1 CARTA DE SOLICITUD
12 CONTRATO ORIGINAL
15 CERTIFICADO FUNDEMPRESA
18 MEDIO MAGNETICO
PROYECTO:
3 COMPUTOS METRICOS
4 PLANOS REFERENCIALES
9 FOTOGRAFIAS DE RESPALDO
3 INFORME LEGAL
SUPERVISOR. FISCAL:
CHECK LIST CONTRATO MODIFICATORIO
SUP. DE OBRAS:
3 COMPUTOS METRICOS
4 PLANOS REFERENCIALES
9 FOTOGRAFIAS DE RESPALDO
3 INFORME LEGAL
SUPERVISOR. FISCAL:
INFORME TECNICO
CITE: G.A.M.C./D.O.P.U./Nº 037/2017
A: PROF. JUAN CHINO SALINAS
H. ALCALDE MUNICIPAL DE CARACOLLO
VIA: LORENZO MAYTA CHILLCA
SECRETARIO MUNICIPAL TECNICO
DE: OMAR QUISPE FERNANDEZ
FISCAL DE OBRA G.A.M.C.
PROYECTOCONSTRUCCION UNIDAD EDUCATIVA TECNICO HUMANISTICO EVO MORALES AYMA - CARACOLLO
INFORME DE APROBACION DE CONTRATO MODIFICATORIO Nº1 POR CREACION DE NUEVOS ITEMS Y
REF.:
AMPLIACION DE PLAZO.
FECHA: Monday, May 15, 2017
El motivo de la presente para dirigirme a su autoridad, con respecto al contrato modificatorio Nº 1 por ceracion de nuevos items y ampliacion de
plazo del proyecto mensionado líneas arriba, a la misma tengo a bien informar lo siguiente:
1.- ANTECEDENTES
El proyecto CONSTRUCCION UNIDAD EDUCATIVA TECNICO HUMANISTICO EVO MORALES AYMA - CARACOLLO, se esta
ejecutando con el financiamiento de la Unidad de Proyectos Especiales (UPRE) dependiente del Ministerio de la Presidencia dentro el Programa
Bolivia Cambia Evo Cumple. Así mismo en fecha 06 de abril del 2016, se realizo la firma de contrato del proyecto entre el GOBIERNO
AUTONOMO MUNICIPAL DE CARACOLLO y la empresa constructora "SERVICIO INTEGRAL EN PLANIFICACION Y
CONSTRUCCION SIPCOM S.R.L.", representado por el señor Nery Herbert Challapa Lucana, por un monto de contrato de Bs. 6'928.321,54
(Seis Millones Novecientos Veintiocho Mil Trescientos Veintiuno con 54/100 Bolivianos), con plazo de ejecución de 345 días calendario, iniciando
la obra en fecha 13/04/2016.
Segun orden de cambio Nº 1 de ampliacion de plazo Nº 1, fue aprobado 56 dias calendario, fecha de conclusion 18 de mayo de 2017 años, total
plazo de ejecucion mas ampliacion de plazo Nº 1 401 dias calendario.
La supervisión es externa y esta cargo de la empresa "COINC - C" CONSTRUCCION DE OBRAS DE INGENIERIA CIVIL Y
CONSULTORIA representado por el señor Ing. Augusto Condori Gomez, de acuerdo a lo solicitud de contrato modificatorio Nº 1 por creacion de
nuevos items y ampliacion de plazo presentada por la empresa ejecutora; la supervisor tuvo la tarea de verificar y revisar los respaldos de
justificacion para considerar el contrato modificatorio y ampliacion de plazo mismo que aprueba con un informe tecnico recepcionado en fecha 15
de mayo de 2017.
2.- CONCLUSIONES
En base al informe técnico elaborado por el Supervisor de obra, después de revisada la documentación de respaldo presentada por la empresa
contratista en lo que se refiere al contrato modificatorio y la ampliación de plazo No. 1, se concluye que es procedente y justificada el contrato
modificatorio por la creación de nuevos ítems y la ampliación de plazo No.1.
