COMPARATIVO DE SUMINISTRO DE CONCRETO

PROYECTO: EDIFICIO THU


CLIENTE: VERAMAR AZUL PERU S.A.C
CONTRATISTA: V Y V BRAVO S.A.C.
FECHA: 11/4/2022
RESPONSABLE: ING. LUCIA CÓRDOVA T.C.: 3.85

PRESUPUESTO UNICON MIXERCON


DESCRIPCIÓN Und Cant. %Desp. m3 + % PU S/. Parcial S/. Und Cant. PU S/. Parcial S/. Und Cant. PU S/. Parcial S/.
S/. S/. S/.
1.00 SUMINISTRO DE CONCRETO

FALSA ZAPATA
CONCRETO EN SUBZAPATAS CEMENTO TIPO I F'C=210 KG/CM2 +30%PG m3 20.72 282.1497 5,844.73 282.15 1,649,089.11 M2 336.15 227.15 76,356.85 M2 336.15 225.00 75,634.13
CALZADURA - - - M3 176.17 227.15 40,017.81 M3 176.17 225.00 39,639.04
CONCRETO EN SUBZAPATAS CEMENTO TIPO I F'C=100 KG/CM2 +30%PG m3 49.14 282.1497 13,864.84 282.15 3,911,959.39 - - - -
CONCRETO ARMADO - SOT - - - - - -
CIMIENTOS DE MURO PANTALLA - - - - - - -
CONCRETO PREMEZCLADO CIMIENTOS DE PANTALLA f'c=210 kg/cm2 CON SERVICIO DE BOMBA m3 98.48 468.87 46,174.36 468.87 21,649,789.23 M3 171.59 280.82 48,185.77 M3 171.59 286.00 49,074.61
MUROS ANCLADOS - - - - - - -
CONCRETO PREMEZCLADO MURO PANTALLA f'c=210 kg/cm2 A 3 DIAS CON SERVICIO DE BOMBA (se m3 218.19 610.1592 133,130.64 610.16 81,230,882.26 M3 402.57 280.82 113,050.79 M3 402.57 286.00 115,136.12
utilizará concreto f´c = 350 kg/cm2)
CONCRETO PREMEZCLADO ULTIMO ANILLO f'c=280 kg/cm2 m3 97.24 576.6572 56,074.15 576.66 32,335,560.10 - - - -
CONCRETO PREMEZCLADO,CEMENTO TIPO I,EN CACHIMBAS f'c=210 kg/cm2 A 3 DIAS CON SERVICIO m3 56.64 488.8842 27,690.40 488.88 13,537,399.58 - - - -
DE BOMBA
ZAPATAS - - - M3 140.80 284.95 40,122.19 M3 140.80 292.00 41,114.86
CONCRETO PREMEZCLADO ZAPATAS f'c=210 kg/cm2 m3 137.29 326.3946 44,810.71 326.39 14,625,975.28 - - - -
CIMIENTOS ARMADOS - - M3 327.29 322.00 105,387.99 M3 327.29 304.00 99,496.74
CONCRETO PREMEZCLADO CISTERNA f'c=210 kg/cm2 CON SERVICIO DE BOMBA m3 29.74 326.3946 9,706.98 326.39 3,168,304.35 - - - -
VIGA DE CIMENTACION - - M3 561.07 284.95 159,876.58 M3 561.07 292.00 163,832.12
CONCRETO PREMEZCLADO VIGA DE CIMENTACION f'c=210 kg/cm2 m3 21.84 342.027 7,469.87 342.03 2,554,897.12 - - - -
CIMIENTOS Y SOBRECIMIENTOS TABIQUERIA - - M3 690.55 284.95 196,772.33 M3 690.55 292.00 201,640.71
CONCRETO PREMEZCLADO CIMIENTOS f'c=210 kg/cm2 m3 18.60 326.3946 6,070.94 326.39 1,981,521.89 - - - -
