UBICACIÓN Iquique
DIRECCION
MANDANTE Aguas del Altiplano
Cantidad Duración
Cantidad % incidencia
ÍTEM Faltante de Itemizado UNIDAD CANT. P.UNIT. $ P.TOTAL $ días corridos Inicio Término Transc Prog. Real Control Programa Real
Ejecutada
Ejecutar
OBRA REFUERZO LAS ROSAS E INTERCONEXION NUEVA VICTORIA 16-Dec-16 0.00% 0.00%
1.1 1450 369.31 Traslados kgs 1,819.31 520 946,041 2.10% 8 3-Jan-17 10-Jan-17 11.31% 2.10% 1.68% 23-Dec-16 0.00% 0.0%
2.1.1 275 20.17 Excavación m3 295.17 13,500 3,984,820 8.87% 27
1/13/2017
8-Feb-17 10.84% 8.87% 8.26% 30-Dec-16 0.00% 0.0%
2.1.2 18 2.13 Cama de Arena m3 20.13 14,800 297,991 0.66% 27
1/13/2017
8-Feb-17 0.81% 0.66% 0.59% 6-Jan-17 0.79% 10.0%
2.1.3 10 2.66 Lateral m3 12.66 14,800 187,331 0.42% 27
1/13/2017
8-Feb-17 0.51% 0.42% 0.33% 13-Jan-17 2.20% 18.0%
2.1.4 40 5.33 Inicial m3 45.33 9,750 441,997 0.98% 27
1/13/2017
8-Feb-17 1.20% 0.98% 0.87% 20-Jan-17 8.64% 21.0%
2.1.5 160 11.40 Relleno m3 171.40 9,750 1,671,110 3.72% 27
1/13/2017
8-Feb-17 4.54% 3.72% 3.47% 27-Jan-17 14.87% 24.0%
2.1.6 205 28.85 Retiro de Excedentes m3 233.85 7,500 1,753,899 3.90% 27
1/13/2017
8-Feb-17 4.77% 3.90% 3.42% 3-Feb-17 24.90% 26.0%
Suministro y Transporte de tuberías y Piezas Especiales 1 10-Feb-17 61.78% 44.6%
3.1.1.1 6.00 Copla DN 110 c/u 6.00 7,650 45,900 0.10% 2
2/20/2017
21-Feb-17 0.00% 0.00% 0.00% 17-Feb-17 72.10%
3.1.1.2 8 0.00 Copla DN 200 c/u 8.00 18,000 144,000 0.32% 1
2/6/2017
6-Feb-17 0.32% 0.32% 0.32% 24-Feb-17 79.91%
3.1.1.3 6.00 Stub End DN 110 c/u 6.00 4,500 27,000 0.06% 2
2/20/2017
21-Feb-17 0.00% 0.00% 0.00% 3-Mar-17 87.83%
3.1.1.4 8 0.00 Stub End DN 200 c/u 8.00 15,000 120,000 0.27% 1
2/6/2017
6-Feb-17 0.27% 0.27% 0.27% 10-Mar-17 95.69%
3.1.1.5 6.00 Flange Volante DN 110 c/u 6.00 6,800 40,800 0.09% 1
2/22/2017
22-Feb-17 0.00% 0.00% 0.00% 17-Mar-17 99.92%
3.1.1.6 8 0.00 Flange Volante DN 200 c/u 8.00 15,000 120,000 0.27% 1
2/6/2017
6-Feb-17 0.27% 0.27% 0.27% 24-Mar-17 100.00%
3.1.2.1 20.00 Curva BB 90º DN 100 c/u 20.00 2,200 44,000 0.10% 1
2/23/2017
23-Feb-17 0.00% 0.00% 0.00% 31-Mar-17 0.00%
3.1.2.2 2 0.00 Curva BB 90º DN 200 c/u 2.00 72,100 72,100 0.16% 1
2/6/2017
6-Feb-17 0.16% 0.16% 0.16%
3.1.2.3 1 1.00 Curva Patín BB 90º DN 100 c/u 2.00 75,000 150,000 0.33% 1
2/6/2017
6-Feb-17 0.33% 0.33% 0.17%
3.1.2.4 4.00 TEE BB DN 100 mm c/u 4.00 32,000 128,000 0.28% 1
2/24/2017
24-Feb-17 0.00% 0.00% 0.00%
3.1.2.5 2 0.00 TEE BB DN 200 mm c/u 2.00 85,400 170,800 0.38% 1
2/7/2017
7-Feb-17 0.38% 0.38% 0.38%
3.1.2.6 2.00 Reducción BB 150x75 mm c/u 2.00 25,000 50,000 0.11% 1
2/25/2017
25-Feb-17 0.00% 0.00% 0.00%
3.1.2.7 1.00 Reducción BB 200x100 mm c/u 1.00 41,000 41,000 0.09% 1
2/8/2017
8-Feb-17 0.09% 0.09% 0.00%
