PLANILLA DE AVANCE DE OBRA Nº

NOMBRE DEL PROYECTO :

EMPRESA CONTRATISTA :

PROVINCIA :

MUNICIPIO :

CONTRATO ORIGINAL

ITEM DESCRIPCION UNID. PRECIO


CANT. PRECIO
UNITARIO
PROGR. TOTAL Bs.
Bs.
A B C
1. ACTIVIDADES PRELIMINARES
1 INSTALACION DE FAENAS GLB 26,161.71 1.00 26,161.71
2 PROVISION E INSTALACION DE LETRERO DE OBRA PZA 3,627.68 2.00 7,255.36
SUBTOTAL ACTIVIDADES PRELIMINARES 33,417.07
2. CERCO DE MALLA OLIMPICA
3 REPLANTEO DE CERCO ML 13.66 1,315.00 17,962.90
4 EXCAVACION TERRENO SEMIDURO (MANUAL) M3 88.28 423.56 37,391.88
5 MALLA OLIMPICA NO 10 INCLUYE TUBERIA FG 2" C/2.5 M M2 287.87 3,022.00 869,943.14
6 PORTON DE MALLA OLIMPICA M2 2,077.16 15.35 31,884.41
7 HORMIGON SIMPLE FCK= 180 KG/CM2 M3 1,797.81 15.36 27,614.36
8 PROV Y COLOCADO DE ACERO ESTRUCTURAL FYK= 4200 KG/CM2 KG 15.49 1,548.00 23,978.52
9 HORMIGON CICLOPEO 50% PIEDRA DESPLAZADORA M3 958.09 389.65 373,319.77
10 TRANSPORTE DE MATERIAL EXCEDENTE C/VOLQUETE M3 32.24 550.63 17,752.31
SUBTOTAL CERCO DE MALLA OLIMPICA 1,399,847.29
3. ADMINISTRACION
11 REPLANTEO Y TRAZADO DE OBRAS M2 15.43 192.35 2,967.96
12 EXCAVACION TERRENO SEMIDURO (MANUAL) M3 88.28 28.65 2,529.22
13 CIMIENTOS DE HO CO 50 % PIEDRA DESPLAZADORA M3 695.49 35.65 24,794.22
14 SOBRECIMIENTOS DE HO CO 50% PIEDRA DESPLAZADORA M3 1,154.87 15.36 17,738.80
15 IMPERMEABILIZACION DE SOBRECIMIENTOS CON ASFALTEX ML 45.13 95.85 4,325.71
16 ZAPATA DE HO AO M3 3,274.89 5.65 18,503.13
17 COLUMNA DE HO AO M3 4,045.17 6.53 26,414.96
18 VIGA DE HO AO M3 4,252.80 15.35 65,280.48
19 CUBIERTA DE CALAMINA NO 28 (INCLUYE MADERAMEN ) M2 358.52 196.75 70,538.81
20 MURO DE LADRILLO 6H E=12 CM M2 153.76 396.94 61,033.49
21 REVOQUE INTERIOR DE ESTUCO SOBRE LADRILLO M2 138.38 530.65 73,431.35
22 REVOQUE EXTERIOR CAL/ CEMENTO SOBRE LADRILLO M2 184.01 168.42 30,990.96
23 REVOQUE CIELO FALSO C/MADERAMEN M2 244.80 116.31 28,472.69
24 REVOQUE EN ALERO M2 232.37 33.13 7,698.42
25 EMPEDRADO ( E= 10 CM ) Y CONTRAPISO DE HORMIGON ( E= 5 CM ) M2 201.38 120.35 24,236.08
26 PISO DE CERAMICA NACIONAL M2 264.34 93.65 24,755.44
27 ZOCALO DE CERAMICA NACIONAL ML 50.51 165.35 8,351.83
28 REVESTIMIENTO C/AZULEJO DE COLOR RESISTENTE AL CALOR M2 268.90 84.31 22,670.96
29 PISO DE PARKET MARA M2 217.28 46.48 10,099.17
30 PINTURA LATEX INTERIOR M2 36.11 530.65 19,161.77
31 PINTURA LATEX SOBRE CIELO FALSO M2 37.29 116.31 4,337.20
32 PINTURA LATEX EXTERIOR M2 42.61 564.61 24,058.03
33 BOTAGUAS DE Hº Aº ML 110.59 6.98 771.92
34 VENTANA DE ALUMINIO M2 1,462.66 6.01 8,790.59
35 PUERTA DE MADERA MARA M2 934.66 29.65 27,712.67
36 MESON DE HO AO CON REVESTIMIENTO AZULEJO DE COLOR M2 750.06 4.19 3,142.75
37 PROV. Y COLOC. DE CHAPA Y JALADOR JGO 531.22 12.00 6,374.64
38 PROVISION Y COLOCADO VIDRIO TRIPLE ( 4 MM ) M2 156.61 6.35 994.47
39 MUEBLE DE MADERA PARA MESON GLB 1,541.43 1.00 1,541.43
40 CANALETA DE CALAMINA PLANA NO 28 ML 113.63 37.00 4,204.31
41 BAJANTE DE CALAMINA NO 28 ML 100.36 20.00 2,007.20
42 CAMARA DE REGISTRO 0,40 M X 0,40 M PZA 724.49 5.00 3,622.45
43 VARIOS INSTALACION SANITARIA GLB 407.80 1.00 407.80
44 PROV E INSTALACION DE LAVAPLATOS INOXIDABLE 2 DEPOSITOS INOX PZA 1,054.28 1.00 1,054.28
45 TRANSPORTE DE MATERIAL EXCEDENTE C/VOLQUETE M3 32.24 37.25 1,200.94
SUBTOTAL ADMINISTRACION 634,216.13
4. ARQUITECTURA
CONTRATO ORIGINAL