LOSA SOBRE TERRENO - - M3 544.93 280.82 153,026.20 M3 544.93 286.00 155,848.92
CONCRETO PREMEZCLADO PARA LOSA DE PISO F'C=210 m3 74.31 326.3946 24,254.38 326.39 7,916,499.55 M3 244.07 255.02 62,243.30 M3 244.07 250.00 61,018.06
PIT DE ASCENSOR - - M3 267.77 280.82 75,193.98 M3 267.77 286.00 76,581.00
CONCRETO PREMEZCLADO PARA LOSA DE PISO f´c= 280 kg/cm2 m3 1.35 384.0795 518.51 384.08 199,148.03 M3 - - M3 - -
CISTERNA - - - - - -
CONCRETO PREMEZCLADO CISTERNA f'c=280 kg/cm2 CON SERVICIO DE BOMBA m3 118.73 384.0795 45,601.76 384.08 17,514,700.81 M3 39.63 255.02 10,106.08 M3 39.63 250.00 9,907.14
CISTERNA (PISO) - - M3 - - M3 - -
CONCRETO PREMEZCLADO CISTERNA f'c=280 kg/cm2 CON SERVICIO DE BOMBA m3 25.74 384.0795 9,884.48 384.08 3,796,425.36 - - - -
CORTE MURO - - M3 14.02 255.02 3,574.74 M3 14.02 250.00 3,504.38
CONCRETO PREMEZCLADO PLACAS f'c=210 kg/cm2 m3 47.08 384.0795 18,082.46 384.08 6,945,103.29 - - - -
PLACAS - - M3 1,203.32 255.02 306,870.92 M3 1,203.32 250.00 300,830.25
CONCRETO PREMEZCLADO PLACAS f'c=350 kg/cm2 m3 7.19 404.6051739 2,909.11 404.61 1,177,041.44 - - - -
CONCRETO PREMEZCLADO PLACAS f'c=280 kg/cm2 m3 67.22 379.4786739 25,508.56 379.48 9,679,953.18 M3 - - M3 - -
COLUMNAS - - - - - -
CONCRETO COLUMNAS f'c=210 kg/cm2 m3 - 317.98 - 317.98 - M3 299.91 255.02 76,484.07 M3 299.91 250.00 74,978.51
CONCRETO COLUMNAS f'c=280 kg/cm2 m3 39.18 379.4786739 14,867.97 379.48 5,642,079.23 - - - -
VIGAS Y CORTES - - M3 - - M3 - -
CONCRETO VIGAS f'c=210 kg/cm2 m3 92.26 355.16586 32,768.49 355.17 11,638,248.99 - - - -
PRELOSA ALIGERADA H=20 cm (1 DIRECCION) - - - - - -
CONCRETO PRELOSAS f'c= 210 kg/cm2 m3 65.30 355.16586 23,193.69 355.17 8,237,606.14 M3 162.91 333.45 54,321.58 M3 162.91 324.00 52,782.10
PRELOSA ALIGERADA H=25 CM - - - - - -
CONCRETO PRELOSAS f'c= 210 kg/cm2 m3 91.03 355.16586 32,331.07 355.17 11,482,891.63 M3 84.59 255.02 21,572.97 M3 84.59 250.00 21,148.31
PRELOSA MACIZA H=18 CM - - M3 - - M3 - -
CONCRETO PRELOSAS f'c=210 kg/cm2 m3 40.72 355.16586 14,461.98 355.17 5,136,402.01 - - - -
PRELOSA MACIZA H=20 CM - - M3 1.44 255.02 367.91 M3 1.44 250.00 360.67
CONCRETO PRELOSAS f'c= 210 kg/cm2 m3 35.07 355.16586 12,456.18 355.17 4,424,009.22 - - - -