El contrato Modificatorio no incrementa de ninguna manera el monto de contrato, solo conlleva a reajustar los volúmenes de los ítem del proyecto
además de la creación de nuevos ítems que no fueron contemplados dentro el proyecto inicial y la ampliación de plazo bajo el siguiente detalle:
Nuevos items:
- Escalera de Hormigon Armado.
- Malla de proteccion Granizo.
- Contrapiso sobre Losa.
- Revoque Cielo Falso Incl/Maderamen.
- Muro de contencion de Hº Cº.
- Prov. e Inst. Inodoro Tanque Bajo C/Acc.
- Coloc. Pantalla LET 60 x60 cm. 22 Watts.
- Interruptor Doble.
- Cable 35 mm. x 3 Trifasico.
- Losa Prefabricada Para Graderias (0,60 x 0,16 M).
- Prov. y Coloc. iluminacion 400 incluye cableado.
- Gradas de Hº Cº.
- Cielo Falso Prefabricado.
- Revoque Cielo Falso Incluye Maderamen.
- Zapata de Hormigon Armado.
3.- RECOMENDACIONES
Por consiguiente esta Fiscalización Recomienda que mediante la instancia que corresponde y de acuerdo a términos de contrato según la
CláusulaTrigésima (Modificacion de las obras) numeral 30.4 inciso c) mediante contrato modificatorio párrafo del uno al tres solo en caso
extraordinario en que la obra debe ser complementada o por otras circunstancias de fuerza mayor o caso fortuito que determinen una modificacion
significativa en el diseño de la obray que signifique un decremento o incremento independiente a la emision de ordenes de cambio, el supervisor
podra formular el documento de sustento tecnico - financiero que establesca las causas y razones por las cuales deberia ser suscrito este documento.
A su vez también en base a la aprobación de la supervisión se recomienda la ampliación de plazo de ejecución de la obra en 35 Días Calendario, en
favor de la empresa.
Atentamente.
PLANILLA DE AVANCE N° 2
(EN BOLIVIANOS)
MONTO DE CONTRATO (Bs.): 298544.71 PROYECTO: CONSTRUCCION UNIDAD EDUCATIVA FECHA ORDEN A PROCEDER: 8/31/2016
TECNICO HUMANISTICO EVO MORALES AYMA
MONTO ORDEN DE CAMBIO (Bs.): 0.00 - CARACOLLO FECHA DE PARALIZACION: 0
MONTO FINAL DE EJECUCION (Bs.): 298544.71 CONTRATISTA: EMPRESA CONSTRUCTORA FLOR DE LOS ANDE FECHA DE REINICIO: 0
FECHA DE CONTRATO: 8/24/2016 UBICACIÓN: JANCOÑUÑO - CENTRAL JANCOÑUÑO DIAS PARALIZADOS: 0
PLAZO DE EJECUCION DIAS CALENDARIO: 139 FECHA DE EMISION: 5/15/2017 FECHA DE ENTREGA PROVISIONAL: 1/16/2017
FECHA DE ENTREGA DEFINITIVA:
1 REPLANTEO Y TRAZADO glb 1.00 478.05 478.05 1.00 100.00 478.05 0.00 0.00 0.00 1.00 100.00 478.05
2 EXCAVACION (0-2 M.) S. SEMIDURO m³ 24.41 59.04 1,441.17 24.35 99.75 1,437.62 0.00 0.00 0.00 24.35 99.75 1437.62
