1.1 SEI RED PROVISIONAL COMUNICACIÓN UN 1 $ 1,003,535.

00
1.2 SEI RED ELÉCTRICA PROVICIONAL UN 1 $ 2,236,530.00
1.3 DEMOLICÓN PLACA MACIZA 0.15 M2 1233 $ 47,896.00
1.4 LOCALIZACIÓN Y REPLANTEO DE CIMIENTOS CON ELEMENTOS DEM2 1233 $ 14,942.00
1.5 SEI RED AGUA PROVICIONAL UN 1 $ 1,489,094.00
2.1 EXCAVACIÓN CARGUE A MANO + RETIRO DE ESCOMBROS CON BM3 97.85 $ 67,963.00
2.2 EXCAVACIÓN CON ORUGA Y RETIRO CON VOLQUETA 14M3 M3 1745.46 $ 43,087.00
2.3 SYC RELLENO COMPACTADO ROCA MUERTA INCLUYE PLANEACIÓM3 407.43 $ 50,468.00
3.1 SYP ZAPATAS CONCRETO REFORZADO 21MPa M3 343.42 $ 657,596.00
3.2 SYA ACERO DE REFUERZO 420MPa N 2 1/4" KG 104.4 $ 8,043.00
3.3 SYA ACERO DE REFUERZO 420MPa N 3 3/8" KG 5036.18 $ 8,046.00
3.4 SYA ACERO DE REFUERZO 420MPa N 4 1/2" KG 8750.43 $ 8,046.00
3.5 SYA ACERO DE REFUERZO 420MPa N 5 5/8" KG 5812.48 $ 6,665.00
3.6 SYA ACERO DE REFUERZO 420MPa N 6 3/4" KG 19555.31 $ 6,697.00
3.7 SYA ACERO DE REFUERZO 420MPa N 8 1" KG 791.21 $ 6,697.00
3.8 SYC LOSA DE CONCRETO 21MPa SOBRE LAMINA COLABORANTE M2 2283.3 $ 82,336.00
3.9 SYA ACERO DE REFUERZO 420MPa N 7 7/8 KG 12833.18 $ 6,872.00
3.10 SYC VIGA DE CIMENTACION CONCRETO 21MPa M3 110.87 $ 673,490.00
3.11 CONTRAPISO EN CONCRETO E=0.15 M2 1273.22 $ 145,238.00
3.12 SYC CONCRETO CICLOPEO 2500 PSI 40% RAJON PARA BASES M3 494.98 $ 304,279.00
3.13 SYC PDESTALES CONCRETO 21MPa M 29.19 $ 1,309,535.00
3.14 SYC FOSO ASCENSOR DE CONCRETO 28MPa M3 5.21 $ 683,381.00
3.15 SYC CONCRETO PARA HUELLAS ESCALERAS METALICA 21MPa M3 3.37 $ 570,353.00
3.16 SEI MALLA ELECTROSOLDADA M-131-5MM @15CM 2.40X6M KG 150.48 $ 8,824.00
3.17 SEI MALLA ELECTROSOLDADA M-084-4MM @15CM 2.40X6M KG 8255.46 $ 9,208.00
3.18 SYC GROUTING DE NIVELACION E=0.05 PLACAS BASE UN 42 $ 89,467.00
3.19 SYC
SPM ESTRUCTURA ACERO INCLUYE SOLDADURA TORNILLERÍA M2
SOLADO DE LIMPIEZA E=0.05 7 MPA 458.82 $ 18,737.00
4.1 SAND BLASTING + ANTICORROSIVO KG 576410 $ 9,680.00
4.2 SYC
0.10X0.12X0.29 MORTERO DE PEGA TIPO S INCLUYE LAVADO M2
DECK LAMINA COLABORANTE 2" C 18 2283 $ 157,517.00
5.1 IMPERMEABILIZACIÓN Y SELLO EN AMBAS CARAS M2 699.65 $ 78,692.00
5.2 SEI REFUERZO HORIZONTAL MUROS DE MAMPOSTERÍA EN GRAFKG 2.84 $ 3,679.00
5.3 SEI REFUERZO HORIZONTAL MUROS DE MAMPOSTERÍA EN GRAFKG 528.53 $ 4,095.00
6.1 SYC BASE BASE GRANULAR TIPO INVIAS B-400 M3 190.98 $ 105,555.00
6.2 SYC
SYC JUNTA DE CONTRACCION H0.05 + SELLO AUTONIVELANTE ML
JUNTA DE DE DILATACIÓN DE 6MM 582.54 $ 41,999.00
6.3 CAMA DE APOYO
SEI CUBIERTA + PASAJUNTAS
PANEL TECHMET 40NPIR
6 LISA
CAL0.35MX0.3
26/28 COLOR ML 394.92 $ 44,081.00
7.1 9002/9002 METECNO + CONSUMIBLES M2 1176 $ 248,588.00
7.2 SEI CANAL LÁMINA C 16 + PINTURA AMBAS CARAS + ESCALERILL ML 174 $ 198,469.00
TOTAL COSTO DIRECTO
ADMINISTRACIÓN 7%
IMPREVISTOS 2%
UTILIDAD 2.5%
IVA/UTILIDAD 19.00%

