PLANILLA PLANILLA DE AVANCE Nº 2

DIRECTOR DE OBRAS PUBLICAS: PROF. JUAN CHINO SALINAS


ENTE FINANCIADOR: GOBIERNO AUTONOMO MUNICIPAL DE CARACOLLO
PROGRAMA: GESTION DE SALUD
APERTURA PROGRAMATICA: 20 0002 000
SUPERVISOR DE OBRA: OMAR QUISPE FERNANDEZ
PORCENTAJE AVANCE FISICO ACTUAL: 92.53%
PORCENTAJE AVANCE FINANCIERO ACTUAL: 21.30%
PROYECTO: CONSTRUCCION UNIDAD EDUCATIVA TECNICO HUMANISTICO EVO MORALES A
MONTO DE CONTRATO (Bs.): 298544.71
MONTO ORDEN DE CAMBIO (Bs.): 0.00
298544.71
FECHA DE CONTRATO: 8/24/2016
PLAZO DE EJECUCION DIAS CALENDARIO: 139
EMPRESA CONTRATISTA: EMPRESA CONSTRUCTORA FLOR DE LOS ANDES
UBICACIÓN: JANCOÑUÑO - CENTRAL JANCOÑUÑO
FECHA DE EMISION: 5/15/2017
FECHA ORDEN A PROCEDER: 8/31/2016
FECHA DE PARALIZACION: 0
FECHA DE REINICIO: 0
DIAS PARALIZADOS: 0.00
FECHA DE ENTREGA PROVISIONAL: 1/16/2017
PLAZO PARA ENTREGA DEFINITIVA: 0
FECHA DE ENTREGA DEFINITIVA: 0
CUCE:
REPRESENTANTE LEGAL: FIDEL EDBERTO GUTIERREZ FLORES
DIRECCION DE OBRAS PUBLICAS
SUP. DE OBRAS: OMAR QUISPE FERNANDEZ

CHECK LIST PARA PLANILLA DE AVANCE PRESENTACION DE DOCUMENTOS


N° DE
PROYECTO: CONST. CENTRO DE SALUD JANCOÑUÑO CONTRATO D.J./ CONTRATO
ANPE Nº 007/2016

UBICACIÓN: JANCOÑUÑO - CENTRAL JANCOÑUÑO PLANILLA N° 2

ESTADO
N° DOCUMENTO A ADJUNTAR
ORIGINAL COPIA

1 CARTA DE SOLICITUD

2 INFORME TECNICO DEL SUPERVISOR


Informe tecnico y de Aprobacion aprobado, dirigida al Secretario Municipal Tecnico y Director de OO.PP.

3 PLANILLA DE AVANCE DE OBRA (EMPRESA)

4 PLANILLA DE AVANCE DE OBRA (SUPERVISOR)

5 COMPUTOS METRICOS DE AVANCE ACTUAL

6 PLANOS DE AVANCE ACTUAL (SEGÚN REQUERIMIENTO DEL SUPERVISOR)

7 ORDEN A PROCEDER (ORIGINAL)

8 COPIAS DEL LIBRO DE ORDENES

9 FOTOGRAFIAS DE RESPALDO DEL AVANCE ACTUAL

10 CONTROL DE CALIDAD DE MATERIALES (PRUEBAS DE LABORATORIO)

11 CRONOGRAMA DE ACTIVIDADES ACTUALIZADO

12 CONTRATO ORIGINAL

13 FOTOCOPIA DEL C.I. DEL REPRESENTANTE LEGAL

14 FOTOCOPIA DEL NIT.

15 CERTIFICADO FUNDEMPRESA

16 CERTIFICADO RUPE ORIGINAL

17 COPIA DE PLANILLAS ANTERIORES + CHEQUES

18 MEDIO MAGNETICO

FIRMA Y SELLO SUPERVISOR


FECHA: 14/12/2016
CHECK LIST ORDEN DE CAMBIO
SUP. DE OBRAS:

PROYECTO:

ORDEN DE CAMBIO N° : ORDEN DE CAMBIO N° 1

CONTRATISTA "C-MICAYA" CONSTRUCTORA CONSULTORA "C-MICAYA"

N° DOCUMENTO A RECEPCIONAR SUP. FISC.

SOLICITUD DEL CONTRATISTA INDICANDO LA NECESIDAD DE LA ORDEN DE


1
CAMBIO MAS MEDIO MAGNETICO

2 PLANILLA DE APROBACION TECNICA Y PLANILLA DE BALANCE ECONOMICO

3 COMPUTOS METRICOS

4 PLANOS REFERENCIALES

5 CONTROL DE CALIDAD DE MATERIALES (PRUEBAS DE LABORATORIO)

JUSTIFICACION DEL CONTRATISTA AMPLIACION DE PLAZO DE INCREMENTO DE


6
PRESUPUESTO

7 CRONOGRAMA DE ACTIVIDADES ACTUALIZADO

8 CRONOGRAMA DE DESEMBOLSOS ACTUALIZADO

9 FOTOGRAFIAS DE RESPALDO

10 FOTOCOPIA DEL LIBRO DE ORDENES

FOTOCOPIA DE POLIZAS: GARANTIA DE CUMPLIMIENTO DE CONTRATO Y


11
CORRECTA INVERSION DE ANTICIPO, VIGENTES

12 MANO DE OBRA Y EQUIPO PARA LA EJECUCION

N° DOCUMENTO A RECEPCIONAR SUP. FISC.