ITEM DESCRIPCION UNID. PRECIO


CANT. PRECIO
UNITARIO
PROGR. TOTAL Bs.
Bs.
46 REPLANTEO Y TRAZADO DE OBRAS M2 9.12 6,500.00 59,280.00
47 EXCAVACIÓN 0 A 2 M, S/AGOTAMIENTO TERRENO SEMIDURO M3 27.10 1,350.00 36,585.00
48 CONFORMACION Y COMPACTADO CON MAQUINARIA M3 17.95 750.00 13,462.50
49 CORDON DE ACERA DE HORMIGON SIMPLE 0,20 X O,35 M ML 93.58 1,658.00 155,155.64
50 EMPEDRADO DE CALZADA M2 48.98 6,578.00 322,190.44
51 ACERA DE CONCRETO 4 CM CON BASE DE PIEDRA M2 150.66 815.00 122,787.90
52 BARANDA DE FG 2" Y SUJECIONES ML 884.61 801.00 708,572.61
SUBTOTAL ARQUITECTURA 1,418,034.09
5. COMP II: ELECTROMECANICO
53 PROVISION DE COMPONENTES ELECTROMECANICOS GLB 13,848,249.84 1.00 13,848,249.84
54 INSTALACION,MONTAJE Y PUESTA EN SERVICIO DE EQUIPOS Y ACCESORIOS GLB 2,306,611.02 1.00 2,306,611.02
SUBTOTAL COMP II: ELECTROMECANICO 16,154,860.86
6. COMPONENTE III: AMBIENTAL
55 COMPONENTE AMBIENTAL (PPM-PASA Y PAAS) GLB 400,949.07 1.00 400,949.07
SUBTOTAL COMPONENTE III: AMBIENTAL 400,949.07
COSTO TOTAL DEL PROYECTO 20,041,324.51

TOTAL CONTRATO: P= Bs.


MONTO EJECUTADO EN EL AVANCE ACTUAL R= Bs.
ANTICIPO DEL 20% : S=P*20,00% = Bs.

T=R*Desc.
DESCUENTO POR ANTICIPO: 20.00% por Anticipo=
Bs.

DESCUENTO 7% DE BUENA EJECUCION U=R*7%=


DESCUENTO POR MULTAS Y SANCIONES: MS = Bs.

Presentado por :
FECHA:

EMPRESA CONSTRUCTORA

SELLOS:
PAO Nº

Del : Al:

MONTO
PLAZO DEL CONTRATO : 730 20,041,324.51
CONTRATO:
Fecha de inicio: 1-Jan-20
Fecha conclusión: 30-Dec-21 CODIGO SISIN:

S C : FACTOR MULTAS 1*X :


LIQUIDO PAGABLE ACTUAL: X = R-T-U-MS =

PAO Nº

Aprobado por: Aprobado por:


FECHA: FECHA:

GERENTE DE SUPERVISIÓN FISCAL DE OBRA


GOBIERNO AUTONOMO MUNICIPAL…

CERTIFICADO DE AVANCE DE OBRA CAO Nº 0

Proyecto:

Empresa Constr. Código SISIN:

Departamento: Código contrato :

Provincia: Fecha de inicio:


Plazo: ( Días )
Municipio: Fecha conclusión modificada:

Supervisado por:

% Ordenes de cambio (Acum.):

% Multas (acumulado): 0.00 Descuento por Multas (Acum.) Bs.:

COSTO TOTAL DEL PROYECTO


TOTAL
Monto Financiero Contratado Bs. 20,041,324.51 A
Monto adicional por Ordenes de Cambio Bs. 0.00 B
Total Financiero Aprobado Bs.: 20,041,324.51 C=A+B

ANTICIPO (según contrato) % Anticipo Según Contrato


Anticipo Otorgado (del Contratado) Bs..: 20 4,008,264.90 D = A * % Anticipo
Descuento anticipo acumulado Anterior Bs.: E = D * % Anticipo
Descuento anticipo acumulado Actual Bs.: 0.00 F = D * % Anticipo
Descuento anticipo acumulado Total Bs.: 0.00 G = E + F

EJECUCION FINANCIERA (según planilla) DESCUENTO ANTICIPO Según PLANILLA


Desembolso Acum. hasta el PAO Anterior Bs.: 0.00 H
Planilla de Avance de Obra Actual Bs..: 0.00 I
% Descuento Anticipo Actual s/Planilla 20.00 J
Descuento Actual por anticipo Bs.: 0.00 K = ( I * J ) / 100
Descuento 7% de buena ejecucion Bs.: 0.00 L = Descuento retencion
Descuento por multas y sanciones

LIQUIDO PAGABLE EN PLANILLA ACTUAL : Bs. 0.00 M = I - K - L


Total monto acumulado de avance Bs.: 0.00 N =H + I
Saldo por pagar Bs.: 20,041,324.51 O = C - N

Nombre (Sello): Firmas : Fecha :

Presentado por :
Contratista EMPRESA CONSTRUCTORA

Revisado por :
Supervisor de Obra GERENTE DE SUPERVISION

Revisado por :
Fiscal de Obra FISCAL DE OBRA