3 ZAPATAS DE Hº Aº m³ 3.22 1,904.27 6,131.75 3.22 100.00 6,131.75 0.00 0.00 0.00 3.22 100.00 6131.75
4 COLUMNAS DE H° A° + ENLUCIDO EXTERIOR m³ 2.38 3,009.33 7,162.21 1.97 82.77 5,928.38 0.00 0.00 0.00 1.97 82.77 5928.38
5 CIMIENTO DE HORMIGON CICLOPEO m³ 13.59 439.21 5,968.86 13.41 98.68 5,889.81 0.00 0.00 0.00 13.41 98.68 5889.81
6 SOBRECIMIENTOS DE Hº Cº + IMPERMEABILIZACION m³ 2.74 854.45 2,341.19 2.73 99.64 2,332.65 0.00 0.00 0.00 2.73 99.64 2332.65
7 MURO LADRILLO GAMBOTE (VISTO) m² 192.28 173.93 33,443.26 191.28 99.48 33,269.33 0.00 0.00 0.00 191.28 99.48 33269.33
8 VIGA DE ENCADENADO DE Hº Aº + ENLUCIDO EXTERIOR m³ 3.26 2,506.04 8,169.69 3.24 99.39 8,119.57 0.00 0.00 0.00 3.24 99.39 8119.57
9 CUBIERTA CALAMINA PREPINTADA m² 153.70 284.87 43,784.52 0.00 0.00 0.00 153.70 100.00 43,784.52 153.70 100.00 43784.52
10 CUMBRERA DE CALAMINA PLANA PREPINTADA m 3.70 82.33 304.62 0.00 0.00 0.00 3.70 100.00 304.62 3.70 100.00 304.62
11 PARAPETO DE LADRILLO 6H E=12CM. m² 13.27 130.08 1,726.16 0.00 0.00 0.00 5.25 39.56 682.92 5.25 39.56 682.92
12 CUBERTINA DE Hº Aº m 11.93 133.86 1,596.95 0.00 0.00 0.00 11.93 100.00 1,596.95 11.93 100.00 1596.95
13 REVOQUE EXTERIOR DE CEMENTO m² 13.27 115.18 1,528.44 0.00 0.00 0.00 4.90 36.93 564.38 4.90 36.93 564.38
14 PINTURA EXTERIOR - LATEX m² 13.27 13.50 179.15 0.00 0.00 0.00 5.25 39.56 70.88 5.25 39.56 70.88
15 CIELO FALSO DE YESO MAS MADERAMEN m² 108.94 193.32 21,060.28 0.00 0.00 0.00 107.06 98.27 20,696.84 107.06 98.27 20696.84
PUERTA DE MADERA ROBLE TIPO TABLERO +
16 m² 23.10 1,549.60 35,795.76 0.00 0.00 0.00 23.10 100.00 35,795.76 23.10 100.00 35795.76
QUINCALLERIA
17 PROV. Y COLOC. TUBERIA DE PVC D=1/2" m 40.00 22.56 902.40 0.00 0.00 0.00 20.00 50.00 451.20 20.00 50.00 451.20
18 REVOQUE INTERIOR DE YESO m² 265.11 81.54 21,617.07 0.00 0.00 0.00 264.39 99.73 21,558.36 264.39 99.73 21558.36
19 VENTANA CORREDIZA ALUMINIO MAS VIDRIO E=4MM m² 23.60 477.55 11,270.18 0.00 0.00 0.00 23.60 100.00 11,270.18 23.60 100.00 11270.18
20 ALEROS m² 20.15 244.36 4,923.85 0.00 0.00 0.00 20.15 100.00 4,923.85 20.15 100.00 4923.85
21 BOTAGUAS DE Hº Aº m 23.60 124.06 2,927.82 0.00 0.00 0.00 16.40 69.49 2,034.58 16.40 69.49 2034.58
22 PROV. Y TENDIDO TUBO PVC C/9 DESAGUE 4" m 20.00 37.20 744.00 0.00 0.00 0.00 10.00 50.00 372.00 10.00 50.00 372.00
23 PROV. Y TENDIDO TUBO PVC C/9 DESAGUE 2" m 10.00 25.28 252.80 0.00 0.00 0.00 10.00 100.00 252.80 10.00 100.00 252.80
24 CAJA INTERCEPTORA DE PVC pza 3.00 163.50 490.50 0.00 0.00 0.00 2.00 66.67 327.00 2.00 66.67 327.00
