PROYECCION DE REQUERIMIENTOS EN FUNCION AL PIA+PIM 2022 - S/. 2,234.146.

00 SOLES

OBRA : "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR DE LA CARRETERA TRAMO ACHAYA (PU-140) - ESTRELLA (EMP. PE - 3S) DEL DISTRITO DE ACHAYA - PROVINCIA DE
AZANGARO - DEPARTAMENTO DE PUNO "

CUADRO DE NECESIDADES - PLANILLAS - BIENES - SERVICIOS - SUPERVISION (PLANILLAS, BIENES Y SERVICIOS) EJERCICIO
FISCAL AÑO 2022

CUI: 2440946 - META: 0210

PERIODO VALOR
II TRIMESTRE III TRIMESTRE IV TRIMESTRE

ESPECIFICA DE UNIDAD TOTAL UNITARIO


DE N OMINACION
GASTO MEDIDA NECESI-DAD SEGÚN
ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE TOTAL (S/.)
EXPEDIENTE
TECNICO (S/.)

PLANILLA
2.6.23.24 PERSONAL U.M. 187,901.25

2.6.23.24 PLANILLA DE HABERES CORRESPONDIENTE COSTO DIRECTO PLLA 34,100 34,100 34,100 102,301.25 1.00 102,301.25

2.6.23.24 PLANILLA DE HABERES CORRESPONDIENTE GASTOS GENERALES PLLA 28,533 28,533 28,533 85,600.00 1.00 85,600.00

BIENES
2.6.23.25 MATERIALES U.M. 62,187.50
2.6.23.25 CEMENTO PORTLAND TIPO IP (42.5KG) BOLSA - 800.00 500.00 - - - 1,300.00 23.00 29,900.00

2.6.23.25 ACERO CORRUGADO fy = 4200 kg/cm2 GRADO 60° KG 2,348.10 2,348.10 6.00 14,088.60

2.6.23.25 ALCANTARILLA TMC Ø 36" (PARA ALCANTARILLA) UND 38.00 - - - - - 38.00 30.00 1,140.00

2.6.23.25 TRYPLAY TIPO LUPUNA 6 MM 1.22X2.44M PLANCHA 12.00 - - - - - 12.00 42.00 504.00

2.6.23.25 MADERA TORNILLO P2 987.00 987.00 5.50 5,428.50

2.6.23.25 CURADOR DE CONCRETOBALDE 4LTS UND 1.00 - - - - - 1.00 43.14 43.14

7.6.23.25 AGREGADO GRUESO PARA CONCRETO FC=210 M3 - 109.58 - - - - 109.58 50.00 5,479.12

2.6.23.25 AGREGADO FINO PARA CONCRETO FC= 210 M3 - 76.39 - - - - 76.39 50.00 3,819.61

5.6.23.25 TECNOPOR 3/4" M2 24.91 - - - - - 24.91 1.97 49.07

5.6.23.25 CLAVO DE ACERO 2 1/2" KILOGRAMO 10.00 - - - - - 10.00 6.90 69.00

5.6.23.25 CLAVO DE ACERO 2" KILOGRAMO 40.00 - - - - - 40.00 7.00 280.00

5.6.23.25 CLAVO DE ACERO 3" KILOGRAMO 30.00 - - - - - 30.00 5.00 150.00

5.6.23.25 CLAVO DE ACERO 4" KILOGRAMO 30.00 - - - - - 30.00 9.00 270.00

2.6.23.25 ALAMBRE NEGRO N° 16 KILOGRAMO 113.00 - - - - - 113.00 5.50 621.50

2.6.23.25 ALAMBRE NEGRO N° 08 KILOGRAMO 51.00 - - - - - 51.00 5.50 280.50

2.6.23.25 PINTURA, ESMALTE SINTETICO GALON 2.00 - - - - - 2.00 32.23 64.46

2.6.23.25 HERRAMIENTAS U.M. 3,888.98


PROYECCION DE REQUERIMIENTOS EN FUNCION AL PIA+PIM 2022 - S/. 2,234.146.00 SOLES

OBRA : "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR DE LA CARRETERA TRAMO ACHAYA (PU-140) - ESTRELLA (EMP. PE - 3S) DEL DISTRITO DE ACHAYA - PROVINCIA DE
AZANGARO - DEPARTAMENTO DE PUNO "

CUADRO DE NECESIDADES - PLANILLAS - BIENES - SERVICIOS - SUPERVISION (PLANILLAS, BIENES Y SERVICIOS) EJERCICIO
FISCAL AÑO 2022

CUI: 2440946 - META: 0210

PERIODO VALOR
II TRIMESTRE III TRIMESTRE IV TRIMESTRE

ESPECIFICA DE UNIDAD TOTAL UNITARIO


DE N OMINACION
GASTO MEDIDA NECESI-DAD SEGÚN
ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE TOTAL (S/.)
EXPEDIENTE
TECNICO (S/.)