TOTAL PROYECTO

PLAZO DE ENTREGA
$ 1,003,535.00 $ 1,003,535.00
$ 2,236,530.00 $ 2,236,530.00
$ 47,896.00 $ 59,055,768.00
$ 14,942.00 $ 18,423,486.00
$ 1,489,094.00 $ 1,489,094.00
$ 67,963.00 $ 6,650,179.55
$ 43,087.00 $ 75,206,635.02
$ 50,468.00 $ 20,562,177.24
$ 657,596.00 $ 225,831,618.32
$ 8,043.00 $ 839,689.20
$ 8,046.00 $ 40,521,104.28
$ 8,046.00 $ 70,405,959.78
$ 6,665.00 $ 38,740,179.20
$ 6,697.00 $ 130,961,911.07
$ 6,697.00 $ 5,298,733.37
$ 82,336.00 $ 187,997,788.80
$ 6,872.00 $ 88,189,612.96
$ 673,490.00 $ 74,669,836.30
$ 145,238.00 $ 184,919,926.36
$ 304,279.00 $ 150,612,019.42
$ 1,309,535.00 $ 38,225,326.65
$ 683,381.00 $ 3,560,415.01
$ 570,353.00 $ 1,922,089.61
$ 8,824.00 $ 1,327,835.52
$ 9,208.00 $ 76,016,275.68
$ 89,467.00 $ 3,757,614.00
$ 18,737.00 $ 8,596,910.34
$ 9,680.00 $ 5,579,648,800.00
$ 157,517.00 $ 359,611,311.00
$ 78,692.00 $ 55,056,857.80
$ 3,679.00 $ 10,448.36
$ 4,095.00 $ 2,164,330.35
$ 105,555.00 $ 20,158,893.90
$ 41,999.00 $ 24,466,097.46
$ 44,081.00 $ 17,408,468.52
$ 248,588.00 $ 292,339,488.00
$ 198,469.00 $ 34,533,606.00
OTAL COSTO DIRECTO $ 7,902,420,552.07
ADMINISTRACIÓN 7% $ 553,169,438.64
IMPREVISTOS 2% $ 158,048,411.04
UTILIDAD 2.5% $ 197,560,513.80
IVA/UTILIDAD 19.00% $ 37,536,497.62

TOTAL PROYECTO $ 8,848,735,413.18

PLAZO DE ENTREGA 274


CUADRO DE ZAPATAS

TIPO B(CM) L(CM) T(CM) VOL (M3) ASB (CM) ASL(CM)


Z-1 340 340 70 8.1 24#6 24#6
Z-2 300 300 60 5.4 19#6 19#6
Z-3 300 450 90 12.2 32#7 21#7
Z-4 310 470 100 14.6 29#8 19#8
Z-5 300 300 60 5.4 19#6 19#6
Z-6 270 410 90 10.0 29#7 19#7
Z-7 200 200 60 2.4 12#6 12#6
Z-8 240 360 90 7.8 26# 17#7

