Documentos de Académico
Documentos de Profesional
Documentos de Cultura
Tarea 10 - Morales Lopez Ariadna
Tarea 10 - Morales Lopez Ariadna
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
$0.00
$0.00
$0.00
$0.00
$0.00
MANO DE OBRA
COSTO
UNIDAD CANTIDAD IMPORTE
CATEGORIA UNITARIO
$0.00
$0.00
$0.00
$0.00
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
$0.00
$0.00
$0.00
$0.00
$0.00
MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
UNITARIO
Cuadrilla #1 Jornada 0.0083 $358.64 $2.98
$0.00
$0.00
$0.00
$0.00
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
13
14 cal bulto 0.0083 $80.00 $0.66
15 hilo carrete 0.0166 $65.00 $1.08
16 estacas lote 0.0249 $95.00 $2.37
17 clavos kg 0.0166 $45.00 $0.75
18 $0.00
19
20 SUMA DE MATERIALES $4.86
21
22 MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
23 UNITARIO
24 cuadrilla #1 jornada 0.0083 $358.64 $2.98
25 Topografo hora 4.0000 $75.00 $300.00
26 $0.00
27 $0.00
28 $0.00
29
30 SUMA DE MANO DE OBRA $302.98
31
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
$0.00
$0.00
$0.00
$0.00
$0.00
MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
UNITARIO
Cuadrilla #1 jornada 0.0195 $358.64 $6.99
$0.00
$0.00
$0.00
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
concreto f'c:100 kg/cm2 m3 0.1000 $1,278.44 $127.84
$0.00
$0.00
$0.00
$0.00
MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
UNITARIO
cuadrilla #2 jornada 0.0667 $1,305.94 $87.06
cuadrilla #3 jornada 0.0714 $716.02 $51.14
$0.00
$0.00
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
Concreto f´c= 200kg/cm2 m3 1.2000 $1,732.55 $2,079.06
varilla de 1/2" ton 0.0232 $300.00 $6.96
alambre recocido kg 0.2402 $40.00 $9.61
$0.00
$0.00
MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
UNITARIO
cuadrilla #2 jornada 0.8000 $1,305.94 $1,044.75
cuadrilla #3 jornada 0.0857 $716.02 $61.37
cuadrilla #5 jornada 0.1379 $726.66 $100.19
$0.00
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
Concreto f´c= 200kg/cm2 m3 0.8800 $1,732.55 $1,524.64
varilla de 1/2" ton 0.0184 $32,900.00 $605.36
alambre recocido kg 0.2059 $40.00 $8.24
$0.00
$0.00
MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
UNITARIO
cuadrilla #2 jornada 0.5867 $1,305.94 $766.15
cuadrilla #3 jornada 0.0629 $716.02 $45.01
cuadrilla #5 jornada 0.1094 $726.66 $79.53
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
Concreto f´c= 200kg/cm2 m3 0.8250 $1,732.55 $1,429.35
varilla de 1/2" ton 0.0178 $32,900.00 $585.62
alambre recocido kg 0.2059 $40.00 $8.24
$0.00
$0.00
MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
UNITARIO
cuadrilla #2 jornada 0.5500 $1,305.94 $718.27
cuadrilla #3 jornada 0.0589 $716.02 $42.19
cuadrilla #5 jornada 0.1059 $726.66 $76.97
$0.00
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
Concreto f´c= 200kg/cm2 m3 0.5500 $1,732.55 $952.90
varilla de 1/2" ton 0.0115 $32,900.00 $378.35
alambre recocido kg 0.1287 $40.00 $5.15
$0.00
$0.00
MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
UNITARIO
cuadrilla #2 jornada 0.3667 $1,305.94 $478.84
cuadrilla #3 jornada 0.0393 $716.02 $28.13
cuadrilla #5 jornada 0.0684 $726.66 $49.71
$0.00
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
Concreto f´c= 200kg/cm2 m3 1.0615 $1,732.55 $1,839.10
varilla de 1/2" ton 0.0226 $32,900.00 $742.88
alambre recocido kg 0.2574 $40.00 $10.30
$0.00
$0.00
MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
UNITARIO
cuadrilla #2 jornada 0.7077 $1,305.94 $924.17
cuadrilla #3 jornada 0.0758 $716.02 $54.29
cuadrilla #5 jornada 0.1345 $726.66 $97.70
$0.00
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
concreto f´c 100kg/cm2 m3 0.2500 $1,347.10 $336.78
$0.00
$0.00
$0.00
$0.00
MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
UNITARIO
cuadrilla #2 jornada 0.1667 $1,305.94 $217.66
cuadrilla #3 jornada 0.1667 $716.02 $119.34
$0.00
$0.00
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
concreto f´c 100kg/cm2 m3 0.3000 $1,327.10 $398.13
$0.00
$0.00
$0.00
$0.00
MANO DE OBRA
COSTO
UNIDAD CANTIDAD IMPORTE
CATEGORIA UNITARIO
cuadrilla #2 jornada 0.2000 $1,305.94 $261.19
cuadrilla #3 jornada 0.2000 $716.02 $143.20
$0.00
$0.00
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
concreto F ́C ́=140kg/cm2 m3 0.0900 $1,496.41 $134.68
$0.00
$0.00
$0.00
$0.00
MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
UNITARIO
cuadrilla #2 jornada 0.0600 $1,305.94 $78.36
cuadrilla #3 jornada 0.0600 $716.02 $42.96
$0.00
$0.00
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
concreto F ́C ́=140kg/cm2 m3 0.7500 $1,496.41 $1,122.31
$0.00
$0.00
$0.00
$0.00
MANO DE OBRA
COSTO
UNIDAD CANTIDAD IMPORTE
CATEGORIA UNITARIO
cuadrilla #2 jornada 0.0500 $1,305.94 $65.30
cuadrilla #3 jornada 0.0500 $716.02 $35.80
$0.00
$0.00
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
mortero m3 0.0240 $1,884.00 $45.22
ladrillo kk po III de 15 cm de espesor pieza 35.0000 $9.00 $315.00
$0.00
$0.00
$0.00
MANO DE OBRA
COSTO
UNIDAD CANTIDAD IMPORTE
CATEGORIA UNITARIO
cuadrilla #2 jornada 0.0160 $1,305.94 $20.90
cuadrilla #3 jornada 0.1000 $716.02 $71.60
$0.00
$0.00
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
Varilla de 1/2" toneladas 0.0210 $32,900.00 $690.90
alambrón de 1/4" toneladas 0.0033 $39,000.00 $130.37
concreto f´c=210 kg/cm2 m3 0.1313 $2,001.62 $262.71
alambre recocido kg 0.2600 $40.00 $10.40
$0.00
MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
UNITARIO
cuadrilla #2 jornada 0.0875 $1,305.94 $114.31
cuadrilla #3 jornada 0.0875 $716.02 $62.68
cuadrilla #5 jornada 0.1335 $726.66 $96.99
$0.00
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
Varilla de 1/2" toneladas 0.0140 $32,900.00 $460.60
alambrón de 1/4" toneladas 0.0033 $39,000.00 $130.37
concreto f´c=210 kg/cm2 m3 0.1313 $2,001.62 $262.71
alambre recocido kg 0.1733 $40.00 $6.93
$0.00
MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
UNITARIO
cuadrilla #2 jornada 0.0875 $1,305.94 $114.27
cuadrilla #3 jornada 0.0875 $716.02 $62.68
cuadrilla #5 jornada 0.1092 $726.66 $79.35
$0.00
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
Varilla de 1/2" toneladas 0.0280 $32,900.00 $921.20
alambrón de 1/4" toneladas 0.0033 $39,000.00 $130.37
concreto f´c=210 kg/cm2 m3 0.2063 $2,001.62 $412.83
alambre recocido kg 0.3466 $40.00 $13.86
$0.00
MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
UNITARIO
cuadrilla #2 jornada 0.1375 $1,305.94 $179.57
cuadrilla #3 jornada 0.1375 $716.02 $98.48
cuadrilla #5 jornada 0.1978 $726.66 $143.73
$0.00
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
Varilla de 1/2" toneladas 0.0210 $32,900.00 $690.90
alambrón de 1/4" toneladas 0.0040 $39,000.00 $156.00
concreto f´c=210 kg/cm2 m3 0.2000 $2,001.62 $400.32
alambre recocido kg 0.2600 $40.00 $10.40
$0.00
MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
UNITARIO
cuadrilla #2 jornada 0.1333 $1,305.94 $174.08
cuadrilla #3 jornada 0.1333 $716.02 $95.47
cuadrilla #5 jornada 0.1579 $726.66 $114.72
$0.00
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
Varilla de 1/2" toneladas 0.0280 $32,900.00 $921.20
alambrón de 1/4" toneladas 0.0043 $39,000.00 $167.70
concreto f´c=210 kg/cm2 m3 0.1875 $2,001.62 $375.30
alambre recocido kg 0.3466 $40.00 $13.86
$0.00
MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
UNITARIO
cuadrilla #2 jornada 0.1250 $1,305.94 $163.24
cuadrilla #3 jornada 0.1250 $716.02 $89.50
cuadrilla #5 jornada 0.2040 $726.66 $148.27
$0.00
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
Varilla de 1/2" toneladas 0.0280 $32,900.00 $921.20
alambrón de 1/4" toneladas 0.0046 $39,000.00 $179.40
concreto f´c=210 kg/cm2 m3 0.2500 $2,001.62 $500.41
alambre recocido kg 0.3466 $40.00 $13.86
$0.00
MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
UNITARIO
cuadrilla #2 jornada 0.1667 $1,305.94 $217.70
cuadrilla #3 jornada 0.1667 $716.02 $119.34
cuadrilla #5 jornada 0.2059 $726.66 $149.63
$0.00
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
Varilla de 1/2" toneladas 0.0070 $32,900.00 $230.30
Varilla de 5/8" toneladas 0.0140 $40,000.00 $560.00
alambrón de 1/4" toneladas 0.0040 $39,000.00 $156.00
concreto f´c=210 kg/cm2 m3 0.2000 $2,001.62 $400.32
alambre recocido kg 0.2600 $40.00 $10.40
MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
UNITARIO
cuadrilla #2 jornada 0.1333 $1,305.94 $174.08
cuadrilla #3 jornada 0.1333 $716.02 $95.47
cuadrilla #5 jornada 0.1579 $726.66 $114.72
$0.00
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
Varilla de 1/2" ton 0.0800 $32,900.00 $2,632.00
concreto f´c=200kg/cm2 m3 1.0000 $1,732.55 $1,732.55
varilla de 3/8" ton 0.0857 $32,900.00 $2,818.87
alambre recocido kg 3.0476 $40.00 $121.90
$0.00
MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
UNITARIO
cuadrilla #2 jornada 0.6667 $1,305.94 $870.62
cuadrilla #3 jornada 0.6667 $716.02 $477.35
cuadrilla #5 jornada $726.66 $0.00
$0.00
$0.00
HERRAMIENTA, EQUIPO DE
SEGURIDAD BASE PORCENTAJE IMPORTE
Y MANDOS INTERMEDIOS
HERRAMIENTA MENOR (% M.O) $1,347.96 3% $40.44
EQUIPO DE SEGURIDAD (%M.O) $0.00
MANDOS INTERMEDIOS (% M.O) $1,347.96 10% $134.80
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
varrilla de 5/8" toneladas 0.0621 $40,000.00 $2,483.20
varilla de 1/2" pieza 0.0108 $32,900.00 $356.13
cocnreto f´c:210 kg/cm2 m3 1.0000 $1,732.55 $1,732.55
alambrón de 1/4" toneladas 0.0324 $39,000.00 $1,262.43
alambre recocido kg 0.6667 $40.00 $26.67
MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
UNITARIO
cuadrilla #2 jornada 0.6667 $1,305.94 $870.67
cuadrilla #3 jornada 0.6667 $716.02 $477.35
cuadrilla #5 jornada 0.6623 $726.66 $481.26
$0.00
$0.00
PARTIDA:
FECHA DE ELABORACIÓN:
COSTO
MATERIALES UNIDAD CANTIDAD IMPORTE
UNITARIO
concreto f´c= 210kg/cm2 m3 0.6350 $1,667.24 $1,058.70
varillas de 3/8" ton 0.0071 $32,900.00 $233.59
block ligero de 10x20x30 pieza 6.5000 $10.00 $65.00
malla electrosoldada m2 1.0000 $90.00 $90.00
alambre recocido kg 0.3150 $40.00 $12.60
MANO DE OBRA
COSTO
CATEGORIA UNIDAD CANTIDAD IMPORTE
UNITARIO
cuadrilla #2 jornada 0.4233 $1,305.94 $552.80
cuadrilla #3 jornada 0.4233 $716.02 $303.12
cuadrilla #5 jornada 0.0463 $726.66 $33.67
$0.00
$0.00