2.6.23.25 WINCHA DE NYLON DE 50 MTS UNIDAD 3.00 3.00 50.00 150.00


2.6.23.25 FLEXOMETRO DE 10 MTS UNIDAD 5.00 5.00 57.50 287.50
2.6.23.25 BOMBA MANUAL UNIDAD 1.00 1.00 135.90 135.90
2.6.23.25 ALICATE UNIVERSAL DE 7" UNIDAD 5.00 5.00 21.90 109.50
2.6.23.25 MARTILLO CON MANGO DE MADERA UNIDAD 5.00 5.00 25.90 129.50
2.6.23.25 ARCO DE SIERRA DE 12 " UNIDAD 2.00 2.00 80.00 160.00
2.6.23.25 AMOLADORA ELECTRICA 7" UNIDAD 2.00 2.00 175.90 351.80
2.6.23.25 SERRUCHO DE CARPINTERO CON MANGO DE MADERA UNIDAD 2.00 2.00 21.90 43.80

2.6.23.25 BOMBA INYECTADORA GRASA CON CUBETA 24KG 16850 TRUPER UNIDAD 1.00 1.00 625.00 625.00

2.6.23.25 REGLA DE ALUMINIO 1 1/2" X 3" X 6 MTS UNIDAD 1.00 1.00 16.16 16.16
2.6.23.25 BARRETA DE ACERO 1 1/4" X 1.75 MTS DE 11KG UNIDAD 1.00 1.00 78.00 78.00
PROYECCION DE REQUERIMIENTOS EN FUNCION AL PIA+PIM 2022 - S/. 2,234.146.00 SOLES

OBRA : "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR DE LA CARRETERA TRAMO ACHAYA (PU-140) - ESTRELLA (EMP. PE - 3S) DEL DISTRITO DE ACHAYA - PROVINCIA DE
AZANGARO - DEPARTAMENTO DE PUNO "

CUADRO DE NECESIDADES - PLANILLAS - BIENES - SERVICIOS - SUPERVISION (PLANILLAS, BIENES Y SERVICIOS) EJERCICIO
FISCAL AÑO 2022

CUI: 2440946 - META: 0210

PERIODO VALOR
II TRIMESTRE III TRIMESTRE IV TRIMESTRE

ESPECIFICA DE UNIDAD TOTAL UNITARIO


DE N OMINACION
GASTO MEDIDA NECESI-DAD SEGÚN
ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE TOTAL (S/.)
EXPEDIENTE
TECNICO (S/.)

2.6.23.25 PALA TIPO CUCHARA CON MANGO DE MADERA UNIDAD 5.00 5.00 35.00 175.00
2.6.23.25 RASTRILLO DE 12 DIENTES UNIDAD 5.00 5.00 26.00 130.00
2.6.23.25 BUGGIES UNIDAD 5.00 5.00 195.00 975.00
2.6.23.25 COMBO DE 20 LIBRAS CON MANGO DE MADERA UNIDAD 1.00 1.00 155.00 155.00
2.6.23.25 COMBO DE 10 LIBRAS CON MANGO DE MADERA UNIDAD 1.00 1.00 46.82 46.82
2.6.23.25 CIZALLA DE 12" UNIDAD 2.00 2.00 60.00 120.00
2.6.23.25 CIZALLAS DE 18" UNIDAD 2.00 2.00 100.00 200.00

2.6.23.25 SUMINISTROS Y COMBUSTIBLES U.M. 342,243.20


2.6.23.25 DIESEL B5 S50 GALON 5,000 6,000 6,000 5,000 22,000.00 15.50 341,000.00
2.6.23.25 GASOLINA DE 84 OCT GALON 74.00 74.00 16.80 1,243.20

2.6.23.25 MEDICAMENTOS Y PREVENCION COVID U.M. 3,789.60


PULSIOMETRO (OXIMETRO DE PULSO) DIGITAL RANGO DE MEDICION:35%
2.6.23.25 UNIDAD 2.00 - - - - - 2.00 93.50 187.00
- 100%, PRESICION -+ 2bpm O+- 2%
TERMOMETRO INFRARROJO DIGITAL UNIDADES DE TEMPERATURA °C/°F,
2.6.23.25 UNIDAD 2.00 - - - - - 2.00 135.00 270.00
RESOLUCION:0,1 °C, PRESICION: +-1%
LEJIA AL 5% CONCENTRACION DE HIPOCLORITO DE SODIO - BOTELLA DE
2.6.23.25 UNIDAD 10.00 - - - - - 10.00 5.00 50.00
639 ML