PESO PEDESTALES
PEDESTAL CANTIDADVARILLA No.PESO KGVARILLA No. PESO KG VARILLA No. PESO KG CONCRETO
p1a 6 #7 127.1 #4 27.8 #3 24.7 0.57
p1b 15 #7 127.1 #4 24.4 #3 23.3 0.57
p1c 5 #7 127.1 #4 17.4 #3 16.7 0.57
p2 1 #7 168.9 #4 13.9 #3 13.3 0.57
p3 8 #7 158.8 #4 19.4 #3 22.2 0.66
p3a 7 #7 158.8 #4 31 #3 16.7 0.66
Total kg #7 867.8 #4 133.9 #3 116.9 TOTAL
CONTRATADO

CUADRO PESO TIPOS ZAPATAS FUNDIDAS


TIPO B (M) L(M) ASB kg ASL kg
Z1 3.4 3.4 3.95 24 212 3.95 24 212
Z2 3 3 3.55 19 151 3.55 19 151
Z3 3 4.5 3.25 32 316 5.15 21 329

Z4 3.1 4.7 3.4 29 391.7 5.45 19 411.4

Z5 3 3 3.2 19 135.9 3.55 19 150.8


Z6 2.7 3.1 2.95 29 260.2 4.75 19 274.5

Z7 2 2 2.2 12 59 2.55 12 68.4


Z8 2.4 3.6 2.65 26 209.6 4.25 17 219.8
S

AST(CM) CANTIDAD CONCRETO


TOTAL
#4-10CM 15 121.38
#4-10CM 10 54
#5-10CM 9 109.35
#5-10CM 1 14.57
#4-10CM 3 16.2
#5-10CM 1 9.963
#4-10CM 1 2.4
#5-10CM 2 15.552
TOT M3 343.415
CONTRATADO 343.42
TOTALM3 CONCRETO VIGAS
3.432 VC 51.12
8.58 VC 36.45
2.86 VCE1 1.7
0.572 VCE3 1.2
5.28 VCE4 1.35
4.62 VCE5 1.35
25.34 VCE6 1.13
29.19 VCE2 1.03
TOTAL M3 95.33
CONTRATADO 110.87

O TIPOS ZAPATAS FUNDIDAS


# CANT. TOTAL KG AST kg # TOTAL KG
6 15 6356 3.25 68 219.7 4 3295.1
6 10 3015 2.85 60 170.0 4 1699.7
7 9 5808 2.85 30 303.8 5 2734.236
4.35 45
8 1 803 2.95 29 321.3 5 321.3
4.55 46
6 3 860 2.85 57 161.5 4 484.4
7 1 535 2.55 26 135.1 5 135.1
2.95 30
6 1 127 1.85 37 68.0 4 68.0
7 2 859 2.25 23 184.7 5 369.5
3.45 35
ÁREA
#3 0.71
#4 1.29
#5 1.99
#6 2.84
#7 3.87
#8

KG VARILLAS TOTALES
# TOT KG CONSOLIDADO CONTRATADO
#3 0 3754.9 5036.18
#4 5547 5547 8750.43
#5 3560 3560 5812.48
#6 10359 18252 19555.31
#7 7202 7202 12833.18
#8 803 803 791.25

CONCRETO POR ZATAPAS


Z1 8.09 Z5 5.4
Z2 5.40 Z6 9.96
Z3 12.15 Z7 2.4
Z4 14.57 Z8 7.78
TOTAL M3 343.415
PESO
0.56
0.994
1.552
2.235
3.042
3.973
#6 2.23
KG/M
#3 0.56