1 NOTA DE CONFORMIDAD DEL FISCAL DE OBRAS

2 NOTA E INFORME DEL SUPERVISOR DE OBRA

3 INFORME LEGAL

SUPERVISOR. FISCAL:
CHECK LIST CONTRATO MODIFICATORIO
SUP. DE OBRAS:

MEJ. CANCHA POLIFUNCIONAL (TINGLADO ENMALLADO Y MURO DE


PROYECTO
CONTENCION) J.V. ALTO LURICANCHO

CONTRATO MDF. N° CONTRATO MODIFICATORIO N° 1

CONTRATISTA "TILLKO" CONSTRUCTORA CONSULTORA & SERVICIOS EN GENERAL

N° DOCUMENTO A RECEPCIONAR SUP. FISC.

SOLICITUD DEL CONTRATISTA INDICANDO LA NECESIDAD DEL CONTRATO


1
MODIFICATORIO MAS MEDIO MAGNETICO

2 PLANILLA DE APROBACION TECNICA Y PLANILLA DE BALANCE ECONOMICO

3 COMPUTOS METRICOS

4 PLANOS REFERENCIALES

5 CONTROL DE CALIDAD DE MATERIALES (PRUEBAS DE LABORATORIO)

JUSTIFICACION DEL CONTRATISTA AMPLIACION DE PLAZO E INCREMENTO


6
DE PRESUPUESTO

7 CRONOGRAMA DE ACTIVIDADES ACTUALIZADO

8 CRONOGRAMA DE DESEMBOLSOS ACTUALIZADO

9 FOTOGRAFIAS DE RESPALDO

10 FOTOCOPIA DEL LIBRO DE ORDENES

FOTOCOPIA DE POLIZAS: GARANTIA DE CUMPLIMIENTO DE CONTRATO Y


11
CORRECTA INVERSION DE ANTICIPO, VIGENTES

12 MANO DE OBRA Y EQUIPO PARA LA EJECUCION

N° DOCUMENTO A RECEPCIONAR SUP. FISC.

1 NOTA DE CONFORMIDAD DEL FISCAL DE OBRAS

2 NOTA E INFORME DEL SUPERVISOR DE OBRA

3 INFORME LEGAL

SUPERVISOR. FISCAL:
INFORME TECNICO
CITE: G.A.M.C./D.O.P.U./Nº 037/2017
A: PROF. JUAN CHINO SALINAS
H. ALCALDE MUNICIPAL DE CARACOLLO
VIA: LORENZO MAYTA CHILLCA
SECRETARIO MUNICIPAL TECNICO
DE: OMAR QUISPE FERNANDEZ
FISCAL DE OBRA G.A.M.C.
PROYECTOCONSTRUCCION UNIDAD EDUCATIVA TECNICO HUMANISTICO EVO MORALES AYMA - CARACOLLO
INFORME DE APROBACION DE CONTRATO MODIFICATORIO Nº1 POR CREACION DE NUEVOS ITEMS Y
REF.:
AMPLIACION DE PLAZO.
FECHA: Monday, May 15, 2017

El motivo de la presente para dirigirme a su autoridad, con respecto al contrato modificatorio Nº 1 por ceracion de nuevos items y ampliacion de
plazo del proyecto mensionado líneas arriba, a la misma tengo a bien informar lo siguiente:

1.- ANTECEDENTES

El proyecto CONSTRUCCION UNIDAD EDUCATIVA TECNICO HUMANISTICO EVO MORALES AYMA - CARACOLLO, se esta
ejecutando con el financiamiento de la Unidad de Proyectos Especiales (UPRE) dependiente del Ministerio de la Presidencia dentro el Programa
Bolivia Cambia Evo Cumple. Así mismo en fecha 06 de abril del 2016, se realizo la firma de contrato del proyecto entre el GOBIERNO
AUTONOMO MUNICIPAL DE CARACOLLO y la empresa constructora "SERVICIO INTEGRAL EN PLANIFICACION Y
CONSTRUCCION SIPCOM S.R.L.", representado por el señor Nery Herbert Challapa Lucana, por un monto de contrato de Bs. 6'928.321,54
(Seis Millones Novecientos Veintiocho Mil Trescientos Veintiuno con 54/100 Bolivianos), con plazo de ejecución de 345 días calendario, iniciando
la obra en fecha 13/04/2016.

Segun orden de cambio Nº 1 de ampliacion de plazo Nº 1, fue aprobado 56 dias calendario, fecha de conclusion 18 de mayo de 2017 años, total
plazo de ejecucion mas ampliacion de plazo Nº 1 401 dias calendario.

La supervisión es externa y esta cargo de la empresa "COINC - C" CONSTRUCCION DE OBRAS DE INGENIERIA CIVIL Y
CONSULTORIA representado por el señor Ing. Augusto Condori Gomez, de acuerdo a lo solicitud de contrato modificatorio Nº 1 por creacion de
nuevos items y ampliacion de plazo presentada por la empresa ejecutora; la supervisor tuvo la tarea de verificar y revisar los respaldos de
justificacion para considerar el contrato modificatorio y ampliacion de plazo mismo que aprueba con un informe tecnico recepcionado en fecha 15
de mayo de 2017.