2.6.23.25 MASCARILLA DESCARTABLE DE TRES PLIEGUES X50 UND CAJA 3.00 - - - - - 3.00 10.00 30.00

2.6.23.25 MASCARILLA COMUNITARIA SEGUN RM-135-2020 MINSA UNIDAD 50.00 - - - - - 50.00 4.50 225.00

BOLSAS DE POLIETILENO PARA BASURA DE 50 L PAQUETE DE 10


2.6.23.25 UNIDAD 10.00 - - - - - 10.00 5.10 51.00
UNIDADES

2.6.23.25 JABON LIQUIDO DE TOCADOR CON DISPENSADOR - ENVASE DE 400ML. UNIDAD 35.00 - - - - - 35.00 9.50 332.50

2.6.23.25 TRAPEADOR DE YUTE CON OJALAS DE 56 CM X 80CM UNIDAD 3.00 - - - - - 3.00 7.70 23.10

2.6.23.25 PAPEL TOALLA ECOLOGICO - ROLLO X106 HOJAS UNIDAD 20.00 - - - - - 20.00 2.90 58.00

2.6.23.25 PAÑO SECADOR DE MICROFIBRAS 30CM X 38XM UNIDAD 5.00 - - - - - 5.00 6.00 30.00

2.6.23.25 ALCOHOL 96% - BOTELLA DE 500ML UNIDAD 10.00 - - - - - 10.00 8.50 85.00

2.6.23.25 FRASCO CON ATOMIZADOR /PULVERIZADOR DE 500ML UNIDAD 10.00 - - - - - 10.00 5.90 59.00

2.6.23.25 GEL HIDROALCOHOLICO CONCENTRACION 70% - ENVASE 400 ML UNIDAD 11.00 - - - - - 11.00 12.00 132.00

2.6.23.25 PAR DE GUANTES DE LATEX PARA LIMPIEZA PAR 20.00 - - - - - 20.00 6.00 120.00

CARPA A 2 AGUAS EN LINO PLASTIFICADO MEDIDA:3m x 3m ESTRUCTURA


2.6.23.25 UNIDAD 3.00 - - - - - 3.00 320.00 960.00
DE TUBO REDONDO 1 1/4"

2.6.23.25 MESA DE MADERA DE 80 X 60 X 70 CM UNIDAD 4.00 - - - - - 4.00 115.00 460.00

2.6.23.25 SILLA DE PLASTICO DE 46.7 CM DE ANCHO DE ASIENTO UNIDAD 20.00 - - - - - 20.00 26.00 520.00
PROYECCION DE REQUERIMIENTOS EN FUNCION AL PIA+PIM 2022 - S/. 2,234.146.00 SOLES

OBRA : "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR DE LA CARRETERA TRAMO ACHAYA (PU-140) - ESTRELLA (EMP. PE - 3S) DEL DISTRITO DE ACHAYA - PROVINCIA DE
AZANGARO - DEPARTAMENTO DE PUNO "

CUADRO DE NECESIDADES - PLANILLAS - BIENES - SERVICIOS - SUPERVISION (PLANILLAS, BIENES Y SERVICIOS) EJERCICIO
FISCAL AÑO 2022

CUI: 2440946 - META: 0210

PERIODO VALOR
II TRIMESTRE III TRIMESTRE IV TRIMESTRE

ESPECIFICA DE UNIDAD TOTAL UNITARIO


DE N OMINACION
GASTO MEDIDA NECESI-DAD SEGÚN
ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE TOTAL (S/.)
EXPEDIENTE
TECNICO (S/.)

2.6.23.25 BALDE DE PLASTICO CON 13 L CON PICO Y ASA UNIDAD 5.00 - - - - - 5.00 12.50 62.50
2.6.23.25 BALDE DE PLASTICO CON CAÑO DE 20 L CON ASA Y TAPA UNIDAD 5.00 - - - - - 5.00 26.90 134.50

2.6.23.25 SEÑALIZACION Y SEGURIDAD U.M. 2,604.41


PROYECCION DE REQUERIMIENTOS EN FUNCION AL PIA+PIM 2022 - S/. 2,234.146.00 SOLES

OBRA : "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR DE LA CARRETERA TRAMO ACHAYA (PU-140) - ESTRELLA (EMP. PE - 3S) DEL DISTRITO DE ACHAYA - PROVINCIA DE
AZANGARO - DEPARTAMENTO DE PUNO "

CUADRO DE NECESIDADES - PLANILLAS - BIENES - SERVICIOS - SUPERVISION (PLANILLAS, BIENES Y SERVICIOS) EJERCICIO
FISCAL AÑO 2022

CUI: 2440946 - META: 0210

PERIODO VALOR
II TRIMESTRE III TRIMESTRE IV TRIMESTRE

ESPECIFICA DE UNIDAD TOTAL UNITARIO


DE N OMINACION
GASTO MEDIDA NECESI-DAD SEGÚN
ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE TOTAL (S/.)
EXPEDIENTE
TECNICO (S/.)

2.6.23.25 CHALECOS DE SEGURIDAD UNIDAD 7.00 7.00 10.96 76.72


2.6.23.25 BANDERINES UNIDAD 2.00 2.00 5.29 10.58
2.6.23.25 TRANQUETAS UNIDAD 3.00 3.00 5.00 15.00
2.6.23.25 LETREROS, AVISOS DE TRANSITO UNIDAD 6.00 6.00 134.54 807.24
2.6.23.25 CILINDRO DE SEGURIDAD REFLECTIVO UNIDAD 5.00 5.00 181.79 908.95
2.6.23.25 LUZ DE BARRINCADA A BATERIA 6V UNIDAD 4.00 4.00 123.49 493.96
2.6.23.25 TACHAS DELINEADORAS BIDIRECCIONALES UNIDAD 2.00 2.00 6.54 13.08
2.6.23.25 CONOS DE SEÑALIZACIÓN DE 28" Y 7 lm UNIDAD 6.00 6.00 46.48 278.88

2.6.2.3.2.5 VESTUARIO DE PERSONAL - GATOS GENERALES U.M. 9,127.00


2.6.23.25 CASCOS DE SEGURIDAD PARA PERSONAL OBRERO UND 18.00 18.00 35.00 630.00
2.6.23.25 CASCOS DE SEG. PARA PROFESIONALES ,TECNICOS, AUXILIARES UND 6.00 6.00 50.00 300.00
2.6.23.25 BOTAS DE JEBE PAR 15.00 15.00 37.40 561.00
2.6.23.25 GUANTES DE CUERO PAR 10.00 10.00 8.00 80.00
2.6.23.25 CHALECOS DE SEGURIDAD CON CINTA REFLECTORA UND 20.00 20.00 30.00 600.00
2.6.23.25 CORTAVIENTO UND 20.00 20.00 7.00 140.00
2.6.23.25 LENTES TRANSPARENTES DE PROTECCION (3M) UND 6.00 6.00 20.00 120.00