PRELOSA MACIZA H=15 CM - - M3 1.58 333.45 527.98 M3 1.58 324.00 513.02
CONCRETO PRELOSAS f'c=210 kg/cm2 m3 0.80 355.16586 285.06 355.17 101,242.20 - - - -
ESCALERAS - - M3 12.68 333.45 4,227.09 M3 12.68 324.00 4,107.29
CONCRETO ESCALERAS f´c=210 kg/cm2 m3 13.04 359.132413 4,683.09 359.13 1,681,848.21 - - - -
BASE DE EQUIPOS - - M3 10.83 284.95 3,085.47 M3 10.83 292.00 3,161.81
CONCRETO PREMEZCLADO f´c=210 kg/cm2 m3 5.06 384.0795 1,944.40 384.08 746,805.13 - - - -
CONCRETO PREMEZCLADO F'C=280 KG/CM2 PARA MURO DE CERCO M3 - - - M3 - - M3 - -
PLACAS - -
CONCRETO PREMEZCLADO PLACAS f'c=210 kg/cm2 m3 251.72 353.4806739 88,978.16 353.48 31,452,058.28
CONCRETO PREMEZCLADO PLACAS f'c=280 kg/cm2 m3 291.35 379.4786739 110,561.11 379.48 41,955,584.03
CONCRETO PREMEZCLADO PLACAS f'c=350 kg/cm2 m3 5.85 404.6051739 2,366.94 404.61 957,676.28
CONCRETO PREMEZCLADO PLACAS f'c=420 kg/cm2 m3 11.70 420.3551739 4,918.16 420.36 2,067,372.13
COLUMNAS - -
CONCRETO COLUMNAS f'c=210 kg/cm2 m3 34.30 353.4806739 12,124.74 353.48 4,285,861.48
CONCRETO COLUMNAS f'c=280 kg/cm2 m3 28.84 379.4786739 10,944.16 379.48 4,153,077.20
VIGAS y CORTES - -
CONCRETO VIGAS f'c=210 kg/cm2 m3 480.44 355.16586 170,634.11 355.17 60,603,410.41
CONCRETO ARMADO - TOR - -
PRELOSA ALIGERADA H=20 cm - -
CONCRETO PRELOSAS f'c= 210 kg/cm2 m3 302.94 355.16586 107,595.39 355.17 38,214,210.85
PRELOSA MACIZA H=15 cm - -
CONCRETO PRELOSAS f'c= 210 kg/cm2 m3 1.45 355.16586 513.57 355.17 182,402.47
PRELOSA MACIZA H=18 CM - -
CONCRETO PRELOSAS f'c= 210 kg/cm2 m3 59.71 355.16586 21,208.27 355.17 7,532,451.72
PRELOSA MACIZA H=20 cm - -
CONCRETO PRELOSAS f'c=210 kg/cm2 m3 83.76 355.16586 29,749.99 355.17 10,566,181.61
ESCALERAS - -
CONCRETO ESCALERAS f´c=210 kg/cm2 m3 24.59 359.132413 8,831.07 359.13 3,171,522.06
MUROS DE CONCRETO EN PISCINA Y JARDINERIA - -
CONCRETO PREMEZCLADO, CEMENTO TIPO I, MUROS EN PISCINA DE CONCRETO f'c=210 kg/cm2 m3 41.75 351.7815 14,686.88 351.78 5,166,571.84
SOBRELOSA EN AREA DE PISCINA - -
CONCRETO PREMEZCLADO, CEMENTO TIPO I, MUROS EN PISCINA DE CONCRETO f'c=210 kg/cm2 m3 5.14 359.132413 1,845.94 359.13 662,937.10
BASES DE EQUIPOS - -
CONCRETO PREMEZCLADO f´c=210 kg/cm2 m3 4.50 384.0795 1,728.36 384.08 663,826.78