2.- DE LA BOLETA DE GARANTIA


MONTO DE FECHA DE
GARANTIA EMITIDA POR LA
TIPO DE GARANTIA GARANTIA VENCIMIE ESTADO
Nº ASEGURADORA
(Bs.) NTO
BOLETA DE GARANTIA DE EJECUCION INMEDIATA A
BGNC - 01 DE AGOSTO VIGENT
PRIMER REQUERIMIENTO DEL BENEFICIARIO (CORRECTA MERCANTIL SANTA CRUZ 432,234.13
1000105584 DE 2017 E
INVERSION DE ANTICIPO)
BOLETA DE GARANTIA DE EJECUCION INMEDIATA A
BGNC - 29 DE JULIO VIGENT
PRIMER REQUERIMIENTO DEL BENEFICIARIO MERCANTIL SANTA CRUZ 484,982.55
1000098408 DE 2017 E
(CUMPLIMIENTO DE CONTRATO)

2.- CONCLUSIONES

En base al informe técnico elaborado por el Supervisor de obra, después de revisada la documentación de respaldo presentada por la empresa
contratista en lo que se refiere al contrato modificatorio y la ampliación de plazo No. 1, se concluye que es procedente y justificada el contrato
modificatorio por la creación de nuevos ítems y la ampliación de plazo No.1.

El contrato Modificatorio no incrementa de ninguna manera el monto de contrato, solo conlleva a reajustar los volúmenes de los ítem del proyecto
además de la creación de nuevos ítems que no fueron contemplados dentro el proyecto inicial y la ampliación de plazo bajo el siguiente detalle:
Nuevos items:
- Escalera de Hormigon Armado.
- Malla de proteccion Granizo.
- Contrapiso sobre Losa.
- Revoque Cielo Falso Incl/Maderamen.
- Muro de contencion de Hº Cº.
- Prov. e Inst. Inodoro Tanque Bajo C/Acc.
- Coloc. Pantalla LET 60 x60 cm. 22 Watts.
- Interruptor Doble.
- Cable 35 mm. x 3 Trifasico.
- Losa Prefabricada Para Graderias (0,60 x 0,16 M).
- Prov. y Coloc. iluminacion 400 incluye cableado.
- Gradas de Hº Cº.
- Cielo Falso Prefabricado.
- Revoque Cielo Falso Incluye Maderamen.
- Zapata de Hormigon Armado.
3.- RECOMENDACIONES

Por consiguiente esta Fiscalización Recomienda que mediante la instancia que corresponde y de acuerdo a términos de contrato según la
CláusulaTrigésima (Modificacion de las obras) numeral 30.4 inciso c) mediante contrato modificatorio párrafo del uno al tres solo en caso
extraordinario en que la obra debe ser complementada o por otras circunstancias de fuerza mayor o caso fortuito que determinen una modificacion
significativa en el diseño de la obray que signifique un decremento o incremento independiente a la emision de ordenes de cambio, el supervisor
podra formular el documento de sustento tecnico - financiero que establesca las causas y razones por las cuales deberia ser suscrito este documento.

A su vez también en base a la aprobación de la supervisión se recomienda la ampliación de plazo de ejecución de la obra en 35 Días Calendario, en
favor de la empresa.

Orden a proceder......................................................................................................................13 de abril de 2016


Plazo segun contrato.................................................................................................................345 dias calendario
Fecha de conclusion segun contrato.....................................................................................23 de marzo de 2017

Orden de Cambio Nº 1 de ampliacion de plazo.................................................................56 dias calendario


Fecha de conclusion + Orden de Cambio Nº 1 de ampliacion de plazo........................18 de mayo de 2017
Total plazo contrato + Orden de Cambio Nº 1 de ampliacion de plazo.........................401 dias calendario

Contrato Modificatorio Nº 1......................................................................................................45 dias calendario


Fecha de conclusion + Contrato Modificatorio Nº 1............................................................02 de julio de 2017
Total plazo contrato + ampliacion de plazo Nº 2.................................................................446 dias calendario

Se adjunta al presente informe tres forders de palanca con la siguiente documentacion:


informe tecnico de la supervision, solicitud de contrato modificatorio mas justificacion, Planilla del contrato modificatorio, Balance general del
proyecto, Cómputos métricos, Ítems nuevos (Precios Unitarios, Especificaciones Técnicas),fotografias de la obra, Fotocopia de libro de órdenes,
Planos, Cronograma de ejecución de la obra actualizado, Ampliación de plazo, Documentos Varios (Memorandum de designacion, Fotocopia de
Convenio, fotocopia de Boleta de Garantía, fotocopia de Orden de proceder, Fotocopia de contrato, documentos legales de la empresa).

Es cuanto puedo informar a su autoridad con referencia al presente informe.