2.6.23.25 CASACAS PARA PERSONAL PROFESIONAL, TECNICOS, AUXILIAR UND 18.00 18.00 40.00 720.00

2.6.23.25 CHALECOS PARA PERSONAL PROFESIONAL, TECNICOS, AUXLI. UND 20.00 20.00 20.00 400.00
2.6.23.25 MAMELUCO UND 20.00 20.00 40.00 800.00
2.6.23.25 PROTECTOR DE RUIDO (OREJERAS) UND 4.00 4.00 46.50 186.00
2.6.23.25 GUANTES DE JEBE PAR 20.00 20.00 10.00 200.00
2.6.23.25 ZAPATOS DE SEGURIDAD PARA PERSONAL OBRERO UND 20.00 20.00 80.00 1,600.00

2.6.23.25 ZAPATOS DE SEGURIDAD PROFESIONAL, TECNICOS, AUXILIAR UND 6.00 6.00 400.00 2,400.00

2.6.23.25 LENTES DE SEGURIDAD UND 25.00 25.00 10.00 250.00


2.6.23.25 MASCARA PROTECTOR DE POLVO UND 4.00 4.00 35.00 140.00

2.6.23.25 UTILES DE ESCRITORIO U.M. 846.20


2.6.23.25 CUADERNO DE OBRA AUTOCOPIATIVO DE 100 FOLIOS UND 2.00 2.00 57.00 114.00
2.6.23.25 BORRADOR UND 6.00 6.00 2.00 12.00
2.6.23.25 CUADERNO A4 CUADRICULADO X 100 HOJAS UND 7.00 7.00 6.00 42.00
2.6.23.25 FOLDER MANILA A-4 UND 34.00 34.00 0.50 17.00
2.6.23.25 LIBRETA TOPOGRAFICA UND 3.00 3.00 5.00 15.00
2.6.23.25 ESCALIMETRO UND 1.00 1.00 13.10 13.10
2.6.23.25 PLUMONES UND 12.00 12.00 2.00 24.00
2.6.23.25 SELLOS UND 5.00 5.00 25.00 125.00
2.6.23.25 CINTA MASKINTAPE UND 5.00 5.00 2.50 12.50
PROYECCION DE REQUERIMIENTOS EN FUNCION AL PIA+PIM 2022 - S/. 2,234.146.00 SOLES

OBRA : "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR DE LA CARRETERA TRAMO ACHAYA (PU-140) - ESTRELLA (EMP. PE - 3S) DEL DISTRITO DE ACHAYA - PROVINCIA DE
AZANGARO - DEPARTAMENTO DE PUNO "

CUADRO DE NECESIDADES - PLANILLAS - BIENES - SERVICIOS - SUPERVISION (PLANILLAS, BIENES Y SERVICIOS) EJERCICIO
FISCAL AÑO 2022

CUI: 2440946 - META: 0210

PERIODO VALOR
II TRIMESTRE III TRIMESTRE IV TRIMESTRE

ESPECIFICA DE UNIDAD TOTAL UNITARIO


DE N OMINACION
GASTO MEDIDA NECESI-DAD SEGÚN
ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE TOTAL (S/.)
EXPEDIENTE
TECNICO (S/.)

2.6.23.25 PAPEL BOND A-4 COLOR BLANCO 75 GR. MILL 2.00 2.00 15.00 30.00
2.6.23.25 ARCHIVADOR DE PALANCA GRANDE UND 15.00 15.00 6.00 90.00
2.6.23.25 ARCHIVADOR DE PALANCA 1/2 OFICIO - LOMO ANCHO UND 6.00 6.00 3.50 21.00
2.6.23.25 PORTAMINAS UND 3.00 3.00 7.00 21.00
PROYECCION DE REQUERIMIENTOS EN FUNCION AL PIA+PIM 2022 - S/. 2,234.146.00 SOLES

OBRA : "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR DE LA CARRETERA TRAMO ACHAYA (PU-140) - ESTRELLA (EMP. PE - 3S) DEL DISTRITO DE ACHAYA - PROVINCIA DE
AZANGARO - DEPARTAMENTO DE PUNO "

CUADRO DE NECESIDADES - PLANILLAS - BIENES - SERVICIOS - SUPERVISION (PLANILLAS, BIENES Y SERVICIOS) EJERCICIO
FISCAL AÑO 2022

CUI: 2440946 - META: 0210

PERIODO VALOR
II TRIMESTRE III TRIMESTRE IV TRIMESTRE

ESPECIFICA DE UNIDAD TOTAL UNITARIO


DE N OMINACION
GASTO MEDIDA NECESI-DAD SEGÚN
ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE TOTAL (S/.)
EXPEDIENTE
TECNICO (S/.)

2.6.23.25 REPUESTOS PARA PORTAMINAS UND 2.00 2.00 1.00 2.00


2.6.23.25 LAPICEROS TINTA SECA UND 24.00 24.00 1.00 24.00
2.6.23.25 LAPICEROS TINTA LIQUIDA UND 6.00 6.00 3.50 21.00
2.6.23.25 RESALTADOR UND 6.00 6.00 2.00 12.00
2.6.23.25 GRAPAS 26/6 X 5000 CAJA 3.00 3.00 3.80 11.40
2.6.23.25 PAPEL BOND 75 GR (COLORES) MILL 2.00 2.00 19.00 38.00
2.6.23.25 PAPEL LUSTRE COLORES UND 25.00 25.00 0.60 15.00
2.6.23.25 CORRECTOR UND 3.00 3.00 2.50 7.50
2.6.23.25 CINTA DE EMBALAJE UND 3.00 3.00 5.00 15.00
2.6.23.25 FASTENER CAJA 1.00 1.00 8.50 8.50
2.6.23.25 FORRO DE PLASTICO T/OFICIO COLOR TRASPARENTE UND 5.00 5.00 9.50 47.50
2.6.23.25 ENGRAPADOR UND 2.00 2.00 25.50 51.00
2.6.23.25 PERFORADOR UND 1.00 1.00 15.20 15.20
2.6.23.25 CLIPS BINDER 2" (51mm) x 12und CAJA 3.00 3.00 9.50 28.50
2.6.23.25 CLIPS METAL 100 UND CAJA 2.00 2.00 2.00 4.00
2.6.23.25 POST - IT 76X76MM PAQ 1.00 1.00 5.50 5.50
2.6.23.25 SACA GRAPAS UND 1.00 1.00 3.50 3.50