25 CONTRAPISO DE CEMENTO + EMPEDRADO m² 108.94 113.05 12,315.67 0.00 0.00 0.00 107.06 98.27 12,103.13 107.06 98.27 12103.13
26 REJILLA DE PISO pza 3.00 64.09 192.27 0.00 0.00 0.00 2.00 66.67 128.18 2.00 66.67 128.18
27 PISO DE CERAMICA ESMALTADA m² 108.94 196.36 21,391.46 0.00 0.00 0.00 107.06 98.27 21,022.30 107.06 98.27 21022.30
28 ZOCALO DE CERAMICA ESMALTADA H=0.20 M. m 117.68 83.31 9,803.92 0.00 0.00 0.00 117.43 99.79 9,783.09 117.43 99.79 9783.09
29 REVESTIMIENTO DE CERAMICA m² 25.12 196.60 4,938.59 0.00 0.00 0.00 25.12 100.00 4,938.59 25.12 100.00 4938.59
30 PINTURA INTERIOR LATEX m² 374.05 20.18 7,548.33 0.00 0.00 0.00 371.45 99.30 7,495.86 371.45 99.30 7495.86
31 ILUMINACION FLUORECENTE 2 X 40W pto 12.00 414.19 4,970.28 0.00 0.00 0.00 12.00 100.00 4,970.28 12.00 100.00 4970.28
32 TOMACORRIENTES pto 12.00 173.06 2,076.72 0.00 0.00 0.00 12.00 100.00 2,076.72 12.00 100.00 2076.72
33 TABLERO DE DISTRIBUCION pza 1.00 375.02 375.02 0.00 0.00 0.00 1.00 100.00 375.02 1.00 100.00 375.02
34 TANQUE DE AGUA PLASTICO 600LT + ACCESORIOS pza 1.00 863.99 863.99 0.00 0.00 0.00 1.00 100.00 863.99 1.00 100.00 863.99
35 LAVAMANOS BLANCO C/PEDESTAL pza 2.00 544.25 1,088.50 0.00 0.00 0.00 2.00 100.00 1,088.50 2.00 100.00 1088.50
36 INODORO TANQUE BAJO pza 2.00 555.30 1,110.60 0.00 0.00 0.00 2.00 100.00 1,110.60 2.00 100.00 1110.60
37 DUCHA pza 1.00 1,150.64 1,150.64 0.00 0.00 0.00 1.00 100.00 1,150.64 1.00 100.00 1150.64
38 CAMARA DE INSPECCION H° C° (60*60) pza 2.00 857.48 1,714.96 0.00 0.00 0.00 1.00 50.00 857.48 1.00 50.00 857.48
39 CAMARA SEPTICA pza 1.00 3,075.81 3,075.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
40 POZO ABSORBENTE D=2.00 MTS pza 1.00 1,289.35 1,289.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
41 LOSA LLENA DE Hº Aº m³ 0.29 1,660.58 481.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
42 ACERAS m² 52.72 89.15 4,699.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
43 CANALETA DE CALAMINA PLANA Nº 28 m 32.16 94.79 3,048.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
44 BAJANTE PVC DE 4" m 28.00 39.62 1,109.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
45 PLACA DE ENTREGA DE OBRAS pza 1.00 679.36 679.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
46 LIMPIEZA GENERAL GLB glb 1.00 379.20 379.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
ERROR DE REDONDEO 0.00 0.00 0.00 0.00
298,544.67 21.30% 63587.16 71.23% 212,651.24 92.53% 276,238.39
EMPRESA CONTRATISTA SUPERVISOR G.A.M.C. FISCAL DE OBRA OO. PP. G.A.M.C. STRIO. MPAL. TECNICO G.A.M.C.