Atentamente.
PLANILLA DE AVANCE N° 2
(EN BOLIVIANOS)
MONTO DE CONTRATO (Bs.): 298544.71 PROYECTO: CONSTRUCCION UNIDAD EDUCATIVA FECHA ORDEN A PROCEDER: 8/31/2016
TECNICO HUMANISTICO EVO MORALES AYMA
MONTO ORDEN DE CAMBIO (Bs.): 0.00 - CARACOLLO FECHA DE PARALIZACION: 0
MONTO FINAL DE EJECUCION (Bs.): 298544.71 CONTRATISTA: EMPRESA CONSTRUCTORA FLOR DE LOS ANDE FECHA DE REINICIO: 0
FECHA DE CONTRATO: 8/24/2016 UBICACIÓN: JANCOÑUÑO - CENTRAL JANCOÑUÑO DIAS PARALIZADOS: 0
PLAZO DE EJECUCION DIAS CALENDARIO: 139 FECHA DE EMISION: 5/15/2017 FECHA DE ENTREGA PROVISIONAL: 1/16/2017
FECHA DE ENTREGA DEFINITIVA:

SEGUN CONTRATO AVANCE ANTERIOR AVANCE ACTUAL TOTAL AVANCE ACUMUNLADO


Nº DESCRIPCION UNIDAD
MONTO % DE
CANT. P. U. CANT. % MONTO CANT. % MONTO CANT. MONTO
ITEM AVANCE

1 REPLANTEO Y TRAZADO glb 1.00 478.05 478.05 1.00 100.00 478.05 0.00 0.00 0.00 1.00 100.00 478.05
2 EXCAVACION (0-2 M.) S. SEMIDURO m³ 24.41 59.04 1,441.17 24.35 99.75 1,437.62 0.00 0.00 0.00 24.35 99.75 1437.62
3 ZAPATAS DE Hº Aº m³ 3.22 1,904.27 6,131.75 3.22 100.00 6,131.75 0.00 0.00 0.00 3.22 100.00 6131.75
4 COLUMNAS DE H° A° + ENLUCIDO EXTERIOR m³ 2.38 3,009.33 7,162.21 1.97 82.77 5,928.38 0.00 0.00 0.00 1.97 82.77 5928.38
5 CIMIENTO DE HORMIGON CICLOPEO m³ 13.59 439.21 5,968.86 13.41 98.68 5,889.81 0.00 0.00 0.00 13.41 98.68 5889.81
6 SOBRECIMIENTOS DE Hº Cº + IMPERMEABILIZACION m³ 2.74 854.45 2,341.19 2.73 99.64 2,332.65 0.00 0.00 0.00 2.73 99.64 2332.65
7 MURO LADRILLO GAMBOTE (VISTO) m² 192.28 173.93 33,443.26 191.28 99.48 33,269.33 0.00 0.00 0.00 191.28 99.48 33269.33
8 VIGA DE ENCADENADO DE Hº Aº + ENLUCIDO EXTERIOR m³ 3.26 2,506.04 8,169.69 3.24 99.39 8,119.57 0.00 0.00 0.00 3.24 99.39 8119.57
9 CUBIERTA CALAMINA PREPINTADA m² 153.70 284.87 43,784.52 0.00 0.00 0.00 153.70 100.00 43,784.52 153.70 100.00 43784.52
10 CUMBRERA DE CALAMINA PLANA PREPINTADA m 3.70 82.33 304.62 0.00 0.00 0.00 3.70 100.00 304.62 3.70 100.00 304.62
11 PARAPETO DE LADRILLO 6H E=12CM. m² 13.27 130.08 1,726.16 0.00 0.00 0.00 5.25 39.56 682.92 5.25 39.56 682.92
12 CUBERTINA DE Hº Aº m 11.93 133.86 1,596.95 0.00 0.00 0.00 11.93 100.00 1,596.95 11.93 100.00 1596.95
13 REVOQUE EXTERIOR DE CEMENTO m² 13.27 115.18 1,528.44 0.00 0.00 0.00 4.90 36.93 564.38 4.90 36.93 564.38
14 PINTURA EXTERIOR - LATEX m² 13.27 13.50 179.15 0.00 0.00 0.00 5.25 39.56 70.88 5.25 39.56 70.88
15 CIELO FALSO DE YESO MAS MADERAMEN m² 108.94 193.32 21,060.28 0.00 0.00 0.00 107.06 98.27 20,696.84 107.06 98.27 20696.84
PUERTA DE MADERA ROBLE TIPO TABLERO +
16 m² 23.10 1,549.60 35,795.76 0.00 0.00 0.00 23.10 100.00 35,795.76 23.10 100.00 35795.76
QUINCALLERIA
17 PROV. Y COLOC. TUBERIA DE PVC D=1/2" m 40.00 22.56 902.40 0.00 0.00 0.00 20.00 50.00 451.20 20.00 50.00 451.20
18 REVOQUE INTERIOR DE YESO m² 265.11 81.54 21,617.07 0.00 0.00 0.00 264.39 99.73 21,558.36 264.39 99.73 21558.36
19 VENTANA CORREDIZA ALUMINIO MAS VIDRIO E=4MM m² 23.60 477.55 11,270.18 0.00 0.00 0.00 23.60 100.00 11,270.18 23.60 100.00 11270.18
20 ALEROS m² 20.15 244.36 4,923.85 0.00 0.00 0.00 20.15 100.00 4,923.85 20.15 100.00 4923.85
21 BOTAGUAS DE Hº Aº m 23.60 124.06 2,927.82 0.00 0.00 0.00 16.40 69.49 2,034.58 16.40 69.49 2034.58