SERVICIOS
2.6.23.26 SERVICIOS DE ALQUILER EQUIPOS LIVIANOS H.E. 25,623.55
2.6.23.26 SERVICIO DE ALQUILER DE NIVEL TOPOGRAFICO H-E 54.64 54.64 6.90 377.02
2.6.23.26 SERVICIO DE ALQUILAR DE ESTACION TOTAL H-E 109.00 109.00 16.95 1,847.55
2.6.23.26 MOTOBOMBA 7-10 HP 3-4" H-E 19.00 19.00 7.00 133.00
2.6.23.26 COMPACTADORA VIBRATORIA TIPO PLANCHA 7 HP H-E 50.00 50.00 3.00 150.00
2.6.23.26 COMPRESORA NEUMATICA 250 - 330 PCM - 87 HP H-E 97.39 97.39 80.00 7,791.20
2.6.23.26 GRUPO ELECTROGENO DE 380HP 250 KW. H-E 80.00 80.00 150.00 12,000.00
2.6.23.26 VIBRADOR DE CONCRETO 4 HP 1.5" H-E 71.00 71.00 3.81 270.51
2.6.23.26 MEZCLADORA DE CONCRETO 11 P3 (18 HP) H-E 71.00 71.00 23.73 1,684.83
2.6.23.26 ZARANDA ESTATICA H-E 742.51 742.51 1.00 742.51
2.6.23.26 MOTOSIERRA H-E 11.00 11.00 5.83 64.13
2.6.23.26 SOLDADORA ELECTRICA TRIFASICA 400 A H-E 56.28 56.28 10.00 562.80

2.6.23.26 SERVICIOS DE ALQUILER MAQUINARIA U.M. 1,223,507.70


2.6.23.26 MOTONIVELADORA 145-150 HP H-M 11.53 280.00 280.00 571.53 200.00 114,306.00

2.6.23.26 RODILLO LISO VIBRATORIO AUTOPROPULSADO 101-135 HP 10-12tn H-M 12.00 300.00 300.00 612.00 150.00 91,800.00

2.6.23.26 CARGADOR SOBRE LLANTAS DE 100-115 HP 2-2.25 Y3 H-M 94.00 550.00 550.00 1,194.00 120.00 143,280.00
2.6.23.26 EXCAVADORA SOBRE ORUGAS 115-165 HP 0.75-1.4Y3 H-M 400.00 600.00 590.00 1,590.00 250.00 397,500.00
2.6.23.26 CAMION CISTERNA 4x2(agua) 145-165 hp H-M 92.00 350.00 350.00 792.00 90.00 71,280.00
PROYECCION DE REQUERIMIENTOS EN FUNCION AL PIA+PIM 2022 - S/. 2,234.146.00 SOLES

OBRA : "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR DE LA CARRETERA TRAMO ACHAYA (PU-140) - ESTRELLA (EMP. PE - 3S) DEL DISTRITO DE ACHAYA - PROVINCIA DE
AZANGARO - DEPARTAMENTO DE PUNO "

CUADRO DE NECESIDADES - PLANILLAS - BIENES - SERVICIOS - SUPERVISION (PLANILLAS, BIENES Y SERVICIOS) EJERCICIO
FISCAL AÑO 2022

CUI: 2440946 - META: 0210

PERIODO VALOR
II TRIMESTRE III TRIMESTRE IV TRIMESTRE

ESPECIFICA DE UNIDAD TOTAL UNITARIO


DE N OMINACION
GASTO MEDIDA NECESI-DAD SEGÚN
ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE TOTAL (S/.)
EXPEDIENTE
TECNICO (S/.)

2.6.23.26 CAMION VOLQUETE DE 15 m3 H-M 1,000.00 1,200.00 1,500.00 3,700.00 100.00 370,000.00

2.6.23.26 CAMIONETA PICK UP DOBLE CABINA 4X4 POR REDUCCION DE CAPACIDAD DIA 30.00 30.00 30.00 90.00 133.30 11,997.00

2.6.23.26 RETROEXCAVADORA SOBRE LLANTA 80 - 110 HP 0.5-1.3 Y3 H-M 17.00 17.00 150.00 2,550.00
PROYECCION DE REQUERIMIENTOS EN FUNCION AL PIA+PIM 2022 - S/. 2,234.146.00 SOLES

OBRA : "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR DE LA CARRETERA TRAMO ACHAYA (PU-140) - ESTRELLA (EMP. PE - 3S) DEL DISTRITO DE ACHAYA - PROVINCIA DE
AZANGARO - DEPARTAMENTO DE PUNO "

CUADRO DE NECESIDADES - PLANILLAS - BIENES - SERVICIOS - SUPERVISION (PLANILLAS, BIENES Y SERVICIOS) EJERCICIO
FISCAL AÑO 2022

CUI: 2440946 - META: 0210

PERIODO VALOR
II TRIMESTRE III TRIMESTRE IV TRIMESTRE

ESPECIFICA DE UNIDAD TOTAL UNITARIO


DE N OMINACION
GASTO MEDIDA NECESI-DAD SEGÚN
ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE TOTAL (S/.)
EXPEDIENTE
TECNICO (S/.)