-
DESCRIPCIÓN UND METRADO
EJECUCIÓN DE PISTA H=20cm RIMAC
CONCRETO PREMEZCLADO PISTA f'c=210 kg/cm2 m3 60
ENCOFRADO DE LOSA PARA VACIADO m2 300
CURADO DE PISO M2 300
A.P.U PARCIAL

S.461.44 S.27,686.31
S.17.86 S.5,358.00
S.1.33 S.399.00
S.33,443.31

.
Análisis de precios unitarios

Partida CONCRETO PREMEZCLADO LOSA DE PISO f'c=210 kg/cm2


Rendimiento m3/DIA 24 Costo unitario directo
Código Descripción Recurso Cuadrilla Cantidad
Mano de Obra 2
0101010002 CAPATAZ hh 0 0
0101010003 OPERARIO hh 7 0.33
0101010004 OFICIAL hh 1 0.33
0101010005 PEON hh 4 1.33

Materiales
0207070002 210N57B m3 1.05

Equipos
0301010006 HERRAMIENTAS MANUALES %mo 0.05

Partida ENCOFRADO DE LOSA PARA VACIADO DE PISO


Rendimiento ml/día 40 Costo unitario directo
Código Descripción Recurso Cuadrilla Cantidad
Mano de Obra 0.4
0101010002 CAPATAZ hh 0 0
0101010003 OPERARIO hh 1 0.2
0101010004 OFICIAL hh 0 0
0101010005 PEON hh 1 0.2

Materiales
0207070002 CLAVOS kg 0.17
0207070002 ADITIVO DESMOLDANTE gl 0.00
0207070002 MADERA TORNILLO p2 1.1

Equipos
0301010006 HERRAMIENTAS MANUALES %mo 0.03
0301010006 CORTADORA DE CONCRETO %mo 0.03

Partida VACIADO DE LOSA DE PISO


Rendimiento ml/día 40 Costo unitario directo
Código Descripción Recurso Cuadrilla Cantidad
Mano de Obra 0.4
0101010002 CAPATAZ hh 0 0
0101010003 OPERARIO hh 1 0.2
0101010004 OFICIAL hh 0 0
0101010005 PEON hh 1 0.2

Materiales
0207070002 CLAVOS kg 0.17
0207070002 ADITIVO DESMOLDANTE gl 0.00
0207070002 MADERA TORNILLO p2 1.1

Equipos
0301010006 HERRAMIENTAS MANUALES %mo 0.03
0301010006 CORTADORA DE CONCRETO %mo 0.03
to unitario directo 461.44
Precio S/. Parcial S/.

31.7625 0
25.41 8.47
19.74 6.58
17.85 23.8
57.85

382.52 401.65

401.65

38.85 1.94
1.94

to unitario directo 17.36


Precio S/. Parcial S/.

31.7625 0
25.41 5.082
19.74 0
17.85 3.57
8.65

4.12 0.69
457.54 1.53
4.4 4.84
7.05

8.65 0.26
56 1.4
1.66

to unitario directo 17.36


Precio S/. Parcial S/.
31.7625 0
25.41 5.082
19.74 0
17.85 3.57
8.65

4.12 0.69
457.54 1.53
4.4 4.84
7.05

8.65 0.26
56 1.4
1.66
Partida 01.04.01.04 CURADO DE ELEMENTOS ESTRUCTURALES EXPUESTOS
Rendimiento m2/DIA MO. 450.0000 EQ. 450.0000

Código Descripción Recurso


Mano de Obra
0101010005 PEON

Materiales
02221800010015 ADITIVO CURADOR DE CONCRETO (20 L)

Equipos
0307090013 APLICADOR DE MOCHILA (ASPERSOR)
03080100010001 HERRAMIENTAS MANUALES
Costo unitario directo por : m2 1.33

Unidad Cuadrilla Cantidad Precio S/ Parcial S/

hh 1.0000 0.0178 17.15 0.31


0.31

gal 0.0090 111.00 1.00


1.00

hm 1.0000 0.0178 0.56 0.01


%mo 3.0000 0.31 0.01
0.02