 780 520 520 196.56 520 582.868 133.69 39 486.85
TERRENO
MOVIMIENTO DE
3
TIERRAS
DESCOLMATACION
3.01 158,800.00 --------- 29,278.75 --------- 5620.61 --------- --------- 13,895.00 4,466.92 46,015.36
DE CAUCE DE RIO
CORTE DEL
3.02 TERRENO CON 221,339.43 27,370.00 27,370.00 27370 22194.22 38,564.33 10,588.20 23,497.56 1,102.62 52,582.52
MAQUINARIA
CONFORMACION DE
3.03 229,830.71 24,360.00 32,480.00 32480 29023.93 15,022.00 10,994.40 26,192.30 1,144.92 91,809.00
DIQUE
EXCAVACION DE
3.04 122,811.15 19,530.00 21,700.00 21700 13986 7,161.00 10,959.80 6,702.70 2,964.65 47,514.45
MATERIAL SUELTO
RELLENO DE FILTRO
3.05 251,232.92 48,030.00 48,030.00 48030 24605.13 --------- 27,564.74 20,940.92 820.83 129,374.57
PARA GEOTEXTIL
ENROCADO DE
4
DIQUE
EXTRACCION Y
4.01 PREPARACION DE 2,495,059.18 354,480.00 354,480.00 354480 354480 339,710.00 192,010.00 251,090.00 0.00 979,606.66
ROCAS
SELECCIÓN Y
4.02 ACOPIO DE ROCA EN 573,508.86 81,480.00 81,480.00 81480 74690 78,085.00 44,135.00 57,715.00 0.00 206,811.45
CANTERA
CARGUIO Y
TRANSPORTE DE
4.03 1,560,045.46 221,640.00 221,640.00 221640 221640 138,525.00 103,986.10 155,148.00 0.00 697,228.65
ROCA DESDE
CANTERA
COLOCACION DE
4.04 GEOTEXTIL NO 492,891.00 78,556.00 78,556.00 69359.2 51693.68 10,059.00 41,119.47 32,844.07 4,483.44 218,973.70
TEJIDO 400 GR/M2
4.05 ACOMODO DE ROCA 913,897.78 139,179.72 139,179.72 172920.83 140460.83 21,640.00 27,141.97 89,726.47 7,060.05 541,758.48
MITIGACION DE
5 IMPACTO
AMBIENTAL
MITIGACION DEL
5.01 66,588.17 7,990.58 7,990.58 7990.58 3329.41 3,995.29 6,259.29 7,324.70 7,175.50 6,392.46
IMPACTO AMBIENTAL
6 CAPACITACION
CAPACITACION EN
6.01 SEGURIDAD, SALUD 12,600.00 630 630 630 945 819 698.04 756 125.05 8,121.96
Y MEDIO AMBIENTE
CAPACITACION PARA
ARTICULAR LAS
6.02 ORGANIZACIONES Y 62,000.00 3,875.00 15,500.00 3875 26350 1,240.00 970.3 2,480.00 2,500.00 52,659.70
PRODUCTORES
PARA
7 LIQUIDACION
LIQUIDACION DE
7.01 20,000.00 --------- --------- --------- --------- 0 20,000.00
OBRA
…………………..
TOTAL COSTO
7,538,540.12 1,033,116.66 1,305,100.89 1,078,632.66 1,059,377.79 702,881.02 506,878.61 712,145.59 36,427.99 3,188,707.11
DIRECTO
GASTOS
GENERALES 527,697.81 72,318.17 91,357.06 75,504.29 74,156.45 49,201.67 35,481.50 49,850.19 2,549.96 223,209.50
7%
SUPERVISION
316,618.69 43,390.90 54,814.24 45,302.57 44,493.87 29,521.00 21,288.90 29,910.11 1,529.98 133,925.70
4.2 %
PRESUPUESTO
8,382,856.61 1,148,825.72 1,451,272.18 1,199,439.52 1,178,028.10 781,603.69 563,649.01 791,905.89 40,507.93 3,545,842.31
TOTAL