2.6.23.26 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS SERVICIO 1.00 1.00 20,794.70 20,794.70

2.6.23.26 OTROS SERVICIOS - GASTOS GENERALES U.M. 7,510.00


2.6.23.26 LEGALIZACION DE CUADERNO DE OBRA UNIDAD 2.00 2.00 50.00 100.00
2.6.23.26 DISEÑO DE MEZCLAS UNIDAD 2.00 2.00 250.00 500.00
2.6.23.26 ROTURA DE BRIQUETAS UNIDAD 15.00 15.00 30.00 450.00
2.6.23.26 IMPREVISTOS GLB 1.00 1.00 3500.00 3,500.00
2.6.23.26 SILLA PARA ESCRITORIO UNIDAD 2.00 2.00 300.00 600.00
2.6.23.26 PIZARRA ACRILICA UNIDAD 1.00 1.00 300.00 300.00
2.6.23.26 TINTA PARA IMPRESORA UNIDAD 2.00 2.00 280.00 560.00
2.6.23.26 IMPRESORA UNIDAD 1.00 1.00 1500.00 1,500.00

2.6.23.26 OTROS SERVICIOS U.M. 273,966.44


SC DELIMITACION DE LAS AREAS DE ACUMULACION TEMPORAL DE
2.6.23.26 UNIDAD 5.00 5.00 8.00 40.00
MATERIAL EXCEDENTE

2.6.23.26 SC PAGO POR DERECHO DE USO DE CANTERA DE RIO M3 33,611.30 33,611.30 2.10 70,583.73

2.6.23.26 SC PAGO POR DERECHO DE USO DE CANTERA M3 30,639.06 30,639.06 1.20 36,766.87

2.6.23.26 SC AFECTACION A TERRENO DE CULTIVO Y PASTO M2 27,304.00 27,304.00 0.71 19,385.84

SC ELABORACION DE PLAN DE MANEJO DE RESIDUOS SOLIDOS Y


2.6.23.26 INF. 3.50 3.50 3,500.00 12,250.00
EFLUENTES

2.6.23.26 SC IMPLEMENTACION DEL SISTEMA DE RESIDUOS SOLIDOS Y EFLUENTES UNIDAD 1.20 1.20 1,200.00 1,440.00

2.6.23.26 SC CAPACITACION AL PERSONAL DEL PROYECTO EN MANEJO DE UNIDAD 2.50 2.50 500.00 1,250.00
RESIDUOS SOLIDOS

2.6.23.26 UNIDAD 7.00 7.00 3,500.00 24,500.00


SC DISPOSICION FINAL DE RESIDUOS DOMESTICOS Y PELIGROSOS

2.6.23.26 SC REVISION Y MANTENIMIENTO PREVENTIVO DE MAQUINARIAS Y UNIDAD 6.00 6.00 2,000.00 12,000.00
EQUIPOS

2.6.23.26 SC IMPLEMENTACION DE INSTALACION DE AREAS AUXILIARES Y UNIDAD 3.00 3.00 1,000.00 3,000.00
SEGURIDAD

2.6.23.26 SC INVENTARIO DE FLORA Y FAUNA EN EL AREA DE INFLUENCIA UNIDAD 2.00 2.00 2,000.00 4,000.00
DIRECTA E INDIRECTA

2.6.23.26 MONITOREO DE CALIDAD DE AGUA UNIDAD 2.50 2.50 2,500.00 6,250.00

2.6.23.26 MONITOREO DE CALIDAD DE AIRE UNIDAD 7.00 7.00 3,500.00 24,500.00


PROYECCION DE REQUERIMIENTOS EN FUNCION AL PIA+PIM 2022 - S/. 2,234.146.00 SOLES

OBRA : "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR DE LA CARRETERA TRAMO ACHAYA (PU-140) - ESTRELLA (EMP. PE - 3S) DEL DISTRITO DE ACHAYA - PROVINCIA DE
AZANGARO - DEPARTAMENTO DE PUNO "

CUADRO DE NECESIDADES - PLANILLAS - BIENES - SERVICIOS - SUPERVISION (PLANILLAS, BIENES Y SERVICIOS) EJERCICIO
FISCAL AÑO 2022

CUI: 2440946 - META: 0210

PERIODO VALOR
II TRIMESTRE III TRIMESTRE IV TRIMESTRE

ESPECIFICA DE UNIDAD TOTAL UNITARIO


DE N OMINACION
GASTO MEDIDA NECESI-DAD SEGÚN
ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE TOTAL (S/.)
EXPEDIENTE
TECNICO (S/.)

2.6.23.26 SC ELABORACION DE PLAN DE MONITOREO DE CALIDAD AMBIENTAL INF 1.00 1.00 3,500.00 3,500.00

2.6.23.26 SC MONITOREO DE CALIDAD DE COBERTURA VEGETAL INF 2.00 2.00 2,000.00 4,000.00
PROYECCION DE REQUERIMIENTOS EN FUNCION AL PIA+PIM 2022 - S/. 2,234.146.00 SOLES

OBRA : "MEJORAMIENTO DEL SERVICIO DE TRANSITABILIDAD VEHICULAR DE LA CARRETERA TRAMO ACHAYA (PU-140) - ESTRELLA (EMP. PE - 3S) DEL DISTRITO DE ACHAYA - PROVINCIA DE
AZANGARO - DEPARTAMENTO DE PUNO "

CUADRO DE NECESIDADES - PLANILLAS - BIENES - SERVICIOS - SUPERVISION (PLANILLAS, BIENES Y SERVICIOS) EJERCICIO
FISCAL AÑO 2022

CUI: 2440946 - META: 0210

PERIODO VALOR
II TRIMESTRE III TRIMESTRE IV TRIMESTRE

ESPECIFICA DE UNIDAD TOTAL UNITARIO


DE N OMINACION
GASTO MEDIDA NECESI-DAD SEGÚN
ABRIL MAYO JUNIO JULIO AGOSTO SETIEMBRE OCTUBRE NOVIEMBRE TOTAL (S/.)
EXPEDIENTE
TECNICO (S/.)

