PRESUPUESTO ADICIONAL Nº 4
01 TRABAJOS PRELIMINARES
01.01 TRANSPORTE DE MATERIALES
01.01.01 TRANSPORTE DE MATERIALES DE SOSTENIMIENTO Kg 112,996.82 0.33 37,288.95 7,457.79 29,831.16 - - 37,288.95
01.01.02 TRAZO DE NIVELES Y REPLANTEO PERMANENTE - TUNEL
M2 7,600.70 4.50 34,203.15 1,554.69 32,648.46 - - 34,203.15
02 SOSTENIMIENTO
02.01 SOSTENIMIENTO DE TÙNEL
02.01.01 INSTALACION DE ARCOS NORUEGOS INC. MATERIAL
UND 52.00 711.15 36,979.80 2,175.28 34,804.52 - - 36,979.80
02.01.02 PERNO DE ANCLAJE D=22 mm x 2.1 m UND 3,082.40 114.74 353,674.58 5,704.43 125,497.43 148,315.15 74,157.57 353,674.58
02.01.03 MALLA ELCTROSOLDADA 4" X 4" M2 4,426.44 25.90 114,644.80 1,879.42 41,347.30 48,865.00 22,553.08 114,644.80
02.01.04 LANZADO DE CONCRETO F'C= 280KG/CM2 (SHOTCRETS)
m3 TUNEL 223.63 672.36 150,359.87 21,479.98 128,879.89 - - 150,359.87
02.01.05 SUMINISTRO E INSTALACIÒN DE PLANCHA ACANALADA
M2 DE 1.20 m319.98
X 0.55 m X 3 mm
172.37 55,154.95 - 55,154.95 - - 55,154.95
03 MOVIMIENTO DE TIERRAS
03.01 TUNEL
03.01.01 ELIMINACIÒN DE MATERIAL EXCEDENTE (TUNEL) DM=1
m3 Km 17.89 10.85 194.11 - 194.11 - - 194.11