22 PROV. Y TENDIDO TUBO PVC C/9 DESAGUE 4" m 20.00 37.20 744.00 0.00 0.00 0.00 10.00 50.00 372.00 10.00 50.00 372.00
23 PROV. Y TENDIDO TUBO PVC C/9 DESAGUE 2" m 10.00 25.28 252.80 0.00 0.00 0.00 10.00 100.00 252.80 10.00 100.00 252.80
24 CAJA INTERCEPTORA DE PVC pza 3.00 163.50 490.50 0.00 0.00 0.00 2.00 66.67 327.00 2.00 66.67 327.00
25 CONTRAPISO DE CEMENTO + EMPEDRADO m² 108.94 113.05 12,315.67 0.00 0.00 0.00 107.06 98.27 12,103.13 107.06 98.27 12103.13
26 REJILLA DE PISO pza 3.00 64.09 192.27 0.00 0.00 0.00 2.00 66.67 128.18 2.00 66.67 128.18
27 PISO DE CERAMICA ESMALTADA m² 108.94 196.36 21,391.46 0.00 0.00 0.00 107.06 98.27 21,022.30 107.06 98.27 21022.30
28 ZOCALO DE CERAMICA ESMALTADA H=0.20 M. m 117.68 83.31 9,803.92 0.00 0.00 0.00 117.43 99.79 9,783.09 117.43 99.79 9783.09
29 REVESTIMIENTO DE CERAMICA m² 25.12 196.60 4,938.59 0.00 0.00 0.00 25.12 100.00 4,938.59 25.12 100.00 4938.59
30 PINTURA INTERIOR LATEX m² 374.05 20.18 7,548.33 0.00 0.00 0.00 371.45 99.30 7,495.86 371.45 99.30 7495.86
31 ILUMINACION FLUORECENTE 2 X 40W pto 12.00 414.19 4,970.28 0.00 0.00 0.00 12.00 100.00 4,970.28 12.00 100.00 4970.28
32 TOMACORRIENTES pto 12.00 173.06 2,076.72 0.00 0.00 0.00 12.00 100.00 2,076.72 12.00 100.00 2076.72
33 TABLERO DE DISTRIBUCION pza 1.00 375.02 375.02 0.00 0.00 0.00 1.00 100.00 375.02 1.00 100.00 375.02
34 TANQUE DE AGUA PLASTICO 600LT + ACCESORIOS pza 1.00 863.99 863.99 0.00 0.00 0.00 1.00 100.00 863.99 1.00 100.00 863.99
35 LAVAMANOS BLANCO C/PEDESTAL pza 2.00 544.25 1,088.50 0.00 0.00 0.00 2.00 100.00 1,088.50 2.00 100.00 1088.50
36 INODORO TANQUE BAJO pza 2.00 555.30 1,110.60 0.00 0.00 0.00 2.00 100.00 1,110.60 2.00 100.00 1110.60
37 DUCHA pza 1.00 1,150.64 1,150.64 0.00 0.00 0.00 1.00 100.00 1,150.64 1.00 100.00 1150.64
38 CAMARA DE INSPECCION H° C° (60*60) pza 2.00 857.48 1,714.96 0.00 0.00 0.00 1.00 50.00 857.48 1.00 50.00 857.48
39 CAMARA SEPTICA pza 1.00 3,075.81 3,075.81 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
40 POZO ABSORBENTE D=2.00 MTS pza 1.00 1,289.35 1,289.35 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
41 LOSA LLENA DE Hº Aº m³ 0.29 1,660.58 481.57 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
42 ACERAS m² 52.72 89.15 4,699.99 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
43 CANALETA DE CALAMINA PLANA Nº 28 m 32.16 94.79 3,048.41 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
44 BAJANTE PVC DE 4" m 28.00 39.62 1,109.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
45 PLACA DE ENTREGA DE OBRAS pza 1.00 679.36 679.36 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
46 LIMPIEZA GENERAL GLB glb 1.00 379.20 379.20 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
ERROR DE REDONDEO 0.00 0.00 0.00 0.00
298,544.67 21.30% 63587.16 71.23% 212,651.24 92.53% 276,238.39

RESUMEN DE PAGO DE PLANILLA

PORCENTAJE DE AVANCE DE OBRA: 92.53%


PORCENTAJE DE AVANCE ECONOMICO: 21.30%
PAGO POR AVANCE DE OBRA ACTUAL: 212,651.24 Bs.
PLANILLAS ANTERIORES: 63587.16 Bs.
TOTAL ANTICIPO DE OBRA 0.00 Bs.
DESCUENTO DE ANTICIPO 20% EN PLANILLAS 0.00 Bs.
RETENCIÓN DEL 7% (POR CUMPLIMIENTO DE OBRA): 14,885.59 Bs.
LIQUIDO PAGABLE: 197,765.65 Bs.
SON: #VALUE!