2.6.23.26 SERVICIO DE CHARLAS DE PREVENCION CONTRA EL COVID - 19 SERVICIO 1.00 1.00 1,000.00 1,000.00

SC INTERACCION CON LAS AUTORIDADES REGIONALES LOCALES Y PROF.


2.6.23.26 REU 5.00 5.00 300.00 1,500.00
DEL PROYECTO

2.6.23.26 SC IMPLEMENTACION CON EQUIPOS DE PROTECCION PERSONAL EPPS UND 25.00 25.00 1,500.00 37,500.00

2.6.23.26 SC TRAMITES ADMINISTRATIVOS DEL PROYECTO (ALA,SENACE,ETC.) REU 3.00 3.00 1,500.00 4,500.00

SC ELABORACION DE MATERIAL INFORMATIVO EN TEMAS AMBIENTALES


2.6.23.26 UNIDAD 3.00 3.00 2,000.00 6,000.00
Y SEGURIDAD

SUPERVISION
GASTO POR LA CONTRATACION DE BIENES - SUPERVICION DE
2.6.8 1.4 1 U.M. 71,780.00
OBRA
2.6.8 1.4 1 PLANILLA DE SUPERVISION PLLA 9000 20000 20000 22780 0 71,780.00 1.00 71,780.00
GASTO POR LA CONTRATACION DE BIENES - SUPERVICION DE
2.6.8 1.4 2 U.M. 13,710.00
OBRA
2.6.8 1.4 2 ADQUISICION DE BIENES GLB 0 13710 13,710.00 1.00 13,710.00
GASTO POR LA CONTRATACION DE SERVICIOS - SUPERVICION
2.6.8 1.4 3 U.M. 5,000.00
DE OBRA
2.6.8 1.4 3 CONTRATACION DE SERVICIOS GLB 1 2500 2500 5,000.00 1.00 5,000.00

PLANILLA 187,901.25
BIENES 425,147.06
RESUMEN TOTAL SOBRE ASIGNACION PIA+PIM A1 2022
QUE CORRESPONDE A S/. 2'234,146.00 SOLES
SERVICIOS 1,530,607.69
SUPERVISION 90,490.00
RESUMEN TOTAL 2,234,146.00
PRESUPUESTO ASIGNADO
ESPECIFICA DE GASTO GASTOS DE CAPITAL
2.6.2.3.2.4 COSTO DE CONSTRUCCION POR ADMINISTRACION DIRECTA - PERSONAL
2.6.2.3.2.5 COSTO DE CONSTRUCCION POR ADMINISTRACION DIRECTA - BIENES
2.6.2.3.2.6 COSTO DE CONSTRUCCION POR ADMINISTRACION DIRECTA - SERVICIOS
2.6.8.1.4.1 GASTO POR LA CONTRATACION DE PERSONAL
2.6.8.1.4.2 GASTO POR LA COMPRA DE BIENES
2.6.8.1.4.3 GASTO POR LA CONTRATACION DE SERVICIOS
TOTAL META 0210
PRESUPUESTO DEL EXPEDIENTE TECNICO
MONTO
175,504.00
811,766.00
1,156,386.00
71,780.00
13,710.00
5,000.00
2,234,146.00
COSTO INDIRECTO TOTAL

ITEM DESCRIPCION COSTO DIRECTO GASTOS GASTOS DE


GASTOS GASTOS DE GASTOS DE GASTOS DE
GENERALES SUPERVISION MONITOREO Y EXPEDIENTES TECNICOS LIQUIDACION S/. %
SEGUIMIENTO

2.6.2.3.2.4 COSTO DE CONSTRUCCION POR ADMINISTRACION DIRECTA - PERSONAL 102,301.25 85,600.00 28,800.00 216,701.25
2.6.2.3.2.5 COSTO DE CONSTRUCCION POR ADMINISTRACION DIRECTA - BIENES 339,950.38 16,636.11 6,000.00 362,586.49
2.6.2.3.2.6 COSTO DE CONSTRUCCION POR ADMINISTRACION DIRECTA - SERVICIOS 1,611,357.52 10,000.00 25,053.87 8,446.87 1,654,858.26

2,053,609.15 112,236.11 59,853.87 8,446.87 0.00 0.00 2,234,146.00


ATRÁS

2 6 2 3 2 4 COSTO DE CONSTRUCCION POR ADMINISTRACIÓN DIRECTA - PERSONAL

No de Coef. De
Cantidad
Meses Part.
Descripción

A) PERSONAL PROFESIONAL Y TECNICO


ING. Residente de Obra 1 3 1
ING. Especialista en Geotecnia 1 2 1
ING. Especialista en Impacto Ambiental y Segurida 0 1 1
ING. Asistente asistente de obra 1 3 1
Técnico en Enfermería 1 1 1

B) PERSONAL DE APOYO PROFESIONAL


C) PERSONAL TECNICO Y AUXILIAR
Topografo 1 2 1
Asistente administrativo 1 3 1
Maestro de obra 1 2 1
Auxiliar de suelos 1 2 1
Almacenero 1 3 1
Dibujante en Autocad 1 0 1
Chofer 1 3 1
Guardian 1 3 1