EJE A KG EJE EJE B KG EJE EJE C


#6 69.9 #6 117.1 #6
VC-1 5.8 3 4.65 3 9 3 8.5 3 9
#3 KG EJE #3 KG EJE #3
1.6 59 52.9 1.6 65 58.2 1.6

EJE A KG EJE EJE B KG EJE EJE C


#6 69.9 #6 117.1 #6
VC-2 5.8 3 4.65 3 9 3 8.5 3 9
#3 KG EJE #3 KG EJE #3
1.6 59 52.9 1.6 65 58.2 1.6

EJE A KG EJE EJE B KG EJE EJE C


#6 69.9 #6 117.1 #6
VC-3 5.8 3 4.65 3 9 3 8.5 3 13.8
#3 KG EJE #3 KG EJE #3
1.6 59 52.9 1.6 65 58.2 1.6

EJE A KG EJE EJE B KG EJE EJE C


#6 69.9 #6 256.6 #6
VC-4 5.8 3 4.65 3 19.6 3 18.75 3 9
#3 KG EJE #3 KG EJE #3
1.6 59 52.9 1.6 65 58.2 1.6

EJE A KG EJE EJE B KG EJE EJE C


#6 69.9 #6 117.1 #6
VC-5 5.8 3 4.65 3 9 3 8.5 3 9
#3 KG EJE #3 KG EJE #3
1.6 59 52.9 1.6 65 58.2 1.6

EJE A KG EJE EJE B KG EJE EJE C


#6 69.9 #6 117.1 #6
VC-6 5.8 3 4.65 3 9 3 8.5 3 9
#3 KG EJE #3 KG EJE #3
1.6 59 52.9 1.6 65 58.2 1.6

EJE 6 KG EJE EJE 5 KG EJE EJE 4


#6 60.9 #6 92.3 #6
VC-7
CANT 5 4.45 3 4.65 3 7 3 6.8 3 7
#3 KG EJE #3 KG EJE #3
1.6 51 45.7 1.6 48 43.0 1.6

EJE 6 KG EJE EJE 5 KG EJE EJE 4


#6 60.9 #6 92.3 #6
VC-7A 4.45 3 4.65 3 7 3 6.8 3 12
#3 KG EJE #3 KG EJE #3
1.6 51 45.7 1.6 48 43.0 1.6
EJE 6 KG EJE EJE 5 KG EJE EJE 4
#6 60.9 #6 92.3 #6
VC-8 4.45 3 4.65 3 7 3 6.8 3 7
#3 KG EJE #3 KG EJE #3
1.6 51 45.7 1.6 48 43.0 1.6