EMPRESA CONTRATISTA SUPERVISOR G.A.M.C. FISCAL DE OBRA OO. PP. G.A.M.C. STRIO. MPAL. TECNICO G.A.M.C.
PLANILLA DE AVANCE N° 1
(EN BOLIVIANOS)
MONTO DE CONTRATO (Bs.): PROYECTO: FECHA ORDEN A PROCEDER:
MONTO ORDEN DE CAMBIO (Bs.): FECHA DE PARALIZACION:
MONTO FINAL DE EJECUCION (Bs.): CONTRATISTA: FECHA DE REINICIO:
FECHA DE CONTRATO: UBICACIÓN: DIAS PARALIZADOS:
PLAZO DE EJECUCION DIAS CALENDARIO: FECHA DE EMISION: FECHA DE ENTREGA DEFINITIVA:
FECHA DE ENTREGA PROVISIONAL:
ORDEN DE CAMBIO O CONTRATO
SEGUN CONTRATO MODIFICATORIO Nº 1 AVANCE ANTERIOR AVANCE ACTUAL TOTAL AVANCE ACUMUNLADO
Nº DESCRIPCION UNIDAD MONTO % DE
CANT. P. U. CANT. P.U. MONTO CANT. % MONTO CANT. % MONTO CANT. MONTO
ITEM AVANCE

1 REFACCION DE CIELO RASO DE YESO M2 80.00 40.10 3,208.00 0.00 40.10 0.00 0.00 0.00 0.00 80.00 100.00 3,208.00 80.00 100.00 3208.00
2 REVOQUE INTERIOR DE YESO M2 80.00 38.02 3,041.50 0.00 38.02 0.00 0.00 0.00 0.00 80.00 100.00 3,041.50 80.00 100.00 3041.50
3 ACERA PERIMETRAL MAS SOLADO DE PIEDRA M2 57.00 45.00 2,565.00 0.00 45.00 0.00 0.00 0.00 0.00 57.00 100.00 2,565.00 57.00 100.00 2565.00
4 REVOQUE EXTERIOR S/ADOBE M2 100.00 45.00 4,500.00 0.00 45.00 0.00 0.00 0.00 0.00 100.00 100.00 4,500.00 100.00 100.00 4500.00
5 PINTURA EXTERIOR LATEX M3 95.00 12.00 1,140.00 0.00 12.00 0.00 0.00 0.00 0.00 95.00 100.00 1,140.00 95.00 100.00 1140.00
6 PINTURA INTERIOR LATEX M2 90.00 10.00 900.00 0.00 10.00 0.00 0.00 0.00 0.00 90.00 100.00 900.00 90.00 100.00 900.00
7 REFACCION DE GRADAS M3 3.10 30.00 93.00 0.00 30.00 0.00 0.00 0.00 0.00 3.10 100.00 93.00 3.10 100.00 93.00
8 ZOCALO DE CEMENTO ENLUCIDO M2 12.50 25.00 312.50 0.00 25.00 0.00 0.00 0.00 0.00 12.50 100.00 312.50 12.50 100.00 312.50
9 PISO DE MACHIMBRE M2 66.00 40.00 2,640.00 0.00 40.00 0.00 0.00 0.00 66.00 100.00 2,640.00 66.00 100.00 2640.00
ERROR DE REDONDEO 0.00 0.00 0.00 0.00 0.00
18,400.00 0.00 0.00% 0.00 100.00% 18,400.00 100.00% 18,400.00

RESUMEN DE PAGO DE PLANILLA

PORCENTAJE DE AVANCE DE OBRA: 100.00%


PORCENTAJE DE AVANCE ECONOMICO: 0.00%
PAGO POR AVANCE DE OBRA ACTUAL: 18,400.00 Bs.
PLANILLAS ANTERIORES: 0.00 Bs.
TOTAL ANTICIPO DE OBRA 0.00 Bs.
DESCUENTO DE ANTICIPO 20% EN PLANILLAS 3,680.00 Bs.
RETENCIÓN DEL 7% (POR CUMPLIMIENTO DE OBRA): 1,288.00 Bs.

LIQUIDO PAGABLE: 13,432.00 Bs.


SON: #VALUE!

EMPRESA CONTRATISTA SUPERVISOR G.A.M.C. FISCAL DE OBRA OO. PP. G.A.M.C. STRIO. MPAL. TECNICO G.A.M.C.
PLANILLA DE RETENCION PAGABLE (7%)
CONSTRUCCION UNIDAD FECHA ORDEN A
MONTO DE CONTRATO (Bs.): 298,544.71 PROCEDER: 8/31/2016
EDUCATIVA TECNICO
PROYECTO:
HUMANISTICO EVO MORALES
MONTO ORDEN DE CAMBIO (Bs.): 0.00 AYMA - CARACOLLO FECHA DE PARALIZACION: 0
EMPRESA CONSTRUCTORA FLOR
MONTO FINAL DE EJECUCION (Bs.): 298,544.71 CONTRATISTA:
DE LOS ANDES
FECHA DE REINICIO: 0
FECHA DE CONTRATO: 8/24/2016 UBICACIÓN: JANCOÑUÑO - CENTRAL JANCOÑ DIAS PARALIZADOS: 0
PLAZO DE EJECUCION DIAS FECHA DE ENTREGA
CALENDARIO:
139 FECHA DE EMISION: 6/24/2016
PROVISIONAL: 1/16/2017
FECHA DE ENTREGA
FECHA ORDEN A PROCEDER: 8/31/2016 DEFINITIVA: 12/30/1899

MONTO DE MONTO CANCELADO


DESCRIPCION RETENCION DE 7% BS
PLANILLAS EN BS EN BS
Anticipo de obra 0.00
Planilla Nº 1 47060.34 43766.12 3294.22
Planilla Nº 2 81328.77 73884.97 5693.01
Error de redondeo 0.00 0.00 0.00

TOTAL 128389.11 117651.09 8987.23


LIQUIDO PAGABLE DEL 7% DE RETENCION EN BS 8987.23

Son: #VALUE!