3.1.2.8 6.00 Terminal BB L=0,60 m DN 100 mm c/u 6.00 45,000 270,000 0.60% 1
2/27/2017
27-Feb-17 0.00% 0.00% 0.00%
3.1.2.9 2 0.00 Terminal BB L=0,60 m DN 200 mm c/u 2.00 85,000 170,000 0.38% 1 9-Feb-17 0.38% 0.38% 0.38%
2/9/2017
3.1.2.10 2.00 Terminal BA DN 100 mm c/u 2.00 76,000 152,000 0.34% 1
2/9/2017
9-Feb-17 0.34% 0.34% 0.00%
3.1.2.11 1.00 Terminal BB L=var m DN 100mm acero c/u 1.00 250,000 250,000 0.56% 1
2/28/2017
28-Feb-17 0.00% 0.00% 0.00%
3.1.3.1 1 1.00 Unión Desmontable DN 100 mm c/u 2.00 65,000 130,000 0.29% 1
2/10/2017
10-Feb-17 0.29% 0.29% 0.14%
3.1.3.2 1 0.00 Unión Desmontable DN 200 mm c/u 1.00 205,000 205,000 0.46% 1
2/10/2017
10-Feb-17 0.46% 0.46% 0.46%
3.1.3.3 8.00 Unión Brida Universal DN 100 mm c/u 8.00 22,000 176,000 0.39% 1
3/1/2017
1-Mar-17 0.00% 0.00% 0.00%
3.1.3.4 1.00 Unión Brida Universal DN 200 mm c/u 1.00 98,000 98,000 0.22% 1
3/1/2017
1-Mar-17 0.00% 0.00% 0.00%
3.1.3.5 1 0.00 Grifo con Brida Intermedia c/u 1.00 225,000 225,000 0.50% 4
2/8/2017
11-Feb-17 0.88% 0.50% 0.50%
Transporte Interno, Colocación y prueba de Tuberías y Piezas Especiales 0.00% 1
4.1.1 16.00 Tubería HDPE PE 100 PN 10 D:110 mm ml 16.00 9,800 156,800 0.35% 2
2/20/2017
21-Feb-17 0.00% 0.00% 0.00%
4.1.2 215 0.00 Tubería HDPE PE 100 PN 10 D:200 mm ml 215.00 15,420 3,315,300 7.38% 41
1/16/2017
25-Feb-17 5.40% 5.40% 7.38%
4.1.3 20.00 Instalación Tubería mediante tunelera d:110 m ml 20.00 350,000 7,000,000 15.57% 2
2/3/2017
4-Feb-17 93.44% 15.57% 0.00%
4.2.1.1 6.00 Junturas Electrofusionadas D:110 mm nº 6.00 12,000 72,000 0.16% 3
2/25/2017
27-Feb-17 0.00% 0.00% 0.00%
4.2.1.2 8 0.00 Junturas Electrofusionadas D:200 mm nº 8.00 19,500 156,000 0.35% 2
2/7/2017
8-Feb-17 1.39% 0.35% 0.35%
4.2.2.1 2.00 Junturas Brida D:75 mm nº 2.00 9,900 19,800 0.04% 2
2/26/2017
27-Feb-17 0.00% 0.00% 0.00%
4.2.2.2 30.00 Junturas Brida D:100 mm nº 30.00 12,400 372,000 0.83% 2
2/26/2017
27-Feb-17 0.00% 0.00% 0.00%
4.2.2.3 12 0.00 Junturas Brida D:200 mm nº 12.00 16,800 201,600 0.45% 6
2/19/2017
24-Feb-17 0.00% 0.00% 0.45%
4.2.3.1 2.00 Junta Anger D:110 mm nº 2.00 25,000 50,000 0.11% 1
2/25/2017
25-Feb-17 0.00% 0.00% 0.00%
4.2.4.1 1 1.00 Juntura Desmontable D:100 mm nº 2.00 8,750 17,500 0.04% 1
2/26/2017
26-Feb-17 0.00% 0.00% 0.02%
4.2.4.2 1.00 Juntura Desmontable D:200 mm nº 1.00 11,450 11,450 0.03% 1
2/27/2017
27-Feb-17 0.00% 0.00% 0.00%
Obras de Hormigón 0.00% 1
40%
20%
0%
16-Dec-16 23-Dec-16 30-Dec-16 6-Jan-17 13-Jan-
conexión Nueva Victoria y modificación ERP Reductora, Iquique.
Contratista:
Avance Programado
Avance Programado
6-Jan-17 13-Jan-17 20-Jan-17 27-Jan-17 3-Feb-17 10-Feb-17 17-Feb-17 24-Feb-17 3-Mar-17 10-Mar-17
P Reductora, Iquique.
Avance Programa
Avance Real