PLANILLA DE AVANCE N° 1
(EN BOLIVIANOS)
MONTO DE CONTRATO (Bs.): PROYECTO: FECHA ORDEN A PROCEDER:
MONTO ORDEN DE CAMBIO (Bs.): FECHA DE PARALIZACION:
MONTO FINAL DE EJECUCION (Bs.): CONTRATISTA: FECHA DE REINICIO:
FECHA DE CONTRATO: UBICACIÓN: DIAS PARALIZADOS:
PLAZO DE EJECUCION DIAS CALENDARIO: FECHA DE EMISION: FECHA DE ENTREGA DEFINITIVA:
FECHA DE ENTREGA PROVISIONAL:
ORDEN DE CAMBIO O CONTRATO
SEGUN CONTRATO MODIFICATORIO Nº 1 AVANCE ANTERIOR AVANCE ACTUAL TOTAL AVANCE ACUMUNLADO
Nº DESCRIPCION UNIDAD MONTO % DE
CANT. P. U. CANT. P.U. MONTO CANT. % MONTO CANT. % MONTO CANT. MONTO
ITEM AVANCE
1 REFACCION DE CIELO RASO DE YESO M2 80.00 40.10 3,208.00 0.00 40.10 0.00 0.00 0.00 0.00 80.00 100.00 3,208.00 80.00 100.00 3208.00
2 REVOQUE INTERIOR DE YESO M2 80.00 38.02 3,041.50 0.00 38.02 0.00 0.00 0.00 0.00 80.00 100.00 3,041.50 80.00 100.00 3041.50
3 ACERA PERIMETRAL MAS SOLADO DE PIEDRA M2 57.00 45.00 2,565.00 0.00 45.00 0.00 0.00 0.00 0.00 57.00 100.00 2,565.00 57.00 100.00 2565.00
4 REVOQUE EXTERIOR S/ADOBE M2 100.00 45.00 4,500.00 0.00 45.00 0.00 0.00 0.00 0.00 100.00 100.00 4,500.00 100.00 100.00 4500.00
5 PINTURA EXTERIOR LATEX M3 95.00 12.00 1,140.00 0.00 12.00 0.00 0.00 0.00 0.00 95.00 100.00 1,140.00 95.00 100.00 1140.00
6 PINTURA INTERIOR LATEX M2 90.00 10.00 900.00 0.00 10.00 0.00 0.00 0.00 0.00 90.00 100.00 900.00 90.00 100.00 900.00
7 REFACCION DE GRADAS M3 3.10 30.00 93.00 0.00 30.00 0.00 0.00 0.00 0.00 3.10 100.00 93.00 3.10 100.00 93.00
8 ZOCALO DE CEMENTO ENLUCIDO M2 12.50 25.00 312.50 0.00 25.00 0.00 0.00 0.00 0.00 12.50 100.00 312.50 12.50 100.00 312.50
9 PISO DE MACHIMBRE M2 66.00 40.00 2,640.00 0.00 40.00 0.00 0.00 0.00 66.00 100.00 2,640.00 66.00 100.00 2640.00
ERROR DE REDONDEO 0.00 0.00 0.00 0.00 0.00
18,400.00 0.00 0.00% 0.00 100.00% 18,400.00 100.00% 18,400.00
EMPRESA CONTRATISTA SUPERVISOR G.A.M.C. FISCAL DE OBRA OO. PP. G.A.M.C. STRIO. MPAL. TECNICO G.A.M.C.
PLANILLA DE RETENCION PAGABLE (7%)
CONSTRUCCION UNIDAD FECHA ORDEN A
MONTO DE CONTRATO (Bs.): 298,544.71 PROCEDER: 8/31/2016
EDUCATIVA TECNICO
PROYECTO:
HUMANISTICO EVO MORALES
MONTO ORDEN DE CAMBIO (Bs.): 0.00 AYMA - CARACOLLO FECHA DE PARALIZACION: 0
EMPRESA CONSTRUCTORA FLOR
MONTO FINAL DE EJECUCION (Bs.): 298,544.71 CONTRATISTA:
DE LOS ANDES
FECHA DE REINICIO: 0
FECHA DE CONTRATO: 8/24/2016 UBICACIÓN: JANCOÑUÑO - CENTRAL JANCOÑ DIAS PARALIZADOS: 0
PLAZO DE EJECUCION DIAS FECHA DE ENTREGA
CALENDARIO:
139 FECHA DE EMISION: 6/24/2016
PROVISIONAL: 1/16/2017
FECHA DE ENTREGA
FECHA ORDEN A PROCEDER: 8/31/2016 DEFINITIVA: 12/30/1899
Son: #VALUE!