EMPRESA CONSTRUCTORA O CONTRATISTA SUPERVISOR G.A.M.C. FISCAL DE OBRAS G.A.M.C. STRIO. MPAL. TECNICO G.A.M.C.
RESUMEN DE PLANILLA
PLANILLA DE PAGO N° 2 (Cierre)

PROYECTO: CONST. CENTRO DE CAPACITACION PRODUCTIVA CONCHAMARCA

A: DATOS DEL PROYECTO


SUPERVISION
ENTIDAD CONTRATISTA UBICACIÓN PLAZO 60 DIAS
OBRAS
INICIO 2/4/2016
GOBIERNO DIRECTOR DE
C-MICAYA
AUTONOMO CONCHAMARCA
CONSTRUCTORA OBRAS
MUNICIPAL CENTRAL
CONSULTORA FINAL PUBLICAS
DE CARACOLLO 4/3/2016
CONTRATO 18,400.00

B: RESUMEN DE PLANILLA N° 1
EJECUCIÓN PRESUPUESTO
PLAZO INICIO FINAL BOLIVIANOS PORCENTAJE
EJECUTADO EN EL
60 2/4/2016 4/4/2016 293,230.62 1593.65%
PERIODO
EJECUTADO
ACUMULADO A LA 60 2/4/2016 4/4/2016 293,230.62 1593.65%
FECHA
SALDO POR EJECUTAR -274,830.62 -1493.65%
RETENCION DEL 20%
POR ANTICIPO DE 20,526.14 111.56%
CONTRATO
RETENCION DEL 7% POR
CUMPL. CONTR. 20,526.14 111.56%
ACUMULADO
LIGUIDO PAGABLE 272,704.48 1482.09%

SON: DIECISIETE MIL CIENTO DOCE CON 00/100

Fecha……………… CONTRATISTA Fecha……………… SUPERVISOR DE OBRA

Fecha……………… DIRECTOR DE OBRAS PUBLICAS Fecha……………… SECRETARIO MUNICIPAL TECNICO


ACTA DE INICIO DE OBRA Y ORDEN A PROCEDER

En la comunidad de ..........................................de la central ............................... perteneciente al Gobierno Autónomo


Municipal de Caracollo, ubicado en la Provincia Cercado, del Departamento de Oruro, a los ......... días del mes
de .......................... del año Dos Mil Dieciséis; en presencia de las Autoridades Municipales, Autoridades de la
Comunidad beneficiada, Empresa Contratista de la obra, y técnicos del municipio, se realizo el ACTO DE INICIO DE
OBRA del siguiente Proyecto:

CONSTRUCCION UNIDAD EDUCATIVA TECNICO HUMANISTICO EVO


MORALES AYMA - CARACOLLO
INFORME TÉCNICO
1 Nº DE CUCE: 0
2 PROYECTO: CONSTRUCCION UNIDAD EDUCATIVA TECNICO HUMANISTICO EVO MORALES AYMA - C
3 ENTIDAD CONTRATANTE: GOBIERNO AUTONOMO MUNICIPAL DE CARACOLLO
4 MONTO DE CONTRATO (Bs.): 298544.71
5 FECHA SUSCRIPCIÓN DE CONTRATO: 8/24/2016
6 UBICACIÓN: JANCOÑUÑO - CENTRAL JANCOÑUÑO
7 PLAZO DE EJECUCIÓN DIAS CALENDARIO: 139
8 SUPERVISOR DE OBRA DESIGNADO: OMAR QUISPE FERNANDEZ

9 FECHA DE INICIO DE OBRA Y ORDEN A PROCEDER: 8/31/2016

10 FECHA DE CONCLUSIÓN PROGRAMADA: 1/17/2017


11 EMPRESA CONTRATISTA: EMPRESA CONSTRUCTORA FLOR DE LOS ANDES
12 REPRESENTANTE LEGAL: FIDEL EDBERTO GUTIERREZ FLORES

La empresa contratista conoce y acepta todas las clausulas establecidas en el contrato firmado entre ambas partes.