EJE B KG EJE EJE C KG EJE


#6 59.1 #6 101.7
VCE-1 2.65 5 2.65 5 7.6 3 7.6 3
#3 KG EJE #3 KG EJE
1.6 43 38.5 1.6 13 11.6 50.2

EJE B / C KG EJE
#6 66.2
VCE-2 4.95 3 4.95 3
#3 KG EJE
1.6 32 28.7 28.7 66.2

EJE B / C KG EJE
#6 48.2
VCE-3
CANT 2 3.6 3 3.6 3
#3 KG EJE
1.6 25 22.4 44.8 96.3

EJEF KG EJE
#6 105.3
VCE-4 5.9 4 5.9 4
#3 KG EJE
1.6 35 31.4 31.4 105.3

EJE F/G KG EJE


#6 107.9
VCE-5 6.05 4 6.05 4
#3 KG EJE
1.6 35 31.4 31.4 107.9

EJE F/G KG EJE


#6 110.6
VCE-6 6.2 4 6.2 4
#3 KG EJE
1.6 35 31.4 31.4 110.6

PEDESTALES
VIGAS DE CIMENTACIÓN

KG EJE EJE D KG EJE EJE E


117.1 #6 110.4 #6
3 8.5 3 8 3 8.5 3 8 3 8
KG EJE #3 KG EJE #3
66 59.1 1.6 58 52.0 1.6 61

KG EJE EJE D KG EJE EJE E


117.1 #6 110.4 #6
3 8.5 3 8 3 8.5 3 8 3 8
KG EJE #3 KG EJE #3
66 59.1 1.6 58 52.0 1.6 61

KG EJE EJE D KG EJE EJE E


188.7 #6 128.1 #6
3 14.4 3 9.75 3 9.4 3 5.7 3 5.2
KG EJE #3 KG EJE #3
66 59.1 2 58 65.0 1.6 61

KG EJE EJE D KG EJE EJE E


117.1 #6 110.4 #6
3 8.5 3 8 3 8.5 3 8 3 8
KG EJE #3 KG EJE #3
66 59.1 2 58 65.0 1.6 61

KG EJE EJE D KG EJE EJE E


117.1 #6 110.4 #6
3 8.5 3 8 3 8.5 3 8 3 8
KG EJE #3 KG EJE #3
66 59.1 2 58 65.0 1.6 61

KG EJE EJE D KG EJE EJE E


0.0 #6 0.0 #6
3 8.5 3 8 3 8.5 3 8 3 8
KG EJE #3 KG EJE #3
66 59.1 2 58 65.0 1.6 61

KG EJE EJE 3 KG EJE EJE 2


93.7 #6 87.0 #6
3 7 3 7 3 6 3 7 3 5.5
KG EJE #3 KG EJE #3
51 45.7 2 37 41.4 1.6 54

KG EJE EJE 3 KG EJE EJE 2


157.2 #6 141.8 #6
3 11.5 3 11.5 3 9.7 3 7 3 5.5
KG EJE #3 KG EJE #3
51 45.7 2 37 41.4 1.6 54
KG EJE EJE 3 KG EJE EJE 2
93.7 #6 87.0 #6
3 7 3 7 3 6 3 7 3 5.5
KG EJE #3 KG EJE #3
52 46.6 2 37 41.4 1.6 54

160.8

TOTAL KG #3 TOTAL KG #6
3754.9 7893.8
TOTAL KG #3 TOTAL KG #6
KG EJE EJE F KG EJE
107.0 #6 109
3 8.1 3 8.2 3
KG EJE #3 KG EJE
54.7 1.6 35 31.4 308.2 630.5

KG EJE EJE F KG EJE


107.0 #6 109
3 8.1 3 8.2 3
KG EJE #3 KG EJE
54.7 1.6 40 35.8 312.7 630.5

KG EJE EJE F KG EJE


72.9 #6 138
3 10.4 3 10.2 3
KG EJE #3 KG EJE
54.7 1.6 45 40.3 330.2 714.5

KG EJE EJE F KG EJE


107.0 #6 146
3 11 3 10.75 3
KG EJE #3 KG EJE
54.7 1.6 51 45.7 335.6 806.5

KG EJE EJE F KG EJE


107.0 #6 151
3 11.4 3 11.2 3
KG EJE #3 KG EJE
54.7 1.6 56 50.2 340.0 672.7

KG EJE EJE F KG EJE


0.0 #6 151
3 11.4 3 11.2 3
KG EJE #3 KG EJE
54.7 1.6 56 50.2 340.0 338.2

KG EJE EJE 1 KG EJE


83.6 #6 58.9
3 4 3 4.8 3
KG EJE #3 KG EJE
48.4 1.6 0 0.0 1121.1 2381.6

KG EJE EJE 1 KG EJE


83.6 #6 58.9
3 4 3 4.8 3
KG EJE #3 KG EJE
48.4 1.6 0 0.0 224.2 594.7
KG EJE EJE 1 KG EJE
83.6 #6 59.9
3 4.05 3 4.9 3
KG EJE #3 KG EJE
48.4 1.6 0 0.0 225.1 477.3
KG ACERO REFUERZO CONCRETO 21M
KG EJECUTADOS KG CONTRATADOS DIF(KG)
#8 803 791.21 -12 ZAPATAS
#7 8070 12833.18 4764 VIGAS CIMENTACIÓN
#6 18252 19555.31 1303 PEDESTALES
#5 3560 5812.48 2252
#4 6279 8750.43 2472
#3 4483.8 5036.18 552

VIGA PERIMETRAL KG VOL (M3)


ML 136.61 5.7
#4 601.084 597.5
#3 1366.1 0.8 1092.88 612.0

ÁREA PESO
#3 0.71 0.56
#4 1.29 0.994
CONCRETO 21MPA
M3 EJECUTADOS M3 CONTRATADOS DIF(M3)
343.42 343.42 0.00
101.1 110.87 9.8
25.34 29.2 3.8