EMPRESA CONSTRUCTORA O CONTRATISTA SUPERVISOR G.A.M.C. FISCAL DE OBRAS G.A.M.C. STRIO. MPAL. TECNICO G.A.M.C.
RESUMEN DE PLANILLA
PLANILLA DE PAGO N° 2 (Cierre)
B: RESUMEN DE PLANILLA N° 1
EJECUCIÓN PRESUPUESTO
PLAZO INICIO FINAL BOLIVIANOS PORCENTAJE
EJECUTADO EN EL
60 2/4/2016 4/4/2016 293,230.62 1593.65%
PERIODO
EJECUTADO
ACUMULADO A LA 60 2/4/2016 4/4/2016 293,230.62 1593.65%
FECHA
SALDO POR EJECUTAR -274,830.62 -1493.65%
RETENCION DEL 20%
POR ANTICIPO DE 20,526.14 111.56%
CONTRATO
RETENCION DEL 7% POR
CUMPL. CONTR. 20,526.14 111.56%
ACUMULADO
LIGUIDO PAGABLE 272,704.48 1482.09%
La empresa contratista conoce y acepta todas las clausulas establecidas en el contrato firmado entre ambas partes.
Para constancia de lo expuesto leneas arriba, firman a la presente acta los presentes.
ACTA DE RECEPCIÓN PROVISIONAL
ENTIDAD CONTRATANTE: GOBIERNO AUTÓNOMO MUNICIPAL DE SICA SICA
CONTRATISTA: Sr. Oscar Oscarin Callex Romeo
ANTECEDENTES:
UBICACIÓN: Oruro - Cercado - Caracollo - Quemalla FECHA: 05 - Nov. - 14 HORA: 10:00 a.m.
PROYECTO: MEJ. AULAS U. E. TOCOPILLA
MONTO DEL CONTRATO: 16,972.80
FECHA ORDEN A PROCEDER: 3/4/2016
MONTO ORDEN DE CAMBIO O CONTRATO MODIFICATORIO: 0.00
MONTO FINAL DE EJECUCIÓN DE LA OBRA (Bs): 16,972.80
PLAZO DE EJECUCIÓN SEGÚN CONTRATO: 40 D.C.
AMPLIACIÓN DE PLAZO: 0 D.C.
TOTAL PLAZO DE EJECUCIÓN: 40 D.C.
PLAZO PARA LA ENTREGA DEFINITIVA: 60 D.C.
OBSERVACIONES:
ÍTEM:……………………………………………………………….…...…………………………………………….
ÍTEM:……………………………………………………………….…...…………………………………………….
ÍTEM:……………………………………………………………….…...…………………………………………….
ÍTEM:……………………………………………………………….…...…………………………………………….
PARTICIPANTES
RECEPCIÓN PROVISIONAL
Luego de haber realizado la verificacion en sitio todos los ítems del contrato ya concluidos al 100%, se da a la Empresa Contratista un
plazo de 5 días calendario, para iniciar con las enmiendas de las observaciones realizadas a la Obra y un maximo de 30 días para la
nueva inspección, antes de la recepción definitiva de la Obra que se realizara a los 90 días de la recepción provisional.
ANTECEDENTES
UBICACIÓN: Oruro - Cercado - Caracollo - Quemalla FECHA: 05 - Nov. - 14 HORA: 10:00 a.m.
PARTICIPANTES
RECEPCIÓN DEFINITIVA:
En vista de haber cumplido y verificado las correcciones efectuadas a las observaciones realizadas en la entrega provisional por la
empresa contratista, se procede a la RECEPCIÓN DEFINITIVA del proyecto, la misma queda a partir de la fecha en manos y
responsabilidad de los beneficiarios, el cuidado y mantenimiento de la infraestructura denominado.