Para constancia de lo expuesto leneas arriba, firman a la presente acta los presentes.
ACTA DE RECEPCIÓN PROVISIONAL
ENTIDAD CONTRATANTE: GOBIERNO AUTÓNOMO MUNICIPAL DE SICA SICA
CONTRATISTA: Sr. Oscar Oscarin Callex Romeo

ANTECEDENTES:
UBICACIÓN: Oruro - Cercado - Caracollo - Quemalla FECHA: 05 - Nov. - 14 HORA: 10:00 a.m.
PROYECTO: MEJ. AULAS U. E. TOCOPILLA
MONTO DEL CONTRATO: 16,972.80
FECHA ORDEN A PROCEDER: 3/4/2016
MONTO ORDEN DE CAMBIO O CONTRATO MODIFICATORIO: 0.00
MONTO FINAL DE EJECUCIÓN DE LA OBRA (Bs): 16,972.80
PLAZO DE EJECUCIÓN SEGÚN CONTRATO: 40 D.C.
AMPLIACIÓN DE PLAZO: 0 D.C.
TOTAL PLAZO DE EJECUCIÓN: 40 D.C.
PLAZO PARA LA ENTREGA DEFINITIVA: 60 D.C.
OBSERVACIONES:
ÍTEM:……………………………………………………………….…...…………………………………………….
ÍTEM:……………………………………………………………….…...…………………………………………….
ÍTEM:……………………………………………………………….…...…………………………………………….
ÍTEM:……………………………………………………………….…...…………………………………………….
PARTICIPANTES

Representantes Nombre Cargo Institución

Rep. Institución: Prof. Juan Chino Salinas H. Alcalde Municipal G.A.M.C.


Rep. Concejo Mpal.: H. Concejal G.A.M.C.
Rep. De la Emp. Contratista: Sr. Oscar Oscarin Callex Romeo Reprentante Legal CONTRATISTA
Rep. Stria. Mpal. Tec.: Fiscal De Obra G.A.M.C.
Rep. Stria. Mpal. Tec.: Supervisor de Obra G.A.M.C.
Rep. Comision de recepcion: Comision de recepcion
Rep. Stria. Mpal. Tec.: Strio. Municipal Técnico G.A.M.C.

RECEPCIÓN PROVISIONAL

Luego de haber realizado la verificacion en sitio todos los ítems del contrato ya concluidos al 100%, se da a la Empresa Contratista un
plazo de 5 días calendario, para iniciar con las enmiendas de las observaciones realizadas a la Obra y un maximo de 30 días para la
nueva inspección, antes de la recepción definitiva de la Obra que se realizara a los 90 días de la recepción provisional.

MEJ. AULAS U. E. TOCOPILLA

…………………………… ………………...……….. ……………………...……….


Rep. Comunidad H. Alcalde Municipal Rep. Concejo Municipal.

…………………………… ……………...…….………. …………………..…………..


Rep. De la Empresa Sup. De Obra Strio Municipal Técnico
……………………………… ……………………..………….
Comisión de Recepción Fiscal De Obra
ACTA DE RECEPCIÓN DEFINITIVA
ENTIDAD CONTRATANTE: GOBIERNO AUTÓNOMO MUNICIPAL DE CARACOLLO

CONTRATISTA: Sr. Oscar Oscarin Callex Romeo

ANTECEDENTES
UBICACIÓN: Oruro - Cercado - Caracollo - Quemalla FECHA: 05 - Nov. - 14 HORA: 10:00 a.m.

PROYECTO: MEJ. AULAS U. E. TOCOPILLA


MONTO DEL CONTRATO: 16,972.80
FECHA ORDEN A PROCEDER:
MONTO ORDEN DE CAMBIO O CONTRATO MODIFICATORIO: 0.00
MONTO FINAL DE EJECUCIÓN DE LA OBRA (Bs): 16,972.80
PLAZO DE EJECUCIÓN SEGÚN CONTRATO: 40 D.C.
AMPLIACIÓN DE PLAZO: 0 D.C.
TOTAL PLAZO DE EJECUCIÓN: 40 D.C.

PARTICIPANTES

Representantes Nombre Cargo Institución


Rep. Institución: Prof. Juan Chino Salinas H. Alcalde Municipal G.A.M.C.
Rep. Concejo Mpal.: H. Concejal G.A.M.C.
Rep. De la Emp. Contratista: Sr. Oscar Oscarin Callex Romeo Reprentante Legal CONTRATISTA
Rep. Stria. Mpal. Tec.: Ing. Lorenzo Mayta Chillca Fiscal De Obra G.A.M.C.
Rep. Stria. Mpal. Tec.: Ing. Romina Vera Condori Supervisor de Obra G.A.M.C.
Rep. Comisión de recepción: Comisión de recepción
Rep. Stria. Mpal. Tec.: Arq. C. Oscar Calle Romero Strio. Municipal Técnico G.A.M.C.

RECEPCIÓN DEFINITIVA:
En vista de haber cumplido y verificado las correcciones efectuadas a las observaciones realizadas en la entrega provisional por la
empresa contratista, se procede a la RECEPCIÓN DEFINITIVA del proyecto, la misma queda a partir de la fecha en manos y
responsabilidad de los beneficiarios, el cuidado y mantenimiento de la infraestructura denominado.

MEJ. AULAS U. E. TOCOPILLA

…………………………… ………………...……….. ……………………...……….


Rep. Comunidad H. Alcalde Municipal Rep. Concejo Municipal.

…………………………… ……………...…….………. …………………..…………..


Rep. De la Empresa Sup. De Obra Strio Municipal Técnico
……………………………… ……………………..………….
Comisión de Recepción Fiscal De Obra