2 6 2 3 2 5 COSTO DE CONSTRUCCION POR ADMINISTRACIÓN DIRECTA - BIENES

Descripción Und Cantidad

A) VESTUARIO
CASCOS DE SEGURIDAD PARA PERSONAL OBRERO UND 18.00
CASCOS DE SEG. PARA PROFESIONALES ,TECNICOS, AUXILIARES UND 6.00
BOTAS DE JEBE PAR 15.00
GUANTES DE CUERO PAR 10.00
CHALECOS DE SEGURIDAD CON CINTA REFLECTORA UND 20.00
CORTAVIENTO UND 20.00
LENTES TRANSPARENTES DE PROTECCION (3M) UND 6.00
CASACAS PARA PERSONAL PROFESIONAL, TECNICOS, AUXILIAR UND 18.00
CHALECOS PARA PERSONAL PROFESIONAL, TECNICOS, AUXLI. UND 20.00
MAMELUCO UND 20.00
PROTECTOR DE RUIDO (OREJERAS) UND 4.00
GUANTES DE JEBE PAR 20.00
ZAPATOS DE SEGURIDAD PARA PERSONAL OBRERO UND 20.00
ZAPATOS DE SEGURIDAD PROFESIONAL, TECNICOS, AUXILIAR UND 6.00
LENTES DE SEGURIDAD UND 25.00
MASCARA PROTECTOR DE POLVO UND 8.00

B) MATERIALES DE ESCRITORIO
CUADERNO DE OBRA DE 50 FOLIOS AUTOCOPIABLE UND 6.00
CUADERNO CUADRICULADO TAMAÑO OFICIO X 200 HOJAS UND 2.00
CUADERNO CUADRICULADO X 200 HOJAS UND 5.00
FOLDER MANILA A-4 UND 20.00
PAPEL BOND A-4 COLOR BLANCO 75 GR. MLL 10.00
LIBRETA TOPOGRAFICA UND 3.00
ESCALIMETRO UND 1.00
PLUMONES UND 10.00
SELLOS UND 3.00
BLOK DE PARTES DIARIOS UND 0.00
BLOK DE PEDIDOS DE MATERIALES UND 0.00
CINTA MASKINTAPE UND 5.00
PAPEL BOND A-4 COLOR BLANCO 75 GR. MLL 0.00
PAPEL CARBON PQT 0.00
ARCHIVADOR DE PALANCA GRANDE UND 15.00
ARCHIVADOR DE PALANCA 1/2 OFICIO - LOMO ANCHO UND 10.00
PORTAMINAS UND 3.00
REPUESTOS PARA PORTAMINAS UND 3.00
LAPICEROS TINTA SECA UND 12.00
LAPICEROS TINTA LIQUIDA UND 5.00
RESALTADOR UND 5.00

C) BIENES DE CONSUMO
TONER PARA IMPRESORA LASER UND 0.00
CARTUCHO DE TINTA COLOR NEGRO PARA PLOTTER UND 0.00
DVD EN BLANCO X 100 UND PQT 0.00
ALIMENTACION PARA EL PERSONAL DE OBRA GLB 0.00
IMPREVISTOS VARIOS GLB 0.00

D) MEDICAMENTOS
MEDICAMENTOS Y BOTIQUIN DE PRIMEROS AUXILIOS GLB 0.00

E) EQUIPAMIENTO Y BIENES DURADEROS


CAMIONETA PICAT 4X4 UND 1.00
FLEXOMETRO DE 5 MTS UND 3.00
CILINDROS VACIOS UND 5.00
BRIQUETERA PARA CONCRETO UND 3.00
WINCHA DE LONA DE 50 MTS UND 1.00
BUGUIES CON LLANTAS REFORZADAS UND 15.00
PLACA RECORDATORIA UND 1.00
F) COMBUSTIBLE
COMBUSTIBLE DIESSEL GLN 950.00
COMBUSTIBLE GASOHOL GLN 470.00
280583.333333333

Costo Mensual Parcial

5200 15600
3800 7600
3800 0
3800 11400
3000 3000

3200 6400
2500 7500
3300 6600
2500 5000
2500 7500
2500 0
2800 8400
2200 6600
TOTAL 85,600.00

DIRECTA - BIENES S/. 48,659.00

Precio Parcial

S/. 9,005.00
35.00 630.00
50.00 300.00
35.00 525.00
8.00 80.00
30.00 600.00
10.00 200.00
20.00 120.00
40.00 720.00
20.00 400.00
40.00 800.00
40.00 160.00
5.00 100.00
80.00 1,600.00
400.00 2,400.00
10.00 250.00
15.00 120.00

S/. 825.00
30.00 180.00
15.00 30.00
6.00 30.00
0.50 10.00
25.00 250.00
5.00 15.00
25.00 25.00
1.50 15.00
25.00 75.00
20.00 0.00
20.00 0.00
2.50 12.50
15.00 0.00
20.00 0.00
6.00 90.00
3.50 35.00
7.00 21.00
1.00 3.00
0.50 6.00
3.50 17.50
2.00 10.00

S/. 0.00
250.00 0.00
170.00 0.00
50.00 0.00
93892.14 0.00
8500.00 0.00

S/. 0.00
2886.67 0.00

S/. 16,349.00
12500.00 12,500.00
8.00 24.00
70.00 350.00
250.00 750.00
50.00 50.00
115.00 1,725.00
950.00 950.00
S/. 22,480.00
15.50 14,725.00
16.50 7,755.00